SlideShare a Scribd company logo
1 of 34
Download to read offline
1
Costs and Prices of 2013:
Are they reasonable ?
Dr Tilak Siyambalapitiya
2
At the end of this session, you would be able to
…………
• Visualize the sub-businesses within the power
industry, and their stated costs for 2013
• Question: How reasonable are the cost components?
• Appreciate the correction mechanism
• Understand the cost of supply to each customer
category
• Appreciate the subsidies and surcharges on each
customer category
• Look at the past and visualize where Sri Lanka got it
wrong
• Look into the future to examine the cost profiles.
Sub-businesses within the Electricity
Business
Generators
Transmission Network Distribution Network
Customers
Generators and transmission, distribution networks are all over
the country, but they can be represented as above.
Like to see the where they are ???
Where are the Power Plants, Transmission Lines ?
Too many distribution
lines to show on this map
PUC Publication: National Average Cost of Supply 2013
Costs of each sub-business
LKR/kWh
Generation (capacity) 2.75
Generation (energy) 15.57
Transmission 0.77 Transmission wires + system operation business
Distribution 2.72 Distribution wires and supply business
Total 21.80
Generation business
Generators
Transmission Network Distribution Network
Customers
So, 2.75 is really, really too high. Or is it ?
Is the Generation Capacity Cost Reasonable ?
Additions:
• Finance costs ?
• Maintenance costs ?
• Hydros produce less than 7008 kWh per year
• All 7008 kWh cannot be sold, owing to network losses
• IPPs need a return on equity
Subtractions:
• Depreciated old generators
• CEB generators do not need cost recovery, no return on equity ?
Consider
a power
plant of
one
kilowatt
Investment on this power plant = 1500 USD
Lifetime = 25 years
Annual electricity output = 8760*80%
= 7008 kWh
Cost of investment recovery = 1500/(25x7008)
= 0.009 USD/kWh
= 1.11 Rs/kWh
Is the Generation Capacity Cost Reasonable ?
1.11 Rs/kWh 2.75 Rs/kWh
Initial estimate
Actual Allowed cost
Annual maintenance costs 2% of investment
= 2%*1500
= 30 USD/year
Maintenance cost = 30/7008
= 0.00428 USD/kWh
= 0.00428*130
= 0.56 Rs/kWh
Therefore, cost now = 1.11 + 0.56
= 1.67 Rs/kWh
When 100 kWh is produced, only 89 kWh can be
sold to customers. The balance is lost.
So, capacity cost now = 1.67 x 100/89
= 1.88 Rs/kWh
Is the Generation Capacity Cost Reasonable ?
All Power Plants do not produce 7008 kWh per year: Some power plants, are for
Dry season backup, hydropower plants are used for peak-time duties. However, all
them have to be maintained.
Total power generating capacity = 3400 MW
Energy expected generation in 2013 = 11,000 GWh (million kWh)
Energy capability of total capacity = 3400 x 8760 x 80% = 23,800 GWh
Therefore, estimated capacity cost = 1.88 x 11000/23800
= 4.07 Rs/kWh
Therefore, on the face of it, the capacity cost of Rs 2.75 per kWh
sold seems reasonable. But ? ………
There are quite a lot of distortions in CEB power plant capacity
costs. Need to streamline them by signing PPAs between each
CEB generating plant and CEB transmission.
Generation Capacity Costs of IPPs and CEB
-
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
0 2 4 6 8 10 12 14 16
Capacitycharge(LKR/kWhatMGEA)
Year of operation
WestCoast Power
Asia Power
ACE Power
Embilipitiya
Heladhanavi
ACE Power
Horana
ACE Power
MataraAES Kelanitissa
Colombo Power
Lakdhanavi
Expected typical profile
Avg for CEB Power Plants
Norochcholai estimate
(not published yet)
Conclusion on Generation Capacity Cost
• Presently: Rs 2.75 per kWh sold
• Acceptable ?: Yes, but certainly there is
room for improvement
• Target: Rs 2.00 per kWh sold is likely to be
possible,
- provided ALL generation is CEB-owned
- with no return on equity
- no IPPs
Are the Generation Energy (Fuel) Costs Efficient ?
2013
Primary Source Ownership Share Cost
Rs/unit
Hydro CEB 30% -
Small Renewables Private 7% 18.00
Coal CEB 15% 8.30
Oil CEB and Private 48% 23.41
Average 100% 13.74
• One litre of oil: Produces between 3 to 5 kWh of electricity
• One kilogram of coal: Produces about 2.5 kWh of electricity
• Coal price reflected above: USD 150 per tonne (correct ?)
• Oil prices reflected above: Rs 120 per litre of diesel, Rs 90 per litre of
fuel oil (correct ?)
• Can hydro produce more?
• What if oil prices decrease after these costs are allowed ?
• What if it rains heavily after these estimates are done ?
Fuel Costs (Rs/kWh)
Coal 8.30
Residual oil 23.50
Furnace oil 24.53
Diesel 25.94
