SlideShare a Scribd company logo
1 of 25
Download to read offline
Media Briefing Damage to Majuba power station coal storage silo 03 November 2014 Tshediso Matona Chief Executive
2 
Introduction 
Conclusion 
Majuba power station incident 
The system outlook and plan
3 
Introduction 
Conclusion 
Majuba power station incident 
The system outlook and plan
Majuba power station – situated in the Mpumalanga Province 
4 
Majuba 
It is the youngest commercially operated power station in the fleet
Majuba Power Station 
•Majuba Power Station, situated in Mpumalanga, has an installed capacity of 4110 MW generated 
•The station is 13 years old and became fully operational in 2001 when the last of its six units came on line 
•Three, 10 000 ton coal storage silos were constructed in 1994 
•The latest civil visual inspection was conducted in September 2013 by an external specialist, in line with best practice 
•The concrete structure was found to be in good condition. 
•Some moderate cases of external physical damage that was reported has since been repaired 
•The risk classification was low 
5
Sequence of events (1 November 2014) 
1 November 2014 All Majuba power station units were running normally, contracted loads 
Approximately 12:30 
Operating staff reported a visible crack on silo 20 
Immediately thereafter all personnel working in the area evacuated 
13:12 
Silo 20 collapsed 
No injuries reported. 
The area was secured and protected 
Station output immediately reduced from 3 600 MW to 1800 MW and currently running at 600 MW
Majuba silo
Majuba response 
Senior Engineers and members of the Executive Committee immediately joined the Power Station manager on-site 
Eskom triggered its Emergency Command Centre. First priority was to protect the power grid and look at the impact of power supply to the country 
Arrangements were made for permits to transport mobile coal feeders to site to enable a manual feed of coal to five of the six units. This to ensure that the power station is able to operate at a minimum of half- load 
The cause and cost are yet to be determined as the incident is now under investigation 
As a result of the early evacuation no injuries were reported 
The situation is being constantly monitored and progress updates on contingency plans will be communicated
9 
Introduction 
Conclusion 
Majuba power station incident 
The system outlook and plan
Majuba 
Main Supply, Coal from Coal Stock Yard, 
(Overland conveyers), 2 250 T/h 
Coal Supply to the Unit, (boiler Incline conveyer) 800T/h 
Max burn rate per Unit, 375 T/h. Station burn rate, 54 000 T/day 
Over silo link Conveyers, 1200T/h
Majuba 
Coal stockyard
Majuba
Majuba
14 
Introduction 
Conclusion 
Majuba power station incident 
The system outlook and plan
15 
Summer profile 
•The system remains tight in summer, with different challenges due to the load profile 
•Unlike winter, where the demand increases significantly during the evening peak (5pm - 9pm), the demand profile during summer is much flatter with an increased demand profile throughout the day 
•This is because of a relatively high percentage of almost constant industrial load and the impact of air conditioning in the commercial and marginally in the residential sector during the day. The significant residential component over evening peak is not as evident in summer. If there is a constraint, the system is constrained all day 
•Summer is typically maintenance season, but this summer maintenance will increase based on the generation strategy as most of the maintenance is fixed and can’t be deferred. 
•The challenge is to ensure that there is sufficient generation capacity throughout the day, as we continue with our maintenance plan and focus on reducing unplanned outages 
•The degree of tightness will depend on the performance of the plant and the level of unplanned maintenance (UCLF) as well as the available capacity 
•Eskom will not compromise its generation plant and will load shed if necessary to protect the power system from total collapse
Summer profile continued 
•Summer poses a different challenge as the profile looks flat and our planned maintenance (PCLF) increases significantly compared to Winter 
16 
22000 
24000 
26000 
28000 
30000 
32000 
34000 
00:00 
01:00 
02:00 
03:00 
04:00 
05:00 
06:00 
07:00 
08:00 
09:00 
10:00 
11:00 
12:00 
13:00 
14:00 
15:00 
16:00 
17:00 
18:00 
19:00 
20:00 
21:00 
22:00 
23:00 
Summer points to note 
•Table Mountain profile 
•Constrained all day incl. from 6am - 10pm 
•Air-conditioning, geysers & pool pumps primarily impact demand 
•Commercial, agricultural & residential customers can make the biggest difference 
Constrained all day
•Renewable independent power producers peak at over 900 MW (about 1 274 MW installed) 
•As we move more into a flatter profile, the renewables will increasingly offset some of the OCGT usage 
•IPPs (wind & solar variability) unavailable during evening peak when demand is high 
Impact of renewable generation on the system 
17 
September hourly Solar (PV) and Wind 
Overlap of renewable generation and OCGT for one week 
The situation today has been exaggerated by the generally cloudy conditions across the entire country which has reduced the supply from solar plants by almost 500 MW
Sunday: No loss of additional MW and Majuba at 600MW output 
18 
Keeping to scheduled hours at Palmiet and Drakensberg. 
Date 
Time 
Current Avail Cap (Incl Primary Constraints) 
MW Expected to Return/Go Off 
Forecast 
Shortfall/Surplus on demand 
02/11/2014 
00:00 to 01:00 
27440 
0 
22411 
5029 
