China Bangla Engineers & Consultants Ltd.
Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info
Uttara, Dhaka 1230
Clay Bricks Production Line of 200,000. Pcs/day
(254mm*127mm*76mm,Tunnel kiln of 160*3.9 meters×2)
A. Clay brick plan data:
1. Plant area: 32000 m2 (24 Bigha) or more (about 200 meters length), and we can make design based
on your plant size;
2. Construction area: 6800 m2 (Including raw materials storage shad, 800 m2; Wet bricks storage shad,
18*120=2160m2; Producing equipments workshop (15*40=600 m2); Tunnel kiln and bricks unloading
shad, 15*170=2550 m2; Office building area, 600 m2);
3. Raw materials area: 1200 m2;
4. Finished bricks area: 7000 m2;
5. Raw materials needed per day: 530-550 m3;
6. Workers needed: 30 workers per shift;
7. Producing capacity: 16000-20000 pcs/hour.
8. Raw materials plastic index: 7-17;
9. Moisture content of green brick: 16-18%.
B. Tunnel kiln technical data:
1. Tunnel kiln length: 160 meters×2 tunnel kiln;
2. Tunnel kiln inner width: 3.9 meters;
3. Tunnel kiln Inside Height: 1.56 meters;
4. Kiln car size: 3.6×4.0×0.87 meter;
5. Bricks setting layers in the kiln car: 13 layers
6. Brick setting quantity in the kiln car: 5600 standard bricks;
7. Kiln car quantity in the tunnel kiln: 40;
8. Bricks drying time: 24 hours;
9. Bricks firing time: 42 hours;
10. Firing temperature: 950-1100 ℃;
11. Moisture of green brick: 16-18%;
12. Moisture of bricks after drying: ≀6%;
13. Finished firing bricks ratio: ≄95%;
14. Working time per year: 300 days;
C. Clay bricks producing equipments:
No. Item Power,
KW
Price, USD
FOB
Qingdao
Quantity Sub-total
value
Note
A Clay Brick
producing
equipments
C01 Wheel loader,
FL935E (Rated
load, 3000 KG;
Bucket capacity,
36800 1 36800
China Bangla Engineers & Consultants Ltd.
Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info
Uttara, Dhaka 1230
1.8 m3
)
C02 Box feeder, 3.5
meter, with
hopper
7.5 7960 1 7960
C03 De-ironing 1400 2 2800
C04 GS800×600 roller
crusher
37 15870 1 15870
C05 Fine roller
crusher, 800×600
60 24700 1 24700
C06 Double shaft
mixer, 3.5 meters
45 12870 1 12870
C07 TDS 60 Conveyor 55 210 140
meters
29400
C08 JKY70/70-4.0 clay
bricks extruder,
DAUBLE-STAGE
VACUUM
(Extrusion
pressure, 4.0 MPa,
including vacuum
pump, air
compressor)
220+90+
18.5
177500 1 177500
C09 AUTOMATIC
BRICK CUTTER
11 24500 1 24500
C10 Brick
DISTRIBUTION
TABLE and AUTO
STACKING
MACHINE ON THE
KILN CART
22 193500 1 193500
C11 Waring parts for
one year
19000
China Bangla Engineers & Consultants Ltd.
Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info
Uttara, Dhaka 1230
D. Tunnel kiln (160*3.9 meters×2)
Item Name Quantity Unit price Sub-total Note
1 Clay brick
(254mm*127mm*76mm)
1.2 million 120000 Supplied by the
client
2 Cement 700 MT 105000 Supplied by the
client
3 Sand 3300 m3 60000 Supplied by the
client
4 Stone 1400 m3 210000 Supplied by the
client
5 Wood 4 m3 1000 Supplied by the
client
6 Kiln Car 200 sets 2260 USD 452000
7 Ferry car 3 12740 38220
8 Pusher 2 9700 19400
9 Windlass 7 6500 45500
10 Wind blower (Y473-20D) 2 29350 58700
