The Challenges of Construction-
There are three components of project
a. cost of the project (Budget)
b. Quantity and quality of construction facilities (Scope)
c. Time of completion of the project (Schedule)
The job of a project manager is to establish the balance between the aforementioned three
components of the project. In other ways, challenge in construction is to have a Trade-off among
cost, time and quality. Cost, time and quality depend upon various factors which are shown in
the figure 3 below.
Following main parties are involved in the construction
a. Owner
b. Designer
c. Contractors
The relation between these is shown in the figure 2 below. The challenge of project manager is to
have coordination among the owner, designer and contractor. There is only one goal of the
project to have construction facility. All the three should work as a team in amenable manner.
Among the various operations during the project, planning, design and construction are
prominent activity. One of the challenge of the project manage is to establish the coordination
and control between planning, design and construction. Hence these depend upon many factors.
These features are enumerated in the diagram.
In the civil engineering project,
depending upon the nature of the work,
one has to accomplish some of the
activity. In civil engineering project, the
type of management involved are
a. Functional management
b. Project management
The functional management involve in the
coordination of repeated work of various
nature whereas project management is the organization of one fine work. Actually in civil
engineering project, both type of management are followed.
Civil engineers in construction industry start their life
as so called site engineers.
There are various jobs to be carried out at the site.
In the diagram we have shown the value of the job to
be carried out and the learning requirements of a
construction engineer.
The diagram also shows the principles behind these
activities.
The purpose of the table is to give an overview of what
a construction engineer needs to know.
We shall call the group, which is involved with construction as contractor. In the civil
engineering project, in a narrow sense, ideas of owners is translated into engineering. Creation
by designer/architect and is given real force by contractor. We have a three party system as –
This is the simple
model for the party
involved in the civil
engineering
construction. These
three bodies are having
contradictory
objectives, but they
work in non-adversery
conditions and should
help each other.
In the civil engineering
project, major
activities are Design and Construction and all the activity and process are to help them.
 Thus, the persons involved in design are involved with the
mechanics and properties of materials. We shall call the group
of people involved in designs as designer.
 A designer may be a person or a group of persons or a
company.
 Other engineering creation of designer has to translate into
the real facilities. This is process of construction, which is
shown in the diagram below.
 During the life cycle of projects, various parties
come together and work to fulfill objective of the
project.
 We need to know how these parties are
communicating to each other and what ways are
they communicating among themselves.
 The first point is called delivery methods or
contractual relations, the second issues are
termed as type of contracts.
 The flow of information between various parties
involved takes place in many ways. i.e . there are
different approaches used to organize the project
team to manage the entire design and
construction process.
 Thus we shall discuss various delivery methods.
 The relations existing between various parties
also vary in terms of monetary payment and
goods as well as service delivery.
 These points we shall discuss for type of
contracts.
 Although the exact nature of arrangement in terms of
reporting sub reporting getting feed-back, payments
of execution is unique to the particular project, these
discussions will help us in understanding particular
project team arrangement.
 Also, we can make our own arrangement depending
upon the local nature of the project.
 From the degree of freedom point of view we can
classify the project as:
 Public project.
 Private project
Public project:
 Public project consists of primary infrastructure project.
 Public projects work on fixed sets of guideline fixed by
particular department.
 For example in Pakistan, Public Works Departments (PWD)
works with their own rules. These are called PWD manuals.
 These manuals are well documented and describe what to do
when and how.
 Deviation from these documents needs special permission
from apex body depending on the nature of change or
sometimes there is almost no scope of change.
 Similarly each state government maintains its own
contract rules to execute the work.
 Like in Punjab Public works departments has its own
way of doing the things.
 Similarly Pakistan railways execute the works based on
guidelines fixed by the department.
 Similar situation are existing in other countries. As for
example, US transport department does the work
according to its own document.
 But, there are many points common between their
contractual arrangement as well as contractual
agreements.
 Contracts are selected based on competition
bidding.
 In our country, public project mainly works on
minimum cost bidding system.
 In recent year, much effort has been paid to
improve the low cost bidding system by
introducing technical bidding and price
bidding separately.
 Private project:
 There are more flexibilities in the private project.
 Depending on the nature of the project, the owner or project manager can
arrange the project team.
 Whom to select, how to select and what kind of information exchange
systems will exists between various project team members is dependent
on the owner.
 Due to these natures, various forms of delivery methods have developed
in practice.
 Owner select the designer or contractor based on the quality and
reputation of the contractor plus the negotiated money or competition
bidding.
 We are going to talk about how different members of
project team gets organized during the life cycle of the
project or in the process of design and construction in
particular, or life cycle of project.
 The different approaches are called Delivery methods.
Traditional Methods
Design- construct
Project management method
Traditional Method:
 In this method, owner acts as overall coordinator of the project.
 He engages a designer or design form to design the facilities and
also prepare complete set of contract documents.
 With complete set of contract documents, owner employs
contractor either through negotiation or competitive bid.

