SlideShare a Scribd company logo
1 of 62
FAILURE ANALYSIS OF MALFUNCTION WATER
  RESOURCES PROJECT IN THE NORTHEASTERN
                THAILAND:
   INTEGRATED MENTAL MODELS AND PROJECT LIFE CYCLE
                PERSPECTIVE APPROACH

                              By
                   Piriya URAIWONG
                 Kochi University of Technology


                Advisor:                    Professor, Dr.Tsunemi Watanabe
                Examination Committee:      Professor, Dr.Seigo Nasu
                                            Professor, Dr.Osamu Tomisawa
                                            Professor, Dr.Yoshinori Nakagawa
                                            Associate Professor, Dr.Takashi Goso
2013/2/12
Research questions
    Answer      1. Causes of this malfunction?               Determine
                2. Stakeholder’s behavior associated
                   with malfunction?
                3. Solution for the problem?
    Conclusions                      Research          Methodology
                                     problem
1. Identified failure
                            Malfunction         1. Failure analysis
   causes and
                               water            2. Stakeholder’s
   solutions
                             resources             mental models
2. New failure
                              project              analysis
   analysis approach
                1. Integrated mental models with
                   WBS in project life cycle
                   perspective
    Permit      2. Multi-Stakeholder’s behavior in             Produce
                   malfunction project
                               Results                            2
Defining “Malfunction” and “Failure”
• “Malfunction”- Fail to work normally or
  properly (v.), failure of this kind (n.)
  (Oxford advanced learner’s dictionary,1989)
• “Failure” – The inability of the project to
  deliver the intended benefit to the identified
  stakeholders
• Many levels of failure- from mild failure to
  complete failure (Layton, 2011)

                                                   3
Problem statement
• Malfunction small-scaled water resources
  project – “a project that Fail to work normally
  or properly to deliver the intended benefit to
  the identified stakeholders”




                                                4
Problem statement
            5%
      8%              17%
                                        Good condition
                                        Minor reconstruction
                                        Rehabilitation
                              27%
43%                                     Re-construction
                                        Rejected


           Water resources project condition
       (Department of Water Resources: DWR, 2008)
                                                          5
Research objectives
1. To identify factors which cause malfunction
   in water resources project
2. To study behavior of key stakeholder who
   participated in malfunction of water
   resources project
3. To offer tools and methods that loosen
   constraints regarding malfunction water
   resources project

                                                 6
Research questions

RQ1   • What are factors which cause an malfunction
        of water resources project?

      • What are behavior of key stakeholder’s who
RQ2     participated in malfunction of water
        resources project?

      • What would be proposed measures or
RQ3     mechanism to improve water resources
        project management in Thailand?

                                                     7
Methodology




              8
Research methodology
   1. Preliminary diagnose malfunction project:
           Failure Knowledge Database
                            Develop analysis method

2. Introducing integrated failure analysis approach
                            Application to cases

  3. Multi-Stakeholder’s mental models analysis
                            Constraint-measure

      4. Proposes measures and action plan
                                                      9
Introducing integrated mental models
  and project life cycle approach for
           failure analysis




                                    10
Previous work on failure analysis
• Check sheets and Modified Pareto analysis (1897)
• Cause-and-effect diagram (Ishikawa
  diagrams, 1960’s)
• Fault tree analysis (Fussel, 1976)
• Failure Mode and Effects Analysis: FMEA (IEEE
  std 352)
• Failure knowledge database (Hatamura, 2005)
• Integrated Water Resources Management (1992)

                                                 11
Limitation of conventional analysis and
        Proposal of new approach
 • Conventional analysis -> Less include
   stakeholder’s mindset in failure analysis
                                            Recommendation
                         Root cause
Data collection                               generation and
                        identification
                                             implementation

          Integrate
                      Propose -> Overcome limitation of
  Stakeholder’s
     mindset
                      regardless complexity of stakeholder
                      mindset and behavior associated with a
                      failure project
                                                          12
Mental models
• “The images (attitudes and assumptions) we
  carry in our minds about ourselves, other
  people, institutions, and every aspect of the
  world which guide our interpretations and
  behavior.”




                                        (HSBC sign ad)

                                                    13
Coding and mapping mental models

 Stakeholder
     semi-                   Coding             Mapping
  structured
   interview
                                       Statement
                                               Network of
                           concepts             concepts


                                               Influence
               (Adapted from Carley, 1997)        map
                                                            14
Key aspects and process of mental
    models of an individual in decision
                                                      influence      Heuristics/
      (1) Selective              Mental models
          observation                                                  biases
      (2) Perception
                                 Background: personal, cultural, education
     (changed)                                                        Individual
                             (4)                 (3)
Action Situation (AS)
                        Framing issue       Mental models
     / Outcome
                                             processing


              Action           Possible actions &
                                     effects



                                        (Adapted from Isendahl, 2010)              15
Mental models and situations
                                Project

 AS1              AS2             AS3     AS4           AS5




       Mental                  Mental      Mental
       models 1                models 2    models 3




       AS = Action situation               (Pahl-Wostl et.al., 2006)
                                                                       16
Project life cycle and work breakdown
                structure
                 The project life cycle

Initiating and                            Operation and
                     Construction
   Planning                               Maintenance

     Work                  Work                 Work
  element 1.1           element 2.1          element 3.1

     Work                  Work                 Work
  element 1.2           element 2.2          element 3.2

                                                       17
                                  (Haugan, 2003)
Chronological progression of failure
        Background




Cause            Event              Action          Sequel

                         (Result)
                                       (Hatamura, 2005)
                                                          18
Integrated approach
            Differences
            of actual
            situation




Influence          Consequence   Integrate




              Influence




                                             19
Integrated framework
                     Stakeholder 1    Stakeholder 2   Stakeholder 3

                       Mental           Mental          Mental        Cause/
                       models 1         models 2        models 3      Background


Planning phase          AS 1.1            AS 2.1         AS 3.1


                                                                        Event/
Construction phase      AS 1.2            AS 2.2         AS 3.2         Action


Operation and                            AS 2.3
                        AS 1.3                           AS 3.3
maintenance phase


                                     Result/ Sequel
                                                                          20
Integrated process
1. Define problem context:
   project, phenomenal, etc. (by Failure
   knowledge database and project lifecycle and
   work breakdown structure)
2. Identify stakeholders and elicit stakeholder’s
   mental models
3. Apply multi-stakeholder’s mental models
   under project life cycle and work breakdown
   structure

                                                21
Practical application of integrated
            approach




                                      22
Failure Knowledge Database
                   Cause
                           Actions
                                     Results




(Hatamura, 2005)
                                          23
Initial diagnosed factors related to
             malfunction project
01. Occurrence of abnormal
 02. Insufficient knowledge
                                      Causes
       :
         08. Poor concept
                09. Poor planning
                       :                       Actions
                       15. Self-protection
                          16. Economic loss
                                       :                 Results
                               21. External damage

                                                                   24
      (Complete result can be found in attachment # 1)
Case study I
                  Fractures on     Broken radial
Downstream          concrete     gates with stolen
 blockage           structure         pulleys




                                               25
Case study II
                                  No use of canal
Structural                        (growing rice in
                      No area        the canal)
  failure           maintenance




                                             26
Semi-structured interview
          Interviewee group           Number
Officer in the Department of Water
                                        5
Resources (DWR)
Officer in the Local Administration
                                        4
Office (LAO)
Project user                            12

                Total                   21

                                               27
Partial mental models influence
           diagram
 The DWR lack of                         The DWR lack of training
continuity to follow                     and education in project
  up the project                              operation and
                                              maintenance
                          Project user
                          disregard of
                           procedure                    No specific budget
                                                         for maintenance
                                                              work
                       Project user lack of
                          maintenance
       Idea of “I need
       water, but I don’t              Malfunction of project
       want to fix when
       the project is
       broken”                                                          28
DWR-HQ03 mental models influence
                             diagram                                                                                                                                       the Bureau of Budget didn't
                                                                                                                                                                                see importance of
                                                                                                          bureaucratic reform of the                                           maintenance budget
                                                                                                         Thai government in October
                                                      DWR-HQ03                                                      2002