11 Moisture removing blower 2 1800 3600
12 Hydraulic stepping pusher 6 8700 52200
13 Hauling machine 2 8500 17000
14 Refractory bricks 500 MT 210 105000
Total value 544,900
China Bangla Engineers & Consultants Ltd.
Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info
Uttara, Dhaka 1230
15 Refractory clay 80 MT 210 16800
16 Steel I-beam (20#) 13 MT 920 11180
U shape screw 3000 sets 7.2 21600
17 Steel plate, 20 mm 1.5 MT 920 1380
18 Rail (18 KG) 46 MT 920 42320
19 Other steel 15 MT 920 13800
20 Cement slab for dryer 220 pcs 35 7700
21 Cement slab for tunnel kiln 160 pcs 42 6720
22 Cement slab for gas flue 920 meters 12 11040
23 Ceramic fiber blanket, High
alumina fiber blanket
60 MT 1760 105600
24 Anchor 7980 pcs 4.5 35910
25 U shape nails 5200 pcs 0.45 2340
26 Clip 5200 pcs 0.45 2340
27 High-strength hardener 1000 KG 4.5 4500
28 High-strength sealing plate 9000 KG 1.9 17100
29 Steel I-beam (12#), angle
steel, steel plate
53 MT 920 48760
30 Steel rebar 1200 pcs 12 14400
31 Fire controller 260 sets 16 4160
32 Air brake 80 sets 140 11200
33 Air controller 60 sets 120 7200
34 Tunnel kiln control system 87900
35 De-sulfur system 98780 For environmental
protection, and can
be deleted based
on clients’s choice.
36 Complete set of air
conducts
55700
37 Concrete floor and shed 6110 m2 38 USD/m2 Including raw
materials storage
shad, 800 m2; Wet
bricks storage
shad,
18*120=2160m2;
Producing
equipments
workshop
(15*40=600 m2);
Tunnel kiln and
China Bangla Engineers & Consultants Ltd.
Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info
Uttara, Dhaka 1230
bricks unloading
shad,
15*170=2550 m2.
Total value for tunnel kiln 1420020
Total value for clay
bricks producing
equipments
544900
Design cost 64500
a Total FOB Qingdao value 2,029,420.
b Sea freight cost to
Chittagong
Open
c Total CFR value (a+b) Open
d Installation,
commissioning,
operators training and
trial operation cost
61500 Based on 6
months
Total value 2,090,920. USD FOB Qingdao, China
Note:
1. The buyer bear all the cost after goods reaching Chittagong, including customs clearing and
transportation to the buyer’s plant, etc.
2. The buyer bear the cost of related construction materials, including clay brick, sand, cement, stone,
wood, etc.
3. The buyer bear the cost of civil-building construction of the plant.
4. The seller will supply some engineers & drawing of kiln(s), and the buyer must supply related
construction equipments and tools, and 50-100 workers daily at buyer's cost for construction of Kiln(s).
The seller send 5 engineers to Bangladesh and responsible for the salary, visa, air ticket of engineers,
and the buyer are responsible for the food, hotel, accommodation, etc. of engineers in Bangladesh.
E. Clay bricks producing process:
China Bangla Engineers & Consultants Ltd.
Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info
Uttara, Dhaka 1230
F. Clay brick plant drying with tunnel kiln
China Bangla Engineers & Consultants Ltd.
Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info
Uttara, Dhaka 1230

