SlideShare a Scribd company logo
1 of 7
Download to read offline
ASSIGNMENT 1: PIPE SIZING
1. Discuss the process design of rotameter.
2. Discuss in brief about NPSH for centrifugal pumps and explain process design of pump
3. For the specified location of the pump calculated value of (NPSH)A is coming less than
(NSPH)R. Suggest all possible solutions to make(NPSH)A greater than (NPSH)R.
4. Discuss the Process Design of Orifice meter. Also Explain various locations of pressure
taps with neat sketch in orifice meter. Also state advantages and disadvantages of orifice
meter.
5. Determine the minimum and maximum flow rate of water at 40 ˚C in rotameter of the
given dimensions.
Viscosity of water at 40 ⁰C = 0.7 cP
Density of water at 40 ⁰C = 992.2 kg/m3
Float material = Stainless steel
Density of stainless steel = 8000 kg/m3
Float is made from stainless steel plate of 2 mm thickness.
Cd=0.775
Angle made by tapered tube with vertical plane is 2 degree.
Mass flow rate through rotameter:
6. A centrifugal pump is drawing water from an overhead tank, exposed to atmosphere.
Vertical distance between free surface of liquid in the tank and center line of pump is 10
m. Capacity of centrifugal pump is 10000 kg/h. Maximum operating temperature is 50 ˚C.
Vapor pressure of water at 50 ˚C is 92.51 torr. Total length of suction pipe is 10.5 m
having two 90˚ elbows. Determine the size of suction pipe and (NPSH)A of centrifugal
pump. Material of pipe is carbon steel. Density of water = 1000 kg/m3
. Viscosity of water
= 0.558 mPa s (or cP). Surface roughness of carbon steel =0.0457 mm. K value for 90 ˚
elbow = 0.75. Surface roughness of carbon steel and friction factor are 0.0457 mm &
0.005 respectively. For the velocity of water in suction line 1 m/s, Determine (i) the size of
suction pipe (ii) total frictional pressure drop in suction line (iii) (NPSH) of centrifugal
pump.
7. Hexane at 40 0
C is pumped through the system at the rate of 10 m3/hr. The tank is at
atmospheric pressure. Pressure at the end of the discharge pipe is 400 kPa g. The discharge is 4.5
m above the pump center line while the suction lift is 1 m above the level of the liquid in the
tank. The friction loss in the suction line is 4 kPa and that in the discharge line is 40 kPa. The
mechanical efficiency of the pump is 65%. The density of hexane is 650 kg/m3 and its vapour
pressure at 40 0
C is 35 kPa. Calculate power required by centrifugal pump
8. Calculate the Manometer reading generated by orifice meter based on following
data:
Name of the fluid: Water
Flow rate: 90000 kg/h
Inside diameter of pipe=154 mm
Operating temperature = 32 °C
Density of water = 995 kg/m3 Viscosity of water = 0.765 cP
Manometer fluid = Mercury, Density of mercury = 13516.47 kg/m3
Take β = 0.5. C0=0.6055
9. A three stage reciprocating compressor is used to compress 306 Sm3
/h of methane from
0.95 atm a to 61.3 atm a. The inlet temperature is 26.7 °C. Specific heat ratio of methane is
1.31. Calculate (1) Power required for compression, if mechanical efficiency is 80% and
(2) discharge temperature of gas after 1st
stage.
10. Benzene at 38°C is pumped through the system at a rate 9.09 m3/hr with the help of a
centrifugal pump. The reservoir is at atmospheric pressure. Pressure at the end of discharge
line is 345 kPa g. The discharge head is 3.05 meter and the pump suction head is 1.22
meter above the level of liquid in reservoir. The friction loss in suction line is 3.45 kPa and
that in discharge line is 37.9 kPa. The mechanical efficiency of the pump is 0.6. The
density of benzene is 865 kg/m3 and its vapor pressure at 38°C is 26.2 kPa. Calculate (1)
NPSH and (2) Power required by pump. Power required by pump is given by,
Where P= power required in kW, H= Total dynamic head in meter, qv= volumetric flow
rate, m3
/hr, ρ= density of fluid, kg/m3
, η= mech. efficiency of pump.
11. Carbon dioxide is to be conveyed from the top of the stripper of ammonia plant to urea
plant. Calculate the pipe size required based on following data.
(i) Flow rate of CO2 = 1000 t/day
(ii) Total length of pipe = 800 m
(iii) Available pressure at inlet of pipe = 24 kPa g
(iv) Discharge pressure of CO2 from pipe required = atmospheric
(v) No. of butterfly valve in pipeline = 1
(vi) No. of 90o
elbows in pipeline = 8
(vii) Temperature of gas = 60o
C
(viii) Viscosity of CO2 gas = 0.016 cP
(ix) Equivalent number of velocity heads for butterfly valve =0.24
(x) Equivalent number of velocity heads for 90o
elbows = 0.75
(xi)MOC of Pipe = Carbon Steel
ASSIGNMENT 2 HEAT EXCHANGER
1. In design of vertical thermosyphon reboiler recirculation ratio is determined via trial and
error calculations. In these calculations one of the following
hypothetical conditions arises for the assumed value of recirculation ratio.