02/11/2014 
01:00 to 02:00 
27440 
0 
22021 
5419 
02/11/2014 
02:00 to 03:00 
27440 
0 
21835 
5605 
02/11/2014 
03:00 to 04:00 
27440 
0 
21717 
5723 
02/11/2014 
04:00 to 05:00 
27440 
0 
21894 
5546 
02/11/2014 
05:00 to 06:00 
27440 
0 
22527 
4913 
02/11/2014 
06:00 to 07:00 
27890 
0 
23982 
3908 
02/11/2014 
07:00 to 08:00 
28590 
0 
25945 
2645 
02/11/2014 
08:00 to 09:00 
28590 
0 
27449 
1141 
02/11/2014 
09:00 to 10:00 
28590 
0 
27857 
733 
02/11/2014 
10:00 to 11:00 
28590 
0 
27699 
891 
02/11/2014 
11:00 to 12:00 
28590 
0 
27606 
984 
02/11/2014 
12:00 to 13:00 
28590 
0 
27407 
1183 
02/11/2014 
13:00 to 14:00 
28590 
0 
26817 
1773 
02/11/2014 
14:00 to 15:00 
28590 
0 
26181 
2409 
02/11/2014 
15:00 to 16:00 
28590 
0 
26011 
2579 
02/11/2014 
16:00 to 17:00 
28590 
0 
26155 
2435 
02/11/2014 
17:00 to 18:00 
28590 
0 
26674 
1916 
02/11/2014 
18:00 to 19:00 
28590 
0 
27902 
688 
02/11/2014 
19:00 to 20:00 
28790 
0 
29491 
-701 
02/11/2014 
20:00 to 21:00 
28590 
0 
28155 
435 
02/11/2014 
21:00 to 22:00 
28590 
0 
25785 
2805 
02/11/2014 
22:00 to 23:00 
27690 
0 
24036 
3654 
02/11/2014 
23:00 to 00:00 
27440 
0 
22690 
4750
Monday: Units return as expected and Majuba at 600 MW output 
19 
Keeping to scheduled hours at Palmiet and Drakensberg. 
Date 
Time 
Current Avail Cap (Incl Primary Constraints) 
MW Expected to Return/Go Off 
Forecast 
Shortfall/Surplus on demand 
03/11/2014 
00:00 to 01:00 
27440 
679 
22217 
5902 
03/11/2014 
01:00 to 02:00 
27440 
1358 
21921 
6802 
03/11/2014 
02:00 to 03:00 
27440 
1358 
21856 
6867 
03/11/2014 
03:00 to 04:00 
27440 
1358 
22265 
6458 
03/11/2014 
04:00 to 05:00 
27440 
1451 
23591 
5132 
03/11/2014 
05:00 to 06:00 
28590 
1543 
26898 
2975 
03/11/2014 
06:00 to 07:00 
28590 
1543 
28346 
1527 
03/11/2014 
07:00 to 08:00 
28590 
1543 
27931 
1942 
03/11/2014 
08:00 to 09:00 
28590 
1543 
28676 
1197 
03/11/2014 
09:00 to 10:00 
28590 
1543 
28835 
1038 
03/11/2014 
10:00 to 11:00 
29040 
1543 
29146 
1177 
03/11/2014 
11:00 to 12:00 
29040 
1543 
29057 
1266 
03/11/2014 
12:00 to 13:00 
29040 
1543 
29019 
1304 
03/11/2014 
13:00 to 14:00 
28840 
1543 
28820 
1303 
03/11/2014 
14:00 to 15:00 
29090 
1543 
28882 
1491 
03/11/2014 
15:00 to 16:00 
28590 
1543 
29382 
491 
03/11/2014 
16:00 to 17:00 
28590 
1543 
29621 
252 
03/11/2014 
17:00 to 18:00 
29240 
1543 
29878 
905 
03/11/2014 
18:00 to 19:00 
29990 
1543 
30868 
665 
03/11/2014 
19:00 to 20:00 
29990 
1543 
31317 
216 
03/11/2014 
20:00 to 21:00 
29990 
1543 
30157 
1116 
03/11/2014 
21:00 to 22:00 
28590 
1543 
27986 
1887 
03/11/2014 
22:00 to 23:00 
28590 
1236 
25914 
3652 
03/11/2014 
23:00 to 00:00 
27890 
928 
24569 
3989
Outlook 
1. Sunday 
•Sunday shedding at Stage 2 will build up reserves for the week ahead 
•The current projection is to keep load shedding Stage 2 to ensure significant recovery of the Peaking resources to ensure the impact of load shedding is less severe during the week 
•Solar & wind currently sending out 160 MW and 90 MW respectively. Solar is normally up to 500 MW (cloudiness affecting it significantly). Majuba currently sending out about 600 MW (2 machines at half load) 
2. Monday projection 
•Generation Capacity at 31 500 MW for the day, provided we do not have any further breakdowns 
•Demand forecast for evening peak (31 317 MW highest of the day) 
•Risk of load shedding in particular between 18:00 – 20:00 
20
Outlook continued 
3. The rest of the week 
•If the capacity stays at the same level, we would have similar system status. With the extensive usage of the water resources it would mean by Wednesday we start to be constrained with water 
•If the capacity is still at the same level we would need to consider Stage 1 load shedding possibly on Thursday (whole day) or as early as Wednesday evening ( 4 – 6 hours) 
21
How can consumers help? 
•Saving electricity reduces pressure on the grid and cuts your electricity bill and South Africa’s carbon emissions 
•The power system remains vulnerable all day up to 10pm 
1.Switch off air-conditioning or use efficiently 
- Set air-conditioning at 23 degrees 
2.Switch off all geysers and pool pumps all day until 10pm 
3.Switch off all non-essential lighting 
4.Respond to the Power Alert messages by switching off all appliances that are not being used 
22
23 
Introduction 
Conclusion 
Majuba power station incident 
The system outlook and plan
Conclusion 
•While the system is tight, this unplanned incident exacerbated the situation and it is very likely that load shedding will continue for the week 
•An investigation is already underway into the cause of the incident, but it appears that this is an isolated incident specific to the coal infrastructure at Majuba. 
•Mobile coal feeders are on-site and the team is optimistic that they can maintain half of the total from the power station 
•The Minister of DPE is being kept abreast of all developments. Eskom has also informed all key stakeholders including the Department of Education and the national disaster management centre to minimise the impact for matriculants and all communities 
•Eskom apologises to all electricity consumers but call on you yet again to switch off unnecessary lights, the geyser, pool pump and air-conditioning 
•Load shedding schedules are available on Eskom website, and municipal customers should contact their municipalities for details 
•We are painfully aware of the impact of this incident given the electricity supply situation in the country 
•We will continue to communicate via the media
Thank you 
25