                                                                                                                                            establishment of                       no maintenance budget
                                                                                                                                                                                    when the DWR was
                                                                                                                                               the DWR
                                                                                                                                                                                        established
                                                                                      human resource
                                                                                       management                                                                                     problem of agency              solving by making
                                                                                                                                        projects under the ARD
                                                                                                                                                                                       shortage number                     alliance
                                                                                                                organization vision,   were transfered to the DWR
                                                                                                             mission and policy design
                                                                                                                                                                                                                          budget and
                                    the DWR transfers                           adaptation of officers                                               projects inventory           small public hearing                technology support
                                    knowledge to local                          from various agencies                                                     system                process for couple hours
                                       administration

                                                                        the Decentralization                  process of budget                    budget and projects
                                                                                                           approvement took almost             inventory approvement from                                                                                   previous constitution didn't
                                                                             Act 1999
                                                                                                                  2-3 years                             the cabinet                           put people at center                                            pay attention on public
                             project O&M, project                                                                                                                                             and adjust ourselve                                                  participation
                          management, establishment of            projects transfer to local                                                                        creat the DWR
                               water user group                     adminstration office                                                                                 value                                  trust from local is the
different budget system                                                                                                                                                                                            most important
     from the DWR                                                                                                                                                                                                                                                problem in public
                                                                                                     no budget for project          no activity on      lack of continuity on                                                                                      participation
                                                                                                                                                        project maintenance             attitude of the
                                                                                                         maintenance                  projects                                          DWR officers
                      local administration office's                                                                                                                                                           regional office               annual
                        budget problems in first               transfered project                                                                                                                            negotiation with
                                                                 facing problem                                                                                                                                                       implementation plan
                              couple years                                                                                                                                                                       politician                                     public participation process
                                                                                                                                          malfunction             not sharing experiences and                                                                   stated in the Prime Minister
                                                                                                                                           projects                    problems in public                                                                            Office Regulation
       the local administration                                                                                                                                        participation work
      need to manage their own                                                                                                                                                                        projects proposed              projects proposed by
               budget                                                                                            tendency of                                                                             by politicain
                                             running by own      technical support                                                             no attention on maintenance                                                                local's need
                                                                                                             decreasing in number
                                                   fund           from the DWR                                                                 work for projects transfered
                                                                                                                                                      from the ARD                                                                                               government implement
                                                                                                                                                                                            the DWR                                                             more public participation
                                                                                                                                                                                                                        coordination between
                                                                                                            locals satisfy with a                                                      implementation plan             politician, the DWR and                          activity
                    the DWR does not                                                                                                   increasing income
                  support budget all time                 establishment of                                        project                                                                                                    local is needed
                                                          water user group
                                                                                                                                          area development                              regional office pay                regional office               project
                    otherwise they will
                                                      cooperation between                                                                                                            attention on new project               responsibility          maintenance work
                    only wait for help
                                                      the DWR and locals                   the DWR provide local              local feel that the DWR
                                                                                               a stage to speak                  doesn't leave them
                           integrated work of
                          bureaus in the DWR                     proposal on hiring consultant
                                                                     company for public
                                                                     participation work
                                                                                                                                                                                                                                                                         29
KY-LAO02 mental models influence
                                      diagram
                                                                      no water user group for
 free access                     insufficient water                      the weir project                                                                           drastic water fluctuation      heavy traffic over
                               quantity for agriculture                                                                                                              in dry and wet season
 flooding                                use                                                                                                                                                           the weir


                                                                      Kud Sri Pum weir                                                           the pulley was
                              pumping station and user                    project                                                                    stolen                           slump and cracks
  decision made by
                                group establishment                                                                                                                                   occurance on the
majority of water users                                                                                                                                                                  infrastructure
                                                                        no bridge to cross the
                                                                                                                                                 unable to close
                                                                          stream in this area                                                                                                                      lack of knowledge on
                                                                                                                                                    the gate
                                                                                                                                                                                                                   project operation and
conflict resolution done by                                                                                                                                                                                             maintenance
voting among water users                                                                                                                                              malfunction of the
                                                      function as a bridge to cross a             unequal benefit      disign rule preventing                              project
                                                                                                 among water users   overloaded truck to cross
                                                       canal to transport agriculture
                                                                  product                                                     the weir
                                                                                                                                                                                                    perceive as project
                                                                                                                                                                                                       working well
                                                                                                                                                                 afraid of occurance of
                                                                                               social mechanism                                               serious structure damages in
      problems related to
                                                     tax payers                               preventing personal      incooperate with                                   future
          this project                                                                            selfishness              the TAO

                                                                                                                                                              becoming the TAO
                                                  expectation of benefit                                                                                           burden
   looking for solution from                         from the local                           percieved as sense                                                                                          request full rehabilitation of
     the TAO as priority                             administration                              of ownership                                                                                               project to be in a good
                                                                                                                                                                                                                   condition
                                                                                                                                                                     rejection on project
                                              villager benefit lost                                                                                                transfer from the DWR
     the TAO responsibility
        for all civil work
                                                                                                                        KY-LAO01 mental models                                                                     accept the project
                                                               the TAO                                                                                                                                              from the DWR
                           project damages
                                                           uncapable of help
                              assesment

       under capability of          over capability of
           the TAO                      the TAO                         solving problem by
                                                                         themselves at last


                                      looking for help from
             repair work
                                         othe agencies                                                                                                                                                                              30
KY-LV06 mental models influence
                            diagram
          small storage tempolary weir
           and always broken in rain
                     season                                            KY-LV06



             discussion among local
                                                                                                                     small conflict between             negotiation by
              villagers for new wier
                                                                                                                   upstream and downstream               villager chief


             villager chief requested
                                                     the politician contacted                project was
                project to the local                                                                                                       rule for water intake from the
                                                        the ARD agnency                      constructed                                                                               meeting among
                     politician                                                                                                                stream from villagers's                   villagers
                                                                                                                                                     agreement
                                difficult to get a                   function as a
                                     project                                               water usage for
                                                                        bridge                                        pumping station
                                                                                             agriculture
                                                                                                                                                    villagers agree and
          need to take care of                   monitoring                                                                                           respect the rule
               a project                      overloaded truck        pulley chain was
                                                                                                                     serving half of the
                                                                           broken                                     sub-district area

                                                             fixed by villagers's          pulleys were stolen                                             if budget is sufficient,
                                                                   money                                                                                 villagers will help to take
                                                                                                                       buy new pulley from                     care a project
                                           old concrete                                                                 villagers's money
                                                                water leaking from        two out of four sluice
                              broken rubber seal                     spillway             gate are not working           limited budget of the
                             around the sluicegate                                                                       DWR and the TAO                         large amount of water
                                                                                                                                                                released from the dam in
                                                        water leaking from                                                                                              one time
                                                             the gate                            project                   understanding the
       explanation and                                                                         malfunctions                    limitation           flooding                      weir structure is
     compromisation by                                                                                                                                                                secured
        villager chief                                            no maintenance
                                                                       plan                                                                poor road               damages on                    negotiation with the dam
                                                                                            maintenance work                                                   agriculture products
                                                                                                                                           condition                                            on water release regulation
                                                                                              by the DWR
   difficulty in consensus on
                                                                    so far we can use
     public property issue
                                   unwilling to spend much               it, it's ok
                                      money on public                                                                                                                                            looking for appropriate
                                                                                               no cooperation with      adding riprap at difficulty in agriculture        income lost
                                     maintenance work                                                                                                                                          compensation from the dam
                                                                                                    the TAO              downstream        product transport


  concern for personal
benefit rather than public
                                                unwilling to share
                                            responsibility but want the
                                                                             sometimes fix some damages
                                                                             because villagers benefit from
                                                                                                                     benefit from a project is
                                                                                                                      percieved as sense of
                                                                                                                                                                                                                    31
          benefit                                 same benefit                         a project                          ownership22
Malfunction influence diagram