(i) Δ Pav ≈ Δ Pt
(ii) Δ Pav >> Δ Pt
(iii) Δ Pav < Δ Pt
Discuss how to find or fix the recirculation ratio in each of the above condition.
2. Discuss process design of Thermosyphon reboiler.
3. Discuss the design procedure for Kettle type Reboiler.
4. Discuss the design of plate type heat exchanger.
5. Describe in brief criteria of selection between horizontal and vertical condenser.
6. Discuss in detail about criteria of selection between kettle type and thermosyphon reboiler.
7. State the functions of the followings in shell and tube heat exchanger.
(1) Baffles (2) tie rods (3) spacers (4) Tube sheet (5) sealing strips
8. Baffle spacing in heat exchanger,
9. Discuss the Advantages and disadvantages of plate heat exchanger over shell and tube heat
exchanger.
10.Write a brief note on selection of heating media and cooling media in heat
Exchanger OR Write a brief note on Fluid allocation in shell and tube heat exchanger.
11.Give the stepwise design procedure for Shell & Tube heat exchanger.
12.Explain in brief Tinker’s Flow Model for Shell and Tube heat exchanger.
13.State the various types of shell and tube heat exchanger. Discuss the advantagesand
disadvantages of different types of shell and tube heat exchanger with each other.
14.Gas oil at 200 °C is to be cooled to 40 °C. The oil flow rate is 22500 kg/h. Cooling water
is available at 30 °C and the temperature rise is to be limited to 20 °C. The pressure drop
allowance for each stream is 100 kN/m2
. Design a suitable heat exchanger. Physical
properties of the fluid:
Temperature correction factor Ft = 0.94
Base your design on overall heat transfer coefficient = 500 W/m2
°C
Tube OD = 20 mm, Tube ID = 16mm, Tube length = 4m, Triangular pitch
pt=1.25dO, Number of tube side passes =04,
Shell diameter = 667 mm, baffle spacing = 133 mm Take water in tube side.
Oil side heat transfer coefficient = 5000 W/m2
°C
Water side heat transfer coefficient = 4000 W/m2
°C
Thermal conductivity of tube wall material = 45 W/m °C
Assume the pressure drop are within permissible limit.
shell side heat transfer coefficient:
15.10900 kg/h of nearly pure saturated methyl ethyl ketone (MEK) vapor at 13.73 kPa g is to
be condensed and cooled to 60 ᵒC by cooling water which is available in plant at 32 ᵒC.
Assme Uc = 800 W/m2
ᵒC and Usub = 200 W/m2
ᵒC. Calculate the % excess heat transfer
area for the given condenser.
(1) Latent heat of condensation of MEK at condensation temperature, 83.87ᵒC = 438.27
KJ/Kg
(2) Specific heat of MEK liquid = 2.298 KJ/Kg ᵒC
(3) No. of tube side pass = 4 , for 4 passes k1 = 0.175, n1 = 2.285
(4) Tube OD = 19.05 mm , Tube ID = 15.748 mm , Tube length = 1.83 m
(5) Viscosity of water = 0.72 cP,
(6) Thermal conductivity of water = 0.6228 W/m ᵒC
(7) Mean temperature of condensate film = 71.22 ᵒC
(8) Physical properties of MEK liquid condensate at 71.22 ᵒC,
Viscosity = 0.31 cP, density = 805 kg/m3
, Thermal conductivity = 0173 W/m ᵒC
(9) For subcooling zone hosub = 283.77 W/m2
ᵒC
(10) dirt factor for organic vapor = 10000 W/m2
ᵒC
(11) dirt factor for cooling water = 4000 W/m2
ᵒC
(12) Thermal conductivity of SS 304 material = 16.3 W/m ᵒC
16.1-2 shell and tube heat exchanger is used to cool methanol condensate from 95 °C to 40°C.
Flow rate of methanol is 100000 kg/h. Brackish water is used as coolant with temperature
rise from 25 °C to 40 °C.
Property Methanol Brackish Water
Heat Capacity, kJ/kg °C 2.84 4.2
Density, kg/m3 750 995
Viscosity, mNs/m2 0.34 0.8
Thermal conductivity, W/m °C 0.19 0.59
Choose 20mm od, 16 mm id, 4.88 m long cupro-nickle tubes with triangular pitch
Pt=1.25dO.
Based on overall heat transfer coefficient 600 W/m2 °C, Calculate
(1) Number of tubes
(2) Shell Diameter
(3) Tube side heat transfer coefficient. (Take brackish water in tubes).
K1 and n1 for tube bundle diameter: (For triangular pitch pt=1.25dO)
No of tube
side passes
1 2 4 6 8
K1 0.319 0.249 0.175 0.0743 0.0365
n1 2.142 2.207 2.285 2.499 2.675
Heat transfer coefficient for tube side: for Re>4000
NU =0.023RQ
0.8Pr
0.33(µ/ µW)0.14
17.50000 kg/hr ethanol liquid is to be cooled from 850
C to 500
C in gasketed plate heat
exchanger. Operating pressure at the inlet of heat exchanger is 2 atm g. Cooling water is
available at 320
C, is used as a cooling medium. Design the suitable plate heat exchanger.
Assume the temperature correct ion factor to be 0.97. Select the effective plate width 0.5 m
and effective plate length 1.5 m having plate thickness 1 mm. Take gap between
successive plate to be 3 mm. Assume the constant to be a=0.65, b= 0.4 and c=0.26.
Take density of ethanol = 775 kg/m3
and viscosity to be 0.6 cP Thermal conductivity
of ethanol = 0.147 W/ (m. 0
C) and sp. heat = 2.84 KJ /Kg K
Take density of water = 1000 kg/m3 and viscosity to be 0.8 cP Thermal conductivity