Renewables 18.00
If Sri Lanka wants lower prices, what should we
produce electricity from ?
13
Are the Wire business + supply costs
efficient ?
Rs/unit
Transmission 0.77
Distribution 2.72
• What should be done ?
– Constant Monitoring
– Benchmarking
– Publishing results
– Awards for improved management of costs and losses (?)
– X-factor (improved efficiency factor)
– Presently, inflation adjustment is awarded
14
Are the Allowed Losses Reasonable ?
• Allowed losses (technical + commercial)
Year
Total TL and all DL networks Policy
target
for Sri
Lanka
T&D
losses
Summarised from filed sales and losses Summarised from approved sales and losses
Sales to
End-use
Customers
(GWh)
Sales
growth
Input to
TL's
network
(GWh)
Sri
Lanka
T&D
Loss
Sales to
End-use
Customers
(GWh)
Sales
growth
Input to
TL's
network
(GWh)
Sri
Lanka
T&D
Loss
2009 8,351 8,371 - 9,754 14.2% 13.5%
2010 8,908 6.7% 10,634 16.2% 9,031 7.9% 10,503 14.0%
2011 9,460 6.2% 11,185 15.4% 9,667 7.0% 11,185 13.6%
2012 10,078 6.5% 11,917 15.4% 10,308 6.6% 11,903 13.4%
2013 10,736 6.5% 12,645 15.1% 10,989 6.6% 12,612 12.9%
2014 11,437 6.5% 13,424 14.8% 11,713 6.6% 13,375 12.4%
2015 12,184 6.5% 14,229 14.4% 12,485 6.6% 14,206 12.1% 12.1%
2016 12.0%
2012 Actuals
Distribution
Entity
Target Loss
(% of input)
Actual Loss
(% of input)
CEB R1 8.9% 6.6%
CEB R2 11.8% 9.3%
CEB R3 8.9% 7.8%
CEB R4 10.1% 4.9%
LECO 5.6% 6.6%
All distribution 10.7% 7.4%
CEB Transmission: Target 3.0%, Actual 4.4% in 2012
15
Network Loss Management
– Are we really so efficient ?
• Bulk sales cause a loss of less than 1.5%
• Therefore retail sales should be causing a loss
exceeding 15%
• Engineering models say it should be 5% !!!
• So, although the loss performance is good, there is
substantial room for improvement
• Investments for loss improvement are included in
the allowed distribution revenue (Rs 2.72 per kWh)
Total Cost of Production and Delivery of Electricity: 2013
and estimate for 2014
2013 Rs/unit
Primary Source Ownership Share Cost
Rs/unit
Generation Capacity 2.75
Hydro CEB 30% - Fuel 13.74
Small Renewables Private 7% 18.00 Transmission 0.77
Coal CEB 15% 8.30 Distribution 2.72
Oil CEB and Private 48% 23.41 Network Loss Adjustment 1.82
Average 100% 13.74 Short-term Debt repayment 0.32
Total cost 22.12
2014
Primary Source Ownership Share Cost
Rs/unit
Generation Capacity 2.50
Hydro CEB 30% - Fuel 9.30
Small Renewables Private 7% 18.00 Transmission 0.77
Coal CEB 45% 8.50 Distribution 2.72
Oil CEB and Private 18% 23.41 Network Loss Adjustment 1.27
Average 100% 9.30 Short-term Debt repayment 0.32
16.87
Observation: Generation capacity costs are likely to increase when the PPAs for
Norochcholai and Upper Kotmale (CEB-GL to CEB-TL) become effective
Interpretation of System Costs: 2013
Generators
Transmission Network Distribution Network
Customers
Fixed Costs in Rs per kWh sold to end users
2.75 0.77 2.72
Fuel Costs in Rs per kWh
13.74 15.57
18
Indicative Revenue Management Mechanism 2013:
Single Buyer
Bulk Supply
Transactions
Account
Generators
(CEB, IPP,SPP)Shot-term
debt
repayment
GOSL
Subsidy
8,013
million
LKR
3,504
million
LKR
DL1
8,484
million LKR
DL2
8,920
million LKR
DL3
5,247
million LKR
DL4
4,167
million LKR
DL5
2,913
million LKR
TL
8435
million LKR
8,435
million LKR
xxxxxx
million LKR
xxxxxx
million LKR
xxxxxx
million LKR
xxxxxxxx
million LKR
xxxxxx
million LKR
186,770
million LKR
xxxxx
million LKR
xxxxxxx
million LKR
xxxxxx
million LKR
xxxxxx
million LKR
xxxxxx
million LKR
190,398
million LKR
19
Role of the Bulk Supply Transactions Account (BSTA)
Single Buyer
Bulk Supply
Transactions
Account
Pay
Transmission
Licensee
Income from
Sales to
Distribution
Pay
Generation
Licensees:
CEB, IPPs,
SPPs
Receive
Govt
Subsidies
Main Source of
Income
Rainfall
above
average,
lower
fuel
prices
Rainfall
below
average,
higher
fuel
prices
20
Revenue Correction Mechanism: Wire and Supply
Businesses
• All five DLs must report profits (there is no reason
for any DL to report losses): to realize this, annual
accounts must be prepared and published
• The TL must report profits
• Annually: TL and DL allowed revenues are adjusted
– Upwards for inflation
– Downwards for required efficiency improvement (X-factor)
– Downward for return on investment planned but not done
– Upwards for any unforeseen investments (eg: substantial
weather damage)
21
Revenue Correction Mechanism: Bulk Supply Business
• Changes too rapid to wait for one year
• Once in six months:
For next six months (eg: Jul-Dec 2013)
– Forecast generation cost (based on storage, forecast