                         Stakeholder A   Stakeholder B     Stakeholder C

                         Mental            Mental               Mental
Planning
 phase




                Work     models            models               models
               element
                                  AS1          AS1        AS1
                         Mental                 Mental          Mental
Construction




                Work     models                 models          models
   phase




               element
                                   AS2   AS2             AS2
                         Mental                 Mental          Mental
phase
O& M




                Work     models                 models          models
               element             AS3   AS3             AS3


                                               Sequel                    32
Malfunction influence diagram
                   Department of Water Resources            Local Administration             Project User
                                                                   Office

                   Low attention                                                             Being ignored
development




                                                                   Being ignored
                   in stakeholder                                      from                      from
   Project




                                         Less public
   phase




                    participation       participation              participation             participation
                                           activity
                   No long-term                                 No project                  Low project
                       plan           Poor planning            involvement              information sharing
Construction




                   Focus on project      No training for     No involvement in           No involvement in
                                         operation and         construction                construction
   phase




                       delivery
                                         maintenance
                                                                                         No             Expect
                                            Project’s                No knowledge     knowledge       benefit from
                                         infrastructure                                                 project
maintenance




                     No maintenance           No                   Fear of burden     No benefit
 Operation




                                                                                     from project
   phase




                         budget           maintenance             and loosing face
    and




                                              Minor          Avoidance of              Ignorance of
                                             damages         responsibility              damages
        Mental
        models
                                                           Malfunction project
        Actual                                                                                               33
       situation
Case I




         34
Case II




          35
Summary of mental models toward
            project management
   Perspective       Department of       Local Administration       Project Users
                     Water Resources            Office

Priority of project Delivery of         Responsibility for all   Water needs and
goals               construction        infrastructure project   water usage
                    project
Main driving        Organization        Community                Economic
force               missions and        development              incentives
                    regulations
Timescale of        Short to medium     Long term                Long term
implementation term
Ownership of the Authority from law     Local authority and     Based on benefit
project             and regulation      organization capability from a project
Responsibility of   Central authority   Local authority and      Based on benefit
operation and       and available       available budget         from a project
maintenance         budget                                                     36
Summary of mental models toward
           project management
 Perspective       Department of Water        Local Administration        Project Users
                        Resources                    Office

Causes of     -     Budget constraint     -     Budget constraint -      Self-interest in
malfunction -       No project life cycle -     Limited number           priority
/ Constraints       management plan             of skilled-workers -     Lack of
              -     Politician            -     Fear of burden           knowledge in
                    interference                from malfunction         operation and
               -    Corruption                  project                  maintenance
               -    Lack of coordination                           -     Absence of
                    between units in                                     responsibility
                    the organization                                     sharing
               -    Low quality control                              -   Ignorance of
                    in construction                                      malfunction
                    work                                             -   Belief in
                                                                         politician’s power
                                                                                      37
Identified constraints

                Lack of planning for implementation of the
                DWR



                Capacity of the DWR and staff in project
                management



                Absence of stakeholder participation

DWR= the Department of Water Resources                       38
Proposed measures




                    39
Constraints and proposed measures

           Constraint 1:                           Thematic 1:
Lack of planning for                     Utilization project life cycle
implementation of the DWR                planning and management

           Constraint 2:                           Thematic 2:
Capacity of the DWR and                  Improving the DWR capacity
staff in project management                   to deliver service

           Constraint 3:                           Thematic 3:
Absence of stakeholder                    Stakeholder participation
participation                               and building capacity

DWR= the Department of Water Resources                              40
Thematic 1: Utilization project life
 cycle planning and management
                    Identification


       Evaluation                    Appraisal




       Operation
          and                        Financing
      maintenance

                    Construction


                                                 41
Thematic 1: Utilization project life
               cycle planning and management
          Project phase                                 Proposed measures
 Project identification                     1. The DWR should conduct situation and
                                               problem analysis and stakeholder
               Identification
                                               analysis
 Evaluation                     Appraisal   2. Incorporate “Hierarchical cooperative
                                               objectives or goals” in the project
                                               identification process
 Operation
    and                         Financing
maintenance

               Construction




                                                                                  42
Thematic 1: Utilization project life
               cycle planning and management
         Project phase                                    Proposed measures
    Project appraisal                       1. The DWR should concern on the
               Identification
                                               sustainability aspects of the project
                                               formulation
 Evaluation                     Appraisal


                                            2. Project should have capacity to
 Operation
                                               continue and become sustainable
    and
maintenance
                                Financing      without external support
               Construction
                                            3. Estimation the life cycle cost over the
                                               whole life of the project or at least first
                                               four years is needed
                                                                                        43
Thematic 1: Utilization project life
               cycle planning and management
         Project phase                                  Proposed measures
     Project financial                      1. The DWR’s executive negotiation with
      management                               the Bureau of Budget on operational
                                               and maintenance fund
               Identification


 Evaluation                     Appraisal




 Operation
    and                         Financing
maintenance

               Construction




                                                                                  44
Thematic 1: Utilization project life
               cycle planning and management
         Project phase                                   Proposed measures
Project construction                        1. Formulate the construction quality
and quality control                            control committee composed of
                                               representatives from the DWR, the
               Identification
                                               Local Administration Office and project
 Evaluation                     Appraisal

                                            2. Foster a proper sense of professional
                                               ethics in the DWR staff of pride in the
 Operation
    and                         Financing      work and the value of the job
maintenance

               Construction
                                            3. Continual education, training and
                                               monitoring system are necessary
                                                                                         45
Thematic 1: Utilization project life
               cycle planning and management
         Project phase                                      Proposed measures
Project operation and 1. Established the provisional operation plan and
 maintenance phase       maintenance schedule
                                            2.   The DWR should take a role of a facilitator to
               Identification                    facilitate the technical issues
                                            3.   Maintain a performance database including
 Evaluation                     Appraisal        maintenance records, condition assessment
                                                 data and other items
                                            4.   Periodic inspection in project performance is
 Operation                                       needed
    and                         Financing
maintenance                                 5.   Adequate funding and resources must be
               Construction
                                                 secured for the operation and maintenance
                                            6.   Establish the emergency maintenance fund at
                                                 the central office

                                                                                              46
Thematic 1: Utilization project life
               cycle planning and management
         Project phase                                  Proposed measures
  Project monitoring                        1. Framework of the project assessment
    and evaluation                             system
               Identification


 Evaluation                     Appraisal




 Operation
    and                         Financing
maintenance

               Construction




                                                                                     47
Framework of the project assessment system
                                         Indicator categories
    Index        Themes                  Resources used correctly
                                 Obtained result compared to result used
                                  Complication of project management
                Efficiency
                                         Stakeholder relationship
                                   Implemented activities compared to
                                          objectives and plan
               Effectiveness       Degree of achieving expected results
    Overall                          Long-term impact on the project
  assessment                            surrounding environment
                  Impact        Direct and indirect change produced by the
                                                  project
                                Likelihood the benefit produced by the
                                 project to continue without external
               Sustainability                  subsidies
                                Capacity of organization established for the
                                                  project
                                   Developed competencies of staff             48
Thematic 2: Improving the DWR
   capacity to deliver service
Establishment of “the capacity building unit”

• provide training, technical assistance and
  management support service

Identify and develop a series of practical
guidelines for operation
• Review process of project planning, designing,
  construction and implementing
• Guideline for appropriate and effective public
  participation, etc.