More Related Content

What's hot

Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structuresAnirudh Gupta
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Darshiini Vig
 
BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT jolynnTJL
 
Project management project 1 report (pr architects)
Project management project 1 report (pr architects)Project management project 1 report (pr architects)
Project management project 1 report (pr architects)Jannah Jailani
 
CONDITION SURVEY REPORT FOR MELAKA STAMP MUSEUM
CONDITION SURVEY REPORT FOR MELAKA STAMP MUSEUMCONDITION SURVEY REPORT FOR MELAKA STAMP MUSEUM
CONDITION SURVEY REPORT FOR MELAKA STAMP MUSEUMFakhrul Afifi
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
MEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESMEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESwendyteosy
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materialsHamdija Velagic
 
Bricks
BricksBricks
Brickshlksd
 
Replacement of Steel by Bamboo Reinforcement
Replacement of Steel by Bamboo ReinforcementReplacement of Steel by Bamboo Reinforcement
Replacement of Steel by Bamboo ReinforcementIOSR Journals
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of QuantityArissa Loh
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQashleyyeap
 
Curtain wall introduction & requirements
Curtain wall introduction & requirementsCurtain wall introduction & requirements
Curtain wall introduction & requirementsArshad khan
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsGrace Henry
 

What's hot (20)

Building construction(sujith)
Building construction(sujith)Building construction(sujith)
Building construction(sujith)
 
Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structures
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 
BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT
 
Project management project 1 report (pr architects)
Project management project 1 report (pr architects)Project management project 1 report (pr architects)
Project management project 1 report (pr architects)
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
CONDITION SURVEY REPORT FOR MELAKA STAMP MUSEUM
CONDITION SURVEY REPORT FOR MELAKA STAMP MUSEUMCONDITION SURVEY REPORT FOR MELAKA STAMP MUSEUM
CONDITION SURVEY REPORT FOR MELAKA STAMP MUSEUM
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
MEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESMEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDES
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materials
 
Bricks
BricksBricks
Bricks
 
Replacement of Steel by Bamboo Reinforcement
Replacement of Steel by Bamboo ReinforcementReplacement of Steel by Bamboo Reinforcement
Replacement of Steel by Bamboo Reinforcement
 
Bricks
Bricks Bricks
Bricks
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQ
 
Curtain wall introduction & requirements
Curtain wall introduction & requirementsCurtain wall introduction & requirements
Curtain wall introduction & requirements
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 
Bill Of Quantities
Bill Of QuantitiesBill Of Quantities
Bill Of Quantities
 

Similar to Cbecl clay brick project with tunnel kiln-200000 pcs per day

Cbecl tunnel kiln and dryer auto brick machinery-100000pcs
Cbecl tunnel kiln and dryer auto brick machinery-100000pcsCbecl tunnel kiln and dryer auto brick machinery-100000pcs
Cbecl tunnel kiln and dryer auto brick machinery-100000pcsLucky Meme
 
Cbecl tunnel kiln and dryer auto brick machinery-100000pcs
Cbecl tunnel kiln and dryer auto brick machinery-100000pcsCbecl tunnel kiln and dryer auto brick machinery-100000pcs
Cbecl tunnel kiln and dryer auto brick machinery-100000pcsAbu Rayhan
 
Environment friendly building_material_technologies_for_low_cost_housing
Environment friendly building_material_technologies_for_low_cost_housingEnvironment friendly building_material_technologies_for_low_cost_housing
Environment friendly building_material_technologies_for_low_cost_housingkunal singh
 
Total project cost of 100000 pcs auto brick field
Total project cost of 100000 pcs auto brick fieldTotal project cost of 100000 pcs auto brick field
Total project cost of 100000 pcs auto brick fieldCBECL BD
 
50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI
50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI
50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYIJimmy Ma
 
92795289 building-data
92795289 building-data92795289 building-data
92795289 building-dataimaduddin91
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Fence BOQ with Materials.pdf
Fence BOQ with Materials.pdfFence BOQ with Materials.pdf
Fence BOQ with Materials.pdfMutha Morgan
 
Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Akshaya Selvam
 
FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12Bharat kuvadiya
 
study of self-compacting concrete for economical construction
study of self-compacting concrete for economical constructionstudy of self-compacting concrete for economical construction
study of self-compacting concrete for economical constructionTejas6957
 
Final Paper on Study and Design of Footbridge to connect the first floor of C...
Final Paper on Study and Design of Footbridge to connect the first floor of C...Final Paper on Study and Design of Footbridge to connect the first floor of C...
Final Paper on Study and Design of Footbridge to connect the first floor of C...IRJET Journal
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadLachhmikant. Prasad
 
50 TPD wheat flour mill by cbecl 2
50 TPD wheat flour mill by cbecl 250 TPD wheat flour mill by cbecl 2
50 TPD wheat flour mill by cbecl 2Lucky Meme
 
50TPD wheat flour mill Quotation by cbecl
50TPD wheat flour mill Quotation by cbecl50TPD wheat flour mill Quotation by cbecl
50TPD wheat flour mill Quotation by cbeclAlibaba Construction Ltd.
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 

Similar to Cbecl clay brick project with tunnel kiln-200000 pcs per day (20)