inflows, fuel prices, economic dispatch)
For the past six months (eg: Jul-Dec 2012)
– Upwards/downwards if hydro contribution was
lower/higher than expected in the Jul-Dec 2012 forecast
– Upwards/downwards if fuel prices were higher/lower than
expected in the Jul-Dec 2012 forecast
– Any extraordinary situations the TL submits
– No correction for changes in network losses
• Customer tariffs changed once in six months
22
From Costs to Pricing
The Professional Approach
• Calculate the cost of supply at
• Each voltage level
• At different times of day
• Cost of supply is blind to
• The income of user (rich or poor)
• Purpose of use (household, business, industry)
• Appliances used
• Adequate examples: Fuel pricing in Sri Lanka, LPG, all
commodities including food
• Electricity is the only commercial in Sri Lanka good where
the price is intentionally distorted at the point of sale
23
Demand
Charge
Fixed Charge
(LKR/kVA.
month)
(LKR/month)
Households All day 15.00 - - 100
Day 15.00
Peak 18.00
off-peak 12.00
Day 10.00
Peak 13.00
off-peak 7.00
Day 9.00
Peak 12.00
off-peak 8.00
MV Bulk 1200 0.4 2000
LV Bulk 1500 0.5 1000
Other retail - - 100
Customers Energy charge
(LKR/kWh)
Reactive
power
Charge
(LKR/kVArh)
Tariff figures are only for illustration
Ideal Price Structure
24
All customers are not located in the same Point of the
Network. They impose different burdens on the network
Therefore, comparing prices against the national
average cost (Rs 21.80 per kWh) is unfair, incorrect
About 44% of electricity sold in Sri Lanka is for bulk
customers, for whom the distribution and supply costs
are zero or lower
Generators
Transmission Network Distribution Network
Customers
MV Bulk LV Bulk
Other
Retail
Households
LKR/kWh
Household average 27.86
Religious average 25.74
Other retail (Industry, Commercial) 20.40
Bulk supply at LV (medium industry, commercial) 17.73
Bulk supply at MV (large industry, commercial) 15.08
National average 21.80
Cost of supply in terms of Position in the
Distribution Network
Generators
Transmission Network Distribution Network
Customers
15.08 17.73 20.40 27.86
Latest Price Announcement: Households
But how much are they being asked to pay ?: Households
Prices announced in April, Mayday concessions not included
2013 figures not published as yet
Surcharges and Cross-Subsidies: 2011 (1)
Customer Category in
year 2010 tariffs (and
kWh/month for
households)
Subsidy or surcharge as a
% of cost of supply
Volume of cross
subsidy received or
provided (LKR
million/year)Subsidised
customers
Customers
paying a
surcharge
LV Retail
0-30 80% (4,373)
31-60 77% (12,135)
61-90 70% (14,001)
91-120 40% (4,672)
121-180 20% (2,066)
181-600 29% 2,429
>600 122% 1,802
Sub Total 45% (33,016)
Other LV
Religious 61% (614)
General Purpose 1 36% 7,500
Government 1 3%
Industrial 1 18% (558)
Hotel 1 34% 7
Street Lighting 100% (2,310)
Sub Total 18% 4,024
2013 figures not published as yet
Surcharges and Cross-Subsidies: 2011 (2)
LV BULK
General Purpose 2 87% 9,942
Government 2 38%
Industrial 2 10% 1,947
Industrial 2 TOU 10% 214
Hotels 2 TOU 33% 9
Hotels 2 (GP) 36% 299
Hotels 2 (IP) 30% 195
Sub Total 38% 12,606
MEDIUM VOLTAGE
General Purpose 3 89% 2,347
Government 3 35%
Industrial 3 14% 1,583
Industrial 3 TOU 29% 403
Hotels 3 40% 31
Hotel 3 TOU 41% 256
Sub Total 30% 4,619
Total 8% (11,767)
30
The Cash Crisis in the Power Sector
31
From a Presentation on 16 July 2010
0%
5%
10%
15%
20%
25%
30%
35%
2010 2011 2012 2013 2014 2015
CumulativeTariffincrease
-20,000
-10,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
AnnualGrosssubsidyrequired(Rsmillion)
Scanario A1: Required tariff increase (% cumulative)
Scanario A2: Required tariff increase (% cumulative)
Scanerio A2: Annual gross subsidy required
Scanario A3: Annual gross subsidy required
In constant 2010
currency-no
inflation or fuel
price escalations
Red band is declining, significantly from 2014, and benefits should be given
to customers, when the methodology is implemented.
Are we coming out of the high cost regime ? Yes we are.
How ? By building lower-cost generation
33
The Evolving Cost Structure
3.20
4.03 4.01 4.53 4.65 4.62
10.54 8.64 9.15
9.49
7.04
5.59
0.45
0.79
0.85
0.96
1.12
1.06
2.71
2.88
2.67
2.49
2.30
2.12
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
2010 2011 2012 2013 2014 2015
Averagecostofsalestoend-users(Rs/kWh)
Distribution
Transmission
Generation Fuel
Generation capacity
In constant 2010 currency-no
inflation or fuel price
escalations
13.74
34
The End