More Related Content

What's hot

ppt by amit 5 from iet lko
ppt by amit 5 from iet lkoppt by amit 5 from iet lko
ppt by amit 5 from iet lkoamitietlko
 
7311 STEVENS CROFT PRESENTATION
7311 STEVENS CROFT PRESENTATION7311 STEVENS CROFT PRESENTATION
7311 STEVENS CROFT PRESENTATIONMark Johnston
 
2017 irao export presentation eng
2017 irao export presentation eng2017 irao export presentation eng
2017 irao export presentation engViacheslav Leonov
 
21st Century Coal Power Plants
21st Century Coal Power Plants21st Century Coal Power Plants
21st Century Coal Power PlantsJeffrey Phillips
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer trainingShivam Jain
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC pptkirbadh
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT94600banti
 
Cng marine for gas distribution in indonesia 2012 s
Cng marine for gas distribution in indonesia 2012 sCng marine for gas distribution in indonesia 2012 s
Cng marine for gas distribution in indonesia 2012 sFurqon Hanief
 
Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptaryan5808
 
Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt nilesh choubey
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpurShrey Dhasmana
 

What's hot (20)

ppt by amit 5 from iet lko
ppt by amit 5 from iet lkoppt by amit 5 from iet lko
ppt by amit 5 from iet lko
 
7311 STEVENS CROFT PRESENTATION
7311 STEVENS CROFT PRESENTATION7311 STEVENS CROFT PRESENTATION
7311 STEVENS CROFT PRESENTATION
 
2017 irao export presentation eng
2017 irao export presentation eng2017 irao export presentation eng
2017 irao export presentation eng
 
Ntpc ppt
Ntpc pptNtpc ppt
Ntpc ppt
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
Training NTPC
Training NTPCTraining NTPC
Training NTPC
 
Rankin Units
Rankin UnitsRankin Units
Rankin Units
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
project -2
project -2project -2
project -2
 
21st Century Coal Power Plants
21st Century Coal Power Plants21st Century Coal Power Plants
21st Century Coal Power Plants
 
NTPC training
NTPC trainingNTPC training
NTPC training
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
ntpc
ntpcntpc
ntpc
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
 
Cng marine for gas distribution in indonesia 2012 s
Cng marine for gas distribution in indonesia 2012 sCng marine for gas distribution in indonesia 2012 s
Cng marine for gas distribution in indonesia 2012 s
 
Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training ppt
 
Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 

Viewers also liked

New Simulation Systems installed by Transnet
New Simulation Systems installed by TransnetNew Simulation Systems installed by Transnet
New Simulation Systems installed by TransnetRailways and Harbours
 
PICTURES-SASOL-RLL1-LRC-KP795-RLL1-NOV-DEC-16
PICTURES-SASOL-RLL1-LRC-KP795-RLL1-NOV-DEC-16PICTURES-SASOL-RLL1-LRC-KP795-RLL1-NOV-DEC-16
PICTURES-SASOL-RLL1-LRC-KP795-RLL1-NOV-DEC-16Edmond GOUGNARD
 
SASOL Technology COP Presentation. 26 August 2011.
SASOL Technology COP Presentation. 26 August 2011. SASOL Technology COP Presentation. 26 August 2011.
SASOL Technology COP Presentation. 26 August 2011. knowledgeconversations
 
Transnet port terminals on stay ahead of the competition, presented during af...
Transnet port terminals on stay ahead of the competition, presented during af...Transnet port terminals on stay ahead of the competition, presented during af...
Transnet port terminals on stay ahead of the competition, presented during af...Transnet Port Terminals
 
Partnership pitch presentation to ESKOM ppt
Partnership pitch presentation to ESKOM pptPartnership pitch presentation to ESKOM ppt
Partnership pitch presentation to ESKOM pptJustice Ndaba
 
Leaders in Aviation Africa
Leaders in Aviation AfricaLeaders in Aviation Africa
Leaders in Aviation AfricaLeon Swartz
 
Transnet enterprise development hub Saldanha - 2015
Transnet enterprise development hub  Saldanha - 2015Transnet enterprise development hub  Saldanha - 2015
Transnet enterprise development hub Saldanha - 2015Transnet Port Terminals
 
Transnet who we are- by Transnet Port Terminals Chief Executive, Karl Socikwa
Transnet  who we are- by Transnet Port Terminals Chief Executive, Karl SocikwaTransnet  who we are- by Transnet Port Terminals Chief Executive, Karl Socikwa
Transnet who we are- by Transnet Port Terminals Chief Executive, Karl SocikwaTransnet Port Terminals
 
2008:Power and the Economy
2008:Power and the Economy2008:Power and the Economy
2008:Power and the Economyeconsultbw
 
Transnet Future strategies and meeting increasing expectations of port uses, ...
Transnet Future strategies and meeting increasing expectations of port uses, ...Transnet Future strategies and meeting increasing expectations of port uses, ...
Transnet Future strategies and meeting increasing expectations of port uses, ...Railways and Harbours
 
Eskom's Renewables Strategy
Eskom's Renewables StrategyEskom's Renewables Strategy
Eskom's Renewables Strategysimguybar
 
Working in synergy with neighbouring countries to seamlessly transport coal o...
Working in synergy with neighbouring countries to seamlessly transport coal o...Working in synergy with neighbouring countries to seamlessly transport coal o...
Working in synergy with neighbouring countries to seamlessly transport coal o...Tristan Wiggill
 
Eskom south africa: "A case of Planning Failure"
Eskom south africa: "A case of Planning Failure"Eskom south africa: "A case of Planning Failure"
Eskom south africa: "A case of Planning Failure"Simon Christian MAKOSO
 
Hall 2C Tuesday 13h30 - Jan Wessels
Hall 2C Tuesday 13h30 - Jan WesselsHall 2C Tuesday 13h30 - Jan Wessels
Hall 2C Tuesday 13h30 - Jan Wessels7391456
 
ZA National Plan FY16 Story Final
ZA National Plan FY16 Story FinalZA National Plan FY16 Story Final
ZA National Plan FY16 Story FinalRiedwaan Bassadien
 
