Developing Country Studies                                                                            www.iiste.org
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol 2, No.10, 2012




      Analysis And Prediction Of Cost And Time Overrun Of
 Millennium Development Goals (MDGS) Construction Projects In
                             Nigeria.

                  Edoka Augustine Ijigah Ezekiel Babatunde Ogunbode*          Moshood O. Ibrahim
           Department Of Building, Federal University of Technology, P.M.B. 65, Minna, Niger State Nigeria.
                          * E-mail of the corresponding author: onbodmail@yahoo.com
Abstract
The paper focuses on the analysis and forecast of cost and time overrun of MDGs construction projects in Nigeria.
Twenty five MDGs construction projects from (2006-2009) were critically investigated and time and cost overrun
of the project were studied. The Statistical Package for Social Scientists (SPSS) 19.0 version was used to analyse
the variables using Paired t-test and simple regression at 95% confidence limits. The analysis was based on the
adaptation of requisition method. The validity test on the efficiency of the model was highlighted using the
confidence interval to enhance the application of the models. Mathematical models were developed. The findings
shows that there is a significant different between the total contract sum, cost overrun, total contract duration, and
time overrun for the MDGS projects. The study suggests acute need for government to engage in proactive
strategic planning and approaches to keep construction project cost and time within reasonable limit for the
actualization of MDGs policy of development and environmental sustainability.

Keywords: Analysis and Prediction, Cost Overrun, Time Overrun, Millennium Development Goals and
Construction Projects.

1. Introduction

The Millennium Development Goals which are to be realized by 2015 are a set of developmental targets aimed at
affecting measurable improvement in the life of the world’s poorest citizens. The goals are related to poverty
reduction, gender inequality, child and material health, combating HIV/AIDS, malaria and other diseases,
environmental sustainability, and international cooperation for development. (MDGs, 2010). Eboh, (2008); UNDP
(2009); UN (2009) UNECA (2009) & MDGs (2010) all reports that a variety of problems have persisted, slowing
the country’s growth and attainment of development objectives. These include inadequate human development,
inefficient agricultural systems, weak infrastructure, lacklustre growth in the manufacturing sector, a poor policy
and regulatory environment, and mismanagement and misuse of resources. The above issue propelled the United
Nation General Assembly to adopt and declare the millennium development goals (MDGs), committing nations of
the world to battle poverty, diseases, gender inequality, and environmental degradation and to foster a global
partnership for development (Otti, 2012).

Following the debt-relief grant of US$18 billion in 2005, a Virtual Poverty Fund was established to ensure that
monies realised (about US$1 billion each year) from debt relief were channelled towards poverty reduction and the
other MDGs. In collaboration, the federal government took both policy and institutional step towards achieving
the MDGs. These include: the National Economic Empowerment and Development Strategy (NEEDS) , State
Economic Empowerment and Development Strategy (SEEDS), Fiscal Responsibility Act, Medium-Term Sector
Strategies (MTSSs), Medium-Term Expenditure Framework (MTEF), Nigeria Vision 20:2020, NEEDS II and 7-
Point Agenda (MDGs, 2008) . Simultaneously, several states have developed their own medium-term development
strategies which have been harmonised with the Vision 20:2020 National Plan and currently provides the overall
(national) policy framework for the MDGs in Nigeria.

The construction industry is generally responsible for the physical development or the transformation of the
environment (Hillebrandt, 2000). The built environment is vital to social-economic development of a nation and
its contribution to MDGS goals are crucial and a focus of any nation's economy (Ijigah, Oloruntaba & Mohn,
                                                        140
Developing Country Studies                                                                            www.iiste.org
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol 2, No.10, 2012




2012). But several finding of studies shows that the industry has reduced in its contribution to the national
economy and its performance in terms of cost and time of project (Olomolaiye, 1987; Aniekwu, 1995; Adeyemi et
al. 2005; Oladipo, 2006; Oladapo, 2011 & Ijigah, et al. 2012).

High construction costs have been a major pointer to the malfunction of the construction industry in Nigeria today
(0tti, 2012 & Ijigah et al.,2012). This has manifested in low construction activities and abandoned projects with
severe consequences on the nation's socio-economic and technological development. Most construction project are
being completed at costs much higher than initial estimated which indicate that initial cost estimates on
construction projects can hardly be relies upon by clients (Achuenu & Kolawole, 1998; Kunya,2006; Oladipo,
2011; 0tti, 2012 & Ijigah et al. 2012). The study of Adewuyi & Anigbogu (2006) also assert the scenario in which
clients are compared to pay for unbudgeted increase in projects or abandon the project out rightly. Ogunsemi
(2002); Achuenu & Ujene (2006); kunya (2006) ; Otti (2012) & Ijigah et al. (2012) all submits that in the recent
past, many projects are still subjected to cost and time overruns which results in claims between clients and
contractors. This has also affected the MDGs projects as the study by Otti (2012) & Ijigah et al. (2012) reviewed
that several of the 2006 MDGs construction projects funded still remained at different stages of completion as at
June 2007 while many had not started at all.

Considering the relationship between construction projects and the national Development , it becomes necessary
that the cost and time overrun of MDGs construction projects be investigated as they is insufficient data to
achieve a significant improvement in the lives of at least 100 million slum dwellers in Nigeria in the 2010 MDGs
report.

It is against this background that this study, therefore seeks to developed mathematical forecasting model for
predicting cost and time overrun that are likely to arise from any MDGs construction project in Abuja Nigeria.
Kunya (2006) have at different time developed similar models for predicting project variation claims of public
buildings. Kunya (2006) states that the efficiency of such models is based on certain assumptions such as
controllable and predictable inflating trends, availability of historical construction data and quick access to
construction project information.

2. Methodology

A non-probability convenience sampling method was adopted; this is a sampling method) that involves choosing
from a sample that is not only accessible (Teddlie & Yu, (2007) and Collins, Onwuegbuziu & Jiao (2007) but the
respondent are willing to take part in the study. This work deals with the analysis of data sourced from various
contract documents of completed (MDGs) construction projects in Abuja, F.C.T. from 2006-2009. Thirty three
contract documents submitted were collated from consultants, out of which eight were discarded for lack of
constancy and twenty five were used for analysis (75.76%). The characteristics of the project were obtained and
used to tabulate the estimated project duration, final project duration, estimated project cost and final project cost
of the (MDGs) projects. The Statistical Package for Social Scientists (SPSS) 19.0 version was used to analyse the
variables using Paired t-test and simple regression at 95% confidence limits. The paired t-test method of analysis
compares two samples and determines the likelihood of the observed different between the samples occurring by
change. The change is reported as the p-value (Kunya, 2006). A p-value close to 1 means, it is likely that the
hypothesized and sample means are the same, since it is very likely that such would happen by change, if the null
hypotheses of no difference exist. Regression method of analysis was adopted, where relationship between
variables is determined using the method of least, squares which sicks to minimize the sum of the square of the
difference between the observed values and the predicted values of the form.

y = a + bx

Where; y - is a dependent variable, (Time Overrun, %Time Overrun, Cost Overrun and %Cost Overrun,); x - is an
independent variable (Project Duration and Project Cost?)