More Related Content

What's hot

Project report-TATA Power
Project report-TATA PowerProject report-TATA Power
Project report-TATA Power
SHIVAM DWIVEDI
 
Financial Opportunities And Constraints For Hydropower Development 021010
Financial Opportunities And Constraints For Hydropower Development 021010Financial Opportunities And Constraints For Hydropower Development 021010
Financial Opportunities And Constraints For Hydropower Development 021010
ronmiller74
 
Low-CapEx approach to synthetic transport fuels from biomass – From laborator...
Low-CapEx approach to synthetic transport fuels from biomass – From laborator...Low-CapEx approach to synthetic transport fuels from biomass – From laborator...
Low-CapEx approach to synthetic transport fuels from biomass – From laborator...
Ilkka Hannula
 

What's hot (17)

Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
Renewable Energy Certificate
Renewable Energy CertificateRenewable Energy Certificate
Renewable Energy Certificate
 
Distributed Generation Feasibility
Distributed Generation FeasibilityDistributed Generation Feasibility
Distributed Generation Feasibility
 
Project report-TATA Power
Project report-TATA PowerProject report-TATA Power
Project report-TATA Power
 
Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) Mechanism
 
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine FarmsMichael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
 
Jim Parks - SMUD
Jim Parks - SMUDJim Parks - SMUD
Jim Parks - SMUD
 
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
 
Tata Power - DDL Company Profile
Tata Power - DDL Company ProfileTata Power - DDL Company Profile
Tata Power - DDL Company Profile
 
Financial Opportunities And Constraints For Hydropower Development 021010
Financial Opportunities And Constraints For Hydropower Development 021010Financial Opportunities And Constraints For Hydropower Development 021010
Financial Opportunities And Constraints For Hydropower Development 021010
 
Clean power plans - the role of the smart grid
Clean power plans  - the role of the smart gridClean power plans  - the role of the smart grid
Clean power plans - the role of the smart grid
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Tatapower.ppt
Tatapower.pptTatapower.ppt
Tatapower.ppt
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Low-CapEx approach to synthetic transport fuels from biomass – From laborator...
Low-CapEx approach to synthetic transport fuels from biomass – From laborator...Low-CapEx approach to synthetic transport fuels from biomass – From laborator...
Low-CapEx approach to synthetic transport fuels from biomass – From laborator...
 
Biomass And The RHI
Biomass And The RHIBiomass And The RHI
Biomass And The RHI
 
6 energy efficiency & smart grid mvdu.
6 energy efficiency & smart grid mvdu.6 energy efficiency & smart grid mvdu.
6 energy efficiency & smart grid mvdu.
 

Viewers also liked

Applicability of Smart Metering Technology in Sri Lanka
Applicability of Smart Metering Technology in Sri LankaApplicability of Smart Metering Technology in Sri Lanka
Applicability of Smart Metering Technology in Sri Lanka
JLanka Technologies (Pvt) Limited
 

Viewers also liked (18)

Optimizing Commercial Solar PV Systems : How much energy lost from Partial Sh...
Optimizing Commercial Solar PV Systems : How much energy lost from Partial Sh...Optimizing Commercial Solar PV Systems : How much energy lost from Partial Sh...
Optimizing Commercial Solar PV Systems : How much energy lost from Partial Sh...
 
Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
 
Solar PV a major electricity source - An IRENA View
Solar PV a major electricity source - An IRENA ViewSolar PV a major electricity source - An IRENA View
Solar PV a major electricity source - An IRENA View
 
JLanka-Solar-System-vs-Conventional-Systems
JLanka-Solar-System-vs-Conventional-SystemsJLanka-Solar-System-vs-Conventional-Systems
JLanka-Solar-System-vs-Conventional-Systems
 
Climate Change 2013 : The Physical Science Basis
Climate Change 2013 : The Physical Science BasisClimate Change 2013 : The Physical Science Basis
Climate Change 2013 : The Physical Science Basis
 
Ceylon Electricity Board
Ceylon Electricity BoardCeylon Electricity Board
Ceylon Electricity Board
 
How much energy really gets lost from Partial Shading?
 How much energy really gets lost from Partial Shading? How much energy really gets lost from Partial Shading?
How much energy really gets lost from Partial Shading?
 
Power systems İntroduction
Power systems İntroductionPower systems İntroduction
Power systems İntroduction
 
Training report
Training reportTraining report
Training report
 
Final training report PDF
Final training report PDFFinal training report PDF
Final training report PDF
 
CEB Executive Team 1999
CEB Executive Team 1999CEB Executive Team 1999
CEB Executive Team 1999
 
Presentation on Low cost solutions for mass scale renewables
 Presentation on Low cost solutions for mass scale renewables Presentation on Low cost solutions for mass scale renewables
Presentation on Low cost solutions for mass scale renewables
 
Copy Of Pv Calc For Sri Lanka Home
Copy Of Pv Calc For Sri Lanka HomeCopy Of Pv Calc For Sri Lanka Home
Copy Of Pv Calc For Sri Lanka Home
 
Renewable Power Generation Costs in 2012: IRENA Analysis
Renewable Power Generation Costs in 2012: IRENA AnalysisRenewable Power Generation Costs in 2012: IRENA Analysis
Renewable Power Generation Costs in 2012: IRENA Analysis
 
Agreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plusAgreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plus
 
Applicability of Smart Metering Technology in Sri Lanka
Applicability of Smart Metering Technology in Sri LankaApplicability of Smart Metering Technology in Sri Lanka
Applicability of Smart Metering Technology in Sri Lanka
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
 

Similar to Costs and Prices of Electricity in Sri Lanka 2013: Are they reasonable..?