                                                   49
Thematic 3: Stakeholder participation
       and capacity building
  Stakeholder participation and stakeholder
  capacity building program is a repetitive activity
  • could be achieved through supportive reasonable
    budget

  Diagnose and identify particular factors that can
  make public participation difficult to implement
  • describe the difficulties and identifies practice

  Be carefully in adopting a process for selecting
  best techniques and tools for the situation
                                                        50
Propose of Beneficiary Contribution
              Approach
1. Scheme is identified by local with technical
   supports and construction work from the DWR
2. Beneficiaries and related stakeholders must be
   involved in all stages
3. Scheme must produce sufficient benefit for
   project life cycle management
4. Beneficiaries contribute equivalent to the cost of
   first year of Operation and maintenance
5. Monitoring and evaluation system must be
   applied to project

                                                    51
Stages in Beneficiary Contribution
              Approach
                                                 III: Construction
                                                 and operation and
                                                 maintenance
                       II: Water users’          phase
                       cooperative               • Beneficiary
                       establishment and a         contribution
                       project plan              • Project O&M
                       development phase           supported by the
I: Development of                                  DWR
                       • Detailed design& Cost
project preliminary
                       • Stakeholder analysis
phase
                       • Water user
• Preliminary design     cooperative
• Information            organization & MOU
  sharing
                                                                  52
Conclusion




             53
Conclusion 1: Integrated stakeholder’s
  mental models in failure analysis
• Applicable and useful method




                                     54
Conclusion 2: Causes of malfunction
              project
– Lack of planning for implementation of the
  Department of Water Resources (DWR)
– Capacity of the DWR and staff in project planning
  and management; and
– Absence of stakeholder participation and
  stakeholder capacity building




                                                  55
Conclusion 3: Stakeholder’s behavior
• The Department of Water Resources (DWR)
   – Focusing on delivery project side
   – Low respond to project operation and maintenance
     management demand
• Local administration office
   – Recognized their limitation of budget and low capability
   – Avoid or transfer burden may occurred from malfunction
     project to the project owner
• Project users
   – Very sensitive, income is main driving force
   – Disregard of maintenance  ignorance after project
     became malfunction and made no benefit  the project
     was abandoned                                              56
Conclusion 4: Proposed measures
• Three thematic
  – Thematic 1:Utilization project life cycle planning
    and management
  – Thematic 2:Improving the DWR capacity
    to deliver service
  – Thematic 3:Stakeholder participation and building
    capacity
• Beneficiary contribution approach

                                                     57
Publications




               58
Publications
International Journal
1. Uraiwong, P. & Watanabe T. (2012). “Small-scaled water
   resources project in Thailand: Failure analysis and
   improvement of stakeholder involvement”. Journal of
   Society for Social Management Systems (Peer-reviewed)
   serial SMS12-6080.
2. Komatsu T., Nakaya S., Uraiwong P., and Watanabe T. "Multi-
   Stakeholder Mental Model in Monobe River Improvement
   and Maintenance. "Journal of Society for Social
   Management Systems (Peer-reviewed) serial SMS12-9459.
3. Uraiwong, P. & Watanabe T. (2011). “Stakeholder analysis of
   water resources projects in Thailand”. Journal of Society for
   Social Management Systems (Peer-reviewed) serial SMS11-
   5587.

                                                               59
Publications
International Conference
1.   Uraiwong, P. & Watanabe T. (2012). “Small-scaled water resources
     project in Thailand: Failure analysis and improvement of stakeholder
     involvement”. The 8th International Symposium on Social Management
     Systems SSMS2012 - Disaster Prevention and Reconstruction
     Management -, 2-4 May 2012, Kaohsiung, Taiwan, R.O.C.
2.   Komatsu T., Nakaya S., Uraiwong P., and Watanabe T. (2012). "Multi-
     Stakeholder Mental Model in Monobe River Improvement and
     Maintenance. The 8th International Symposium on Social Management
     Systems SSMS2012 - Disaster Prevention and Reconstruction
     Management -, 2-4 May 2012, Kaohsiung, Taiwan, R.O.C.
3.   Uraiwong, P. & Watanabe T. (2011). “Stakeholder analysis of water
     resources projects in Thailand”. IESL-SSMS Joint International
     Symposium on Social Management Systems 2011, 14-16 September
     2011, Colombo, Sri Lanka
                                                                            60
Publications
International Conference (cont.)
4. Uraiwong, P. & Watanabe T. (2012). "Public Awareness
Campaigns and Education Program in the Monobe River."
Thailand-Japan International Academic Conference 2012
Proceeding. Tokyo, Japan, October 2012
5. Uraiwong, P. & Watanabe T. (2011). "Model for Small-scaled
Water Resources Project Development: Based on Thai Case."
Thailand-Japan International Academic (TJIA) Conference 2011.
Tokyo, Japan, November 2011
6. Uraiwong, P. & Watanabe T. (2010). “Community mechanisms
for water resources risk management”. Proceeding of
International conference for a sustainable Greater Mekong
Subregion, King Mongkut’s University of
Technology, Bangkok, Thailand,26-27 August 2010, pp.431-434.

                                                            61
62

More Related Content

Similar to Failure analysis integrated multi stakeholder mental model and project life cycle

HCI lecture notes by Sanjay Goel, JIIT 2012
HCI lecture notes by Sanjay Goel, JIIT 2012HCI lecture notes by Sanjay Goel, JIIT 2012
HCI lecture notes by Sanjay Goel, JIIT 2012Sanjay Goel
 
Opening Horizons keynote COST Poland 2011
Opening Horizons keynote COST Poland 2011Opening Horizons keynote COST Poland 2011
Opening Horizons keynote COST Poland 2011Totti Könnölä
 
Design Principles of Advanced Task Elicitation Systems
Design Principles of Advanced Task Elicitation SystemsDesign Principles of Advanced Task Elicitation Systems
Design Principles of Advanced Task Elicitation SystemsProf. Dr. Alexander Maedche
 
Adjusting the Focus: Usability Study Aligns Organization Vision with Communit...
Adjusting the Focus: Usability Study Aligns Organization Vision with Communit...Adjusting the Focus: Usability Study Aligns Organization Vision with Communit...
Adjusting the Focus: Usability Study Aligns Organization Vision with Communit...Laurie Bennett
 
OO Development 1 - Introduction to Object-Oriented Development
OO Development 1 - Introduction to Object-Oriented DevelopmentOO Development 1 - Introduction to Object-Oriented Development
OO Development 1 - Introduction to Object-Oriented DevelopmentRandy Connolly
 
Luciano pr 08-849_ontology_evaluation_methods_metrics
Luciano pr 08-849_ontology_evaluation_methods_metricsLuciano pr 08-849_ontology_evaluation_methods_metrics
Luciano pr 08-849_ontology_evaluation_methods_metricsJoanne Luciano
 
Luciano pr 08-849_ontology_evaluation_methods_metrics
Luciano pr 08-849_ontology_evaluation_methods_metricsLuciano pr 08-849_ontology_evaluation_methods_metrics
Luciano pr 08-849_ontology_evaluation_methods_metricsJoanne Luciano
 
small-scale water resources project development
small-scale water resources project developmentsmall-scale water resources project development
small-scale water resources project developmentPiriya Uraiwong
 
Open2012 teaching-innovation-multidisciplinary-collaboration
Open2012 teaching-innovation-multidisciplinary-collaborationOpen2012 teaching-innovation-multidisciplinary-collaboration
Open2012 teaching-innovation-multidisciplinary-collaborationthe nciia
 
iSamples Research Coordination Network (C4P Webinar)
iSamples Research Coordination Network (C4P Webinar)iSamples Research Coordination Network (C4P Webinar)
iSamples Research Coordination Network (C4P Webinar)Kerstin Lehnert
 
시나리오 베이스 디자인 방법론 (Scenario Based Design)
시나리오 베이스 디자인 방법론 (Scenario Based Design)시나리오 베이스 디자인 방법론 (Scenario Based Design)
시나리오 베이스 디자인 방법론 (Scenario Based Design)Hajin Lim
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010NASAPMC
 

Similar to Failure analysis integrated multi stakeholder mental model and project life cycle (20)

HCI lecture notes by Sanjay Goel, JIIT 2012
HCI lecture notes by Sanjay Goel, JIIT 2012HCI lecture notes by Sanjay Goel, JIIT 2012
HCI lecture notes by Sanjay Goel, JIIT 2012
 
Opening Horizons keynote COST Poland 2011
Opening Horizons keynote COST Poland 2011Opening Horizons keynote COST Poland 2011
Opening Horizons keynote COST Poland 2011
 
Design Principles of Advanced Task Elicitation Systems
Design Principles of Advanced Task Elicitation SystemsDesign Principles of Advanced Task Elicitation Systems
Design Principles of Advanced Task Elicitation Systems
 
Single-user problems
Single-user problemsSingle-user problems
Single-user problems
 
Adjusting the Focus: Usability Study Aligns Organization Vision with Communit...
Adjusting the Focus: Usability Study Aligns Organization Vision with Communit...Adjusting the Focus: Usability Study Aligns Organization Vision with Communit...
Adjusting the Focus: Usability Study Aligns Organization Vision with Communit...
 