                                                        141
Developing Country Studies                                                                          www.iiste.org
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol 2, No.10, 2012




The choice of this model is informed by the fact that once the relationship has been determined, it can be used to
mark any number of forecasts simply by inserting the value of x for which a forecast is necessary. Where change
may have taken place, it is necessary to collect new set of data and recomputed the value of “a” and “b”

The following equation were also used in the analysis

Time overrun = actual project duration - estimated project duration

Cost overrun = actual project cost - estimated project cost

%cost overrun = cost overrun x100

                  estimated project cost

%time overrun = time overrun x100

                     estimated project duration

3. Results and Discussion

The results of the analysis for the (mdgs) construction projects studied are presented below:
Table 1: Cost and Time Overrun of (MDGs) Construction Project in Abuja

      Estimated      Actual        Time           % Time        Estimated   Final Cost    Cost         % Cost
      Project        Project       Overrun        Overrun       Cost of     of Project    Overrun      Overrun
      Duration       Duration       Months                      Project
      (Months)       (Months)                                   N,000,000   N,000,000      N,000,000


1     12.0           17.0          5.0            41.67         4.70        6.00          1.30         27.66
2     12.0           13.5          1.5            12.50         86.40       93.50         7.10         8.22
3     24.0           18.5          6.0            27.08         21.02       25.76         4.74         22.55
4     23.0           30.5          6.5            13.04         300.00      370.00        70.00        23.30
5     15.0           20.0          5.0            33.33         30.90       40.00         9.10         29.45
6     8.0            11.5          3.5            43.75         4.74        6.84          2.10         44.30
7     18.0           25.0          7.0            38.89         62.80       89.6          26.8         42.68
8     13.0           16.0          3.0            23.08         5.70        6.10          0.40         7.02
9     11.0           12.5          1.5            13.64         402.00      503.00        101.00       25.12
10    24.0           38.0          14.0           58.33         20.67       29.23         18.56        31.74
11    12.0           10.0          2.0            16.67         78.00       89.00         11.00        14.10

12    7.0            8.5           1.5            21.43         254.00      290.00        36.00        14.17

13    24.0           28.0          4.0            16.67         60.87       50.45         10.42        17.12

14    22.0           28.0          6.0            27.23         4.50        6.70          2.20         48.89

15    12.0           15.5          3.0            25.00         24.00       27.00         3.00         12.50



                                                          142
Developing Country Studies                                                                         www.iiste.org
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol 2, No.10, 2012




16        23.0       29.5         6.5             28.26          300.00   370.00         70.00         23.33

17        17.0       24.5         7.5             44.12          320.00   358.00         38.00         11.88

18        7.0        8.0          1.0             14.29          12.00    10.00          2.00          16.67

19        24.0       36.0         12.0            50.00          17.23    22.94          5.71          33.14

20        16.0       19.0         3.0             18.75          53.30    64.10          10.80         20.26

21        21.0       27.5         6.5             30.95          48.00    62.00          14.00         29.17

22        24.0       29.0         5.0             20.83          72.60    85.50          12.90         17.77

23        9.0        13.5         4.5             50.00          4.74     5.84           1.10          23.21

24        5.0        7.0          2.0             40.00          43.70    54.80          11.10         25.40

25        24.0       29.0         5.0             20.83          58.30    72.50          14.20         24.36
Table 1 below presented the project cost and time overrun for the twenty five authenticated project studied. They
are (MDGS) projects executed in Abuja between 2006-2009 and they have cost and time overrun. It shows that the
maximum percentage time and cost overrun are (58.33 & 48.89) while the minimum percentage time and cost
overrun are (12.50 & 7.02). This indicates that the (MDGs) projects all have cost and time overrun. The paired t-
test results show significant differences of 5% level of significant between contract duration and time overrun and
contract cost and cost overrun for projects considered for this study. The results are summarized in Table 2 and
Table 3. A similar study by Adewuyi & Anigbogu (2006) on duration performance of universal basic education
reviewed that only 69.6% of projects awarded in Nigeria were completed and the balance of 30.4% were either
under construction or abandoned after 4½ years of contract award (Adewuyi & Anigbogu, 2006). The research by
Otti (2012) & Ijigah et al. (2012) have shown that they is an improvement in the performance of the construction
industry from 2008. These are due to better project management, improved contract method and the involvement
of clients and contractors in project delivery.

Table 2. Paired t-test Results of Contract Duration and Time Overrun


                                        Project Duration                    Time overrun
Mean                                    16.2800                             4.9000
Std. Deviation                          6.58610                             3.12916
Observation                             25                                  25
Hypothesis                              0
df                                      24
t-start                                 11.480
Sig. (2-tailed)                         0.00
P(T<=t)one                              0.00
t critical one                          12.359
P(T<=t)two                              0.00
t critical two                          7.830


                                                           143
Developing Country Studies                                                                             www.iiste.org
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol 2, No.10, 2012




In the comparison in Table 2, p-value of 0.00 <0.05 means that there is less than 5% chance of contract time
overrun to be higher than the total project duration. This shows that for this project, contract duration is always
higher than the time overrun


Table 3. Paired t-test Results of Contract Cost and Cost overrun


                                       Project Cost                            Cost Overrun
Mean                                   91.6068                                 19.3412
Std. Deviation                         118.77983                               25.57566
Observation                            25                                      25
Hypothesis                             0
df                                     24
t-start                                3.787
Sig. (2-tailed)                        0.001
P(T<=t)one                             0.001
t critical one                         3.856
P(T<=t)two                             0.001
t critical two                         3.781


In the comparison in Table 3, p-value of 0.00 <0.05 means that there is less than 5% chance of contract time
overrun to be higher than the total project duration. This shows that for this project, contract duration is always
higher than the time overrun.
Table 4. Regression Analysis Result (summary) of Project Duration and Time Overrun


Multiple R                                                 0.694
R Square                                                   0.481
Adjusted R Square                                          0.458
Std. Error of the Estimate                                 2.302
Observation                                                25.00
                    6
P value = 5.5 x10
From Table 4 above, regression coefficient of 0.69 shows a positive linear relationship between the project
duration and time overrun. A p value of 5.5 x106 shows a 0.0% chance of no difference between project duration
and time overrun. Also from the regression analysis summary (Table 4) shows a degree of determination of 0.481
suggesting a present of negative relationship between these variables. Total regression analysis reveals the
following models;
y = - 0.467 + 0.330x
Where; y = time overrun; x= project duration.