of water = 0.62 W/ (m. 0
C) and sp. heat = 4.186 KJ /Kg K.
Assume the fouling coefficient of water and ethanol to be 10000 w/ (m2
. 0
C)
Assume plate material to be titanium with thermal conductivity = 21 W/ (m. 0
C)
Start the design assuming U = 1500 W/m2
K and finalize after one trial only the area
required as per 10% excess area. Pressure drop calculation is not required.
18.Design shell and tube horizontal condensor for condensation of 46000 kg/hr n-propanol at
0.25 kgf/cm2
g by cooling water at 320
C. The condensing temp. at this pressure is 81.2 0
C.
The dirt factors of both shell and tube side is 2000 kcal/hr m2
C. Assume that allowable
pressure drop on both the side is within limit. Assume the tube o.d. of 19.05 mm and 23.81
mm triangular pitch. Tube wall thickness to be taken as 1.65 mm. Assume isothermal
condensation.
Properties for n-propanol:
Latent heat of condensation: 158 kcal/kg
Thermal conductivity : 0.14 kcal/hr m C
Liquid density : 800 kg/m3
Liquid viscosity: 0.62 cP Vapor viscosity: 0.01 cP
Assume thermal conductivity of tube metal = 39 kcal/hr mC
Condensation coefficient is to be calculated as
Where,
Water side coefficient is calculated as:
Where, t = water side average temperature, 0
C
di = inside diameter of tube, mm
ut = tube side velocity, m/sec
For triangular pitch, constants for bundle diameter are as:
19.A horizontal 1-4 heat exchanger (condenser) is used to condense 45000 kg/hr of mixed
light hydrocarbon vapors. The condenser to operate at 10 bar. The vapor will enter the
condenser saturated at 60 °C and the condensation will be completed at 45 °C. The average
molecular weight of vapor is 52. The enthalpy of the vapor is 596.5 kJ/kg and the
condensate 247 kJ/kg. Cooling water is available at 30 °C and the temperature rise is
limited to 10°C. Plant standards requires tubes of 20 mm od, 16.8 mm id, 4.88 m long of
admiralty brass. Use square pitch tube arrangement with pt=1.25dO. The vapors are to be
totally condensed and no sub cooling is required. Take temperature correction factor
Ft=0.92.
Based on overall heat transfer coefficient = 900 W/m2°C, Calculate
(1) Number of tubes (2) Shell Diameter (3) Tube side heat transfer coefficient and (4)
Shell side heat transfer coefficient
Physical properties of condensate at 47°C are:
μL=0.16 mNs/m, ρL=551 kg/m3, kL=0.13W/m°C.
Specific heat of water at 35°C=4.18 kJ/kg C. Density of water = 993 kg/m3,
Thermal conductivity of water = 0.628 W/m °
20.Lube oil is to be cooled from 65 °C to 45 °C by using cooling water in shell and tube heat
exchanger having following data.
Lube oil flow rate - 450 L/min
Density of lube oil - 869 kg/m3
Specific heat of lube oil - 2.1413 kJ/kg °C
Thermal conductivity of lube oil - 0.13 W/m °C
Viscosity of lube oil - 15 cP
Cooling water inlet temperature - 35 °C
Cooling water outlet temperature - 39 °C
Specific heat of water - 4.1868 kJ/kg°C
Viscosity of water - 0.73 cP
Thermal conductivity of water - 0.628 W/m °C
Density of Water - 993.32 kg/m3
Specification of fixed tube sheet heat exchanger:
Shell inside diameter – 418 mm
Tube O.D. - 15.875 mm
Type of baffle – 25 % segmental
Tube I.D -13.3858 mm
Baffle spacing - 83.6 mm
Tube length - 3.048 m
Tube pitch - 1.25dO
Type of tube arrangement - Triangular
Nos. of tube side passes – 4
LMTD correction factor : 0.95
Assume overall heat transfer Coefficient = 400 W/m2
°C
Fixed tube sheet type shell and tube heat exchanger is used for this duty. Take lube oil on
shell side and water on tube side. Calculate (i) Number of tubes (ii) tube side heat transfer
coefficient (iii) shell side heat transfer coefficient.
Use following correlation:
ASSIGNMENT 3 EXTRACTION
1. State and discuss the industrial applications of liquid-liquid extraction.
2. Discuss the criteria for the choice of solvent for liquid – liquid extraction OR Discuss the
desirable solvent properties required in liquid-liquid extraction.
3. Discuss the Process design of Horizontal and Vertical Settlers in details
4. Explain the process design of counter current multistage extractor.
5. State the merits and demerits of mixer-settler. Discuss the design steps for the process
design of horizontal and vertical gravity settler. OR Discuss the process design of settlers.
6. For the separation of dimethylformamide (DMF) from its dilute solution having a flow rate
of 1000 kg/h and containing 20 % DMF by mass is to be counter currently extracted with
methylene chloride to reduce the DMF concentration to 1 % in the final raffinate.
Determine (i) the minimum amount of solvent which can be used and (ii) the number of
theoretical stages if actual amount of solvent is double than the minimum required. Phase
equilibrium equation is given by 𝑌=0.5555 𝑋 at 25 o
C where, Yand X are mass fractions of
solute.