Cbecl tunnel kiln and dryer auto brick machinery-100000pcs
Cbecl tunnel kiln and dryer auto brick machinery-100000pcsCbecl tunnel kiln and dryer auto brick machinery-100000pcs
Cbecl tunnel kiln and dryer auto brick machinery-100000pcs
 
Cbecl tunnel kiln and dryer auto brick machinery-100000pcs
Cbecl tunnel kiln and dryer auto brick machinery-100000pcsCbecl tunnel kiln and dryer auto brick machinery-100000pcs
Cbecl tunnel kiln and dryer auto brick machinery-100000pcs
 
Environment friendly building_material_technologies_for_low_cost_housing
Environment friendly building_material_technologies_for_low_cost_housingEnvironment friendly building_material_technologies_for_low_cost_housing
Environment friendly building_material_technologies_for_low_cost_housing
 
Total project cost of 100000 pcs auto brick field
Total project cost of 100000 pcs auto brick fieldTotal project cost of 100000 pcs auto brick field
Total project cost of 100000 pcs auto brick field
 
50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI
50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI
50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI
 
92795289 building-data
92795289 building-data92795289 building-data
92795289 building-data
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Fence BOQ with Materials.pdf
Fence BOQ with Materials.pdfFence BOQ with Materials.pdf
Fence BOQ with Materials.pdf
 
Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...
 
Stilt house
Stilt houseStilt house
Stilt house
 
FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12
 
study of self-compacting concrete for economical construction
study of self-compacting concrete for economical constructionstudy of self-compacting concrete for economical construction
study of self-compacting concrete for economical construction
 
Final Paper on Study and Design of Footbridge to connect the first floor of C...
Final Paper on Study and Design of Footbridge to connect the first floor of C...Final Paper on Study and Design of Footbridge to connect the first floor of C...
Final Paper on Study and Design of Footbridge to connect the first floor of C...
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasad
 
50 TPD wheat flour mill by cbecl 2
50 TPD wheat flour mill by cbecl 250 TPD wheat flour mill by cbecl 2
50 TPD wheat flour mill by cbecl 2
 
50TPD wheat flour mill Quotation by cbecl
50TPD wheat flour mill Quotation by cbecl50TPD wheat flour mill Quotation by cbecl
50TPD wheat flour mill Quotation by cbecl
 
Kabaddi
KabaddiKabaddi
Kabaddi
 
Ch12
Ch12Ch12
Ch12
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 

More from Abu Rayhan

CBECL - Your Go-To Concrete Block Making Machine Supplier in Bangladesh.pdf
CBECL - Your Go-To Concrete Block Making Machine Supplier in Bangladesh.pdfCBECL - Your Go-To Concrete Block Making Machine Supplier in Bangladesh.pdf
CBECL - Your Go-To Concrete Block Making Machine Supplier in Bangladesh.pdfAbu Rayhan
 
Sample Project Profile Bangladesh. Importance of project profile.
Sample Project Profile Bangladesh. Importance of project profile.Sample Project Profile Bangladesh. Importance of project profile.
Sample Project Profile Bangladesh. Importance of project profile.Abu Rayhan
 
Bangladesh Bank EEF/ESF Fund Circular 2018 PDF Download
Bangladesh Bank EEF/ESF Fund Circular 2018 PDF DownloadBangladesh Bank EEF/ESF Fund Circular 2018 PDF Download
Bangladesh Bank EEF/ESF Fund Circular 2018 PDF DownloadAbu Rayhan
 
Auto Bricks Factory Layout and Design: Section view of kiln
Auto Bricks Factory Layout and Design: Section view of kilnAuto Bricks Factory Layout and Design: Section view of kiln
Auto Bricks Factory Layout and Design: Section view of kilnAbu Rayhan
 
Quation of cold store 5000 mt
Quation of cold store 5000 mtQuation of cold store 5000 mt
Quation of cold store 5000 mtAbu Rayhan
 
4000 bph pet bottle production line cbecl
4000 bph pet bottle production line cbecl4000 bph pet bottle production line cbecl
4000 bph pet bottle production line cbeclAbu Rayhan
 
