SlideShare a Scribd company logo
1 of 19
Download to read offline
18th Mac 2019
MARRIOT HOTEL, PUTRAJAYA
Azah Ahmad
Director of Renewable Energy Technology (RET) Division
Sustainable Energy Development Authority (SEDA) Malaysia
BRIEFING ON THE NEW NEM, INTRODUCTION TO SELF-CONSUMPTION (SELCO) AND
RPVI DIRECTORY APPLICATION
2
Regulator Implementing Agency
Distribution Licensee
NEM Participants
NEM Implementation
Domestic Commercial Industrial
Agriculture
NEM Concept
NEM Calculation
Net Charge Amount (RM) = (Energy Imported from Distribution Licensee* x GazettedTariff) – (Energy Exported to
Distribution Licensee x Gazetted Tariff)
*Energy imported is subjected to SST, KWTBB, ICPT, where applicable
Note: 1 kWh exported to the grid will be offset against 1kWh consumed from the grid with the gazetted tariff. The export charges are charged
in descending order (start from the highest tariff rate charged on the applicable month)
NEM Statistic: Approved & Commissioned as of Feb 2019
Approved and NEM Commencement Date (NEMCD)
Category
(Peninsular
Malaysia)
Approved NEM Commencement Date (NEMCD)
(Completed)
Installed Capacity
(kWp)
No. of Applications Installed Capacity (kWp) No. of Applications
Domestic 2,747.48 391 1,328.64 179
Commercial 11,139.10 143 3,616.63 55
Industrial 20,639.60 87 4,931.48 26
Total 34,526.18 621 9,876.75 260
Note:
1. Implementations - 12 months from approval.
2. NEMCD- contract signed, a copy to SEDA, to upload in the e-NEM system.
6
 Quota allocation will be based on first-come first-served basis;
 Quota applied in MWac;
NEM Available Quota
Quota Allocation
Location Peninsular Malaysia
Year 2017 - 2020
Quota Allocated *Quota Taken *Quota Balance
Category of
Consumers
Domestic/Residential,
MWp
50 3 47
Agriculture, MWac 450 35 415
Commercial, MWac
Industrial, MWac
Total, MWp 500 38 462
* As of 13th March 2019
7
 NEM Assessment Study (NEMAS) report is required prior to NEM application to SEDA Malaysia;
 The studies shall be conducted by TNB or its appointed consultant to establish the technical and safety
requirements and determine the feasibility of connection.
NEM Assessment Study (NEMAS)
Installed Capacity Study Required Fee of Study (RM)
1-72 kW No -
>72 kW - 180 kW Yes RM1,000.00
>180 kW - 425 kW Yes RM5,000.00
>425 kW - 1 MW Yes RM8,000.00
>1 MW - 2 MW Yes RM15,000.00
>2 MW - 5 MW Yes RM20,000.00
>5 MW - 10 MW Yes RM30,000.00
>10 MW - 30 MW Yes RM40,000.00
Note: Study period = 30 days
NEM Contractor
Duration required
NEM approval
(3 + 7 working
days)
NEMAS Report
(30 days)
+ pre-conditioning
3 weeks
NEMAS (>72kW)
Application
NEM application
Procurement,
installation & apply
Public Generation
License
Installation
completed &
request for
NEM meter
TNB meter replacement
& NEM Contract
(TNB Kawasan)
Testing &
Commissioning
and project
completed
4 - 7 weeks 2 weeks NEM Guideline maximum 12 months
Public Generation
License (>72kW)
(3 months)
How to Apply? Process Flowchart
Note: NEMAS - NEM Assessment Study
9
 A mechanism where an eligible consumer installs a solar PV system
entirely for own use and in the event of excess of generation, the
energy is not allowed to be exported to the grid
 Issuer of SelCo Guidelines: Suruhanjaya Tenaga
Self-Consumption (SelCo)
10
 Eligibility
An individual or commercial premise consumer
 Capacity Limit
a) stand-alone system (off-grid) - no capacity limit
b) non-stand-alone system (grid-connected) - less than 75% of the maximum demand of the
consumer’s existing installation.
 Connection Requirements