More Related Content

What's hot

Ammonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming CatalystsAmmonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming CatalystsGerard B. Hawkins
 
iaetsd Heat transfer enhancement of shell and tube heat exchanger using conic...
iaetsd Heat transfer enhancement of shell and tube heat exchanger using conic...iaetsd Heat transfer enhancement of shell and tube heat exchanger using conic...
iaetsd Heat transfer enhancement of shell and tube heat exchanger using conic...Iaetsd Iaetsd
 
Dr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingDr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingamaborig
 
Thermodynamics lab manual
Thermodynamics lab manualThermodynamics lab manual
Thermodynamics lab manualDr. Ramesh B
 
Boiler design-calculation 3
Boiler design-calculation 3Boiler design-calculation 3
Boiler design-calculation 3Ebra21
 
Design Project Presentation
Design Project PresentationDesign Project Presentation
Design Project PresentationRobert Cote
 
Refrigeration system 2
Refrigeration system 2Refrigeration system 2
Refrigeration system 2Yuri Melliza
 
Natural gas processing: Production of LPG
Natural gas processing: Production of LPG Natural gas processing: Production of LPG
Natural gas processing: Production of LPG Asma-ul Husna
 
Numerical Investigation of Finned-Tube Heat-exchanger with Circular, Elliptic...
Numerical Investigation of Finned-Tube Heat-exchanger with Circular, Elliptic...Numerical Investigation of Finned-Tube Heat-exchanger with Circular, Elliptic...
Numerical Investigation of Finned-Tube Heat-exchanger with Circular, Elliptic...Hasibul Hasan Shovon
 
Simulation of the flue gas flow through the superheat
Simulation of the flue gas flow through the superheatSimulation of the flue gas flow through the superheat
Simulation of the flue gas flow through the superheatHuy Nguyen
 
Ky0907
Ky0907Ky0907
Ky0907thuan8
 
Gas chromatography1
Gas chromatography1Gas chromatography1
Gas chromatography1HAMEED ULLAH
 
Reformer Tube Inspection & Issues Affecting Tube Life
Reformer Tube Inspection & Issues Affecting Tube LifeReformer Tube Inspection & Issues Affecting Tube Life
Reformer Tube Inspection & Issues Affecting Tube LifeThomas Fortinberry
 

What's hot (19)

Ammonia converter
Ammonia converterAmmonia converter
Ammonia converter
 
Ammonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming CatalystsAmmonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming Catalysts
 
iaetsd Heat transfer enhancement of shell and tube heat exchanger using conic...
iaetsd Heat transfer enhancement of shell and tube heat exchanger using conic...iaetsd Heat transfer enhancement of shell and tube heat exchanger using conic...
iaetsd Heat transfer enhancement of shell and tube heat exchanger using conic...
 
Research_Publication
Research_PublicationResearch_Publication
Research_Publication
 
Dr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingDr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processing
 
Thermodynamics lab manual
Thermodynamics lab manualThermodynamics lab manual
Thermodynamics lab manual
 
Boiler design-calculation 3
Boiler design-calculation 3Boiler design-calculation 3
Boiler design-calculation 3
 
Design Project Presentation
Design Project PresentationDesign Project Presentation
Design Project Presentation
 
Hvac formulas
Hvac formulasHvac formulas
Hvac formulas
 
Refrigeration system 2
Refrigeration system 2Refrigeration system 2
Refrigeration system 2
 
13 venting requirements
13 venting requirements13 venting requirements
13 venting requirements
 
Natural gas processing: Production of LPG
Natural gas processing: Production of LPG Natural gas processing: Production of LPG
Natural gas processing: Production of LPG
 
Numerical Investigation of Finned-Tube Heat-exchanger with Circular, Elliptic...
Numerical Investigation of Finned-Tube Heat-exchanger with Circular, Elliptic...Numerical Investigation of Finned-Tube Heat-exchanger with Circular, Elliptic...
Numerical Investigation of Finned-Tube Heat-exchanger with Circular, Elliptic...
 
Simulation of the flue gas flow through the superheat
Simulation of the flue gas flow through the superheatSimulation of the flue gas flow through the superheat
Simulation of the flue gas flow through the superheat
 
Ky0907
Ky0907Ky0907
Ky0907
 
Gas chromatography1
Gas chromatography1Gas chromatography1
Gas chromatography1
 
Reformer Tube Inspection & Issues Affecting Tube Life
Reformer Tube Inspection & Issues Affecting Tube LifeReformer Tube Inspection & Issues Affecting Tube Life
Reformer Tube Inspection & Issues Affecting Tube Life
 
Final Year Project Presentation
Final Year Project PresentationFinal Year Project Presentation
Final Year Project Presentation
 
PLATE FREEZER
PLATE FREEZERPLATE FREEZER
PLATE FREEZER
 

Similar to Process equipment numericals problems

Me ies-2014-conventional-i
Me ies-2014-conventional-iMe ies-2014-conventional-i
Me ies-2014-conventional-ikrutti
 
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 08 Assignment
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 08 AssignmentCH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 08 Assignment
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 08 Assignmentsemihypocrite
 
Me2202 engineering thermodynamics uq - april may 2010
Me2202 engineering thermodynamics   uq - april may 2010Me2202 engineering thermodynamics   uq - april may 2010
Me2202 engineering thermodynamics uq - april may 2010BIBIN CHIDAMBARANATHAN
 
Me6301 engineering thermodynamics uq - may june 2016
Me6301 engineering thermodynamics   uq - may june 2016Me6301 engineering thermodynamics   uq - may june 2016
Me6301 engineering thermodynamics uq - may june 2016BIBIN CHIDAMBARANATHAN
 
A109210305 thermodynamics1
A109210305 thermodynamics1A109210305 thermodynamics1
A109210305 thermodynamics1jntuworld
 
Chemical engineering department
Chemical engineering departmentChemical engineering department
Chemical engineering departmentMujeeb UR Rahman
 