4000 bph complete mineral water production line cbecl
4000 bph complete mineral water production line cbecl4000 bph complete mineral water production line cbecl
4000 bph complete mineral water production line cbeclAbu Rayhan
 
2500 bpd,5gallon mineral water production line cbecl
2500 bpd,5gallon mineral water production line cbecl2500 bpd,5gallon mineral water production line cbecl
2500 bpd,5gallon mineral water production line cbeclAbu Rayhan
 
2000 bph complete pet bottle production line cbecl
2000 bph complete pet bottle production line cbecl2000 bph complete pet bottle production line cbecl
2000 bph complete pet bottle production line cbeclAbu Rayhan
 
Quation of rice bran oil plant cbecl huatai
Quation of rice bran oil plant cbecl huataiQuation of rice bran oil plant cbecl huatai
Quation of rice bran oil plant cbecl huataiAbu Rayhan
 
Cbecl acme 50 tpd parboiled rice mill plant
Cbecl acme 50 tpd parboiled rice mill plantCbecl acme 50 tpd parboiled rice mill plant
Cbecl acme 50 tpd parboiled rice mill plantAbu Rayhan
 
Amp cbecl 240 tpd rice mill plant
Amp cbecl 240 tpd rice mill plantAmp cbecl 240 tpd rice mill plant
Amp cbecl 240 tpd rice mill plantAbu Rayhan
 
Quotation of 500 tpd paroiled rice milling plant cbecl
Quotation of 500 tpd paroiled rice milling plant cbeclQuotation of 500 tpd paroiled rice milling plant cbecl
Quotation of 500 tpd paroiled rice milling plant cbeclAbu Rayhan
 
Cbecl acme 120 tpd parboiled rice mill plant
Cbecl acme 120 tpd parboiled rice mill plantCbecl acme 120 tpd parboiled rice mill plant
Cbecl acme 120 tpd parboiled rice mill plantAbu Rayhan
 

More from Abu Rayhan (14)

CBECL - Your Go-To Concrete Block Making Machine Supplier in Bangladesh.pdf
CBECL - Your Go-To Concrete Block Making Machine Supplier in Bangladesh.pdfCBECL - Your Go-To Concrete Block Making Machine Supplier in Bangladesh.pdf
CBECL - Your Go-To Concrete Block Making Machine Supplier in Bangladesh.pdf
 
Sample Project Profile Bangladesh. Importance of project profile.
Sample Project Profile Bangladesh. Importance of project profile.Sample Project Profile Bangladesh. Importance of project profile.
Sample Project Profile Bangladesh. Importance of project profile.
 
Bangladesh Bank EEF/ESF Fund Circular 2018 PDF Download
Bangladesh Bank EEF/ESF Fund Circular 2018 PDF DownloadBangladesh Bank EEF/ESF Fund Circular 2018 PDF Download
Bangladesh Bank EEF/ESF Fund Circular 2018 PDF Download
 
Auto Bricks Factory Layout and Design: Section view of kiln
Auto Bricks Factory Layout and Design: Section view of kilnAuto Bricks Factory Layout and Design: Section view of kiln
Auto Bricks Factory Layout and Design: Section view of kiln
 
Quation of cold store 5000 mt
Quation of cold store 5000 mtQuation of cold store 5000 mt
Quation of cold store 5000 mt
 
4000 bph pet bottle production line cbecl
4000 bph pet bottle production line cbecl4000 bph pet bottle production line cbecl
4000 bph pet bottle production line cbecl
 
4000 bph complete mineral water production line cbecl
4000 bph complete mineral water production line cbecl4000 bph complete mineral water production line cbecl
4000 bph complete mineral water production line cbecl
 
2500 bpd,5gallon mineral water production line cbecl
2500 bpd,5gallon mineral water production line cbecl2500 bpd,5gallon mineral water production line cbecl
2500 bpd,5gallon mineral water production line cbecl
 
2000 bph complete pet bottle production line cbecl
2000 bph complete pet bottle production line cbecl2000 bph complete pet bottle production line cbecl
2000 bph complete pet bottle production line cbecl
 
Quation of rice bran oil plant cbecl huatai
Quation of rice bran oil plant cbecl huataiQuation of rice bran oil plant cbecl huatai
Quation of rice bran oil plant cbecl huatai
 