Solar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation SlidesSolar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
SlideTeam
 
Power market operation 발표
Power market operation 발표Power market operation 발표
Power market operation 발표
상진 정
 
Samit Jain - Advit Foundation
Samit Jain - Advit FoundationSamit Jain - Advit Foundation
Samit Jain - Advit Foundation
guest17a0764
 
Finding financing for industrial energy efficiency & chp
Finding financing for industrial energy efficiency & chpFinding financing for industrial energy efficiency & chp
Finding financing for industrial energy efficiency & chp
TNenergy
 
Switch energy customer presentation
Switch energy customer presentationSwitch energy customer presentation
Switch energy customer presentation
Switch Energy
 
Energy management.9901366442
Energy management.9901366442Energy management.9901366442
Energy management.9901366442
NMIMS ASSIGNMENTS HELP
 
Cutting Costs for Energy Producers by 1 Cent per Kilowatt Hour
Cutting Costs for Energy Producers by 1 Cent per Kilowatt HourCutting Costs for Energy Producers by 1 Cent per Kilowatt Hour
Cutting Costs for Energy Producers by 1 Cent per Kilowatt Hour
Sentient Science
 

Similar to Costs and Prices of Electricity in Sri Lanka 2013: Are they reasonable..? (20)

Accounting On-Field Project
Accounting On-Field ProjectAccounting On-Field Project
Accounting On-Field Project
 
Energy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and managementEnergy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and management
 
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation SlidesSolar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
 
webinar on " Economics Behind the Solutions to Optimize KVAh Billing”
webinar on " Economics Behind the Solutions to Optimize KVAh Billing”webinar on " Economics Behind the Solutions to Optimize KVAh Billing”
webinar on " Economics Behind the Solutions to Optimize KVAh Billing”
 
uday scheme
uday schemeuday scheme
uday scheme
 
Power sector reforms
Power sector reformsPower sector reforms
Power sector reforms
 
Power market operation 발표
Power market operation 발표Power market operation 발표
Power market operation 발표
 
TPDDL Excellence Journey
TPDDL Excellence JourneyTPDDL Excellence Journey
TPDDL Excellence Journey
 
Anglian Water Trial – Cambridge
Anglian Water Trial – CambridgeAnglian Water Trial – Cambridge
Anglian Water Trial – Cambridge
 
Counting the Capacity that Didn't Hatch
Counting the Capacity that Didn't HatchCounting the Capacity that Didn't Hatch
Counting the Capacity that Didn't Hatch
 
Samit Jain - Advit Foundation
Samit Jain - Advit FoundationSamit Jain - Advit Foundation
Samit Jain - Advit Foundation
 
Iniciativas de Eficiência Energética na Ásia e Pacífico
Iniciativas de Eficiência Energética na Ásia e Pacífico	Iniciativas de Eficiência Energética na Ásia e Pacífico
Iniciativas de Eficiência Energética na Ásia e Pacífico
 
Michel Sacotte - Schneider Electric
Michel Sacotte - Schneider ElectricMichel Sacotte - Schneider Electric
Michel Sacotte - Schneider Electric
 
Finding financing for industrial energy efficiency & chp
Finding financing for industrial energy efficiency & chpFinding financing for industrial energy efficiency & chp
Finding financing for industrial energy efficiency & chp
 
Switch energy customer presentation
Switch energy customer presentationSwitch energy customer presentation
Switch energy customer presentation
 
6: Energy Management in Water Supply Systems - Life-Cycle Cost Analysis
6: Energy Management in Water Supply Systems - Life-Cycle Cost Analysis6: Energy Management in Water Supply Systems - Life-Cycle Cost Analysis
6: Energy Management in Water Supply Systems - Life-Cycle Cost Analysis
 
Operating costing
Operating costingOperating costing
Operating costing
 
Energy management.9901366442
Energy management.9901366442Energy management.9901366442
Energy management.9901366442
 
Cutting Costs for Energy Producers by 1 Cent per Kilowatt Hour
Cutting Costs for Energy Producers by 1 Cent per Kilowatt HourCutting Costs for Energy Producers by 1 Cent per Kilowatt Hour
Cutting Costs for Energy Producers by 1 Cent per Kilowatt Hour
 
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...
 

More from JLanka Technologies (Pvt) Limited

SolarEdge_Distributed_Power_Harvesting_System_Overview
SolarEdge_Distributed_Power_Harvesting_System_OverviewSolarEdge_Distributed_Power_Harvesting_System_Overview
SolarEdge_Distributed_Power_Harvesting_System_Overview
JLanka Technologies (Pvt) Limited
 

More from JLanka Technologies (Pvt) Limited (13)

Climate Change 2014: Impacts, Adaptation, and Vulnerability - SUMMARY FOR POL...
Climate Change 2014: Impacts, Adaptation, and Vulnerability - SUMMARY FOR POL...Climate Change 2014: Impacts, Adaptation, and Vulnerability - SUMMARY FOR POL...
Climate Change 2014: Impacts, Adaptation, and Vulnerability - SUMMARY FOR POL...
 
SolarEdge Performance of PV Topologies under Shaded Conditions - NREL Study
SolarEdge Performance of PV Topologies under Shaded Conditions - NREL StudySolarEdge Performance of PV Topologies under Shaded Conditions - NREL Study
SolarEdge Performance of PV Topologies under Shaded Conditions - NREL Study
 
Making Solar PV Panels Smarter - Up to 25% More Energy
Making Solar PV Panels Smarter - Up to 25% More EnergyMaking Solar PV Panels Smarter - Up to 25% More Energy
Making Solar PV Panels Smarter - Up to 25% More Energy
 
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
 
Solar Thermal Energy an Industry Report
Solar Thermal Energy an Industry ReportSolar Thermal Energy an Industry Report
Solar Thermal Energy an Industry Report
 
Solaredge System Outperforms String And Micro Inverters In NREL-Designed Inde...
Solaredge System Outperforms String And Micro Inverters In NREL-Designed Inde...Solaredge System Outperforms String And Micro Inverters In NREL-Designed Inde...
Solaredge System Outperforms String And Micro Inverters In NREL-Designed Inde...
 