Me2202 engineering thermodynamics uq - nov dec 2011
Me2202 engineering thermodynamics   uq - nov dec 2011Me2202 engineering thermodynamics   uq - nov dec 2011
Me2202 engineering thermodynamics uq - nov dec 2011BIBIN CHIDAMBARANATHAN
 
Me2202 engineering thermodynamics uq - nov dec 2015
Me2202 engineering thermodynamics   uq - nov dec 2015Me2202 engineering thermodynamics   uq - nov dec 2015
Me2202 engineering thermodynamics uq - nov dec 2015BIBIN CHIDAMBARANATHAN
 
مبدل های حرارتی
مبدل های حرارتیمبدل های حرارتی
مبدل های حرارتیObeid Aghaei
 
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...IRJET Journal
 
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 07 Assignment
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 07 AssignmentCH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 07 Assignment
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 07 Assignmentsemihypocrite
 
Me2202 engineering thermodynamics uq - nov dec 2010
Me2202 engineering thermodynamics   uq - nov dec 2010Me2202 engineering thermodynamics   uq - nov dec 2010
Me2202 engineering thermodynamics uq - nov dec 2010BIBIN CHIDAMBARANATHAN
 
Functional Design of Heat Exchanger
Functional Design of Heat ExchangerFunctional Design of Heat Exchanger
Functional Design of Heat ExchangerShubhajit Sarkhel
 
Kettle reboilers
Kettle reboilersKettle reboilers
Kettle reboilersAtif Khan
 
Me1201 engineering thermodynamics uq - nov dec 2006
Me1201 engineering thermodynamics   uq - nov dec 2006Me1201 engineering thermodynamics   uq - nov dec 2006
Me1201 engineering thermodynamics uq - nov dec 2006BIBIN CHIDAMBARANATHAN
 
Me6301 engineering thermodynamics uq - nov dec 2018
Me6301 engineering thermodynamics   uq - nov dec 2018Me6301 engineering thermodynamics   uq - nov dec 2018
Me6301 engineering thermodynamics uq - nov dec 2018BIBIN CHIDAMBARANATHAN
 
Esign and thermal evaluation of shell and helical coil heat exchanger
Esign and thermal evaluation of shell and helical coil heat exchangerEsign and thermal evaluation of shell and helical coil heat exchanger
Esign and thermal evaluation of shell and helical coil heat exchangereSAT Journals
 
Me1201 engineering thermodynamics uq - may june 2007
Me1201 engineering thermodynamics   uq -  may june 2007Me1201 engineering thermodynamics   uq -  may june 2007
Me1201 engineering thermodynamics uq - may june 2007BIBIN CHIDAMBARANATHAN
 

Similar to Process equipment numericals problems (20)

Me ies-2014-conventional-i
Me ies-2014-conventional-iMe ies-2014-conventional-i
Me ies-2014-conventional-i
 
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 08 Assignment
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 08 AssignmentCH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 08 Assignment
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 08 Assignment
 
Me2202 engineering thermodynamics uq - april may 2010
Me2202 engineering thermodynamics   uq - april may 2010Me2202 engineering thermodynamics   uq - april may 2010
Me2202 engineering thermodynamics uq - april may 2010
 
Me6301 engineering thermodynamics uq - may june 2016
Me6301 engineering thermodynamics   uq - may june 2016Me6301 engineering thermodynamics   uq - may june 2016
Me6301 engineering thermodynamics uq - may june 2016
 
X10705 (me8595)
X10705 (me8595)X10705 (me8595)
X10705 (me8595)
 
A109210305 thermodynamics1
A109210305 thermodynamics1A109210305 thermodynamics1
A109210305 thermodynamics1
 
Chemical engineering department
Chemical engineering departmentChemical engineering department
Chemical engineering department
 
Me2202 engineering thermodynamics uq - nov dec 2011
Me2202 engineering thermodynamics   uq - nov dec 2011Me2202 engineering thermodynamics   uq - nov dec 2011
Me2202 engineering thermodynamics uq - nov dec 2011
 
Me2202 engineering thermodynamics uq - nov dec 2015
Me2202 engineering thermodynamics   uq - nov dec 2015Me2202 engineering thermodynamics   uq - nov dec 2015
Me2202 engineering thermodynamics uq - nov dec 2015
 
مبدل های حرارتی
مبدل های حرارتیمبدل های حرارتی
مبدل های حرارتی
 
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...
 
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 07 Assignment
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 07 AssignmentCH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 07 Assignment
CH EN 3453 Heat Transfer 2014 Fall Utah Homework HW 07 Assignment
 
Me2202 engineering thermodynamics uq - nov dec 2010
Me2202 engineering thermodynamics   uq - nov dec 2010Me2202 engineering thermodynamics   uq - nov dec 2010
Me2202 engineering thermodynamics uq - nov dec 2010
 
Functional Design of Heat Exchanger
Functional Design of Heat ExchangerFunctional Design of Heat Exchanger
Functional Design of Heat Exchanger
 
Kettle reboilers
Kettle reboilersKettle reboilers
Kettle reboilers
 
Me1201 engineering thermodynamics uq - nov dec 2006
Me1201 engineering thermodynamics   uq - nov dec 2006Me1201 engineering thermodynamics   uq - nov dec 2006
Me1201 engineering thermodynamics uq - nov dec 2006
 