                                                         144
Developing Country Studies                                                                        www.iiste.org
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol 2, No.10, 2012




Table 5. Regression Analysis Result (summary) of Project Duration and Percentage (%) Time Overrun
Multiple R                                              0.28
R Square                                                0.01
Adjusted R Square                                       -0.043
Std. Error of the Estimate                              13.55097
Observation                                             25


From Table 5 above, regression coefficient of 0.28 shows a negative linear relationship between the project
duration and percentage time overrun. This shows a 0.0% chance of no difference between project duration and
percentage time overrun. Also from the regression analysis summary (Table 5) shows a degree of determination of
0.01 suggesting a present of negative relationship between these variables. Total regression analysis reveals the
following models;
y = 28.292 + 0.057x
Where; y = % time overrun; x = project duration.
Table 6. Regression Analysis Result (summary) of Project cost and cost Overrun
Multiple R                                              0.931
R Square                                                0.857
Adjusted R Square                                       0.861
Std. Error of the Estimate                              9.52606
Observation                                             25
P value = 0.00057
From Table 6 above, regression coefficient of 0.93 shows a positive linear relationship between the project
duration and time overrun. A p value of 0.00057 shows a 57% chance of no difference between project cost and
cost overrun. Also from the regression analysis summary (Table 6) shows a degree of determination of 0.857
suggesting a present of high positive relationship between these variables. Total regression analysis reveals the
following models;
y = 0.974 + 0.200x
Where; y = cost overrun; x= project cost.


Table 7. Regression Analysis Result (summary) of Project Cost and Percentage (%) Cost overrun
Multiple R                                              0.238
R Square                                                0.057
Adjusted R Square                                       0.015
Std. Error of the Estimate                              10.64880
Observation                                             25


From Table 7 above, regression coefficient of 0.238 shows a negative linear relationship between the project and
time overrun. This shows a 0.0% chance of no difference between project cost and percentage cost overrun. Also
from the regression analysis summary (Table 7) shows a degree of determination of 0.057 suggesting a present of
negative relationship between these variables. Total regression analysis reveals the following models;
y = 25.728 - 0.21x
Where; y = % cost overrun; x = project cost.
                                                      145
Developing Country Studies                                                                              www.iiste.org
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol 2, No.10, 2012




4. Conclusion
The study was able to establish some average percentage of cost overruns and time overrun of Abuja MDGs
construction project which are found to vary between 58.33% and 12.50% for time overrun and between 48.89%
and 7.02% for cost overrun. The result of the Paired t-test carried out on time/cost of project shows that there is a
significant difference between total project duration/cost and total time/cost overrun with time/cost overrun
representing an increase in initial projects duration and cost. The simple regression analysis indicates that there is a
positive linear relationship between these variables, which shows that total time and cost of project and time and
cost overrun can be predicted from total project duration and cost within 95% confidence limits using simple
regression models. Similarly from the regression analysis result, percentage (%) time overrun and percentage (%)
cost overrun can also be predicted from total project cost within 95% confidence limits using the developed
regression models within certain confidence intervals of regression constant. The study suggests acute need for
government to engage in proactive strategic planning and approaches to keep construction project time and cost
within reasonable limit for the actualization of MDGS policy of affordable shelter for its citizens. There is also the
need to incorporate into tender price the expected cost and time variation as this will address cost and time overrun
of construction projects hence avert the incidence of project abandonment resulting from time and cost overrun of
construction projects.
Reference
Achuenu, E. & kolawole, J.O. (1998). “Assessment of Cost Overrun of Public Building Projects in Nigeria”
Nigerian Journal of Construction Technology and Management Vol.1NO.1, pp11-15.


Achuenu ,E. & Ujene, A.O. (2006). “Evaluation of Material and Labour Cost of Building Elements in Nigeria”
Nigerian Journal of Construction Technology and Management Vol. 7No. 1, pp 99-110.


Adewuyi, T. O. & Anigbogu, N.A.(2006). “Duration Performance of Universal Basic Education (UBE) Project in
Nigeria” Nigerian Journal of Construction Technology and Management Vol.7 No.1, pp 26-38.


Collins,K.M.T., Onwuegbuzie, A.J. & Jiao, Q.G.(2007). “A Mixed Methods Investigation of Mixed Methods
Sampling Designs in Social and Health Science Research” Journal of Mixed Method Research, Vol. 1 No.3, pp
267-294.


Eboh, E.C. (2008). Template for Tracking the Impact of SEEDS Expenditures on the MDGs. Report submitted to
European Union-Support for Reforming Institutions Programme (EU-SRIP), Abuja, Nigeria.


Federal Government of Nigeria. (2004). Nigeria: National Economic Empowerment and
Development Strategy – NEEDS. Abuja: National Planning Commission.


Hillebrandt, P. M. (2000) Economic Theory and the Construction Industry. London.
Macmillan Publishers Ltd.


Human Development Report Nigeria. 2008-2009: Achieving Growth with Equity. Abuja:
UNDP.


Ijigah, E.A.,Oloruntoba, K.. & Mohd H. R. (2012).Towards Accomplishing Millennium Development Goals
(MDGs) In Abuja F.C.T Nigeria: The Project Management Consultants Roles, “International Journal of Research
in Management & Technology” (IJRMT), Vol. 2, No. 4 pp.414-424, (ISSN: 2249-9563)

                                                         146
Developing Country Studies                                                                    www.iiste.org
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol 2, No.10, 2012




Kunya, S.U. (2006). Analysis and Prediction of Contract Variation Claim of Public Building Projects in North-
Eastern Nigeria, Nigerian Journal of Construction Technology and Management, Vol.7 No.1, pp 86-89.


Office of the Senior Special Assistant to the President on the MDGs. (2008). Mid-point Assessment of the
Millennium Development Goals in Nigeria. Abuja: OSSAP-MDGs.