Mypd final x3
Mypd final x3Mypd final x3
Mypd final x3Eskom
 
Saudi arabia railway organisation visit to transnet iron ore line saldanha
Saudi arabia railway organisation visit to transnet iron ore line saldanhaSaudi arabia railway organisation visit to transnet iron ore line saldanha
Saudi arabia railway organisation visit to transnet iron ore line saldanhaTransnet Port Terminals
 
Enterprise Architecture Value Creation - Kevin Govender - Transnet
Enterprise Architecture Value Creation - Kevin Govender - TransnetEnterprise Architecture Value Creation - Kevin Govender - Transnet
Enterprise Architecture Value Creation - Kevin Govender - TransnetSoftware AG South Africa
 
SME policies in the Middle East & North Africa
SME policies in the Middle East & North AfricaSME policies in the Middle East & North Africa
SME policies in the Middle East & North AfricaOECDglobal
 

Viewers also liked (20)

New Simulation Systems installed by Transnet
New Simulation Systems installed by TransnetNew Simulation Systems installed by Transnet
New Simulation Systems installed by Transnet
 
PICTURES-SASOL-RLL1-LRC-KP795-RLL1-NOV-DEC-16
PICTURES-SASOL-RLL1-LRC-KP795-RLL1-NOV-DEC-16PICTURES-SASOL-RLL1-LRC-KP795-RLL1-NOV-DEC-16
PICTURES-SASOL-RLL1-LRC-KP795-RLL1-NOV-DEC-16
 
SASOL Technology COP Presentation. 26 August 2011.
SASOL Technology COP Presentation. 26 August 2011. SASOL Technology COP Presentation. 26 August 2011.
SASOL Technology COP Presentation. 26 August 2011.
 
Innovation in Transnet
Innovation in TransnetInnovation in Transnet
Innovation in Transnet
 
Transnet port terminals on stay ahead of the competition, presented during af...
Transnet port terminals on stay ahead of the competition, presented during af...Transnet port terminals on stay ahead of the competition, presented during af...
Transnet port terminals on stay ahead of the competition, presented during af...
 
Partnership pitch presentation to ESKOM ppt
Partnership pitch presentation to ESKOM pptPartnership pitch presentation to ESKOM ppt
Partnership pitch presentation to ESKOM ppt
 
Leaders in Aviation Africa
Leaders in Aviation AfricaLeaders in Aviation Africa
Leaders in Aviation Africa
 
Transnet enterprise development hub Saldanha - 2015
Transnet enterprise development hub  Saldanha - 2015Transnet enterprise development hub  Saldanha - 2015
Transnet enterprise development hub Saldanha - 2015
 
Transnet who we are- by Transnet Port Terminals Chief Executive, Karl Socikwa
Transnet  who we are- by Transnet Port Terminals Chief Executive, Karl SocikwaTransnet  who we are- by Transnet Port Terminals Chief Executive, Karl Socikwa
Transnet who we are- by Transnet Port Terminals Chief Executive, Karl Socikwa
 
2008:Power and the Economy
2008:Power and the Economy2008:Power and the Economy
2008:Power and the Economy
 
Transnet Future strategies and meeting increasing expectations of port uses, ...
Transnet Future strategies and meeting increasing expectations of port uses, ...Transnet Future strategies and meeting increasing expectations of port uses, ...
Transnet Future strategies and meeting increasing expectations of port uses, ...
 
Eskom's Renewables Strategy
Eskom's Renewables StrategyEskom's Renewables Strategy
Eskom's Renewables Strategy
 
Working in synergy with neighbouring countries to seamlessly transport coal o...
Working in synergy with neighbouring countries to seamlessly transport coal o...Working in synergy with neighbouring countries to seamlessly transport coal o...
Working in synergy with neighbouring countries to seamlessly transport coal o...
 
Eskom south africa: "A case of Planning Failure"
Eskom south africa: "A case of Planning Failure"Eskom south africa: "A case of Planning Failure"
Eskom south africa: "A case of Planning Failure"
 
Hall 2C Tuesday 13h30 - Jan Wessels
Hall 2C Tuesday 13h30 - Jan WesselsHall 2C Tuesday 13h30 - Jan Wessels
Hall 2C Tuesday 13h30 - Jan Wessels
 
ZA National Plan FY16 Story Final
ZA National Plan FY16 Story FinalZA National Plan FY16 Story Final
ZA National Plan FY16 Story Final
 
Mypd final x3
Mypd final x3Mypd final x3
Mypd final x3
 
Saudi arabia railway organisation visit to transnet iron ore line saldanha
Saudi arabia railway organisation visit to transnet iron ore line saldanhaSaudi arabia railway organisation visit to transnet iron ore line saldanha
Saudi arabia railway organisation visit to transnet iron ore line saldanha
 
Enterprise Architecture Value Creation - Kevin Govender - Transnet
Enterprise Architecture Value Creation - Kevin Govender - TransnetEnterprise Architecture Value Creation - Kevin Govender - Transnet
Enterprise Architecture Value Creation - Kevin Govender - Transnet
 
SME policies in the Middle East & North Africa
SME policies in the Middle East & North AfricaSME policies in the Middle East & North Africa
SME policies in the Middle East & North Africa
 

Similar to Eskom load shedding

1_Geothermal_Development_in_Indonesia (2)
1_Geothermal_Development_in_Indonesia (2)1_Geothermal_Development_in_Indonesia (2)
1_Geothermal_Development_in_Indonesia (2)Frank Mercado
 
Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Kachinga-Wankunda Phiri
 
MINE-MOUTH-POWER-PLANTS-PRESENTATION-11152016-final-combined
MINE-MOUTH-POWER-PLANTS-PRESENTATION-11152016-final-combinedMINE-MOUTH-POWER-PLANTS-PRESENTATION-11152016-final-combined
MINE-MOUTH-POWER-PLANTS-PRESENTATION-11152016-final-combinedRobles Arnulfo
 
Benefits of csp with thermal storage
Benefits of csp with thermal storageBenefits of csp with thermal storage
Benefits of csp with thermal storageSolarReference
 
Benefits of csp with thermal storage
Benefits of csp with thermal storageBenefits of csp with thermal storage
Benefits of csp with thermal storageSolar Reference
 