To ensure there is no electricity generation export to the grid. Clause 4.7 : “For self-consumption
purposes, the consumer and registered Electrical Contractor are responsible to ensure there is no
electricity generation export to the grid..”
 Power System Study (PSS)
Power System Study (PSS) for the solar PV system with a capacity of 425 kWp and above.
 Registration of the Installation with the Distribution Licensee
The consumer of the solar PV system is required to register the installation with the DL
 Licensing requirements
For solar PV system installation above 24kW for single phase and 72kW for three phase, any person
who uses, works or operates the installation shall require a license.
SelCo Requirements
Any investors who provide Solar Power
Purchase Agreement (PPA) or Solar
Leasing services to NEM customers
REGISTERED SOLAR PV INVESTOR (RPVI)
RPVI Directory
RPVI Directory :
• Open from 2nd January 2019
• Hosted & managed by SEDA Malaysia
• A pool of both local and foreign investors be
registered to provide/serve as a reference to
interested buyers/clients.
• Serve as a checking mechanism in terms of
foreign participation in the NEM
programme.
• Total approved : 20 RPVIs (as of 18 Mac 2019)
SEDA Malaysia Portal
Foreign Company Local Company
solar PV projects of above 250kW only solar PV projects of all Capacity
 Companies must be incorporated in Malaysia;
 Minimum paid-up capital of at least RM10 million;
 minimum 80% of local employment (based on
company’s organization chart)
 has 100% local Engineering, Procurement and
Construction (EPC) by appointing a Registered PV Solar
Service Provider with SEDA Malaysia
 Companies must be incorporated in Malaysia;
 minimum paid-up capital of at least RM1million;
 Project EPC can be carried out by themselves or
awarded to the Registered PV Service Provider (RPVSP)
with SEDA Malaysia;
 Companies can be a Registered PV Service Provider with
SEDA;
 Registration and/or annual fees: USD2,500.00, to be
renewed annually
 Registration and/or annual fees: RM3,000.00, to be
renewed annually
Note; checking mechanism will be conducted during project implementation to ensure compliance failing which, de-listing in the directory
RPVI Requirements
Check RPVI
requirements
Online submission & Terms and Conditions compliance
https://services.seda.gov.my/rpvi/rpvi/login
Review and approval process
(RPVI’s Committee Meeting)
Registration & Annual
Fee payment
RPVI Certificate & listed in
RPVI Directory
Local or Foreign Investor
RM3,000 (local) and USD2,500 (foreign)
Monthly meeting
How to Apply? Process Flowchart
RPVI Business Model
SOLAR POWER PURCHASE AGREEMENT (PPA) OR SOLAR LEASING SERVICES
SOLAR
PPA
Payment in Energy (RM/kWh)
Customers pay based on per kWh for power generated from PV system
SOLAR
LEASING/
HIRE
PURCHASE
Fixed Monthly payment (RM)
Customers pay a fixed amount monthly in return for the use of the PV system and the system will be owned by
consumer after lease period ends
Method of Payment
TNB does the billing, collection & remittance of payment by
customers to RPVI in return for a service fee (2sen/kWh).
Direct payment with solar investor/lessor Supply Agreement for Renewable Energy (SARE)
OR
RPVI receive payment from customer directly
17
For further enquiries, please contact:
SEDA Malaysia
Galeria PjH, Level 9
Jalan P4W, Persiaran Perdana,
Presint 4, 62100 Putrajaya
T: +603 – 8870 5824
Tel: +6088-252101/251462
E: NEM@seda.gov.my
W: www.seda.gov.my
RENEWABLE ENERGY PROGRAMMES IN MALAYSIA
Purchase Mode via Outright Purchase