Office of the Senior Special Assistant to the President on the MDGs. (2010). Assessment of the Millennium
Development Goals in Nigeria. Abuja:


Ogunsemi D. R. (2002), Cost and Time Performance of Construction Projects in South-westernNigeria. A Phd.
thesis submitted to the School of Postgraduate Studies, Federal University of Technology Akure.


Oladapo, A. A. (2006). The Impact of ICT on Professional Practice in the Nigerian Construction Industry. The
Electronic Journal of Information Systems in Developing Countries Vol.24 No.2, pp1-19.


Oladipo, F.O. & Oni, O. (2012). A Review of Selected Macroeconomic Factors Impacting Building Material
Prices In Developing Countries – A Case Of Nigeria, Ethiopian Journal of Environmental Studies and
Management EJESM Vol. 5 No. 2 pp. 131-137


Otti, V.I. (2012). Engineering Implication for Millennium development Goals in Revamping and Sustaining
Nigeria Economy, International Journal of Engineering Research and Applications (IJERA), Vol. 2, no. 2,
pp.1373-1377 ISSN: 2248-9622


Teddie, C. & Yu, F. (2007). Mixed Methods Sampling, A Typology with Examples, Journal of Mixed Methods
Research Vol.1 No.1, pp 77-100.


United Nations Development Programme. (2009). Human Development Report Nigeria. 2008-2009: Achieving
Growth with Equity. Abuja: UNDP.


United Nations Economic Commission for Africa. (2009). Assessing Progress in Africa toward the Millennium
Development Goals. Addis Ababa: UNECA.


United Nations. (2010). Global Millennium Development Goals 2010 Report. New York: UN. United Nations
Development Programme. (2009).


United Nations Economic Commission for Africa. (2009). Assessing Progress in Africa toward the Millennium
Development Goals. Addis Ababa: UNECA.




                                                    147
This academic article was published by The International Institute for Science,
Technology and Education (IISTE). The IISTE is a pioneer in the Open Access
Publishing service based in the U.S. and Europe. The aim of the institute is
Accelerating Global Knowledge Sharing.

More information about the publisher can be found in the IISTE’s homepage:
http://www.iiste.org


                               CALL FOR PAPERS

The IISTE is currently hosting more than 30 peer-reviewed academic journals and
collaborating with academic institutions around the world. There’s no deadline for
submission. Prospective authors of IISTE journals can find the submission
instruction on the following page: http://www.iiste.org/Journals/

The IISTE editorial team promises to the review and publish all the qualified
submissions in a fast manner. All the journals articles are available online to the
readers all over the world without financial, legal, or technical barriers other than
those inseparable from gaining access to the internet itself. Printed version of the
journals is also available upon request of readers and authors.

IISTE Knowledge Sharing Partners

EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open
Archives Harvester, Bielefeld Academic Search Engine, Elektronische
Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial
Library , NewJour, Google Scholar

More Related Content

Viewers also liked

Cost management model
Cost management modelCost management model
Cost management modelMohit Singla
 
Peter Ed Love Offshore Technology Conference
Peter Ed Love Offshore Technology ConferencePeter Ed Love Offshore Technology Conference
Peter Ed Love Offshore Technology Conferencepedlove
 
Scheduling and Cost Control
Scheduling and Cost ControlScheduling and Cost Control
Scheduling and Cost ControlTurki Alsulami
 
Difference between Cost control and Cost reduction
Difference between Cost control and Cost reductionDifference between Cost control and Cost reduction
Difference between Cost control and Cost reductionDinil A E
 
Probability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun ProfilesProbability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun Profilespedlove
 
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...Ahmad Samy M.Sc.
 
Cost control and reduction
Cost control and reduction Cost control and reduction
Cost control and reduction k sudheer
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management Ahmad Maharma, PMP,RMP
 
Cost Control Systems
Cost Control SystemsCost Control Systems
Cost Control SystemsUmesh Charki
 
Factory cost reduction strategies
Factory cost reduction strategiesFactory cost reduction strategies
Factory cost reduction strategiesBakeryBazar .com
 
Cost Control
Cost ControlCost Control
Cost Controlmudduckk
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
control techniques
control techniquescontrol techniques
control techniquesRakesh Kumar
 
Cost control and reduction
Cost control and reductionCost control and reduction
Cost control and reductionShri Theja
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
Cost Reduction Strategies:Focus and Techniques
Cost Reduction Strategies:Focus and TechniquesCost Reduction Strategies:Focus and Techniques
Cost Reduction Strategies:Focus and TechniquesThomas Tanel
 
Cost effective construction techniques
Cost effective construction techniquesCost effective construction techniques
Cost effective construction techniquesSayali Darakh
 

Viewers also liked (20)

Cost management model
Cost management modelCost management model
Cost management model
 
Peter Ed Love Offshore Technology Conference
Peter Ed Love Offshore Technology ConferencePeter Ed Love Offshore Technology Conference
Peter Ed Love Offshore Technology Conference
 
Scheduling and Cost Control
Scheduling and Cost ControlScheduling and Cost Control
Scheduling and Cost Control
 
Difference between Cost control and Cost reduction
Difference between Cost control and Cost reductionDifference between Cost control and Cost reduction
Difference between Cost control and Cost reduction
 
Probability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun ProfilesProbability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun Profiles
 
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
 
Cost control and reduction
Cost control and reduction Cost control and reduction
Cost control and reduction
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management
 
Cost Control Systems
Cost Control SystemsCost Control Systems
Cost Control Systems
 
Factory cost reduction strategies
Factory cost reduction strategiesFactory cost reduction strategies
Factory cost reduction strategies
 
COST CONTROL
COST CONTROLCOST CONTROL
COST CONTROL
 
Cost Control
Cost ControlCost Control
Cost Control
 
Cost control
Cost controlCost control
Cost control
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
control techniques
control techniquescontrol techniques
control techniques
 
Cost control and reduction
Cost control and reductionCost control and reduction
Cost control and reduction
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Cost Reduction Plan
Cost  Reduction  PlanCost  Reduction  Plan
Cost Reduction Plan
 
Cost Reduction Strategies:Focus and Techniques
Cost Reduction Strategies:Focus and TechniquesCost Reduction Strategies:Focus and Techniques
Cost Reduction Strategies:Focus and Techniques
 
Cost effective construction techniques
Cost effective construction techniquesCost effective construction techniques
Cost effective construction techniques
 

Similar to Analysis and prediction of cost and time overrun of

Building information-modeling-and-construction-projects-performance-the-effec...
Building information-modeling-and-construction-projects-performance-the-effec...Building information-modeling-and-construction-projects-performance-the-effec...
Building information-modeling-and-construction-projects-performance-the-effec...oircjournals
 