Singapore Energy Scenerio
Singapore Energy ScenerioSingapore Energy Scenerio
Singapore Energy ScenerioJasbir Arora
 
Aemo's system event report new south wales, 10 february 2017 (nsw)
Aemo's system event report new south wales, 10 february 2017 (nsw)Aemo's system event report new south wales, 10 february 2017 (nsw)
Aemo's system event report new south wales, 10 february 2017 (nsw)Lisa Munoz
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPCRahul Kurapati
 
#MP2013 Presentation of the MInister of Power
#MP2013  Presentation of the MInister of Power#MP2013  Presentation of the MInister of Power
#MP2013 Presentation of the MInister of PowerFMINigeria
 
A Presentaion from the Ministry of Power
A  Presentaion from the Ministry of PowerA  Presentaion from the Ministry of Power
A Presentaion from the Ministry of PowerNigeria Centenary
 
Ministry of Power
Ministry of PowerMinistry of Power
Ministry of PowerTransformNG
 
Teiiti marita-renewable-energy-progress-in-the-cook-islands
Teiiti marita-renewable-energy-progress-in-the-cook-islandsTeiiti marita-renewable-energy-progress-in-the-cook-islands
Teiiti marita-renewable-energy-progress-in-the-cook-islandsjames hamilton
 
Solar for the home installation and maintenance-20161
Solar for the home installation and maintenance-20161Solar for the home installation and maintenance-20161
Solar for the home installation and maintenance-20161Reynante Alvarado
 
1 145-143444129513-18
1 145-143444129513-181 145-143444129513-18
1 145-143444129513-18shushay hailu
 
Developments and Future Expansions Potential in the Electric Power System in ...
Developments and Future Expansions Potential in the Electric Power System in ...Developments and Future Expansions Potential in the Electric Power System in ...
Developments and Future Expansions Potential in the Electric Power System in ...Ravish P.Y. Mehairjan
 
Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...
Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...
Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...Sammy S. Aiau
 
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...OECD Environment
 
Energy survey of the Brimsu Water Supply Station
Energy survey of the Brimsu Water Supply Station Energy survey of the Brimsu Water Supply Station
Energy survey of the Brimsu Water Supply Station Jacob Amengor
 

Similar to Eskom load shedding (20)

1_Geothermal_Development_in_Indonesia (2)
1_Geothermal_Development_in_Indonesia (2)1_Geothermal_Development_in_Indonesia (2)
1_Geothermal_Development_in_Indonesia (2)
 
Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16
 
MINE-MOUTH-POWER-PLANTS-PRESENTATION-11152016-final-combined
MINE-MOUTH-POWER-PLANTS-PRESENTATION-11152016-final-combinedMINE-MOUTH-POWER-PLANTS-PRESENTATION-11152016-final-combined
MINE-MOUTH-POWER-PLANTS-PRESENTATION-11152016-final-combined
 
Benefits of csp with thermal storage
Benefits of csp with thermal storageBenefits of csp with thermal storage
Benefits of csp with thermal storage
 
Benefits of csp with thermal storage
Benefits of csp with thermal storageBenefits of csp with thermal storage
Benefits of csp with thermal storage
 
Singapore Energy Scenerio
Singapore Energy ScenerioSingapore Energy Scenerio
Singapore Energy Scenerio
 
Aemo's system event report new south wales, 10 february 2017 (nsw)
Aemo's system event report new south wales, 10 february 2017 (nsw)Aemo's system event report new south wales, 10 february 2017 (nsw)
Aemo's system event report new south wales, 10 february 2017 (nsw)
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPC
 
Dr. Yondongombo
Dr. YondongomboDr. Yondongombo
Dr. Yondongombo
 
Sunoryx sizing tool
Sunoryx sizing toolSunoryx sizing tool
Sunoryx sizing tool
 
#MP2013 Presentation of the MInister of Power
#MP2013  Presentation of the MInister of Power#MP2013  Presentation of the MInister of Power
#MP2013 Presentation of the MInister of Power
 
A Presentaion from the Ministry of Power
A  Presentaion from the Ministry of PowerA  Presentaion from the Ministry of Power
A Presentaion from the Ministry of Power
 
Ministry of Power
Ministry of PowerMinistry of Power
Ministry of Power
 
Teiiti marita-renewable-energy-progress-in-the-cook-islands
Teiiti marita-renewable-energy-progress-in-the-cook-islandsTeiiti marita-renewable-energy-progress-in-the-cook-islands
Teiiti marita-renewable-energy-progress-in-the-cook-islands
 
Solar for the home installation and maintenance-20161
Solar for the home installation and maintenance-20161Solar for the home installation and maintenance-20161
Solar for the home installation and maintenance-20161
 
1 145-143444129513-18
1 145-143444129513-181 145-143444129513-18
1 145-143444129513-18
 
Developments and Future Expansions Potential in the Electric Power System in ...
Developments and Future Expansions Potential in the Electric Power System in ...Developments and Future Expansions Potential in the Electric Power System in ...
Developments and Future Expansions Potential in the Electric Power System in ...
 
Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...
Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...
Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...
 
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
 
Energy survey of the Brimsu Water Supply Station
Energy survey of the Brimsu Water Supply Station Energy survey of the Brimsu Water Supply Station
Energy survey of the Brimsu Water Supply Station
 

More from Matthew Le Cordeur

DA presentation: MYPD 3 Reopener
DA presentation: MYPD 3 Reopener DA presentation: MYPD 3 Reopener
DA presentation: MYPD 3 Reopener Matthew Le Cordeur
 
NYPD3 Selective Reopener Nersa public hearings - 23 June 2015
NYPD3 Selective Reopener  Nersa public hearings  - 23 June 2015NYPD3 Selective Reopener  Nersa public hearings  - 23 June 2015
NYPD3 Selective Reopener Nersa public hearings - 23 June 2015Matthew Le Cordeur
 
Nersa submission by Chris Yelland.
Nersa submission by Chris Yelland. Nersa submission by Chris Yelland.
Nersa submission by Chris Yelland. Matthew Le Cordeur
 