OO Development 1 - Introduction to Object-Oriented Development
OO Development 1 - Introduction to Object-Oriented DevelopmentOO Development 1 - Introduction to Object-Oriented Development
OO Development 1 - Introduction to Object-Oriented Development
 
Luciano pr 08-849_ontology_evaluation_methods_metrics
Luciano pr 08-849_ontology_evaluation_methods_metricsLuciano pr 08-849_ontology_evaluation_methods_metrics
Luciano pr 08-849_ontology_evaluation_methods_metrics
 
Luciano pr 08-849_ontology_evaluation_methods_metrics
Luciano pr 08-849_ontology_evaluation_methods_metricsLuciano pr 08-849_ontology_evaluation_methods_metrics
Luciano pr 08-849_ontology_evaluation_methods_metrics
 
IEA DSM Pecha Kucha Brussels workshop
IEA DSM Pecha Kucha Brussels workshopIEA DSM Pecha Kucha Brussels workshop
IEA DSM Pecha Kucha Brussels workshop
 
small-scale water resources project development
small-scale water resources project developmentsmall-scale water resources project development
small-scale water resources project development
 
Neri conference Task 24
Neri conference Task 24Neri conference Task 24
Neri conference Task 24
 
How a behavioral scientist can work productively with an HCI researcher?
How a behavioral scientist can work productively with an HCI researcher?How a behavioral scientist can work productively with an HCI researcher?
How a behavioral scientist can work productively with an HCI researcher?
 
MCP1
MCP1MCP1
MCP1
 
Open2012 teaching-innovation-multidisciplinary-collaboration
Open2012 teaching-innovation-multidisciplinary-collaborationOpen2012 teaching-innovation-multidisciplinary-collaboration
Open2012 teaching-innovation-multidisciplinary-collaboration
 
Hmc webinar 11 10 14
Hmc webinar 11 10 14Hmc webinar 11 10 14
Hmc webinar 11 10 14
 
iSamples Research Coordination Network (C4P Webinar)
iSamples Research Coordination Network (C4P Webinar)iSamples Research Coordination Network (C4P Webinar)
iSamples Research Coordination Network (C4P Webinar)
 
Managing change
Managing changeManaging change
Managing change
 
GIA Singapore - Introduction (Mulgan)
GIA Singapore - Introduction (Mulgan)GIA Singapore - Introduction (Mulgan)
GIA Singapore - Introduction (Mulgan)
 
시나리오 베이스 디자인 방법론 (Scenario Based Design)
시나리오 베이스 디자인 방법론 (Scenario Based Design)시나리오 베이스 디자인 방법론 (Scenario Based Design)
시나리오 베이스 디자인 방법론 (Scenario Based Design)
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010
 

More from Piriya Uraiwong

การวิเคราะห์โครงการแหล่งน้ำขนาดเล็กโดยวิธี integrated mental model and projec...
การวิเคราะห์โครงการแหล่งน้ำขนาดเล็กโดยวิธี integrated mental model and projec...การวิเคราะห์โครงการแหล่งน้ำขนาดเล็กโดยวิธี integrated mental model and projec...
การวิเคราะห์โครงการแหล่งน้ำขนาดเล็กโดยวิธี integrated mental model and projec...Piriya Uraiwong
 
การบริหารจัดการความเสี่ยงโครงการแหล่งน้ำขนาดเล็กโดยกลุ่มผู้มีส่วนได้ส่วนเสีย
การบริหารจัดการความเสี่ยงโครงการแหล่งน้ำขนาดเล็กโดยกลุ่มผู้มีส่วนได้ส่วนเสียการบริหารจัดการความเสี่ยงโครงการแหล่งน้ำขนาดเล็กโดยกลุ่มผู้มีส่วนได้ส่วนเสีย
การบริหารจัดการความเสี่ยงโครงการแหล่งน้ำขนาดเล็กโดยกลุ่มผู้มีส่วนได้ส่วนเสียPiriya Uraiwong
 
Multi stakeholder risk management in small-scaled water resources project
Multi stakeholder risk management in small-scaled water resources projectMulti stakeholder risk management in small-scaled water resources project
Multi stakeholder risk management in small-scaled water resources projectPiriya Uraiwong
 
Public awareness campaigns and education programs in the Monobe River
Public awareness campaigns and education programs in the Monobe RiverPublic awareness campaigns and education programs in the Monobe River
Public awareness campaigns and education programs in the Monobe RiverPiriya Uraiwong
 
Thai flood 2011 and risk perception (Japanese)
Thai flood 2011 and risk perception (Japanese)Thai flood 2011 and risk perception (Japanese)
Thai flood 2011 and risk perception (Japanese)Piriya Uraiwong
 
multi-party risk management for water resources project
multi-party risk management for water resources projectmulti-party risk management for water resources project
multi-party risk management for water resources projectPiriya Uraiwong
 
Stakeholder analysis for small-scale water resource project in Thailand
Stakeholder analysis for small-scale water resource project in ThailandStakeholder analysis for small-scale water resource project in Thailand
Stakeholder analysis for small-scale water resource project in ThailandPiriya Uraiwong
 

More from Piriya Uraiwong (7)

การวิเคราะห์โครงการแหล่งน้ำขนาดเล็กโดยวิธี integrated mental model and projec...
การวิเคราะห์โครงการแหล่งน้ำขนาดเล็กโดยวิธี integrated mental model and projec...การวิเคราะห์โครงการแหล่งน้ำขนาดเล็กโดยวิธี integrated mental model and projec...
การวิเคราะห์โครงการแหล่งน้ำขนาดเล็กโดยวิธี integrated mental model and projec...
 
การบริหารจัดการความเสี่ยงโครงการแหล่งน้ำขนาดเล็กโดยกลุ่มผู้มีส่วนได้ส่วนเสีย
การบริหารจัดการความเสี่ยงโครงการแหล่งน้ำขนาดเล็กโดยกลุ่มผู้มีส่วนได้ส่วนเสียการบริหารจัดการความเสี่ยงโครงการแหล่งน้ำขนาดเล็กโดยกลุ่มผู้มีส่วนได้ส่วนเสีย
การบริหารจัดการความเสี่ยงโครงการแหล่งน้ำขนาดเล็กโดยกลุ่มผู้มีส่วนได้ส่วนเสีย
 
Multi stakeholder risk management in small-scaled water resources project
Multi stakeholder risk management in small-scaled water resources projectMulti stakeholder risk management in small-scaled water resources project
Multi stakeholder risk management in small-scaled water resources project
 
Public awareness campaigns and education programs in the Monobe River
Public awareness campaigns and education programs in the Monobe RiverPublic awareness campaigns and education programs in the Monobe River
Public awareness campaigns and education programs in the Monobe River
 
Thai flood 2011 and risk perception (Japanese)
Thai flood 2011 and risk perception (Japanese)Thai flood 2011 and risk perception (Japanese)
Thai flood 2011 and risk perception (Japanese)
 
multi-party risk management for water resources project
multi-party risk management for water resources projectmulti-party risk management for water resources project
multi-party risk management for water resources project
 