Cost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfCost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfYohannesBizuneheWeld
 
Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Gafel Kareem
 
Projrkzni menadžment - istraživanje
Projrkzni menadžment - istraživanjeProjrkzni menadžment - istraživanje
Projrkzni menadžment - istraživanjemsisko
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Project+Management+Evolution+to+Improve+Economic+Success+of+Infrastructure+Pr...
Project+Management+Evolution+to+Improve+Economic+Success+of+Infrastructure+Pr...Project+Management+Evolution+to+Improve+Economic+Success+of+Infrastructure+Pr...
Project+Management+Evolution+to+Improve+Economic+Success+of+Infrastructure+Pr...million22
 
Sustainability Indicators in Building Projects in Khartoum State during Const...
Sustainability Indicators in Building Projects in Khartoum State during Const...Sustainability Indicators in Building Projects in Khartoum State during Const...
Sustainability Indicators in Building Projects in Khartoum State during Const...IJAEMSJORNAL
 
1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziriOyeniyi Samuel
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Publishing House
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
Critical Success Factors of Sustainable Research Paper.pdf
Critical Success Factors of Sustainable Research Paper.pdfCritical Success Factors of Sustainable Research Paper.pdf
Critical Success Factors of Sustainable Research Paper.pdfEngr_Emad Khan
 
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...inventionjournals
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
Effect of quality culture on building construction project in nigeria
Effect of quality culture on building construction project in nigeriaEffect of quality culture on building construction project in nigeria
Effect of quality culture on building construction project in nigeriaResearchWap
 
Cost Effective Methods in Construction Engineering
Cost Effective Methods in Construction EngineeringCost Effective Methods in Construction Engineering
Cost Effective Methods in Construction Engineeringcivejjour
 
Cost Effective Methods in Construction Engineering
Cost Effective Methods in Construction EngineeringCost Effective Methods in Construction Engineering
Cost Effective Methods in Construction Engineeringcivejjour
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 

Similar to Analysis and prediction of cost and time overrun of (20)

Building information-modeling-and-construction-projects-performance-the-effec...
Building information-modeling-and-construction-projects-performance-the-effec...Building information-modeling-and-construction-projects-performance-the-effec...
Building information-modeling-and-construction-projects-performance-the-effec...
 
Cost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfCost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdf
 
Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...
 
Projrkzni menadžment - istraživanje
Projrkzni menadžment - istraživanjeProjrkzni menadžment - istraživanje
Projrkzni menadžment - istraživanje
 
C1303032126
C1303032126C1303032126
C1303032126
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Project+Management+Evolution+to+Improve+Economic+Success+of+Infrastructure+Pr...
Project+Management+Evolution+to+Improve+Economic+Success+of+Infrastructure+Pr...Project+Management+Evolution+to+Improve+Economic+Success+of+Infrastructure+Pr...
Project+Management+Evolution+to+Improve+Economic+Success+of+Infrastructure+Pr...
 
Sustainability Indicators in Building Projects in Khartoum State during Const...
Sustainability Indicators in Building Projects in Khartoum State during Const...Sustainability Indicators in Building Projects in Khartoum State during Const...
Sustainability Indicators in Building Projects in Khartoum State during Const...
 
1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
Critical Success Factors of Sustainable Research Paper.pdf
Critical Success Factors of Sustainable Research Paper.pdfCritical Success Factors of Sustainable Research Paper.pdf
Critical Success Factors of Sustainable Research Paper.pdf
 
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
Effect of quality culture on building construction project in nigeria
Effect of quality culture on building construction project in nigeriaEffect of quality culture on building construction project in nigeria
Effect of quality culture on building construction project in nigeria
 
Cost Effective Methods in Construction Engineering
Cost Effective Methods in Construction EngineeringCost Effective Methods in Construction Engineering
Cost Effective Methods in Construction Engineering
 
Cost Effective Methods in Construction Engineering
Cost Effective Methods in Construction EngineeringCost Effective Methods in Construction Engineering
Cost Effective Methods in Construction Engineering
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 

More from Alexander Decker

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Alexander Decker
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inAlexander Decker
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesAlexander Decker
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksAlexander Decker
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dAlexander Decker
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceAlexander Decker
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifhamAlexander Decker
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaAlexander Decker
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenAlexander Decker
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksAlexander Decker
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget forAlexander Decker
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabAlexander Decker
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...Alexander Decker
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalAlexander Decker
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesAlexander Decker
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbAlexander Decker
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloudAlexander Decker
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveragedAlexander Decker
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenyaAlexander Decker
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health ofAlexander Decker
 

More from Alexander Decker (20)