More Related Content

What's hot

Energy Management PowerPoint Presentation Slides
Energy Management PowerPoint Presentation SlidesEnergy Management PowerPoint Presentation Slides
Energy Management PowerPoint Presentation SlidesSlideTeam
 
Energy Management functional areas
Energy Management functional areasEnergy Management functional areas
Energy Management functional areasalnaidu305
 
Solar power integration with grid
Solar power integration with gridSolar power integration with grid
Solar power integration with gridashishant
 
Assessment of Photovoltaic Module Failures in the Field
Assessment of Photovoltaic Module Failures in the FieldAssessment of Photovoltaic Module Failures in the Field
Assessment of Photovoltaic Module Failures in the FieldLeonardo ENERGY
 
Industrial energy efficiency techniques and energy management (1)
Industrial energy efficiency techniques and energy management (1)Industrial energy efficiency techniques and energy management (1)
Industrial energy efficiency techniques and energy management (1)Anish Maman
 
ISO 50001 Energy Management Presentation
ISO 50001 Energy Management PresentationISO 50001 Energy Management Presentation
ISO 50001 Energy Management PresentationCertification Europe
 
Financial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantFinancial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantDr Naim R Kidwai
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 
Overview on iso 50001 energy management system
Overview on iso 50001 energy management systemOverview on iso 50001 energy management system
Overview on iso 50001 energy management systemiso50001consultant
 
DEPLOYING NORTH AMERICA’S LARGEST 2ND LIFE BATTERY STORAGE PROJECT
DEPLOYING NORTH AMERICA’S LARGEST 2ND LIFE BATTERY STORAGE PROJECTDEPLOYING NORTH AMERICA’S LARGEST 2ND LIFE BATTERY STORAGE PROJECT
DEPLOYING NORTH AMERICA’S LARGEST 2ND LIFE BATTERY STORAGE PROJECTDesignTeam8
 
ISO 50001 & Energy Management System (EMS)
ISO 50001 & Energy Management System (EMS)ISO 50001 & Energy Management System (EMS)
ISO 50001 & Energy Management System (EMS)TecnoVeritas
 
20190522_近期新加坡能源相關政策探討
20190522_近期新加坡能源相關政策探討20190522_近期新加坡能源相關政策探討
20190522_近期新加坡能源相關政策探討懂能源團隊
 
Renewable energy projects in jordan
Renewable energy projects in jordanRenewable energy projects in jordan
Renewable energy projects in jordanRCREEE
 
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)Asian Paint Bangladesh Ltd
 
DOE Efficiency Enhancing Solar Downconverting Phosphor Layer
DOE Efficiency Enhancing Solar Downconverting Phosphor LayerDOE Efficiency Enhancing Solar Downconverting Phosphor Layer
DOE Efficiency Enhancing Solar Downconverting Phosphor Layerjeep82cj
 

What's hot (20)

Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18
 
Energy Management PowerPoint Presentation Slides
Energy Management PowerPoint Presentation SlidesEnergy Management PowerPoint Presentation Slides
Energy Management PowerPoint Presentation Slides
 
Energy Management functional areas
Energy Management functional areasEnergy Management functional areas
Energy Management functional areas
 
Solar power integration with grid
Solar power integration with gridSolar power integration with grid
Solar power integration with grid
 
Accounting Question Anaysis ICAB KL
Accounting Question Anaysis ICAB KLAccounting Question Anaysis ICAB KL
Accounting Question Anaysis ICAB KL
 
Assessment of Photovoltaic Module Failures in the Field
Assessment of Photovoltaic Module Failures in the FieldAssessment of Photovoltaic Module Failures in the Field
Assessment of Photovoltaic Module Failures in the Field
 
Industrial energy efficiency techniques and energy management (1)
Industrial energy efficiency techniques and energy management (1)Industrial energy efficiency techniques and energy management (1)
Industrial energy efficiency techniques and energy management (1)
 
ISO 50001 Energy Management Presentation
ISO 50001 Energy Management PresentationISO 50001 Energy Management Presentation
ISO 50001 Energy Management Presentation
 
Guide to Solar Project Implementation
Guide to Solar Project ImplementationGuide to Solar Project Implementation
Guide to Solar Project Implementation
 
Financial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantFinancial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plant
 
ISO 9001改版的五十道問題 part2
ISO 9001改版的五十道問題 part2ISO 9001改版的五十道問題 part2
ISO 9001改版的五十道問題 part2
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 
Overview on iso 50001 energy management system
Overview on iso 50001 energy management systemOverview on iso 50001 energy management system
Overview on iso 50001 energy management system
 
DEPLOYING NORTH AMERICA’S LARGEST 2ND LIFE BATTERY STORAGE PROJECT
DEPLOYING NORTH AMERICA’S LARGEST 2ND LIFE BATTERY STORAGE PROJECTDEPLOYING NORTH AMERICA’S LARGEST 2ND LIFE BATTERY STORAGE PROJECT
DEPLOYING NORTH AMERICA’S LARGEST 2ND LIFE BATTERY STORAGE PROJECT
 
ISO 50001 & Energy Management System (EMS)
ISO 50001 & Energy Management System (EMS)ISO 50001 & Energy Management System (EMS)
ISO 50001 & Energy Management System (EMS)
 
20190522_近期新加坡能源相關政策探討
20190522_近期新加坡能源相關政策探討20190522_近期新加坡能源相關政策探討
20190522_近期新加坡能源相關政策探討
 
Renewable energy projects in jordan
Renewable energy projects in jordanRenewable energy projects in jordan
Renewable energy projects in jordan
 