Stakeholder analysis for small-scale water resource project in Thailand
Stakeholder analysis for small-scale water resource project in ThailandStakeholder analysis for small-scale water resource project in Thailand
Stakeholder analysis for small-scale water resource project in Thailand
 

Failure analysis integrated multi stakeholder mental model and project life cycle

  • 1. FAILURE ANALYSIS OF MALFUNCTION WATER RESOURCES PROJECT IN THE NORTHEASTERN THAILAND: INTEGRATED MENTAL MODELS AND PROJECT LIFE CYCLE PERSPECTIVE APPROACH By Piriya URAIWONG Kochi University of Technology Advisor: Professor, Dr.Tsunemi Watanabe Examination Committee: Professor, Dr.Seigo Nasu Professor, Dr.Osamu Tomisawa Professor, Dr.Yoshinori Nakagawa Associate Professor, Dr.Takashi Goso 2013/2/12
  • 2. Research questions Answer 1. Causes of this malfunction? Determine 2. Stakeholder’s behavior associated with malfunction? 3. Solution for the problem? Conclusions Research Methodology problem 1. Identified failure Malfunction 1. Failure analysis causes and water 2. Stakeholder’s solutions resources mental models 2. New failure project analysis analysis approach 1. Integrated mental models with WBS in project life cycle perspective Permit 2. Multi-Stakeholder’s behavior in Produce malfunction project Results 2
  • 3. Defining “Malfunction” and “Failure” • “Malfunction”- Fail to work normally or properly (v.), failure of this kind (n.) (Oxford advanced learner’s dictionary,1989) • “Failure” – The inability of the project to deliver the intended benefit to the identified stakeholders • Many levels of failure- from mild failure to complete failure (Layton, 2011) 3
  • 4. Problem statement • Malfunction small-scaled water resources project – “a project that Fail to work normally or properly to deliver the intended benefit to the identified stakeholders” 4
  • 5. Problem statement 5% 8% 17% Good condition Minor reconstruction Rehabilitation 27% 43% Re-construction Rejected Water resources project condition (Department of Water Resources: DWR, 2008) 5
  • 6. Research objectives 1. To identify factors which cause malfunction in water resources project 2. To study behavior of key stakeholder who participated in malfunction of water resources project 3. To offer tools and methods that loosen constraints regarding malfunction water resources project 6
  • 7. Research questions RQ1 • What are factors which cause an malfunction of water resources project? • What are behavior of key stakeholder’s who RQ2 participated in malfunction of water resources project? • What would be proposed measures or RQ3 mechanism to improve water resources project management in Thailand? 7
  • 9. Research methodology 1. Preliminary diagnose malfunction project: Failure Knowledge Database Develop analysis method 2. Introducing integrated failure analysis approach Application to cases 3. Multi-Stakeholder’s mental models analysis Constraint-measure 4. Proposes measures and action plan 9
  • 10. Introducing integrated mental models and project life cycle approach for failure analysis 10
  • 11. Previous work on failure analysis • Check sheets and Modified Pareto analysis (1897) • Cause-and-effect diagram (Ishikawa diagrams, 1960’s) • Fault tree analysis (Fussel, 1976) • Failure Mode and Effects Analysis: FMEA (IEEE std 352) • Failure knowledge database (Hatamura, 2005) • Integrated Water Resources Management (1992) 11
  • 12. Limitation of conventional analysis and Proposal of new approach • Conventional analysis -> Less include stakeholder’s mindset in failure analysis Recommendation Root cause Data collection generation and identification implementation Integrate Propose -> Overcome limitation of Stakeholder’s mindset regardless complexity of stakeholder mindset and behavior associated with a failure project 12
  • 13. Mental models • “The images (attitudes and assumptions) we carry in our minds about ourselves, other people, institutions, and every aspect of the world which guide our interpretations and behavior.” (HSBC sign ad) 13
  • 14. Coding and mapping mental models Stakeholder semi- Coding Mapping structured interview Statement Network of concepts concepts Influence (Adapted from Carley, 1997) map 14
  • 15. Key aspects and process of mental models of an individual in decision influence Heuristics/ (1) Selective Mental models observation biases (2) Perception Background: personal, cultural, education (changed) Individual (4) (3) Action Situation (AS) Framing issue Mental models / Outcome processing Action Possible actions & effects (Adapted from Isendahl, 2010) 15
  • 16. Mental models and situations Project AS1 AS2 AS3 AS4 AS5 Mental Mental Mental models 1 models 2 models 3 AS = Action situation (Pahl-Wostl et.al., 2006) 16
  • 17. Project life cycle and work breakdown structure The project life cycle Initiating and Operation and Construction Planning Maintenance Work Work Work element 1.1 element 2.1 element 3.1 Work Work Work element 1.2 element 2.2 element 3.2 17 (Haugan, 2003)
  • 18. Chronological progression of failure Background Cause Event Action Sequel (Result) (Hatamura, 2005) 18
  • 19. Integrated approach Differences of actual situation Influence Consequence Integrate Influence 19
  • 20. Integrated framework Stakeholder 1 Stakeholder 2 Stakeholder 3 Mental Mental Mental Cause/ models 1 models 2 models 3 Background Planning phase AS 1.1 AS 2.1 AS 3.1 Event/ Construction phase AS 1.2 AS 2.2 AS 3.2 Action Operation and AS 2.3 AS 1.3 AS 3.3 maintenance phase Result/ Sequel 20
  • 21. Integrated process 1. Define problem context: project, phenomenal, etc. (by Failure knowledge database and project lifecycle and work breakdown structure) 2. Identify stakeholders and elicit stakeholder’s mental models 3. Apply multi-stakeholder’s mental models under project life cycle and work breakdown structure 21
  • 22. Practical application of integrated approach 22
  • 23. Failure Knowledge Database Cause Actions Results (Hatamura, 2005) 23
  • 24. Initial diagnosed factors related to malfunction project 01. Occurrence of abnormal 02. Insufficient knowledge Causes : 08. Poor concept 09. Poor planning : Actions 15. Self-protection 16. Economic loss : Results 21. External damage 24 (Complete result can be found in attachment # 1)
  • 25. Case study I Fractures on Broken radial Downstream concrete gates with stolen blockage structure pulleys 25
  • 26. Case study II No use of canal Structural (growing rice in No area the canal) failure maintenance 26
  • 27. Semi-structured interview Interviewee group Number Officer in the Department of Water 5 Resources (DWR) Officer in the Local Administration 4 Office (LAO) Project user 12 Total 21 27
  • 28. Partial mental models influence diagram The DWR lack of The DWR lack of training continuity to follow and education in project up the project operation and maintenance Project user disregard of procedure No specific budget for maintenance work Project user lack of maintenance Idea of “I need water, but I don’t Malfunction of project want to fix when the project is broken” 28
  • 29. DWR-HQ03 mental models influence diagram the Bureau of Budget didn't see importance of bureaucratic reform of the maintenance budget Thai government in October DWR-HQ03 2002 establishment of no maintenance budget when the DWR was the DWR established human resource management problem of agency solving by making projects under the ARD shortage number alliance organization vision, were transfered to the DWR mission and policy design budget and the DWR transfers adaptation of officers projects inventory small public hearing technology support knowledge to local from various agencies system process for couple hours administration the Decentralization process of budget budget and projects approvement took almost inventory approvement from previous constitution didn't Act 1999 2-3 years the cabinet put people at center pay attention on public project O&M, project and adjust ourselve participation management, establishment of projects transfer to local creat the DWR water user group adminstration office value trust from local is the different budget system most important from the DWR problem in public no budget for project no activity on lack of continuity on participation project maintenance attitude of the maintenance projects DWR officers local administration office's regional office annual budget problems in first transfered project negotiation with facing problem implementation plan couple years politician public participation process malfunction not sharing experiences and stated in the Prime Minister projects problems in public Office Regulation the local administration participation work need to manage their own projects proposed projects proposed by budget tendency of by politicain running by own technical support no attention on maintenance local's need decreasing in number fund from the DWR work for projects transfered from the ARD government implement the DWR more public participation coordination between locals satisfy with a implementation plan politician, the DWR and activity the DWR does not increasing income support budget all time establishment of project local is needed water user group area development regional office pay regional office project otherwise they will cooperation between attention on new project responsibility maintenance work only wait for help the DWR and locals the DWR provide local local feel that the DWR a stage to speak doesn't leave them integrated work of bureaus in the DWR proposal on hiring consultant company for public participation work 29
  • 30. KY-LAO02 mental models influence diagram no water user group for free access insufficient water the weir project drastic water fluctuation heavy traffic over quantity for agriculture in dry and wet season flooding use the weir Kud Sri Pum weir the pulley was pumping station and user project stolen slump and cracks decision made by group establishment occurance on the majority of water users infrastructure no bridge to cross the unable to close stream in this area lack of knowledge on the gate project operation and conflict resolution done by maintenance voting among water users malfunction of the function as a bridge to cross a unequal benefit disign rule preventing project among water users overloaded truck to cross canal to transport agriculture product the weir perceive as project working well afraid of occurance of social mechanism serious structure damages in problems related to tax payers preventing personal incooperate with future this project selfishness the TAO becoming the TAO expectation of benefit burden looking for solution from from the local percieved as sense request full rehabilitation of the TAO as priority administration of ownership project to be in a good condition rejection on project villager benefit lost transfer from the DWR the TAO responsibility for all civil work KY-LAO01 mental models accept the project the TAO from the DWR project damages uncapable of help assesment under capability of over capability of the TAO the TAO solving problem by themselves at last looking for help from repair work othe agencies 30
  • 31. KY-LV06 mental models influence diagram small storage tempolary weir and always broken in rain season KY-LV06 discussion among local small conflict between negotiation by villagers for new wier upstream and downstream villager chief villager chief requested the politician contacted project was project to the local rule for water intake from the the ARD agnency constructed meeting among politician stream from villagers's villagers agreement difficult to get a function as a project water usage for bridge pumping station agriculture villagers agree and need to take care of monitoring respect the rule a project overloaded truck pulley chain was serving half of the broken sub-district area fixed by villagers's pulleys were stolen if budget is sufficient, money villagers will help to take buy new pulley from care a project old concrete villagers's money water leaking from two out of four sluice broken rubber seal spillway gate are not working limited budget of the around the sluicegate DWR and the TAO large amount of water released from the dam in water leaking from one time the gate project understanding the explanation and malfunctions limitation flooding weir structure is compromisation by secured villager chief no maintenance plan poor road damages on negotiation with the dam maintenance work agriculture products condition on water release regulation by the DWR difficulty in consensus on so far we can use public property issue unwilling to spend much it, it's ok money on public looking for appropriate no cooperation with adding riprap at difficulty in agriculture income lost maintenance work compensation from the dam the TAO downstream product transport concern for personal benefit rather than public unwilling to share responsibility but want the sometimes fix some damages because villagers benefit from benefit from a project is percieved as sense of 31 benefit same benefit a project ownership22