Me6301 engineering thermodynamics uq - nov dec 2018
Me6301 engineering thermodynamics   uq - nov dec 2018Me6301 engineering thermodynamics   uq - nov dec 2018
Me6301 engineering thermodynamics uq - nov dec 2018
 
Esign and thermal evaluation of shell and helical coil heat exchanger
Esign and thermal evaluation of shell and helical coil heat exchangerEsign and thermal evaluation of shell and helical coil heat exchanger
Esign and thermal evaluation of shell and helical coil heat exchanger
 
Me1201 engineering thermodynamics uq - may june 2007
Me1201 engineering thermodynamics   uq -  may june 2007Me1201 engineering thermodynamics   uq -  may june 2007
Me1201 engineering thermodynamics uq - may june 2007
 
C1303071722
C1303071722C1303071722
C1303071722
 

Recently uploaded

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 

Recently uploaded (20)

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Process equipment numericals problems

  • 1. ASSIGNMENT 1: PIPE SIZING 1. Discuss the process design of rotameter. 2. Discuss in brief about NPSH for centrifugal pumps and explain process design of pump 3. For the specified location of the pump calculated value of (NPSH)A is coming less than (NSPH)R. Suggest all possible solutions to make(NPSH)A greater than (NPSH)R. 4. Discuss the Process Design of Orifice meter. Also Explain various locations of pressure taps with neat sketch in orifice meter. Also state advantages and disadvantages of orifice meter. 5. Determine the minimum and maximum flow rate of water at 40 ˚C in rotameter of the given dimensions. Viscosity of water at 40 ⁰C = 0.7 cP Density of water at 40 ⁰C = 992.2 kg/m3 Float material = Stainless steel Density of stainless steel = 8000 kg/m3 Float is made from stainless steel plate of 2 mm thickness. Cd=0.775 Angle made by tapered tube with vertical plane is 2 degree. Mass flow rate through rotameter: 6. A centrifugal pump is drawing water from an overhead tank, exposed to atmosphere. Vertical distance between free surface of liquid in the tank and center line of pump is 10 m. Capacity of centrifugal pump is 10000 kg/h. Maximum operating temperature is 50 ˚C. Vapor pressure of water at 50 ˚C is 92.51 torr. Total length of suction pipe is 10.5 m having two 90˚ elbows. Determine the size of suction pipe and (NPSH)A of centrifugal pump. Material of pipe is carbon steel. Density of water = 1000 kg/m3 . Viscosity of water = 0.558 mPa s (or cP). Surface roughness of carbon steel =0.0457 mm. K value for 90 ˚ elbow = 0.75. Surface roughness of carbon steel and friction factor are 0.0457 mm & 0.005 respectively. For the velocity of water in suction line 1 m/s, Determine (i) the size of suction pipe (ii) total frictional pressure drop in suction line (iii) (NPSH) of centrifugal pump.
  • 2. 7. Hexane at 40 0 C is pumped through the system at the rate of 10 m3/hr. The tank is at atmospheric pressure. Pressure at the end of the discharge pipe is 400 kPa g. The discharge is 4.5 m above the pump center line while the suction lift is 1 m above the level of the liquid in the tank. The friction loss in the suction line is 4 kPa and that in the discharge line is 40 kPa. The mechanical efficiency of the pump is 65%. The density of hexane is 650 kg/m3 and its vapour pressure at 40 0 C is 35 kPa. Calculate power required by centrifugal pump 8. Calculate the Manometer reading generated by orifice meter based on following data: Name of the fluid: Water Flow rate: 90000 kg/h Inside diameter of pipe=154 mm Operating temperature = 32 °C Density of water = 995 kg/m3 Viscosity of water = 0.765 cP Manometer fluid = Mercury, Density of mercury = 13516.47 kg/m3 Take β = 0.5. C0=0.6055 9. A three stage reciprocating compressor is used to compress 306 Sm3 /h of methane from 0.95 atm a to 61.3 atm a. The inlet temperature is 26.7 °C. Specific heat ratio of methane is 1.31. Calculate (1) Power required for compression, if mechanical efficiency is 80% and (2) discharge temperature of gas after 1st stage. 10. Benzene at 38°C is pumped through the system at a rate 9.09 m3/hr with the help of a centrifugal pump. The reservoir is at atmospheric pressure. Pressure at the end of discharge line is 345 kPa g. The discharge head is 3.05 meter and the pump suction head is 1.22 meter above the level of liquid in reservoir. The friction loss in suction line is 3.45 kPa and that in discharge line is 37.9 kPa. The mechanical efficiency of the pump is 0.6. The density of benzene is 865 kg/m3 and its vapor pressure at 38°C is 26.2 kPa. Calculate (1) NPSH and (2) Power required by pump. Power required by pump is given by, Where P= power required in kW, H= Total dynamic head in meter, qv= volumetric flow rate, m3 /hr, ρ= density of fluid, kg/m3 , η= mech. efficiency of pump. 11. Carbon dioxide is to be conveyed from the top of the stripper of ammonia plant to urea plant. Calculate the pipe size required based on following data. (i) Flow rate of CO2 = 1000 t/day (ii) Total length of pipe = 800 m (iii) Available pressure at inlet of pipe = 24 kPa g (iv) Discharge pressure of CO2 from pipe required = atmospheric (v) No. of butterfly valve in pipeline = 1 (vi) No. of 90o elbows in pipeline = 8 (vii) Temperature of gas = 60o C (viii) Viscosity of CO2 gas = 0.016 cP (ix) Equivalent number of velocity heads for butterfly valve =0.24 (x) Equivalent number of velocity heads for 90o elbows = 0.75 (xi)MOC of Pipe = Carbon Steel