Eskom MYPD 3Selective Reopener presentation
Eskom MYPD 3Selective Reopener presentationEskom MYPD 3Selective Reopener presentation
Eskom MYPD 3Selective Reopener presentationMatthew Le Cordeur
 
Stats SA 2015 First Quarter Labour Force Survey
Stats SA 2015 First Quarter Labour Force SurveyStats SA 2015 First Quarter Labour Force Survey
Stats SA 2015 First Quarter Labour Force SurveyMatthew Le Cordeur
 
A plan for the Gauteng City Region towards Vision 2030
A plan for the Gauteng City Region towards Vision 2030A plan for the Gauteng City Region towards Vision 2030
A plan for the Gauteng City Region towards Vision 2030Matthew Le Cordeur
 
Western Cape Residential Property Review by John Loos
Western Cape Residential Property Review by John Loos Western Cape Residential Property Review by John Loos
Western Cape Residential Property Review by John Loos Matthew Le Cordeur
 
FNB home loans briefing on 9 April 2015 tommy nel
FNB home loans briefing on 9 April 2015 tommy nelFNB home loans briefing on 9 April 2015 tommy nel
FNB home loans briefing on 9 April 2015 tommy nelMatthew Le Cordeur
 
Passion for life: a look at the life insurance industry
Passion for life: a look at the life insurance industryPassion for life: a look at the life insurance industry
Passion for life: a look at the life insurance industryMatthew Le Cordeur
 
Business Partners Limited SME confidence index Q3 2014 final
Business Partners Limited SME confidence index Q3 2014 finalBusiness Partners Limited SME confidence index Q3 2014 final
Business Partners Limited SME confidence index Q3 2014 finalMatthew Le Cordeur
 
The Dynamic Workplace – driving disruptive innovation
The Dynamic Workplace – driving disruptive innovationThe Dynamic Workplace – driving disruptive innovation
The Dynamic Workplace – driving disruptive innovationMatthew Le Cordeur
 
Investing for impact barometer
Investing for impact barometerInvesting for impact barometer
Investing for impact barometerMatthew Le Cordeur
 

More from Matthew Le Cordeur (19)

Value of BEE deals
Value of BEE dealsValue of BEE deals
Value of BEE deals
 
DA presentation: MYPD 3 Reopener
DA presentation: MYPD 3 Reopener DA presentation: MYPD 3 Reopener
DA presentation: MYPD 3 Reopener
 
NYPD3 Selective Reopener Nersa public hearings - 23 June 2015
NYPD3 Selective Reopener  Nersa public hearings  - 23 June 2015NYPD3 Selective Reopener  Nersa public hearings  - 23 June 2015
NYPD3 Selective Reopener Nersa public hearings - 23 June 2015
 
Nersa submission by Chris Yelland.
Nersa submission by Chris Yelland. Nersa submission by Chris Yelland.
Nersa submission by Chris Yelland.
 
Eskom MYPD 3Selective Reopener presentation
Eskom MYPD 3Selective Reopener presentationEskom MYPD 3Selective Reopener presentation
Eskom MYPD 3Selective Reopener presentation
 
Monetary Policy Forum
Monetary Policy Forum Monetary Policy Forum
Monetary Policy Forum
 
Stats SA 2015 First Quarter Labour Force Survey
Stats SA 2015 First Quarter Labour Force SurveyStats SA 2015 First Quarter Labour Force Survey
Stats SA 2015 First Quarter Labour Force Survey
 
SA GDP for Quarter 1 2015
SA GDP for Quarter 1 2015SA GDP for Quarter 1 2015
SA GDP for Quarter 1 2015
 
CIS Stats - Asisa
CIS Stats - AsisaCIS Stats - Asisa
CIS Stats - Asisa
 
A plan for the Gauteng City Region towards Vision 2030
A plan for the Gauteng City Region towards Vision 2030A plan for the Gauteng City Region towards Vision 2030
A plan for the Gauteng City Region towards Vision 2030
 
Western Cape Residential Property Review by John Loos
Western Cape Residential Property Review by John Loos Western Cape Residential Property Review by John Loos
Western Cape Residential Property Review by John Loos
 
FNB home loans briefing on 9 April 2015 tommy nel
FNB home loans briefing on 9 April 2015 tommy nelFNB home loans briefing on 9 April 2015 tommy nel
FNB home loans briefing on 9 April 2015 tommy nel
 
Passion for life: a look at the life insurance industry
Passion for life: a look at the life insurance industryPassion for life: a look at the life insurance industry
Passion for life: a look at the life insurance industry
 
Claims Statistics for 2014
Claims Statistics for 2014Claims Statistics for 2014
Claims Statistics for 2014
 
Business Partners Limited SME confidence index Q3 2014 final
Business Partners Limited SME confidence index Q3 2014 finalBusiness Partners Limited SME confidence index Q3 2014 final
Business Partners Limited SME confidence index Q3 2014 final
 
The Dynamic Workplace – driving disruptive innovation
The Dynamic Workplace – driving disruptive innovationThe Dynamic Workplace – driving disruptive innovation
The Dynamic Workplace – driving disruptive innovation
 
Investing for impact barometer
Investing for impact barometerInvesting for impact barometer
Investing for impact barometer
 
Fnb
FnbFnb
Fnb
 
Ibali lami
Ibali lamiIbali lami
Ibali lami
 

Recently uploaded

Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Sapana Sha
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...makika9823
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...Call Girls in Nagpur High Profile
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...shivangimorya083
 
Andheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot ModelsAndheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot Modelshematsharma006
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance CompanyInterimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance CompanyTyöeläkeyhtiö Elo
 
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...Suhani Kapoor
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure servicePooja Nehwal
 
How Automation is Driving Efficiency Through the Last Mile of Reporting
How Automation is Driving Efficiency Through the Last Mile of ReportingHow Automation is Driving Efficiency Through the Last Mile of Reporting
How Automation is Driving Efficiency Through the Last Mile of ReportingAggregage
 
Log your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignLog your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignHenry Tapper
 
Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Commonwealth
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxhiddenlevers
 
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Chapter 2.ppt of macroeconomics by mankiw 9th edition
Chapter 2.ppt of macroeconomics by mankiw 9th editionChapter 2.ppt of macroeconomics by mankiw 9th edition
Chapter 2.ppt of macroeconomics by mankiw 9th editionMuhammadHusnain82237
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...Henry Tapper
 
Quantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector CompaniesQuantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector Companiesprashantbhati354
 

Recently uploaded (20)

Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
 
Andheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot ModelsAndheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot Models
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
🔝+919953056974 🔝young Delhi Escort service Pusa Road
🔝+919953056974 🔝young Delhi Escort service Pusa Road🔝+919953056974 🔝young Delhi Escort service Pusa Road
🔝+919953056974 🔝young Delhi Escort service Pusa Road
 
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
 
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance CompanyInterimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
 
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Saharanpur Anushka 8250192130 Independent Escort Se...
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
 
How Automation is Driving Efficiency Through the Last Mile of Reporting
How Automation is Driving Efficiency Through the Last Mile of ReportingHow Automation is Driving Efficiency Through the Last Mile of Reporting
How Automation is Driving Efficiency Through the Last Mile of Reporting
 
Log your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignLog your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaign
 
Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
 
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Chapter 2.ppt of macroeconomics by mankiw 9th edition
Chapter 2.ppt of macroeconomics by mankiw 9th editionChapter 2.ppt of macroeconomics by mankiw 9th edition
Chapter 2.ppt of macroeconomics by mankiw 9th edition
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
 
Quantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector CompaniesQuantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector Companies
 