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
 

Analysis and prediction of cost and time overrun of

  • 1. Developing Country Studies www.iiste.org ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol 2, No.10, 2012 Analysis And Prediction Of Cost And Time Overrun Of Millennium Development Goals (MDGS) Construction Projects In Nigeria. Edoka Augustine Ijigah Ezekiel Babatunde Ogunbode* Moshood O. Ibrahim Department Of Building, Federal University of Technology, P.M.B. 65, Minna, Niger State Nigeria. * E-mail of the corresponding author: onbodmail@yahoo.com Abstract The paper focuses on the analysis and forecast of cost and time overrun of MDGs construction projects in Nigeria. Twenty five MDGs construction projects from (2006-2009) were critically investigated and time and cost overrun of the project were studied. The Statistical Package for Social Scientists (SPSS) 19.0 version was used to analyse the variables using Paired t-test and simple regression at 95% confidence limits. The analysis was based on the adaptation of requisition method. The validity test on the efficiency of the model was highlighted using the confidence interval to enhance the application of the models. Mathematical models were developed. The findings shows that there is a significant different between the total contract sum, cost overrun, total contract duration, and time overrun for the MDGS projects. The study suggests acute need for government to engage in proactive strategic planning and approaches to keep construction project cost and time within reasonable limit for the actualization of MDGs policy of development and environmental sustainability. Keywords: Analysis and Prediction, Cost Overrun, Time Overrun, Millennium Development Goals and Construction Projects. 1. Introduction The Millennium Development Goals which are to be realized by 2015 are a set of developmental targets aimed at affecting measurable improvement in the life of the world’s poorest citizens. The goals are related to poverty reduction, gender inequality, child and material health, combating HIV/AIDS, malaria and other diseases, environmental sustainability, and international cooperation for development. (MDGs, 2010). Eboh, (2008); UNDP (2009); UN (2009) UNECA (2009) & MDGs (2010) all reports that a variety of problems have persisted, slowing the country’s growth and attainment of development objectives. These include inadequate human development, inefficient agricultural systems, weak infrastructure, lacklustre growth in the manufacturing sector, a poor policy and regulatory environment, and mismanagement and misuse of resources. The above issue propelled the United Nation General Assembly to adopt and declare the millennium development goals (MDGs), committing nations of the world to battle poverty, diseases, gender inequality, and environmental degradation and to foster a global partnership for development (Otti, 2012). Following the debt-relief grant of US$18 billion in 2005, a Virtual Poverty Fund was established to ensure that monies realised (about US$1 billion each year) from debt relief were channelled towards poverty reduction and the other MDGs. In collaboration, the federal government took both policy and institutional step towards achieving the MDGs. These include: the National Economic Empowerment and Development Strategy (NEEDS) , State Economic Empowerment and Development Strategy (SEEDS), Fiscal Responsibility Act, Medium-Term Sector Strategies (MTSSs), Medium-Term Expenditure Framework (MTEF), Nigeria Vision 20:2020, NEEDS II and 7- Point Agenda (MDGs, 2008) . Simultaneously, several states have developed their own medium-term development strategies which have been harmonised with the Vision 20:2020 National Plan and currently provides the overall (national) policy framework for the MDGs in Nigeria. The construction industry is generally responsible for the physical development or the transformation of the environment (Hillebrandt, 2000). The built environment is vital to social-economic development of a nation and its contribution to MDGS goals are crucial and a focus of any nation's economy (Ijigah, Oloruntaba & Mohn, 140
  • 2. Developing Country Studies www.iiste.org ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol 2, No.10, 2012 2012). But several finding of studies shows that the industry has reduced in its contribution to the national economy and its performance in terms of cost and time of project (Olomolaiye, 1987; Aniekwu, 1995; Adeyemi et al. 2005; Oladipo, 2006; Oladapo, 2011 & Ijigah, et al. 2012). High construction costs have been a major pointer to the malfunction of the construction industry in Nigeria today (0tti, 2012 & Ijigah et al.,2012). This has manifested in low construction activities and abandoned projects with severe consequences on the nation's socio-economic and technological development. Most construction project are being completed at costs much higher than initial estimated which indicate that initial cost estimates on construction projects can hardly be relies upon by clients (Achuenu & Kolawole, 1998; Kunya,2006; Oladipo, 2011; 0tti, 2012 & Ijigah et al. 2012). The study of Adewuyi & Anigbogu (2006) also assert the scenario in which clients are compared to pay for unbudgeted increase in projects or abandon the project out rightly. Ogunsemi (2002); Achuenu & Ujene (2006); kunya (2006) ; Otti (2012) & Ijigah et al. (2012) all submits that in the recent past, many projects are still subjected to cost and time overruns which results in claims between clients and contractors. This has also affected the MDGs projects as the study by Otti (2012) & Ijigah et al. (2012) reviewed that several of the 2006 MDGs construction projects funded still remained at different stages of completion as at June 2007 while many had not started at all. Considering the relationship between construction projects and the national Development , it becomes necessary that the cost and time overrun of MDGs construction projects be investigated as they is insufficient data to achieve a significant improvement in the lives of at least 100 million slum dwellers in Nigeria in the 2010 MDGs report. It is against this background that this study, therefore seeks to developed mathematical forecasting model for predicting cost and time overrun that are likely to arise from any MDGs construction project in Abuja Nigeria. Kunya (2006) have at different time developed similar models for predicting project variation claims of public buildings. Kunya (2006) states that the efficiency of such models is based on certain assumptions such as controllable and predictable inflating trends, availability of historical construction data and quick access to construction project information. 2. Methodology A non-probability convenience sampling method was adopted; this is a sampling method) that involves choosing from a sample that is not only accessible (Teddlie & Yu, (2007) and Collins, Onwuegbuziu & Jiao (2007) but the respondent are willing to take part in the study. This work deals with the analysis of data sourced from various contract documents of completed (MDGs) construction projects in Abuja, F.C.T. from 2006-2009. Thirty three contract documents submitted were collated from consultants, out of which eight were discarded for lack of constancy and twenty five were used for analysis (75.76%). The characteristics of the project were obtained and used to tabulate the estimated project duration, final project duration, estimated project cost and final project cost of the (MDGs) projects. The Statistical Package for Social Scientists (SPSS) 19.0 version was used to analyse the variables using Paired t-test and simple regression at 95% confidence limits. The paired t-test method of analysis compares two samples and determines the likelihood of the observed different between the samples occurring by change. The change is reported as the p-value (Kunya, 2006). A p-value close to 1 means, it is likely that the hypothesized and sample means are the same, since it is very likely that such would happen by change, if the null hypotheses of no difference exist. Regression method of analysis was adopted, where relationship between variables is determined using the method of least, squares which sicks to minimize the sum of the square of the difference between the observed values and the predicted values of the form. y = a + bx Where; y - is a dependent variable, (Time Overrun, %Time Overrun, Cost Overrun and %Cost Overrun,); x - is an independent variable (Project Duration and Project Cost?) 141