  • 3. ASSIGNMENT 2 HEAT EXCHANGER 1. In design of vertical thermosyphon reboiler recirculation ratio is determined via trial and error calculations. In these calculations one of the following hypothetical conditions arises for the assumed value of recirculation ratio. (i) Δ Pav ≈ Δ Pt (ii) Δ Pav >> Δ Pt (iii) Δ Pav < Δ Pt Discuss how to find or fix the recirculation ratio in each of the above condition. 2. Discuss process design of Thermosyphon reboiler. 3. Discuss the design procedure for Kettle type Reboiler. 4. Discuss the design of plate type heat exchanger. 5. Describe in brief criteria of selection between horizontal and vertical condenser. 6. Discuss in detail about criteria of selection between kettle type and thermosyphon reboiler. 7. State the functions of the followings in shell and tube heat exchanger. (1) Baffles (2) tie rods (3) spacers (4) Tube sheet (5) sealing strips 8. Baffle spacing in heat exchanger, 9. Discuss the Advantages and disadvantages of plate heat exchanger over shell and tube heat exchanger. 10.Write a brief note on selection of heating media and cooling media in heat Exchanger OR Write a brief note on Fluid allocation in shell and tube heat exchanger. 11.Give the stepwise design procedure for Shell & Tube heat exchanger. 12.Explain in brief Tinker’s Flow Model for Shell and Tube heat exchanger. 13.State the various types of shell and tube heat exchanger. Discuss the advantagesand disadvantages of different types of shell and tube heat exchanger with each other. 14.Gas oil at 200 °C is to be cooled to 40 °C. The oil flow rate is 22500 kg/h. Cooling water is available at 30 °C and the temperature rise is to be limited to 20 °C. The pressure drop allowance for each stream is 100 kN/m2 . Design a suitable heat exchanger. Physical properties of the fluid: Temperature correction factor Ft = 0.94 Base your design on overall heat transfer coefficient = 500 W/m2 °C Tube OD = 20 mm, Tube ID = 16mm, Tube length = 4m, Triangular pitch pt=1.25dO, Number of tube side passes =04, Shell diameter = 667 mm, baffle spacing = 133 mm Take water in tube side. Oil side heat transfer coefficient = 5000 W/m2 °C Water side heat transfer coefficient = 4000 W/m2 °C Thermal conductivity of tube wall material = 45 W/m °C
  • 4. Assume the pressure drop are within permissible limit. shell side heat transfer coefficient: 15.10900 kg/h of nearly pure saturated methyl ethyl ketone (MEK) vapor at 13.73 kPa g is to be condensed and cooled to 60 ᵒC by cooling water which is available in plant at 32 ᵒC. Assme Uc = 800 W/m2 ᵒC and Usub = 200 W/m2 ᵒC. Calculate the % excess heat transfer area for the given condenser. (1) Latent heat of condensation of MEK at condensation temperature, 83.87ᵒC = 438.27 KJ/Kg (2) Specific heat of MEK liquid = 2.298 KJ/Kg ᵒC (3) No. of tube side pass = 4 , for 4 passes k1 = 0.175, n1 = 2.285 (4) Tube OD = 19.05 mm , Tube ID = 15.748 mm , Tube length = 1.83 m (5) Viscosity of water = 0.72 cP, (6) Thermal conductivity of water = 0.6228 W/m ᵒC (7) Mean temperature of condensate film = 71.22 ᵒC (8) Physical properties of MEK liquid condensate at 71.22 ᵒC, Viscosity = 0.31 cP, density = 805 kg/m3 , Thermal conductivity = 0173 W/m ᵒC (9) For subcooling zone hosub = 283.77 W/m2 ᵒC (10) dirt factor for organic vapor = 10000 W/m2 ᵒC (11) dirt factor for cooling water = 4000 W/m2 ᵒC (12) Thermal conductivity of SS 304 material = 16.3 W/m ᵒC 16.1-2 shell and tube heat exchanger is used to cool methanol condensate from 95 °C to 40°C. Flow rate of methanol is 100000 kg/h. Brackish water is used as coolant with temperature rise from 25 °C to 40 °C. Property Methanol Brackish Water Heat Capacity, kJ/kg °C 2.84 4.2 Density, kg/m3 750 995 Viscosity, mNs/m2 0.34 0.8 Thermal conductivity, W/m °C 0.19 0.59 Choose 20mm od, 16 mm id, 4.88 m long cupro-nickle tubes with triangular pitch Pt=1.25dO. Based on overall heat transfer coefficient 600 W/m2 °C, Calculate (1) Number of tubes (2) Shell Diameter (3) Tube side heat transfer coefficient. (Take brackish water in tubes). K1 and n1 for tube bundle diameter: (For triangular pitch pt=1.25dO) No of tube side passes 1 2 4 6 8 K1 0.319 0.249 0.175 0.0743 0.0365