 The contractor hired is totally responsible for the delivery of the
project.
 The designer may employ other designer to do the specific work.
Such as many designer takes help of other team to do the
electrical,. mechanical design in the building project and prepare
the structural design in- house.
 The main designer works as a coordinator of the
design-process.
 Similarly, the contractor may subcontract out some
job to subcontractor.
 These subcontractors will be directly reporting to the
main contractor.
 There is no formal agreement between contractor
and designer.
 Owner himself oversees the quality control.
Sometimes designer may get involved in overseeing
construction work depending upon the owner need.
 Thus we can see, for large project, owner needs
to maintain an engineering department to hire
designer and contractor and oversees the work.
 There are many variations of these
arrangements.
 Owner may have their own design group and
hires only designer for specific jobs or owner
can subcontract the jobs himself and oversees
the project, such as award the contract of piling
for one company and superstructure to other
company.
 A typical government organization in
Pakistan such as
 Pakistan Public Works Department
(PWD),
 Irrigation department works,
 Communication and works department,
 Public health engineering department,
etc works with this pattern.
 Advantage:
 As the owner receives complete set of drawing and specification of the
work, he gets the fixed price of the project.
 He can award the contract in any type of contract; he will have good idea
of the cost of project.

 This system is followed in public sector project.
 Owner, designer, contractor works in the fixed frame work. They might be
working many projects.
 Generally well-documentations are available for different process. PWD
maintains well documented procedure.
 Competitive bidding is easy to implement as complete set of contract
document is available before construction starts.
 Owner need not to worry about day to day activity of the project. He gets
involved only at the specific points.
 Disadvantage:
 Contractors and subcontractors have no input in the design.
 Material or methods specified may not be available or
contractors have knowledge of efficient methods and
materials.
 It is difficult to have overlap between design and construction
phase. So fast tract construction may not be possible.
 Sometimes there may exist different interpretations of
contract document by owner and contractor.
 The change in the methods or material of construction may
give rise to conflict. Unforeseen changes are difficult to
implement.
Design-Construct
 In this method of delivery, design and construction is carried
out by the same company.
 The company may be a single unit or joint venture of two
companies or more than two companies.
 A single company can take a job for design and construction,
but the company sub-contract or contract the construction,
but engaged himself in the management of construction.
 There are different variations available for this mode of
delivery.
 But common point is that the same company takes the job
from conceptual design phase to construction and
implementation..
 Advantage:
 In this method of delivery, designers get benefit of
the input from the contractor. Thus quality of
design improves.
 Due to good coordination between design and
construction phase, project duration can be
decreased.
 Scope of constructability analysis and value
engineering is facilitated.
 Unforeseen changes can be easily incorporated and
scope of dispute doesn't arise.
 Disadvantage:
 Price of the constructed facility is not known before the construction
starts.
 Quality gets sacrificed if project is awarded as fixed price and
design construct cost is in adverse situation.
 In the case of unit price contract, inefficient form may increase the
total cost of construction.
 Owner is not aware of the construction and design. This lack of
knowledge may be handicapped during maintenance phase.
 In the traditional form, owner monitors the quality of conformance
with the design document. But in design-construct method of
delivery, there is no standard for the owner to check and monitor.
 This arrangement doesn't guaranteed the best possible price.
 Project Management Method
There are many variations of this mode of delivery.
Some of these variations are program management;
construction management, professional construction
management.
In this method of delivery, owner hires a construction
management firm at start of the project and involves them in the
project from conceptual design through implementation.
The degree of involvement of the construction management
firm depends upon the expertise and requirement of the owner.
Owner may involve the management firm to select designer,
coordinate the work between designer and contractor, monitor
the constructions. A typical arrangement is shown in the figure
below.
 Advantages :
 It establishes the good communication between design and construction
together with the owner awareness and monitoring.
 Cooperation between different team members increases the value
engineering.
 Designer and contractor can agree on the same coordinated schedules.
 Many time, owner is directly involved with subcontractor, thus, getting
benefit of competition in terms of price.
 Unforeseen changes are easy to implement.
 Disadvantages:
 Irresponsiveness of any team member can spoil the coordination.
 Requires owner knowledge about project management.
 Risks involved during the execution of project is high.
 A typical relation is shown in the
figure below. The ways fees are paid
to contractor or designer depend up
the type of contract,
 It may be unit price, percent of cost
or lump-sum etc. depending on the
nature and agreement in the project.
 Explain Advantages / Disadvantages of
Traditional Methods
Design- construct
Project management method
 In Tabular Form
End of Lecture