  • 3. Developing Country Studies www.iiste.org ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol 2, No.10, 2012 The choice of this model is informed by the fact that once the relationship has been determined, it can be used to mark any number of forecasts simply by inserting the value of x for which a forecast is necessary. Where change may have taken place, it is necessary to collect new set of data and recomputed the value of “a” and “b” The following equation were also used in the analysis Time overrun = actual project duration - estimated project duration Cost overrun = actual project cost - estimated project cost %cost overrun = cost overrun x100 estimated project cost %time overrun = time overrun x100 estimated project duration 3. Results and Discussion The results of the analysis for the (mdgs) construction projects studied are presented below: Table 1: Cost and Time Overrun of (MDGs) Construction Project in Abuja Estimated Actual Time % Time Estimated Final Cost Cost % Cost Project Project Overrun Overrun Cost of of Project Overrun Overrun Duration Duration Months Project (Months) (Months) N,000,000 N,000,000 N,000,000 1 12.0 17.0 5.0 41.67 4.70 6.00 1.30 27.66 2 12.0 13.5 1.5 12.50 86.40 93.50 7.10 8.22 3 24.0 18.5 6.0 27.08 21.02 25.76 4.74 22.55 4 23.0 30.5 6.5 13.04 300.00 370.00 70.00 23.30 5 15.0 20.0 5.0 33.33 30.90 40.00 9.10 29.45 6 8.0 11.5 3.5 43.75 4.74 6.84 2.10 44.30 7 18.0 25.0 7.0 38.89 62.80 89.6 26.8 42.68 8 13.0 16.0 3.0 23.08 5.70 6.10 0.40 7.02 9 11.0 12.5 1.5 13.64 402.00 503.00 101.00 25.12 10 24.0 38.0 14.0 58.33 20.67 29.23 18.56 31.74 11 12.0 10.0 2.0 16.67 78.00 89.00 11.00 14.10 12 7.0 8.5 1.5 21.43 254.00 290.00 36.00 14.17 13 24.0 28.0 4.0 16.67 60.87 50.45 10.42 17.12 14 22.0 28.0 6.0 27.23 4.50 6.70 2.20 48.89 15 12.0 15.5 3.0 25.00 24.00 27.00 3.00 12.50 142
  • 4. Developing Country Studies www.iiste.org ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol 2, No.10, 2012 16 23.0 29.5 6.5 28.26 300.00 370.00 70.00 23.33 17 17.0 24.5 7.5 44.12 320.00 358.00 38.00 11.88 18 7.0 8.0 1.0 14.29 12.00 10.00 2.00 16.67 19 24.0 36.0 12.0 50.00 17.23 22.94 5.71 33.14 20 16.0 19.0 3.0 18.75 53.30 64.10 10.80 20.26 21 21.0 27.5 6.5 30.95 48.00 62.00 14.00 29.17 22 24.0 29.0 5.0 20.83 72.60 85.50 12.90 17.77 23 9.0 13.5 4.5 50.00 4.74 5.84 1.10 23.21 24 5.0 7.0 2.0 40.00 43.70 54.80 11.10 25.40 25 24.0 29.0 5.0 20.83 58.30 72.50 14.20 24.36 Table 1 below presented the project cost and time overrun for the twenty five authenticated project studied. They are (MDGS) projects executed in Abuja between 2006-2009 and they have cost and time overrun. It shows that the maximum percentage time and cost overrun are (58.33 & 48.89) while the minimum percentage time and cost overrun are (12.50 & 7.02). This indicates that the (MDGs) projects all have cost and time overrun. The paired t- test results show significant differences of 5% level of significant between contract duration and time overrun and contract cost and cost overrun for projects considered for this study. The results are summarized in Table 2 and Table 3. A similar study by Adewuyi & Anigbogu (2006) on duration performance of universal basic education reviewed that only 69.6% of projects awarded in Nigeria were completed and the balance of 30.4% were either under construction or abandoned after 4½ years of contract award (Adewuyi & Anigbogu, 2006). The research by Otti (2012) & Ijigah et al. (2012) have shown that they is an improvement in the performance of the construction industry from 2008. These are due to better project management, improved contract method and the involvement of clients and contractors in project delivery. Table 2. Paired t-test Results of Contract Duration and Time Overrun Project Duration Time overrun Mean 16.2800 4.9000 Std. Deviation 6.58610 3.12916 Observation 25 25 Hypothesis 0 df 24 t-start 11.480 Sig. (2-tailed) 0.00 P(T<=t)one 0.00 t critical one 12.359 P(T<=t)two 0.00 t critical two 7.830 143
  • 5. Developing Country Studies www.iiste.org ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol 2, No.10, 2012 In the comparison in Table 2, p-value of 0.00 <0.05 means that there is less than 5% chance of contract time overrun to be higher than the total project duration. This shows that for this project, contract duration is always higher than the time overrun Table 3. Paired t-test Results of Contract Cost and Cost overrun Project Cost Cost Overrun Mean 91.6068 19.3412 Std. Deviation 118.77983 25.57566 Observation 25 25 Hypothesis 0 df 24 t-start 3.787 Sig. (2-tailed) 0.001 P(T<=t)one 0.001 t critical one 3.856 P(T<=t)two 0.001 t critical two 3.781 In the comparison in Table 3, p-value of 0.00 <0.05 means that there is less than 5% chance of contract time overrun to be higher than the total project duration. This shows that for this project, contract duration is always higher than the time overrun. Table 4. Regression Analysis Result (summary) of Project Duration and Time Overrun Multiple R 0.694 R Square 0.481 Adjusted R Square 0.458 Std. Error of the Estimate 2.302 Observation 25.00 6 P value = 5.5 x10 From Table 4 above, regression coefficient of 0.69 shows a positive linear relationship between the project duration and time overrun. A p value of 5.5 x106 shows a 0.0% chance of no difference between project duration and time overrun. Also from the regression analysis summary (Table 4) shows a degree of determination of 0.481 suggesting a present of negative relationship between these variables. Total regression analysis reveals the following models; y = - 0.467 + 0.330x Where; y = time overrun; x= project duration. 144
  • 6. Developing Country Studies www.iiste.org ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol 2, No.10, 2012 Table 5. Regression Analysis Result (summary) of Project Duration and Percentage (%) Time Overrun Multiple R 0.28 R Square 0.01 Adjusted R Square -0.043 Std. Error of the Estimate 13.55097 Observation 25 From Table 5 above, regression coefficient of 0.28 shows a negative linear relationship between the project duration and percentage time overrun. This shows a 0.0% chance of no difference between project duration and percentage time overrun. Also from the regression analysis summary (Table 5) shows a degree of determination of 0.01 suggesting a present of negative relationship between these variables. Total regression analysis reveals the following models; y = 28.292 + 0.057x Where; y = % time overrun; x = project duration. Table 6. Regression Analysis Result (summary) of Project cost and cost Overrun Multiple R 0.931 R Square 0.857 Adjusted R Square 0.861 Std. Error of the Estimate 9.52606 Observation 25 P value = 0.00057 From Table 6 above, regression coefficient of 0.93 shows a positive linear relationship between the project duration and time overrun. A p value of 0.00057 shows a 57% chance of no difference between project cost and cost overrun. Also from the regression analysis summary (Table 6) shows a degree of determination of 0.857 suggesting a present of high positive relationship between these variables. Total regression analysis reveals the following models; y = 0.974 + 0.200x Where; y = cost overrun; x= project cost. Table 7. Regression Analysis Result (summary) of Project Cost and Percentage (%) Cost overrun Multiple R 0.238 R Square 0.057 Adjusted R Square 0.015 Std. Error of the Estimate 10.64880 Observation 25 From Table 7 above, regression coefficient of 0.238 shows a negative linear relationship between the project and time overrun. This shows a 0.0% chance of no difference between project cost and percentage cost overrun. Also from the regression analysis summary (Table 7) shows a degree of determination of 0.057 suggesting a present of negative relationship between these variables. Total regression analysis reveals the following models; y = 25.728 - 0.21x Where; y = % cost overrun; x = project cost. 145