Cbecl acme 50 tpd parboiled rice mill plant
Cbecl acme 50 tpd parboiled rice mill plantCbecl acme 50 tpd parboiled rice mill plant
Cbecl acme 50 tpd parboiled rice mill plant
 
Amp cbecl 240 tpd rice mill plant
Amp cbecl 240 tpd rice mill plantAmp cbecl 240 tpd rice mill plant
Amp cbecl 240 tpd rice mill plant
 
Quotation of 500 tpd paroiled rice milling plant cbecl
Quotation of 500 tpd paroiled rice milling plant cbeclQuotation of 500 tpd paroiled rice milling plant cbecl
Quotation of 500 tpd paroiled rice milling plant cbecl
 
Cbecl acme 120 tpd parboiled rice mill plant
Cbecl acme 120 tpd parboiled rice mill plantCbecl acme 120 tpd parboiled rice mill plant
Cbecl acme 120 tpd parboiled rice mill plant
 

Recently uploaded

Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 

Recently uploaded (20)

Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 

Cbecl clay brick project with tunnel kiln-200000 pcs per day

  • 1. China Bangla Engineers & Consultants Ltd. Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info Uttara, Dhaka 1230 Clay Bricks Production Line of 200,000. Pcs/day (254mm*127mm*76mm,Tunnel kiln of 160*3.9 meters×2) A. Clay brick plan data: 1. Plant area: 32000 m2 (24 Bigha) or more (about 200 meters length), and we can make design based on your plant size; 2. Construction area: 6800 m2 (Including raw materials storage shad, 800 m2; Wet bricks storage shad, 18*120=2160m2; Producing equipments workshop (15*40=600 m2); Tunnel kiln and bricks unloading shad, 15*170=2550 m2; Office building area, 600 m2); 3. Raw materials area: 1200 m2; 4. Finished bricks area: 7000 m2; 5. Raw materials needed per day: 530-550 m3; 6. Workers needed: 30 workers per shift; 7. Producing capacity: 16000-20000 pcs/hour. 8. Raw materials plastic index: 7-17; 9. Moisture content of green brick: 16-18%. B. Tunnel kiln technical data: 1. Tunnel kiln length: 160 meters×2 tunnel kiln; 2. Tunnel kiln inner width: 3.9 meters; 3. Tunnel kiln Inside Height: 1.56 meters; 4. Kiln car size: 3.6×4.0×0.87 meter; 5. Bricks setting layers in the kiln car: 13 layers 6. Brick setting quantity in the kiln car: 5600 standard bricks; 7. Kiln car quantity in the tunnel kiln: 40; 8. Bricks drying time: 24 hours; 9. Bricks firing time: 42 hours; 10. Firing temperature: 950-1100 ℃; 11. Moisture of green brick: 16-18%; 12. Moisture of bricks after drying: ≀6%; 13. Finished firing bricks ratio: ≄95%; 14. Working time per year: 300 days; C. Clay bricks producing equipments: No. Item Power, KW Price, USD FOB Qingdao Quantity Sub-total value Note A Clay Brick producing equipments C01 Wheel loader, FL935E (Rated load, 3000 KG; Bucket capacity, 36800 1 36800
  • 2. China Bangla Engineers & Consultants Ltd. Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info Uttara, Dhaka 1230 1.8 m3 ) C02 Box feeder, 3.5 meter, with hopper 7.5 7960 1 7960 C03 De-ironing 1400 2 2800 C04 GS800×600 roller crusher 37 15870 1 15870 C05 Fine roller crusher, 800×600 60 24700 1 24700 C06 Double shaft mixer, 3.5 meters 45 12870 1 12870 C07 TDS 60 Conveyor 55 210 140 meters 29400 C08 JKY70/70-4.0 clay bricks extruder, DAUBLE-STAGE VACUUM (Extrusion pressure, 4.0 MPa, including vacuum pump, air compressor) 220+90+ 18.5 177500 1 177500 C09 AUTOMATIC BRICK CUTTER 11 24500 1 24500 C10 Brick DISTRIBUTION TABLE and AUTO STACKING MACHINE ON THE KILN CART 22 193500 1 193500 C11 Waring parts for one year 19000