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
 
영문=10mw. fiji
영문=10mw. fiji영문=10mw. fiji
영문=10mw. fiji
 
DOE Efficiency Enhancing Solar Downconverting Phosphor Layer
DOE Efficiency Enhancing Solar Downconverting Phosphor LayerDOE Efficiency Enhancing Solar Downconverting Phosphor Layer
DOE Efficiency Enhancing Solar Downconverting Phosphor Layer
 

Similar to Awareness Briefing on NEM, RPVI and Sel-Co.pdf

Energy audit conditional grant
Energy audit conditional grantEnergy audit conditional grant
Energy audit conditional grantSteve Lojuntin
 
Summary of SECI Tranche III - 1200 MW Hybrid Wind Solar
Summary of SECI Tranche III - 1200 MW Hybrid Wind SolarSummary of SECI Tranche III - 1200 MW Hybrid Wind Solar
Summary of SECI Tranche III - 1200 MW Hybrid Wind SolarPratap Malempati
 
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerRf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerPratap Malempati
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012rupeshsingh_1
 
PIPPA's Perspective on Challenges and Opportunities in Scaling Renewable Ener...
PIPPA's Perspective on Challenges and Opportunities in Scaling Renewable Ener...PIPPA's Perspective on Challenges and Opportunities in Scaling Renewable Ener...
PIPPA's Perspective on Challenges and Opportunities in Scaling Renewable Ener...OECD Environment
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...OECD Environment
 
RENEWABLE ENERGY SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
RENEWABLE ENERGY  SECTOR CONSTRAINTS,SOLUTIONS AND FINANCINGRENEWABLE ENERGY  SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
RENEWABLE ENERGY SECTOR CONSTRAINTS,SOLUTIONS AND FINANCINGNigeria Alternative Energy Expo
 
200 MW Solar Projects Investor's, Developer's Meet - KERALA
200 MW Solar Projects Investor's, Developer's Meet - KERALA200 MW Solar Projects Investor's, Developer's Meet - KERALA
200 MW Solar Projects Investor's, Developer's Meet - KERALATahnoon Elahi
 
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...Harish Sharma
 
Philippines | Jun-16 | PHILIPPINE RENEWABLE ENERGY SITUATIONER
Philippines | Jun-16 | PHILIPPINE RENEWABLE ENERGY SITUATIONERPhilippines | Jun-16 | PHILIPPINE RENEWABLE ENERGY SITUATIONER
Philippines | Jun-16 | PHILIPPINE RENEWABLE ENERGY SITUATIONERSmart Villages
 
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS Harish Sharma
 
REC a market ready for take-off
REC   a market ready for take-offREC   a market ready for take-off
REC a market ready for take-offAnuj Kaushik
 
Rsm GC Advisory Renewable Purchase Obligation (RPO) & Renewable Energy Certif...
Rsm GC Advisory Renewable Purchase Obligation (RPO) & Renewable Energy Certif...Rsm GC Advisory Renewable Purchase Obligation (RPO) & Renewable Energy Certif...
Rsm GC Advisory Renewable Purchase Obligation (RPO) & Renewable Energy Certif...RSM GC
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesSaurabh Mehta
 
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...Diego Berazategui
 

Similar to Awareness Briefing on NEM, RPVI and Sel-Co.pdf (20)

Energy audit conditional grant
Energy audit conditional grantEnergy audit conditional grant
Energy audit conditional grant
 
MYC Power Sector Services proposal
MYC Power Sector Services proposal MYC Power Sector Services proposal
MYC Power Sector Services proposal
 
REC status
REC statusREC status
REC status
 
Summary of SECI Tranche III - 1200 MW Hybrid Wind Solar
Summary of SECI Tranche III - 1200 MW Hybrid Wind SolarSummary of SECI Tranche III - 1200 MW Hybrid Wind Solar
Summary of SECI Tranche III - 1200 MW Hybrid Wind Solar
 
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerRf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012
 
PIPPA's Perspective on Challenges and Opportunities in Scaling Renewable Ener...
PIPPA's Perspective on Challenges and Opportunities in Scaling Renewable Ener...PIPPA's Perspective on Challenges and Opportunities in Scaling Renewable Ener...
PIPPA's Perspective on Challenges and Opportunities in Scaling Renewable Ener...
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
 
RENEWABLE ENERGY SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
RENEWABLE ENERGY  SECTOR CONSTRAINTS,SOLUTIONS AND FINANCINGRENEWABLE ENERGY  SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
RENEWABLE ENERGY SECTOR CONSTRAINTS,SOLUTIONS AND FINANCING
 
CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption
 
200 MW Solar Projects Investor's, Developer's Meet - KERALA
200 MW Solar Projects Investor's, Developer's Meet - KERALA200 MW Solar Projects Investor's, Developer's Meet - KERALA
200 MW Solar Projects Investor's, Developer's Meet - KERALA
 
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
 
Philippines | Jun-16 | PHILIPPINE RENEWABLE ENERGY SITUATIONER
Philippines | Jun-16 | PHILIPPINE RENEWABLE ENERGY SITUATIONERPhilippines | Jun-16 | PHILIPPINE RENEWABLE ENERGY SITUATIONER
Philippines | Jun-16 | PHILIPPINE RENEWABLE ENERGY SITUATIONER
 
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
 
REC a market ready for take-off
REC   a market ready for take-offREC   a market ready for take-off
REC a market ready for take-off
 
Rsm GC Advisory Renewable Purchase Obligation (RPO) & Renewable Energy Certif...
Rsm GC Advisory Renewable Purchase Obligation (RPO) & Renewable Energy Certif...Rsm GC Advisory Renewable Purchase Obligation (RPO) & Renewable Energy Certif...
Rsm GC Advisory Renewable Purchase Obligation (RPO) & Renewable Energy Certif...
 
T.Chandramouli _ Resume
T.Chandramouli _ ResumeT.Chandramouli _ Resume
T.Chandramouli _ Resume
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
 
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
 

Recently uploaded

High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 

Recently uploaded (20)