Importance of sustainable energy
Importance of sustainable energyImportance of sustainable energy
Importance of sustainable energy
 
How the monthly electricity bill is calculated in Sri Lanka
How the monthly electricity bill is calculated in Sri LankaHow the monthly electricity bill is calculated in Sri Lanka
How the monthly electricity bill is calculated in Sri Lanka
 
Problems and Disadvantages in Current Residential & Commercial On-grid PV Sys...
Problems and Disadvantages in Current Residential & Commercial On-grid PV Sys...Problems and Disadvantages in Current Residential & Commercial On-grid PV Sys...
Problems and Disadvantages in Current Residential & Commercial On-grid PV Sys...
 
World energy-outlook-2012
World energy-outlook-2012World energy-outlook-2012
World energy-outlook-2012
 
SolarEdge_Distributed_Power_Harvesting_System_Overview
SolarEdge_Distributed_Power_Harvesting_System_OverviewSolarEdge_Distributed_Power_Harvesting_System_Overview
SolarEdge_Distributed_Power_Harvesting_System_Overview
 
JLanka SolarEdge System Overview
JLanka SolarEdge System OverviewJLanka SolarEdge System Overview
JLanka SolarEdge System Overview
 
Benefits of Solar Energy - Sri Lanka
Benefits of Solar Energy - Sri LankaBenefits of Solar Energy - Sri Lanka
Benefits of Solar Energy - Sri Lanka
 

Recently uploaded

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 

Recently uploaded (20)

Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
HTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesHTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation Strategies
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 

Costs and Prices of Electricity in Sri Lanka 2013: Are they reasonable..?