  • 3. China Bangla Engineers & Consultants Ltd. Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info Uttara, Dhaka 1230 D. Tunnel kiln (160*3.9 meters×2) Item Name Quantity Unit price Sub-total Note 1 Clay brick (254mm*127mm*76mm) 1.2 million 120000 Supplied by the client 2 Cement 700 MT 105000 Supplied by the client 3 Sand 3300 m3 60000 Supplied by the client 4 Stone 1400 m3 210000 Supplied by the client 5 Wood 4 m3 1000 Supplied by the client 6 Kiln Car 200 sets 2260 USD 452000 7 Ferry car 3 12740 38220 8 Pusher 2 9700 19400 9 Windlass 7 6500 45500 10 Wind blower (Y473-20D) 2 29350 58700 11 Moisture removing blower 2 1800 3600 12 Hydraulic stepping pusher 6 8700 52200 13 Hauling machine 2 8500 17000 14 Refractory bricks 500 MT 210 105000 Total value 544,900
  • 4. China Bangla Engineers & Consultants Ltd. Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info Uttara, Dhaka 1230 15 Refractory clay 80 MT 210 16800 16 Steel I-beam (20#) 13 MT 920 11180 U shape screw 3000 sets 7.2 21600 17 Steel plate, 20 mm 1.5 MT 920 1380 18 Rail (18 KG) 46 MT 920 42320 19 Other steel 15 MT 920 13800 20 Cement slab for dryer 220 pcs 35 7700 21 Cement slab for tunnel kiln 160 pcs 42 6720 22 Cement slab for gas flue 920 meters 12 11040 23 Ceramic fiber blanket, High alumina fiber blanket 60 MT 1760 105600 24 Anchor 7980 pcs 4.5 35910 25 U shape nails 5200 pcs 0.45 2340 26 Clip 5200 pcs 0.45 2340 27 High-strength hardener 1000 KG 4.5 4500 28 High-strength sealing plate 9000 KG 1.9 17100 29 Steel I-beam (12#), angle steel, steel plate 53 MT 920 48760 30 Steel rebar 1200 pcs 12 14400 31 Fire controller 260 sets 16 4160 32 Air brake 80 sets 140 11200 33 Air controller 60 sets 120 7200 34 Tunnel kiln control system 87900 35 De-sulfur system 98780 For environmental protection, and can be deleted based on clients’s choice. 36 Complete set of air conducts 55700 37 Concrete floor and shed 6110 m2 38 USD/m2 Including raw materials storage shad, 800 m2; Wet bricks storage shad, 18*120=2160m2; Producing equipments workshop (15*40=600 m2); Tunnel kiln and
  • 5. China Bangla Engineers & Consultants Ltd. Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info Uttara, Dhaka 1230 bricks unloading shad, 15*170=2550 m2. Total value for tunnel kiln 1420020 Total value for clay bricks producing equipments 544900 Design cost 64500 a Total FOB Qingdao value 2,029,420. b Sea freight cost to Chittagong Open c Total CFR value (a+b) Open d Installation, commissioning, operators training and trial operation cost 61500 Based on 6 months Total value 2,090,920. USD FOB Qingdao, China Note: 1. The buyer bear all the cost after goods reaching Chittagong, including customs clearing and transportation to the buyer’s plant, etc. 2. The buyer bear the cost of related construction materials, including clay brick, sand, cement, stone, wood, etc. 3. The buyer bear the cost of civil-building construction of the plant. 4. The seller will supply some engineers & drawing of kiln(s), and the buyer must supply related construction equipments and tools, and 50-100 workers daily at buyer's cost for construction of Kiln(s). The seller send 5 engineers to Bangladesh and responsible for the salary, visa, air ticket of engineers, and the buyer are responsible for the food, hotel, accommodation, etc. of engineers in Bangladesh. E. Clay bricks producing process:
  • 6. China Bangla Engineers & Consultants Ltd. Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info Uttara, Dhaka 1230 F. Clay brick plant drying with tunnel kiln
  • 7. China Bangla Engineers & Consultants Ltd. Phone: +8801716752370, email: cbecl.info@gmail.com www.cbecl.info Uttara, Dhaka 1230