Garmann Miller and the School Board will cover the following slides at the community information session on April 6 at 7:00 pm in the Ayersville Auditorium.
2. Who is the OFCC?
1. Ohio Facilities Construction Commission: (OFCC)
Established in May 1997 as Ohio Schools Facilities Commission (OSFC)
Partnered with State Architects Office in 2012 to become OFCC
Task: Administer state funding for construction of Ohio schools.
2. Classroom Facilities Assistance Program: (CFAP)
Primary OFCC Funding Program
Provide District-wide solution
Based on Equity Ranking (1 thru 612) Currently #199
District Valuation No. Students = $$ per student
Equity Rankings and Costs change every year
Ayersville is eligible TODAY!
4. Proposed OFCC/District Master Plan
Proposed Projected New Costs
Grades Enrollment Bldg Size
Ayersville Local New PK-12 772 Students 119,363 sf $29,167,542
Demolition of existing K-12 (Available if needed) $1,447,325
Total Co-Funded Cost $30,614,867
OFCC State Share 67% $20,511,961
Ayersville Local Share 33% $10,102,906
District LFI’s (100% Local Share)
12,000 SF and 7,000 SF gymnasium 7,237 sf $1,708,294
Terrazzo flooring $240,000
Standing seam metal roof $810,000
Existing building renovation work $800,000
$3,558,294
Total Project Cost for Ayersville 126,600 sf $13,661,200
7. Playground
Existing
Practice Field
Existing Building
New 2-Story
PK-12 Building
Existing Parking
Ayersville Local School
Site Plan
No Additional Land
Ball Fields Remain
Additional Parking
New Front for
Ayersville School
Buildings easily
connected in the
future
New Parking