More Related Content

Similar to lect# 3.pptx

Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014SHKLaw
 
early morning retirement center
early morning retirement centerearly morning retirement center
early morning retirement centerSAIFULLAH MAHMUD
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916George Wilkinson
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Project management final report
Project management final reportProject management final report
Project management final reportSANKET SENAPATI
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsConstruction in Focus
 
Project management final report.By- SANKET SENAPATI
Project management final report.By- SANKET SENAPATI Project management final report.By- SANKET SENAPATI
Project management final report.By- SANKET SENAPATI SANKET SENAPATI
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxMBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxAASTHA76
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
The tomorrow company power point by aung thu
The tomorrow company power point by aung thuThe tomorrow company power point by aung thu
The tomorrow company power point by aung thuSAIFULLAH MAHMUD
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement methodhiewliming
 
Vetting of cost estimates for an underconstruction nh project
Vetting of cost estimates for an underconstruction nh projectVetting of cost estimates for an underconstruction nh project
Vetting of cost estimates for an underconstruction nh projectSandeep Yadav
 
10 lecture project scheduling 2
10 lecture project scheduling 210 lecture project scheduling 2
10 lecture project scheduling 2Ahmad Basim Hamza
 

Similar to lect# 3.pptx (20)

Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014
 
early morning retirement center
early morning retirement centerearly morning retirement center
early morning retirement center
 
Purpose
PurposePurpose
Purpose
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Project contracts
Project contractsProject contracts
Project contracts
 
Pp report
Pp reportPp report
Pp report
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Project management final report
Project management final reportProject management final report
Project management final report
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery models
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
 
Project management final report.By- SANKET SENAPATI
Project management final report.By- SANKET SENAPATI Project management final report.By- SANKET SENAPATI
Project management final report.By- SANKET SENAPATI
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Lec 1 (2).pdf
Lec 1 (2).pdfLec 1 (2).pdf
Lec 1 (2).pdf
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxMBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
The tomorrow company power point by aung thu
The tomorrow company power point by aung thuThe tomorrow company power point by aung thu
The tomorrow company power point by aung thu
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
Vetting of cost estimates for an underconstruction nh project
Vetting of cost estimates for an underconstruction nh projectVetting of cost estimates for an underconstruction nh project
Vetting of cost estimates for an underconstruction nh project
 
10 lecture project scheduling 2
10 lecture project scheduling 210 lecture project scheduling 2
10 lecture project scheduling 2
 

Recently uploaded

Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified Binance Account
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Omaninstagramfab782445
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfDerekIwanaka1
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Falcon Invoice Discounting
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateCannaBusinessPlans
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challengeshemanthkumar470700
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSpanmisemningshen123
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingNauman Safdar
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 

Recently uploaded (20)

Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdf
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 