  • 32. Malfunction influence diagram Stakeholder A Stakeholder B Stakeholder C Mental Mental Mental Planning phase Work models models models element AS1 AS1 AS1 Mental Mental Mental Construction Work models models models phase element AS2 AS2 AS2 Mental Mental Mental phase O& M Work models models models element AS3 AS3 AS3 Sequel 32
  • 33. Malfunction influence diagram Department of Water Resources Local Administration Project User Office Low attention Being ignored development Being ignored in stakeholder from from Project Less public phase participation participation participation participation activity No long-term No project Low project plan Poor planning involvement information sharing Construction Focus on project No training for No involvement in No involvement in operation and construction construction phase delivery maintenance No Expect Project’s No knowledge knowledge benefit from infrastructure project maintenance No maintenance No Fear of burden No benefit Operation from project phase budget maintenance and loosing face and Minor Avoidance of Ignorance of damages responsibility damages Mental models Malfunction project Actual 33 situation
  • 34. Case I 34
  • 35. Case II 35
  • 36. Summary of mental models toward project management Perspective Department of Local Administration Project Users Water Resources Office Priority of project Delivery of Responsibility for all Water needs and goals construction infrastructure project water usage project Main driving Organization Community Economic force missions and development incentives regulations Timescale of Short to medium Long term Long term implementation term Ownership of the Authority from law Local authority and Based on benefit project and regulation organization capability from a project Responsibility of Central authority Local authority and Based on benefit operation and and available available budget from a project maintenance budget 36
  • 37. Summary of mental models toward project management Perspective Department of Water Local Administration Project Users Resources Office Causes of - Budget constraint - Budget constraint - Self-interest in malfunction - No project life cycle - Limited number priority / Constraints management plan of skilled-workers - Lack of - Politician - Fear of burden knowledge in interference from malfunction operation and - Corruption project maintenance - Lack of coordination - Absence of between units in responsibility the organization sharing - Low quality control - Ignorance of in construction malfunction work - Belief in politician’s power 37
  • 38. Identified constraints Lack of planning for implementation of the DWR Capacity of the DWR and staff in project management Absence of stakeholder participation DWR= the Department of Water Resources 38
  • 40. Constraints and proposed measures Constraint 1: Thematic 1: Lack of planning for Utilization project life cycle implementation of the DWR planning and management Constraint 2: Thematic 2: Capacity of the DWR and Improving the DWR capacity staff in project management to deliver service Constraint 3: Thematic 3: Absence of stakeholder Stakeholder participation participation and building capacity DWR= the Department of Water Resources 40
  • 41. Thematic 1: Utilization project life cycle planning and management Identification Evaluation Appraisal Operation and Financing maintenance Construction 41
  • 42. Thematic 1: Utilization project life cycle planning and management Project phase Proposed measures Project identification 1. The DWR should conduct situation and problem analysis and stakeholder Identification analysis Evaluation Appraisal 2. Incorporate “Hierarchical cooperative objectives or goals” in the project identification process Operation and Financing maintenance Construction 42
  • 43. Thematic 1: Utilization project life cycle planning and management Project phase Proposed measures Project appraisal 1. The DWR should concern on the Identification sustainability aspects of the project formulation Evaluation Appraisal 2. Project should have capacity to Operation continue and become sustainable and maintenance Financing without external support Construction 3. Estimation the life cycle cost over the whole life of the project or at least first four years is needed 43
  • 44. Thematic 1: Utilization project life cycle planning and management Project phase Proposed measures Project financial 1. The DWR’s executive negotiation with management the Bureau of Budget on operational and maintenance fund Identification Evaluation Appraisal Operation and Financing maintenance Construction 44
  • 45. Thematic 1: Utilization project life cycle planning and management Project phase Proposed measures Project construction 1. Formulate the construction quality and quality control control committee composed of representatives from the DWR, the Identification Local Administration Office and project Evaluation Appraisal 2. Foster a proper sense of professional ethics in the DWR staff of pride in the Operation and Financing work and the value of the job maintenance Construction 3. Continual education, training and monitoring system are necessary 45
  • 46. Thematic 1: Utilization project life cycle planning and management Project phase Proposed measures Project operation and 1. Established the provisional operation plan and maintenance phase maintenance schedule 2. The DWR should take a role of a facilitator to Identification facilitate the technical issues 3. Maintain a performance database including Evaluation Appraisal maintenance records, condition assessment data and other items 4. Periodic inspection in project performance is Operation needed and Financing maintenance 5. Adequate funding and resources must be Construction secured for the operation and maintenance 6. Establish the emergency maintenance fund at the central office 46
  • 47. Thematic 1: Utilization project life cycle planning and management Project phase Proposed measures Project monitoring 1. Framework of the project assessment and evaluation system Identification Evaluation Appraisal Operation and Financing maintenance Construction 47
  • 48. Framework of the project assessment system Indicator categories Index Themes Resources used correctly Obtained result compared to result used Complication of project management Efficiency Stakeholder relationship Implemented activities compared to objectives and plan Effectiveness Degree of achieving expected results Overall Long-term impact on the project assessment surrounding environment Impact Direct and indirect change produced by the project Likelihood the benefit produced by the project to continue without external Sustainability subsidies Capacity of organization established for the project Developed competencies of staff 48
  • 49. Thematic 2: Improving the DWR capacity to deliver service Establishment of “the capacity building unit” • provide training, technical assistance and management support service Identify and develop a series of practical guidelines for operation • Review process of project planning, designing, construction and implementing • Guideline for appropriate and effective public participation, etc. 49
  • 50. Thematic 3: Stakeholder participation and capacity building Stakeholder participation and stakeholder capacity building program is a repetitive activity • could be achieved through supportive reasonable budget Diagnose and identify particular factors that can make public participation difficult to implement • describe the difficulties and identifies practice Be carefully in adopting a process for selecting best techniques and tools for the situation 50
  • 51. Propose of Beneficiary Contribution Approach 1. Scheme is identified by local with technical supports and construction work from the DWR 2. Beneficiaries and related stakeholders must be involved in all stages 3. Scheme must produce sufficient benefit for project life cycle management 4. Beneficiaries contribute equivalent to the cost of first year of Operation and maintenance 5. Monitoring and evaluation system must be applied to project 51
  • 52. Stages in Beneficiary Contribution Approach III: Construction and operation and maintenance II: Water users’ phase cooperative • Beneficiary establishment and a contribution project plan • Project O&M development phase supported by the I: Development of DWR • Detailed design& Cost project preliminary • Stakeholder analysis phase • Water user • Preliminary design cooperative • Information organization & MOU sharing 52
  • 54. Conclusion 1: Integrated stakeholder’s mental models in failure analysis • Applicable and useful method 54
  • 55. Conclusion 2: Causes of malfunction project – Lack of planning for implementation of the Department of Water Resources (DWR) – Capacity of the DWR and staff in project planning and management; and – Absence of stakeholder participation and stakeholder capacity building 55
  • 56. Conclusion 3: Stakeholder’s behavior • The Department of Water Resources (DWR) – Focusing on delivery project side – Low respond to project operation and maintenance management demand • Local administration office – Recognized their limitation of budget and low capability – Avoid or transfer burden may occurred from malfunction project to the project owner • Project users – Very sensitive, income is main driving force – Disregard of maintenance  ignorance after project became malfunction and made no benefit  the project was abandoned 56
  • 57. Conclusion 4: Proposed measures • Three thematic – Thematic 1:Utilization project life cycle planning and management – Thematic 2:Improving the DWR capacity to deliver service – Thematic 3:Stakeholder participation and building capacity • Beneficiary contribution approach 57
  • 59. Publications International Journal 1. Uraiwong, P. & Watanabe T. (2012). “Small-scaled water resources project in Thailand: Failure analysis and improvement of stakeholder involvement”. Journal of Society for Social Management Systems (Peer-reviewed) serial SMS12-6080. 2. Komatsu T., Nakaya S., Uraiwong P., and Watanabe T. "Multi- Stakeholder Mental Model in Monobe River Improvement and Maintenance. "Journal of Society for Social Management Systems (Peer-reviewed) serial SMS12-9459. 3. Uraiwong, P. & Watanabe T. (2011). “Stakeholder analysis of water resources projects in Thailand”. Journal of Society for Social Management Systems (Peer-reviewed) serial SMS11- 5587. 59
  • 60. Publications International Conference 1. Uraiwong, P. & Watanabe T. (2012). “Small-scaled water resources project in Thailand: Failure analysis and improvement of stakeholder involvement”. The 8th International Symposium on Social Management Systems SSMS2012 - Disaster Prevention and Reconstruction Management -, 2-4 May 2012, Kaohsiung, Taiwan, R.O.C. 2. Komatsu T., Nakaya S., Uraiwong P., and Watanabe T. (2012). "Multi- Stakeholder Mental Model in Monobe River Improvement and Maintenance. The 8th International Symposium on Social Management Systems SSMS2012 - Disaster Prevention and Reconstruction Management -, 2-4 May 2012, Kaohsiung, Taiwan, R.O.C. 3. Uraiwong, P. & Watanabe T. (2011). “Stakeholder analysis of water resources projects in Thailand”. IESL-SSMS Joint International Symposium on Social Management Systems 2011, 14-16 September 2011, Colombo, Sri Lanka 60
  • 61. Publications International Conference (cont.) 4. Uraiwong, P. & Watanabe T. (2012). "Public Awareness Campaigns and Education Program in the Monobe River." Thailand-Japan International Academic Conference 2012 Proceeding. Tokyo, Japan, October 2012 5. Uraiwong, P. & Watanabe T. (2011). "Model for Small-scaled Water Resources Project Development: Based on Thai Case." Thailand-Japan International Academic (TJIA) Conference 2011. Tokyo, Japan, November 2011 6. Uraiwong, P. & Watanabe T. (2010). “Community mechanisms for water resources risk management”. Proceeding of International conference for a sustainable Greater Mekong Subregion, King Mongkut’s University of Technology, Bangkok, Thailand,26-27 August 2010, pp.431-434. 61
  • 62. 62