  • 7. Developing Country Studies www.iiste.org ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol 2, No.10, 2012 4. Conclusion The study was able to establish some average percentage of cost overruns and time overrun of Abuja MDGs construction project which are found to vary between 58.33% and 12.50% for time overrun and between 48.89% and 7.02% for cost overrun. The result of the Paired t-test carried out on time/cost of project shows that there is a significant difference between total project duration/cost and total time/cost overrun with time/cost overrun representing an increase in initial projects duration and cost. The simple regression analysis indicates that there is a positive linear relationship between these variables, which shows that total time and cost of project and time and cost overrun can be predicted from total project duration and cost within 95% confidence limits using simple regression models. Similarly from the regression analysis result, percentage (%) time overrun and percentage (%) cost overrun can also be predicted from total project cost within 95% confidence limits using the developed regression models within certain confidence intervals of regression constant. The study suggests acute need for government to engage in proactive strategic planning and approaches to keep construction project time and cost within reasonable limit for the actualization of MDGS policy of affordable shelter for its citizens. There is also the need to incorporate into tender price the expected cost and time variation as this will address cost and time overrun of construction projects hence avert the incidence of project abandonment resulting from time and cost overrun of construction projects. Reference Achuenu, E. & kolawole, J.O. (1998). “Assessment of Cost Overrun of Public Building Projects in Nigeria” Nigerian Journal of Construction Technology and Management Vol.1NO.1, pp11-15. Achuenu ,E. & Ujene, A.O. (2006). “Evaluation of Material and Labour Cost of Building Elements in Nigeria” Nigerian Journal of Construction Technology and Management Vol. 7No. 1, pp 99-110. Adewuyi, T. O. & Anigbogu, N.A.(2006). “Duration Performance of Universal Basic Education (UBE) Project in Nigeria” Nigerian Journal of Construction Technology and Management Vol.7 No.1, pp 26-38. Collins,K.M.T., Onwuegbuzie, A.J. & Jiao, Q.G.(2007). “A Mixed Methods Investigation of Mixed Methods Sampling Designs in Social and Health Science Research” Journal of Mixed Method Research, Vol. 1 No.3, pp 267-294. Eboh, E.C. (2008). Template for Tracking the Impact of SEEDS Expenditures on the MDGs. Report submitted to European Union-Support for Reforming Institutions Programme (EU-SRIP), Abuja, Nigeria. Federal Government of Nigeria. (2004). Nigeria: National Economic Empowerment and Development Strategy – NEEDS. Abuja: National Planning Commission. Hillebrandt, P. M. (2000) Economic Theory and the Construction Industry. London. Macmillan Publishers Ltd. Human Development Report Nigeria. 2008-2009: Achieving Growth with Equity. Abuja: UNDP. Ijigah, E.A.,Oloruntoba, K.. & Mohd H. R. (2012).Towards Accomplishing Millennium Development Goals (MDGs) In Abuja F.C.T Nigeria: The Project Management Consultants Roles, “International Journal of Research in Management & Technology” (IJRMT), Vol. 2, No. 4 pp.414-424, (ISSN: 2249-9563) 146
  • 8. Developing Country Studies www.iiste.org ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol 2, No.10, 2012 Kunya, S.U. (2006). Analysis and Prediction of Contract Variation Claim of Public Building Projects in North- Eastern Nigeria, Nigerian Journal of Construction Technology and Management, Vol.7 No.1, pp 86-89. Office of the Senior Special Assistant to the President on the MDGs. (2008). Mid-point Assessment of the Millennium Development Goals in Nigeria. Abuja: OSSAP-MDGs. Office of the Senior Special Assistant to the President on the MDGs. (2010). Assessment of the Millennium Development Goals in Nigeria. Abuja: Ogunsemi D. R. (2002), Cost and Time Performance of Construction Projects in South-westernNigeria. A Phd. thesis submitted to the School of Postgraduate Studies, Federal University of Technology Akure. Oladapo, A. A. (2006). The Impact of ICT on Professional Practice in the Nigerian Construction Industry. The Electronic Journal of Information Systems in Developing Countries Vol.24 No.2, pp1-19. Oladipo, F.O. & Oni, O. (2012). A Review of Selected Macroeconomic Factors Impacting Building Material Prices In Developing Countries – A Case Of Nigeria, Ethiopian Journal of Environmental Studies and Management EJESM Vol. 5 No. 2 pp. 131-137 Otti, V.I. (2012). Engineering Implication for Millennium development Goals in Revamping and Sustaining Nigeria Economy, International Journal of Engineering Research and Applications (IJERA), Vol. 2, no. 2, pp.1373-1377 ISSN: 2248-9622 Teddie, C. & Yu, F. (2007). Mixed Methods Sampling, A Typology with Examples, Journal of Mixed Methods Research Vol.1 No.1, pp 77-100. United Nations Development Programme. (2009). Human Development Report Nigeria. 2008-2009: Achieving Growth with Equity. Abuja: UNDP. United Nations Economic Commission for Africa. (2009). Assessing Progress in Africa toward the Millennium Development Goals. Addis Ababa: UNECA. United Nations. (2010). Global Millennium Development Goals 2010 Report. New York: UN. United Nations Development Programme. (2009). United Nations Economic Commission for Africa. (2009). Assessing Progress in Africa toward the Millennium Development Goals. Addis Ababa: UNECA. 147
  • 9. This academic article was published by The International Institute for Science, Technology and Education (IISTE). The IISTE is a pioneer in the Open Access Publishing service based in the U.S. and Europe. The aim of the institute is Accelerating Global Knowledge Sharing. More information about the publisher can be found in the IISTE’s homepage: http://www.iiste.org CALL FOR PAPERS The IISTE is currently hosting more than 30 peer-reviewed academic journals and collaborating with academic institutions around the world. There’s no deadline for submission. Prospective authors of IISTE journals can find the submission instruction on the following page: http://www.iiste.org/Journals/ The IISTE editorial team promises to the review and publish all the qualified submissions in a fast manner. All the journals articles are available online to the readers all over the world without financial, legal, or technical barriers other than those inseparable from gaining access to the internet itself. Printed version of the journals is also available upon request of readers and authors. IISTE Knowledge Sharing Partners EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open Archives Harvester, Bielefeld Academic Search Engine, Elektronische Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial Library , NewJour, Google Scholar