lect# 3.pptx

  • 1.
  • 2. The Challenges of Construction- There are three components of project a. cost of the project (Budget) b. Quantity and quality of construction facilities (Scope) c. Time of completion of the project (Schedule) The job of a project manager is to establish the balance between the aforementioned three components of the project. In other ways, challenge in construction is to have a Trade-off among cost, time and quality. Cost, time and quality depend upon various factors which are shown in the figure 3 below. Following main parties are involved in the construction a. Owner b. Designer c. Contractors The relation between these is shown in the figure 2 below. The challenge of project manager is to have coordination among the owner, designer and contractor. There is only one goal of the project to have construction facility. All the three should work as a team in amenable manner. Among the various operations during the project, planning, design and construction are prominent activity. One of the challenge of the project manage is to establish the coordination and control between planning, design and construction. Hence these depend upon many factors. These features are enumerated in the diagram.
  • 3. In the civil engineering project, depending upon the nature of the work, one has to accomplish some of the activity. In civil engineering project, the type of management involved are a. Functional management b. Project management The functional management involve in the coordination of repeated work of various nature whereas project management is the organization of one fine work. Actually in civil engineering project, both type of management are followed.
  • 4.
  • 5. Civil engineers in construction industry start their life as so called site engineers. There are various jobs to be carried out at the site. In the diagram we have shown the value of the job to be carried out and the learning requirements of a construction engineer. The diagram also shows the principles behind these activities. The purpose of the table is to give an overview of what a construction engineer needs to know.
  • 6.
  • 7. We shall call the group, which is involved with construction as contractor. In the civil engineering project, in a narrow sense, ideas of owners is translated into engineering. Creation by designer/architect and is given real force by contractor. We have a three party system as – This is the simple model for the party involved in the civil engineering construction. These three bodies are having contradictory objectives, but they work in non-adversery conditions and should help each other. In the civil engineering project, major activities are Design and Construction and all the activity and process are to help them.
  • 8.  Thus, the persons involved in design are involved with the mechanics and properties of materials. We shall call the group of people involved in designs as designer.  A designer may be a person or a group of persons or a company.  Other engineering creation of designer has to translate into the real facilities. This is process of construction, which is shown in the diagram below.
  • 9.
  • 10.  During the life cycle of projects, various parties come together and work to fulfill objective of the project.  We need to know how these parties are communicating to each other and what ways are they communicating among themselves.  The first point is called delivery methods or contractual relations, the second issues are termed as type of contracts.
  • 11.  The flow of information between various parties involved takes place in many ways. i.e . there are different approaches used to organize the project team to manage the entire design and construction process.  Thus we shall discuss various delivery methods.  The relations existing between various parties also vary in terms of monetary payment and goods as well as service delivery.  These points we shall discuss for type of contracts.
  • 12.  Although the exact nature of arrangement in terms of reporting sub reporting getting feed-back, payments of execution is unique to the particular project, these discussions will help us in understanding particular project team arrangement.  Also, we can make our own arrangement depending upon the local nature of the project.  From the degree of freedom point of view we can classify the project as:  Public project.  Private project
  • 13. Public project:  Public project consists of primary infrastructure project.  Public projects work on fixed sets of guideline fixed by particular department.  For example in Pakistan, Public Works Departments (PWD) works with their own rules. These are called PWD manuals.  These manuals are well documented and describe what to do when and how.  Deviation from these documents needs special permission from apex body depending on the nature of change or sometimes there is almost no scope of change.
  • 14.  Similarly each state government maintains its own contract rules to execute the work.  Like in Punjab Public works departments has its own way of doing the things.  Similarly Pakistan railways execute the works based on guidelines fixed by the department.  Similar situation are existing in other countries. As for example, US transport department does the work according to its own document.  But, there are many points common between their contractual arrangement as well as contractual agreements.
  • 15.  Contracts are selected based on competition bidding.  In our country, public project mainly works on minimum cost bidding system.  In recent year, much effort has been paid to improve the low cost bidding system by introducing technical bidding and price bidding separately.
  • 16.  Private project:  There are more flexibilities in the private project.  Depending on the nature of the project, the owner or project manager can arrange the project team.  Whom to select, how to select and what kind of information exchange systems will exists between various project team members is dependent on the owner.  Due to these natures, various forms of delivery methods have developed in practice.  Owner select the designer or contractor based on the quality and reputation of the contractor plus the negotiated money or competition bidding.
  • 17.  We are going to talk about how different members of project team gets organized during the life cycle of the project or in the process of design and construction in particular, or life cycle of project.  The different approaches are called Delivery methods. Traditional Methods Design- construct Project management method