  • 5. n1 2.142 2.207 2.285 2.499 2.675 Heat transfer coefficient for tube side: for Re>4000 NU =0.023RQ 0.8Pr 0.33(µ/ µW)0.14 17.50000 kg/hr ethanol liquid is to be cooled from 850 C to 500 C in gasketed plate heat exchanger. Operating pressure at the inlet of heat exchanger is 2 atm g. Cooling water is available at 320 C, is used as a cooling medium. Design the suitable plate heat exchanger. Assume the temperature correct ion factor to be 0.97. Select the effective plate width 0.5 m and effective plate length 1.5 m having plate thickness 1 mm. Take gap between successive plate to be 3 mm. Assume the constant to be a=0.65, b= 0.4 and c=0.26. Take density of ethanol = 775 kg/m3 and viscosity to be 0.6 cP Thermal conductivity of ethanol = 0.147 W/ (m. 0 C) and sp. heat = 2.84 KJ /Kg K Take density of water = 1000 kg/m3 and viscosity to be 0.8 cP Thermal conductivity of water = 0.62 W/ (m. 0 C) and sp. heat = 4.186 KJ /Kg K. Assume the fouling coefficient of water and ethanol to be 10000 w/ (m2 . 0 C) Assume plate material to be titanium with thermal conductivity = 21 W/ (m. 0 C) Start the design assuming U = 1500 W/m2 K and finalize after one trial only the area required as per 10% excess area. Pressure drop calculation is not required. 18.Design shell and tube horizontal condensor for condensation of 46000 kg/hr n-propanol at 0.25 kgf/cm2 g by cooling water at 320 C. The condensing temp. at this pressure is 81.2 0 C. The dirt factors of both shell and tube side is 2000 kcal/hr m2 C. Assume that allowable pressure drop on both the side is within limit. Assume the tube o.d. of 19.05 mm and 23.81 mm triangular pitch. Tube wall thickness to be taken as 1.65 mm. Assume isothermal condensation. Properties for n-propanol: Latent heat of condensation: 158 kcal/kg Thermal conductivity : 0.14 kcal/hr m C Liquid density : 800 kg/m3 Liquid viscosity: 0.62 cP Vapor viscosity: 0.01 cP Assume thermal conductivity of tube metal = 39 kcal/hr mC Condensation coefficient is to be calculated as Where,
  • 6. Water side coefficient is calculated as: Where, t = water side average temperature, 0 C di = inside diameter of tube, mm ut = tube side velocity, m/sec For triangular pitch, constants for bundle diameter are as: 19.A horizontal 1-4 heat exchanger (condenser) is used to condense 45000 kg/hr of mixed light hydrocarbon vapors. The condenser to operate at 10 bar. The vapor will enter the condenser saturated at 60 °C and the condensation will be completed at 45 °C. The average molecular weight of vapor is 52. The enthalpy of the vapor is 596.5 kJ/kg and the condensate 247 kJ/kg. Cooling water is available at 30 °C and the temperature rise is limited to 10°C. Plant standards requires tubes of 20 mm od, 16.8 mm id, 4.88 m long of admiralty brass. Use square pitch tube arrangement with pt=1.25dO. The vapors are to be totally condensed and no sub cooling is required. Take temperature correction factor Ft=0.92. Based on overall heat transfer coefficient = 900 W/m2°C, Calculate (1) Number of tubes (2) Shell Diameter (3) Tube side heat transfer coefficient and (4) Shell side heat transfer coefficient Physical properties of condensate at 47°C are: μL=0.16 mNs/m, ρL=551 kg/m3, kL=0.13W/m°C. Specific heat of water at 35°C=4.18 kJ/kg C. Density of water = 993 kg/m3, Thermal conductivity of water = 0.628 W/m ° 20.Lube oil is to be cooled from 65 °C to 45 °C by using cooling water in shell and tube heat exchanger having following data. Lube oil flow rate - 450 L/min Density of lube oil - 869 kg/m3 Specific heat of lube oil - 2.1413 kJ/kg °C Thermal conductivity of lube oil - 0.13 W/m °C Viscosity of lube oil - 15 cP Cooling water inlet temperature - 35 °C Cooling water outlet temperature - 39 °C Specific heat of water - 4.1868 kJ/kg°C Viscosity of water - 0.73 cP
  • 7. Thermal conductivity of water - 0.628 W/m °C Density of Water - 993.32 kg/m3 Specification of fixed tube sheet heat exchanger: Shell inside diameter – 418 mm Tube O.D. - 15.875 mm Type of baffle – 25 % segmental Tube I.D -13.3858 mm Baffle spacing - 83.6 mm Tube length - 3.048 m Tube pitch - 1.25dO Type of tube arrangement - Triangular Nos. of tube side passes – 4 LMTD correction factor : 0.95 Assume overall heat transfer Coefficient = 400 W/m2 °C Fixed tube sheet type shell and tube heat exchanger is used for this duty. Take lube oil on shell side and water on tube side. Calculate (i) Number of tubes (ii) tube side heat transfer coefficient (iii) shell side heat transfer coefficient. Use following correlation: ASSIGNMENT 3 EXTRACTION 1. State and discuss the industrial applications of liquid-liquid extraction. 2. Discuss the criteria for the choice of solvent for liquid – liquid extraction OR Discuss the desirable solvent properties required in liquid-liquid extraction. 3. Discuss the Process design of Horizontal and Vertical Settlers in details 4. Explain the process design of counter current multistage extractor. 5. State the merits and demerits of mixer-settler. Discuss the design steps for the process design of horizontal and vertical gravity settler. OR Discuss the process design of settlers. 6. For the separation of dimethylformamide (DMF) from its dilute solution having a flow rate of 1000 kg/h and containing 20 % DMF by mass is to be counter currently extracted with methylene chloride to reduce the DMF concentration to 1 % in the final raffinate. Determine (i) the minimum amount of solvent which can be used and (ii) the number of theoretical stages if actual amount of solvent is double than the minimum required. Phase equilibrium equation is given by 𝑌=0.5555 𝑋 at 25 o C where, Yand X are mass fractions of solute.