  • 1. 1 Costs and Prices of 2013: Are they reasonable ? Dr Tilak Siyambalapitiya
  • 2. 2 At the end of this session, you would be able to ………… • Visualize the sub-businesses within the power industry, and their stated costs for 2013 • Question: How reasonable are the cost components? • Appreciate the correction mechanism • Understand the cost of supply to each customer category • Appreciate the subsidies and surcharges on each customer category • Look at the past and visualize where Sri Lanka got it wrong • Look into the future to examine the cost profiles.
  • 3. Sub-businesses within the Electricity Business Generators Transmission Network Distribution Network Customers Generators and transmission, distribution networks are all over the country, but they can be represented as above. Like to see the where they are ???
  • 4. Where are the Power Plants, Transmission Lines ? Too many distribution lines to show on this map
  • 5. PUC Publication: National Average Cost of Supply 2013 Costs of each sub-business LKR/kWh Generation (capacity) 2.75 Generation (energy) 15.57 Transmission 0.77 Transmission wires + system operation business Distribution 2.72 Distribution wires and supply business Total 21.80 Generation business Generators Transmission Network Distribution Network Customers
  • 6. So, 2.75 is really, really too high. Or is it ? Is the Generation Capacity Cost Reasonable ? Additions: • Finance costs ? • Maintenance costs ? • Hydros produce less than 7008 kWh per year • All 7008 kWh cannot be sold, owing to network losses • IPPs need a return on equity Subtractions: • Depreciated old generators • CEB generators do not need cost recovery, no return on equity ? Consider a power plant of one kilowatt Investment on this power plant = 1500 USD Lifetime = 25 years Annual electricity output = 8760*80% = 7008 kWh Cost of investment recovery = 1500/(25x7008) = 0.009 USD/kWh = 1.11 Rs/kWh
  • 7. Is the Generation Capacity Cost Reasonable ? 1.11 Rs/kWh 2.75 Rs/kWh Initial estimate Actual Allowed cost Annual maintenance costs 2% of investment = 2%*1500 = 30 USD/year Maintenance cost = 30/7008 = 0.00428 USD/kWh = 0.00428*130 = 0.56 Rs/kWh Therefore, cost now = 1.11 + 0.56 = 1.67 Rs/kWh When 100 kWh is produced, only 89 kWh can be sold to customers. The balance is lost. So, capacity cost now = 1.67 x 100/89 = 1.88 Rs/kWh
  • 8. Is the Generation Capacity Cost Reasonable ? All Power Plants do not produce 7008 kWh per year: Some power plants, are for Dry season backup, hydropower plants are used for peak-time duties. However, all them have to be maintained. Total power generating capacity = 3400 MW Energy expected generation in 2013 = 11,000 GWh (million kWh) Energy capability of total capacity = 3400 x 8760 x 80% = 23,800 GWh Therefore, estimated capacity cost = 1.88 x 11000/23800 = 4.07 Rs/kWh Therefore, on the face of it, the capacity cost of Rs 2.75 per kWh sold seems reasonable. But ? ……… There are quite a lot of distortions in CEB power plant capacity costs. Need to streamline them by signing PPAs between each CEB generating plant and CEB transmission.
  • 9. Generation Capacity Costs of IPPs and CEB - 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 0 2 4 6 8 10 12 14 16 Capacitycharge(LKR/kWhatMGEA) Year of operation WestCoast Power Asia Power ACE Power Embilipitiya Heladhanavi ACE Power Horana ACE Power MataraAES Kelanitissa Colombo Power Lakdhanavi Expected typical profile Avg for CEB Power Plants Norochcholai estimate (not published yet)
  • 10. Conclusion on Generation Capacity Cost • Presently: Rs 2.75 per kWh sold • Acceptable ?: Yes, but certainly there is room for improvement • Target: Rs 2.00 per kWh sold is likely to be possible, - provided ALL generation is CEB-owned - with no return on equity - no IPPs
  • 11. Are the Generation Energy (Fuel) Costs Efficient ? 2013 Primary Source Ownership Share Cost Rs/unit Hydro CEB 30% - Small Renewables Private 7% 18.00 Coal CEB 15% 8.30 Oil CEB and Private 48% 23.41 Average 100% 13.74 • One litre of oil: Produces between 3 to 5 kWh of electricity • One kilogram of coal: Produces about 2.5 kWh of electricity • Coal price reflected above: USD 150 per tonne (correct ?) • Oil prices reflected above: Rs 120 per litre of diesel, Rs 90 per litre of fuel oil (correct ?) • Can hydro produce more? • What if oil prices decrease after these costs are allowed ? • What if it rains heavily after these estimates are done ?
  • 12. Fuel Costs (Rs/kWh) Coal 8.30 Residual oil 23.50 Furnace oil 24.53 Diesel 25.94 Renewables 18.00 If Sri Lanka wants lower prices, what should we produce electricity from ?
  • 13. 13 Are the Wire business + supply costs efficient ? Rs/unit Transmission 0.77 Distribution 2.72 • What should be done ? – Constant Monitoring – Benchmarking – Publishing results – Awards for improved management of costs and losses (?) – X-factor (improved efficiency factor) – Presently, inflation adjustment is awarded
  • 14. 14 Are the Allowed Losses Reasonable ? • Allowed losses (technical + commercial) Year Total TL and all DL networks Policy target for Sri Lanka T&D losses Summarised from filed sales and losses Summarised from approved sales and losses Sales to End-use Customers (GWh) Sales growth Input to TL's network (GWh) Sri Lanka T&D Loss Sales to End-use Customers (GWh) Sales growth Input to TL's network (GWh) Sri Lanka T&D Loss 2009 8,351 8,371 - 9,754 14.2% 13.5% 2010 8,908 6.7% 10,634 16.2% 9,031 7.9% 10,503 14.0% 2011 9,460 6.2% 11,185 15.4% 9,667 7.0% 11,185 13.6% 2012 10,078 6.5% 11,917 15.4% 10,308 6.6% 11,903 13.4% 2013 10,736 6.5% 12,645 15.1% 10,989 6.6% 12,612 12.9% 2014 11,437 6.5% 13,424 14.8% 11,713 6.6% 13,375 12.4% 2015 12,184 6.5% 14,229 14.4% 12,485 6.6% 14,206 12.1% 12.1% 2016 12.0% 2012 Actuals Distribution Entity Target Loss (% of input) Actual Loss (% of input) CEB R1 8.9% 6.6% CEB R2 11.8% 9.3% CEB R3 8.9% 7.8% CEB R4 10.1% 4.9% LECO 5.6% 6.6% All distribution 10.7% 7.4% CEB Transmission: Target 3.0%, Actual 4.4% in 2012
  • 15. 15 Network Loss Management – Are we really so efficient ? • Bulk sales cause a loss of less than 1.5% • Therefore retail sales should be causing a loss exceeding 15% • Engineering models say it should be 5% !!! • So, although the loss performance is good, there is substantial room for improvement • Investments for loss improvement are included in the allowed distribution revenue (Rs 2.72 per kWh)
  • 16. Total Cost of Production and Delivery of Electricity: 2013 and estimate for 2014 2013 Rs/unit Primary Source Ownership Share Cost Rs/unit Generation Capacity 2.75 Hydro CEB 30% - Fuel 13.74 Small Renewables Private 7% 18.00 Transmission 0.77 Coal CEB 15% 8.30 Distribution 2.72 Oil CEB and Private 48% 23.41 Network Loss Adjustment 1.82 Average 100% 13.74 Short-term Debt repayment 0.32 Total cost 22.12 2014 Primary Source Ownership Share Cost Rs/unit Generation Capacity 2.50 Hydro CEB 30% - Fuel 9.30 Small Renewables Private 7% 18.00 Transmission 0.77 Coal CEB 45% 8.50 Distribution 2.72 Oil CEB and Private 18% 23.41 Network Loss Adjustment 1.27 Average 100% 9.30 Short-term Debt repayment 0.32 16.87 Observation: Generation capacity costs are likely to increase when the PPAs for Norochcholai and Upper Kotmale (CEB-GL to CEB-TL) become effective
  • 17. Interpretation of System Costs: 2013 Generators Transmission Network Distribution Network Customers Fixed Costs in Rs per kWh sold to end users 2.75 0.77 2.72 Fuel Costs in Rs per kWh 13.74 15.57
  • 18. 18 Indicative Revenue Management Mechanism 2013: Single Buyer Bulk Supply Transactions Account Generators (CEB, IPP,SPP)Shot-term debt repayment GOSL Subsidy 8,013 million LKR 3,504 million LKR DL1 8,484 million LKR DL2 8,920 million LKR DL3 5,247 million LKR DL4 4,167 million LKR DL5 2,913 million LKR TL 8435 million LKR 8,435 million LKR xxxxxx million LKR xxxxxx million LKR xxxxxx million LKR xxxxxxxx million LKR xxxxxx million LKR 186,770 million LKR xxxxx million LKR xxxxxxx million LKR xxxxxx million LKR xxxxxx million LKR xxxxxx million LKR 190,398 million LKR
  • 19. 19 Role of the Bulk Supply Transactions Account (BSTA) Single Buyer Bulk Supply Transactions Account Pay Transmission Licensee Income from Sales to Distribution Pay Generation Licensees: CEB, IPPs, SPPs Receive Govt Subsidies Main Source of Income Rainfall above average, lower fuel prices Rainfall below average, higher fuel prices
  • 20. 20 Revenue Correction Mechanism: Wire and Supply Businesses • All five DLs must report profits (there is no reason for any DL to report losses): to realize this, annual accounts must be prepared and published • The TL must report profits • Annually: TL and DL allowed revenues are adjusted – Upwards for inflation – Downwards for required efficiency improvement (X-factor) – Downward for return on investment planned but not done – Upwards for any unforeseen investments (eg: substantial weather damage)
  • 21. 21 Revenue Correction Mechanism: Bulk Supply Business • Changes too rapid to wait for one year • Once in six months: For next six months (eg: Jul-Dec 2013) – Forecast generation cost (based on storage, forecast inflows, fuel prices, economic dispatch) For the past six months (eg: Jul-Dec 2012) – Upwards/downwards if hydro contribution was lower/higher than expected in the Jul-Dec 2012 forecast – Upwards/downwards if fuel prices were higher/lower than expected in the Jul-Dec 2012 forecast – Any extraordinary situations the TL submits – No correction for changes in network losses • Customer tariffs changed once in six months
  • 22. 22 From Costs to Pricing The Professional Approach • Calculate the cost of supply at • Each voltage level • At different times of day • Cost of supply is blind to • The income of user (rich or poor) • Purpose of use (household, business, industry) • Appliances used • Adequate examples: Fuel pricing in Sri Lanka, LPG, all commodities including food • Electricity is the only commercial in Sri Lanka good where the price is intentionally distorted at the point of sale
  • 23. 23 Demand Charge Fixed Charge (LKR/kVA. month) (LKR/month) Households All day 15.00 - - 100 Day 15.00 Peak 18.00 off-peak 12.00 Day 10.00 Peak 13.00 off-peak 7.00 Day 9.00 Peak 12.00 off-peak 8.00 MV Bulk 1200 0.4 2000 LV Bulk 1500 0.5 1000 Other retail - - 100 Customers Energy charge (LKR/kWh) Reactive power Charge (LKR/kVArh) Tariff figures are only for illustration Ideal Price Structure
  • 24. 24 All customers are not located in the same Point of the Network. They impose different burdens on the network Therefore, comparing prices against the national average cost (Rs 21.80 per kWh) is unfair, incorrect About 44% of electricity sold in Sri Lanka is for bulk customers, for whom the distribution and supply costs are zero or lower Generators Transmission Network Distribution Network Customers MV Bulk LV Bulk Other Retail Households
  • 25. LKR/kWh Household average 27.86 Religious average 25.74 Other retail (Industry, Commercial) 20.40 Bulk supply at LV (medium industry, commercial) 17.73 Bulk supply at MV (large industry, commercial) 15.08 National average 21.80 Cost of supply in terms of Position in the Distribution Network Generators Transmission Network Distribution Network Customers 15.08 17.73 20.40 27.86
  • 27. But how much are they being asked to pay ?: Households Prices announced in April, Mayday concessions not included
  • 28. 2013 figures not published as yet Surcharges and Cross-Subsidies: 2011 (1) Customer Category in year 2010 tariffs (and kWh/month for households) Subsidy or surcharge as a % of cost of supply Volume of cross subsidy received or provided (LKR million/year)Subsidised customers Customers paying a surcharge LV Retail 0-30 80% (4,373) 31-60 77% (12,135) 61-90 70% (14,001) 91-120 40% (4,672) 121-180 20% (2,066) 181-600 29% 2,429 >600 122% 1,802 Sub Total 45% (33,016) Other LV Religious 61% (614) General Purpose 1 36% 7,500 Government 1 3% Industrial 1 18% (558) Hotel 1 34% 7 Street Lighting 100% (2,310) Sub Total 18% 4,024
  • 29. 2013 figures not published as yet Surcharges and Cross-Subsidies: 2011 (2) LV BULK General Purpose 2 87% 9,942 Government 2 38% Industrial 2 10% 1,947 Industrial 2 TOU 10% 214 Hotels 2 TOU 33% 9 Hotels 2 (GP) 36% 299 Hotels 2 (IP) 30% 195 Sub Total 38% 12,606 MEDIUM VOLTAGE General Purpose 3 89% 2,347 Government 3 35% Industrial 3 14% 1,583 Industrial 3 TOU 29% 403 Hotels 3 40% 31 Hotel 3 TOU 41% 256 Sub Total 30% 4,619 Total 8% (11,767)
  • 30. 30 The Cash Crisis in the Power Sector
  • 31. 31 From a Presentation on 16 July 2010 0% 5% 10% 15% 20% 25% 30% 35% 2010 2011 2012 2013 2014 2015 CumulativeTariffincrease -20,000 -10,000 0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 AnnualGrosssubsidyrequired(Rsmillion) Scanario A1: Required tariff increase (% cumulative) Scanario A2: Required tariff increase (% cumulative) Scanerio A2: Annual gross subsidy required Scanario A3: Annual gross subsidy required In constant 2010 currency-no inflation or fuel price escalations
  • 32. Red band is declining, significantly from 2014, and benefits should be given to customers, when the methodology is implemented. Are we coming out of the high cost regime ? Yes we are. How ? By building lower-cost generation
  • 33. 33 The Evolving Cost Structure 3.20 4.03 4.01 4.53 4.65 4.62 10.54 8.64 9.15 9.49 7.04 5.59 0.45 0.79 0.85 0.96 1.12 1.06 2.71 2.88 2.67 2.49 2.30 2.12 - 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00 2010 2011 2012 2013 2014 2015 Averagecostofsalestoend-users(Rs/kWh) Distribution Transmission Generation Fuel Generation capacity In constant 2010 currency-no inflation or fuel price escalations 13.74