  • 18. Traditional Method:  In this method, owner acts as overall coordinator of the project.  He engages a designer or design form to design the facilities and also prepare complete set of contract documents.  With complete set of contract documents, owner employs contractor either through negotiation or competitive bid.   The contractor hired is totally responsible for the delivery of the project.  The designer may employ other designer to do the specific work. Such as many designer takes help of other team to do the electrical,. mechanical design in the building project and prepare the structural design in- house.
  • 19.  The main designer works as a coordinator of the design-process.  Similarly, the contractor may subcontract out some job to subcontractor.  These subcontractors will be directly reporting to the main contractor.  There is no formal agreement between contractor and designer.  Owner himself oversees the quality control. Sometimes designer may get involved in overseeing construction work depending upon the owner need.
  • 20.  Thus we can see, for large project, owner needs to maintain an engineering department to hire designer and contractor and oversees the work.  There are many variations of these arrangements.  Owner may have their own design group and hires only designer for specific jobs or owner can subcontract the jobs himself and oversees the project, such as award the contract of piling for one company and superstructure to other company.
  • 21.  A typical government organization in Pakistan such as  Pakistan Public Works Department (PWD),  Irrigation department works,  Communication and works department,  Public health engineering department, etc works with this pattern.
  • 22.
  • 23.  Advantage:  As the owner receives complete set of drawing and specification of the work, he gets the fixed price of the project.  He can award the contract in any type of contract; he will have good idea of the cost of project.   This system is followed in public sector project.  Owner, designer, contractor works in the fixed frame work. They might be working many projects.  Generally well-documentations are available for different process. PWD maintains well documented procedure.  Competitive bidding is easy to implement as complete set of contract document is available before construction starts.  Owner need not to worry about day to day activity of the project. He gets involved only at the specific points.
  • 24.  Disadvantage:  Contractors and subcontractors have no input in the design.  Material or methods specified may not be available or contractors have knowledge of efficient methods and materials.  It is difficult to have overlap between design and construction phase. So fast tract construction may not be possible.  Sometimes there may exist different interpretations of contract document by owner and contractor.  The change in the methods or material of construction may give rise to conflict. Unforeseen changes are difficult to implement.
  • 25. Design-Construct  In this method of delivery, design and construction is carried out by the same company.  The company may be a single unit or joint venture of two companies or more than two companies.  A single company can take a job for design and construction, but the company sub-contract or contract the construction, but engaged himself in the management of construction.  There are different variations available for this mode of delivery.  But common point is that the same company takes the job from conceptual design phase to construction and implementation..
  • 26.
  • 27.  Advantage:  In this method of delivery, designers get benefit of the input from the contractor. Thus quality of design improves.  Due to good coordination between design and construction phase, project duration can be decreased.  Scope of constructability analysis and value engineering is facilitated.  Unforeseen changes can be easily incorporated and scope of dispute doesn't arise.
  • 28.  Disadvantage:  Price of the constructed facility is not known before the construction starts.  Quality gets sacrificed if project is awarded as fixed price and design construct cost is in adverse situation.  In the case of unit price contract, inefficient form may increase the total cost of construction.  Owner is not aware of the construction and design. This lack of knowledge may be handicapped during maintenance phase.  In the traditional form, owner monitors the quality of conformance with the design document. But in design-construct method of delivery, there is no standard for the owner to check and monitor.  This arrangement doesn't guaranteed the best possible price.
  • 29.  Project Management Method There are many variations of this mode of delivery. Some of these variations are program management; construction management, professional construction management. In this method of delivery, owner hires a construction management firm at start of the project and involves them in the project from conceptual design through implementation. The degree of involvement of the construction management firm depends upon the expertise and requirement of the owner. Owner may involve the management firm to select designer, coordinate the work between designer and contractor, monitor the constructions. A typical arrangement is shown in the figure below.
  • 30.
  • 31.  Advantages :  It establishes the good communication between design and construction together with the owner awareness and monitoring.  Cooperation between different team members increases the value engineering.  Designer and contractor can agree on the same coordinated schedules.  Many time, owner is directly involved with subcontractor, thus, getting benefit of competition in terms of price.  Unforeseen changes are easy to implement.  Disadvantages:  Irresponsiveness of any team member can spoil the coordination.  Requires owner knowledge about project management.  Risks involved during the execution of project is high.
  • 32.  A typical relation is shown in the figure below. The ways fees are paid to contractor or designer depend up the type of contract,  It may be unit price, percent of cost or lump-sum etc. depending on the nature and agreement in the project.
  • 33.
  • 34.  Explain Advantages / Disadvantages of Traditional Methods Design- construct Project management method  In Tabular Form