Eskom load shedding

  • 1. Media Briefing Damage to Majuba power station coal storage silo 03 November 2014 Tshediso Matona Chief Executive
  • 2. 2 Introduction Conclusion Majuba power station incident The system outlook and plan
  • 3. 3 Introduction Conclusion Majuba power station incident The system outlook and plan
  • 4. Majuba power station – situated in the Mpumalanga Province 4 Majuba It is the youngest commercially operated power station in the fleet
  • 5. Majuba Power Station •Majuba Power Station, situated in Mpumalanga, has an installed capacity of 4110 MW generated •The station is 13 years old and became fully operational in 2001 when the last of its six units came on line •Three, 10 000 ton coal storage silos were constructed in 1994 •The latest civil visual inspection was conducted in September 2013 by an external specialist, in line with best practice •The concrete structure was found to be in good condition. •Some moderate cases of external physical damage that was reported has since been repaired •The risk classification was low 5
  • 6. Sequence of events (1 November 2014) 1 November 2014 All Majuba power station units were running normally, contracted loads Approximately 12:30 Operating staff reported a visible crack on silo 20 Immediately thereafter all personnel working in the area evacuated 13:12 Silo 20 collapsed No injuries reported. The area was secured and protected Station output immediately reduced from 3 600 MW to 1800 MW and currently running at 600 MW
  • 8. Majuba response Senior Engineers and members of the Executive Committee immediately joined the Power Station manager on-site Eskom triggered its Emergency Command Centre. First priority was to protect the power grid and look at the impact of power supply to the country Arrangements were made for permits to transport mobile coal feeders to site to enable a manual feed of coal to five of the six units. This to ensure that the power station is able to operate at a minimum of half- load The cause and cost are yet to be determined as the incident is now under investigation As a result of the early evacuation no injuries were reported The situation is being constantly monitored and progress updates on contingency plans will be communicated
  • 9. 9 Introduction Conclusion Majuba power station incident The system outlook and plan
  • 10. Majuba Main Supply, Coal from Coal Stock Yard, (Overland conveyers), 2 250 T/h Coal Supply to the Unit, (boiler Incline conveyer) 800T/h Max burn rate per Unit, 375 T/h. Station burn rate, 54 000 T/day Over silo link Conveyers, 1200T/h
  • 14. 14 Introduction Conclusion Majuba power station incident The system outlook and plan
  • 15. 15 Summer profile •The system remains tight in summer, with different challenges due to the load profile •Unlike winter, where the demand increases significantly during the evening peak (5pm - 9pm), the demand profile during summer is much flatter with an increased demand profile throughout the day •This is because of a relatively high percentage of almost constant industrial load and the impact of air conditioning in the commercial and marginally in the residential sector during the day. The significant residential component over evening peak is not as evident in summer. If there is a constraint, the system is constrained all day •Summer is typically maintenance season, but this summer maintenance will increase based on the generation strategy as most of the maintenance is fixed and can’t be deferred. •The challenge is to ensure that there is sufficient generation capacity throughout the day, as we continue with our maintenance plan and focus on reducing unplanned outages •The degree of tightness will depend on the performance of the plant and the level of unplanned maintenance (UCLF) as well as the available capacity •Eskom will not compromise its generation plant and will load shed if necessary to protect the power system from total collapse
  • 16. Summer profile continued •Summer poses a different challenge as the profile looks flat and our planned maintenance (PCLF) increases significantly compared to Winter 16 22000 24000 26000 28000 30000 32000 34000 00:00 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Summer points to note •Table Mountain profile •Constrained all day incl. from 6am - 10pm •Air-conditioning, geysers & pool pumps primarily impact demand •Commercial, agricultural & residential customers can make the biggest difference Constrained all day
  • 17. •Renewable independent power producers peak at over 900 MW (about 1 274 MW installed) •As we move more into a flatter profile, the renewables will increasingly offset some of the OCGT usage •IPPs (wind & solar variability) unavailable during evening peak when demand is high Impact of renewable generation on the system 17 September hourly Solar (PV) and Wind Overlap of renewable generation and OCGT for one week The situation today has been exaggerated by the generally cloudy conditions across the entire country which has reduced the supply from solar plants by almost 500 MW
  • 18. Sunday: No loss of additional MW and Majuba at 600MW output 18 Keeping to scheduled hours at Palmiet and Drakensberg. Date Time Current Avail Cap (Incl Primary Constraints) MW Expected to Return/Go Off Forecast Shortfall/Surplus on demand 02/11/2014 00:00 to 01:00 27440 0 22411 5029 02/11/2014 01:00 to 02:00 27440 0 22021 5419 02/11/2014 02:00 to 03:00 27440 0 21835 5605 02/11/2014 03:00 to 04:00 27440 0 21717 5723 02/11/2014 04:00 to 05:00 27440 0 21894 5546 02/11/2014 05:00 to 06:00 27440 0 22527 4913 02/11/2014 06:00 to 07:00 27890 0 23982 3908 02/11/2014 07:00 to 08:00 28590 0 25945 2645 02/11/2014 08:00 to 09:00 28590 0 27449 1141 02/11/2014 09:00 to 10:00 28590 0 27857 733 02/11/2014 10:00 to 11:00 28590 0 27699 891 02/11/2014 11:00 to 12:00 28590 0 27606 984 02/11/2014 12:00 to 13:00 28590 0 27407 1183 02/11/2014 13:00 to 14:00 28590 0 26817 1773 02/11/2014 14:00 to 15:00 28590 0 26181 2409 02/11/2014 15:00 to 16:00 28590 0 26011 2579 02/11/2014 16:00 to 17:00 28590 0 26155 2435 02/11/2014 17:00 to 18:00 28590 0 26674 1916 02/11/2014 18:00 to 19:00 28590 0 27902 688 02/11/2014 19:00 to 20:00 28790 0 29491 -701 02/11/2014 20:00 to 21:00 28590 0 28155 435 02/11/2014 21:00 to 22:00 28590 0 25785 2805 02/11/2014 22:00 to 23:00 27690 0 24036 3654 02/11/2014 23:00 to 00:00 27440 0 22690 4750
  • 19. Monday: Units return as expected and Majuba at 600 MW output 19 Keeping to scheduled hours at Palmiet and Drakensberg. Date Time Current Avail Cap (Incl Primary Constraints) MW Expected to Return/Go Off Forecast Shortfall/Surplus on demand 03/11/2014 00:00 to 01:00 27440 679 22217 5902 03/11/2014 01:00 to 02:00 27440 1358 21921 6802 03/11/2014 02:00 to 03:00 27440 1358 21856 6867 03/11/2014 03:00 to 04:00 27440 1358 22265 6458 03/11/2014 04:00 to 05:00 27440 1451 23591 5132 03/11/2014 05:00 to 06:00 28590 1543 26898 2975 03/11/2014 06:00 to 07:00 28590 1543 28346 1527 03/11/2014 07:00 to 08:00 28590 1543 27931 1942 03/11/2014 08:00 to 09:00 28590 1543 28676 1197 03/11/2014 09:00 to 10:00 28590 1543 28835 1038 03/11/2014 10:00 to 11:00 29040 1543 29146 1177 03/11/2014 11:00 to 12:00 29040 1543 29057 1266 03/11/2014 12:00 to 13:00 29040 1543 29019 1304 03/11/2014 13:00 to 14:00 28840 1543 28820 1303 03/11/2014 14:00 to 15:00 29090 1543 28882 1491 03/11/2014 15:00 to 16:00 28590 1543 29382 491 03/11/2014 16:00 to 17:00 28590 1543 29621 252 03/11/2014 17:00 to 18:00 29240 1543 29878 905 03/11/2014 18:00 to 19:00 29990 1543 30868 665 03/11/2014 19:00 to 20:00 29990 1543 31317 216 03/11/2014 20:00 to 21:00 29990 1543 30157 1116 03/11/2014 21:00 to 22:00 28590 1543 27986 1887 03/11/2014 22:00 to 23:00 28590 1236 25914 3652 03/11/2014 23:00 to 00:00 27890 928 24569 3989
  • 20. Outlook 1. Sunday •Sunday shedding at Stage 2 will build up reserves for the week ahead •The current projection is to keep load shedding Stage 2 to ensure significant recovery of the Peaking resources to ensure the impact of load shedding is less severe during the week •Solar & wind currently sending out 160 MW and 90 MW respectively. Solar is normally up to 500 MW (cloudiness affecting it significantly). Majuba currently sending out about 600 MW (2 machines at half load) 2. Monday projection •Generation Capacity at 31 500 MW for the day, provided we do not have any further breakdowns •Demand forecast for evening peak (31 317 MW highest of the day) •Risk of load shedding in particular between 18:00 – 20:00 20
  • 21. Outlook continued 3. The rest of the week •If the capacity stays at the same level, we would have similar system status. With the extensive usage of the water resources it would mean by Wednesday we start to be constrained with water •If the capacity is still at the same level we would need to consider Stage 1 load shedding possibly on Thursday (whole day) or as early as Wednesday evening ( 4 – 6 hours) 21
  • 22. How can consumers help? •Saving electricity reduces pressure on the grid and cuts your electricity bill and South Africa’s carbon emissions •The power system remains vulnerable all day up to 10pm 1.Switch off air-conditioning or use efficiently - Set air-conditioning at 23 degrees 2.Switch off all geysers and pool pumps all day until 10pm 3.Switch off all non-essential lighting 4.Respond to the Power Alert messages by switching off all appliances that are not being used 22
  • 23. 23 Introduction Conclusion Majuba power station incident The system outlook and plan
  • 24. Conclusion •While the system is tight, this unplanned incident exacerbated the situation and it is very likely that load shedding will continue for the week •An investigation is already underway into the cause of the incident, but it appears that this is an isolated incident specific to the coal infrastructure at Majuba. •Mobile coal feeders are on-site and the team is optimistic that they can maintain half of the total from the power station •The Minister of DPE is being kept abreast of all developments. Eskom has also informed all key stakeholders including the Department of Education and the national disaster management centre to minimise the impact for matriculants and all communities •Eskom apologises to all electricity consumers but call on you yet again to switch off unnecessary lights, the geyser, pool pump and air-conditioning •Load shedding schedules are available on Eskom website, and municipal customers should contact their municipalities for details •We are painfully aware of the impact of this incident given the electricity supply situation in the country •We will continue to communicate via the media