High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

Awareness Briefing on NEM, RPVI and Sel-Co.pdf

  • 1. 18th Mac 2019 MARRIOT HOTEL, PUTRAJAYA Azah Ahmad Director of Renewable Energy Technology (RET) Division Sustainable Energy Development Authority (SEDA) Malaysia BRIEFING ON THE NEW NEM, INTRODUCTION TO SELF-CONSUMPTION (SELCO) AND RPVI DIRECTORY APPLICATION
  • 2. 2 Regulator Implementing Agency Distribution Licensee NEM Participants NEM Implementation Domestic Commercial Industrial Agriculture
  • 4. NEM Calculation Net Charge Amount (RM) = (Energy Imported from Distribution Licensee* x GazettedTariff) – (Energy Exported to Distribution Licensee x Gazetted Tariff) *Energy imported is subjected to SST, KWTBB, ICPT, where applicable Note: 1 kWh exported to the grid will be offset against 1kWh consumed from the grid with the gazetted tariff. The export charges are charged in descending order (start from the highest tariff rate charged on the applicable month)
  • 5. NEM Statistic: Approved & Commissioned as of Feb 2019 Approved and NEM Commencement Date (NEMCD) Category (Peninsular Malaysia) Approved NEM Commencement Date (NEMCD) (Completed) Installed Capacity (kWp) No. of Applications Installed Capacity (kWp) No. of Applications Domestic 2,747.48 391 1,328.64 179 Commercial 11,139.10 143 3,616.63 55 Industrial 20,639.60 87 4,931.48 26 Total 34,526.18 621 9,876.75 260 Note: 1. Implementations - 12 months from approval. 2. NEMCD- contract signed, a copy to SEDA, to upload in the e-NEM system.
  • 6. 6  Quota allocation will be based on first-come first-served basis;  Quota applied in MWac; NEM Available Quota Quota Allocation Location Peninsular Malaysia Year 2017 - 2020 Quota Allocated *Quota Taken *Quota Balance Category of Consumers Domestic/Residential, MWp 50 3 47 Agriculture, MWac 450 35 415 Commercial, MWac Industrial, MWac Total, MWp 500 38 462 * As of 13th March 2019
  • 7. 7  NEM Assessment Study (NEMAS) report is required prior to NEM application to SEDA Malaysia;  The studies shall be conducted by TNB or its appointed consultant to establish the technical and safety requirements and determine the feasibility of connection. NEM Assessment Study (NEMAS) Installed Capacity Study Required Fee of Study (RM) 1-72 kW No - >72 kW - 180 kW Yes RM1,000.00 >180 kW - 425 kW Yes RM5,000.00 >425 kW - 1 MW Yes RM8,000.00 >1 MW - 2 MW Yes RM15,000.00 >2 MW - 5 MW Yes RM20,000.00 >5 MW - 10 MW Yes RM30,000.00 >10 MW - 30 MW Yes RM40,000.00 Note: Study period = 30 days
  • 8. NEM Contractor Duration required NEM approval (3 + 7 working days) NEMAS Report (30 days) + pre-conditioning 3 weeks NEMAS (>72kW) Application NEM application Procurement, installation & apply Public Generation License Installation completed & request for NEM meter TNB meter replacement & NEM Contract (TNB Kawasan) Testing & Commissioning and project completed 4 - 7 weeks 2 weeks NEM Guideline maximum 12 months Public Generation License (>72kW) (3 months) How to Apply? Process Flowchart Note: NEMAS - NEM Assessment Study
  • 9. 9  A mechanism where an eligible consumer installs a solar PV system entirely for own use and in the event of excess of generation, the energy is not allowed to be exported to the grid  Issuer of SelCo Guidelines: Suruhanjaya Tenaga Self-Consumption (SelCo)
  • 10. 10  Eligibility An individual or commercial premise consumer  Capacity Limit a) stand-alone system (off-grid) - no capacity limit b) non-stand-alone system (grid-connected) - less than 75% of the maximum demand of the consumer’s existing installation.  Connection Requirements To ensure there is no electricity generation export to the grid. Clause 4.7 : “For self-consumption purposes, the consumer and registered Electrical Contractor are responsible to ensure there is no electricity generation export to the grid..”  Power System Study (PSS) Power System Study (PSS) for the solar PV system with a capacity of 425 kWp and above.  Registration of the Installation with the Distribution Licensee The consumer of the solar PV system is required to register the installation with the DL  Licensing requirements For solar PV system installation above 24kW for single phase and 72kW for three phase, any person who uses, works or operates the installation shall require a license. SelCo Requirements
  • 11. Any investors who provide Solar Power Purchase Agreement (PPA) or Solar Leasing services to NEM customers REGISTERED SOLAR PV INVESTOR (RPVI)
  • 12. RPVI Directory RPVI Directory : • Open from 2nd January 2019 • Hosted & managed by SEDA Malaysia • A pool of both local and foreign investors be registered to provide/serve as a reference to interested buyers/clients. • Serve as a checking mechanism in terms of foreign participation in the NEM programme. • Total approved : 20 RPVIs (as of 18 Mac 2019) SEDA Malaysia Portal
  • 13. Foreign Company Local Company solar PV projects of above 250kW only solar PV projects of all Capacity  Companies must be incorporated in Malaysia;  Minimum paid-up capital of at least RM10 million;  minimum 80% of local employment (based on company’s organization chart)  has 100% local Engineering, Procurement and Construction (EPC) by appointing a Registered PV Solar Service Provider with SEDA Malaysia  Companies must be incorporated in Malaysia;  minimum paid-up capital of at least RM1million;  Project EPC can be carried out by themselves or awarded to the Registered PV Service Provider (RPVSP) with SEDA Malaysia;  Companies can be a Registered PV Service Provider with SEDA;  Registration and/or annual fees: USD2,500.00, to be renewed annually  Registration and/or annual fees: RM3,000.00, to be renewed annually Note; checking mechanism will be conducted during project implementation to ensure compliance failing which, de-listing in the directory RPVI Requirements
  • 14. Check RPVI requirements Online submission & Terms and Conditions compliance https://services.seda.gov.my/rpvi/rpvi/login Review and approval process (RPVI’s Committee Meeting) Registration & Annual Fee payment RPVI Certificate & listed in RPVI Directory Local or Foreign Investor RM3,000 (local) and USD2,500 (foreign) Monthly meeting How to Apply? Process Flowchart
  • 15. RPVI Business Model SOLAR POWER PURCHASE AGREEMENT (PPA) OR SOLAR LEASING SERVICES SOLAR PPA Payment in Energy (RM/kWh) Customers pay based on per kWh for power generated from PV system SOLAR LEASING/ HIRE PURCHASE Fixed Monthly payment (RM) Customers pay a fixed amount monthly in return for the use of the PV system and the system will be owned by consumer after lease period ends
  • 16. Method of Payment TNB does the billing, collection & remittance of payment by customers to RPVI in return for a service fee (2sen/kWh). Direct payment with solar investor/lessor Supply Agreement for Renewable Energy (SARE) OR RPVI receive payment from customer directly
  • 17. 17 For further enquiries, please contact: SEDA Malaysia Galeria PjH, Level 9 Jalan P4W, Persiaran Perdana, Presint 4, 62100 Putrajaya T: +603 – 8870 5824 Tel: +6088-252101/251462 E: NEM@seda.gov.my W: www.seda.gov.my
  • 19. Purchase Mode via Outright Purchase