Editor's Notes

  1. Important components in proposed integrated method for failure analysis will be introduced.
  2. The mental constructs the decisions that we take, the actions that we engage inIt is interesting to investigate people’s mental models to understand people’s behavior when they interact with the world.
  3. Individual cannot consider all detail and information of a certain situation but observe selectively through there limited mental models as what is in their interest and concernIn a decision situation, one perceives only those parts the attention has been draw to or make sense to the observerThe perceived information is processed and translatedIssue framing may occur on the basis of an individual mental models or in interaction with othersThese four process of selective observation, perception, mental models processing and issue framing may be influenced by heuristic cognitive processing or person’s bias.
  4. One stakeholder may hold different mental models within one project or paradigm. Stakeholder can apply their individual mental model to different action situation. Different stakeholder may engage in a project with their mental models, holding different interest, beliefs, cultural background.They may interpret each others arguments very differently and may hold different expectations about each other behaviour.
  5. One of the well-known tools in project management is WBS.PMBOK guide define WBS as “a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the require deliverables”
  6. The important aspect here is breaking the failure down into its component parts and expressing that breakdown.The failure events that take place is always witness, but we can’t see the cause or the background. As a developing failure becomes evident as a failure, a person take action to deal with unfolding sequence of events.These events and action taken in response to them as a result or sequel.
  7. In this integrated framework, stakeholder mental models is integrated into project work breakdown structure to identify stakeholder mindset and behavior associated with actual situation in each phase which influence failure of the project.
  8. Generally speaking, the introducing approach is understood to require integration of stakeholder analysis and project analysis. This approach encompasses three essential step:
  9. Failure knowledge database was developed based on learning experience and lesson learns from failure for the purpose of avoiding and preventing project failure.A failure consists of three basic elements; “Cause”, “Action”, and “Result” as illustrated in this presentation
  10. Results from failure knowledge database analysis define the problem context, problem phenomenon and related stakeholder for further analysis.
  11. This is example of officer in the DWR mental models influence diagram
  12. From the constraint-measure-objective analysis, three groups of constraints were identified.Capacity of the DWR and staff in project managementLack of planning for implementation of the DWRAbsence of stakeholder participation
  13. In response to identified constraints, three thematic and cross-sectional modules were proposed as tailor to match with context of Thai water resources management.
  14. Special attention will be paid to the project life cycle management in terms of the process, roles and responsibilities that the different group of stakeholder may have with respect to achieving the stakeholder’s objective and the project goals.
  15. In an attempt to solve the malfunction project problems, beneficiary contribution system is introduced.This approach is a combination of stakeholder management, responsibility sharing and technical matters. The basic principles of beneficiary contribution approach in this research are: