SlideShare a Scribd company logo
1 of 69
Download to read offline
Programmatic Risk Management Work (Handbook)




    Programmatic Risk Management:
    A “not so simple” introduction to the
    complex but critical process of building a
    “credible” schedule


     Program Planning and Controls Workshop, Denver, Colorado
     October 6th and October 14th 2008
                                                                1/69
Agenda



Duration      Topic
 20 Minutes Risk Management in Five Easy Pieces
 15 Minutes Basic Statistics for programmatic risk management
 15 Minutes Monte Carlo Simulation (MCS) theory
 20 Minutes Mechanics of MSFT Project and Risk+
 15 Minutes Programmatic Risk Ranking
 15 Minutes Building a Credible schedule
 20 Minutes Conclusion
120 Minutes




                                                                2/69
When we say “Risk Management”
   What do we really mean?




                                3/69
Five Easy Pieces†:
The Essentials of
Managing
Programmatic Risk



Managing the risk to cost, schedule, and technical performance is the
basis of a successful project management method.
† With apologies to Carole Eastman and Bob Rafelson for their 1970 film staring Jack Nicholson
                                                                                                                4/69
                                                                                                 Risk in Five Easy Pieces
Hope is Not a Strategy

When General Custer was completely surrounded,
his chief scout asked, “General what's our strategy?”
Custer replied, “The first thing we need to do is
make a note to ourselves – never get in this situation
again.”
                Hope is not a strategy!


A Strategy is the plan to successfully complete the project
If the project’s success factors, the processes that deliver them,
the alternatives when they fail, and the measurement of this
success are not defined in meaningful ways for both the
customer and managers of the project – Hope is the only
strategy left.
                                                                              5/69
                                                              Risk in Five Easy Pieces
No Single Point Estimate can be
                       correct without knowing the variance
                        Single Point Estimates use sample data to
                         calculate a single value (a statistic) that serves as a
When estimating          "best guess" for an unknown (fixed or random)
cost and duration        population parameter
for planning
purposes using          Bayesian Inference is a statistical inference where
Point Estimates          evidence or observations are used to infer the
results in the           probability that a hypothesis may be true
least likely result.
A result with a         Identifying underlying statistical behavior of the cost
50/50 chance of          and schedule parameters of the project is the first
being true.
                         step in forecasting future behavior
                        Without this information and the model in which it is
                         used any statements about cost, schedule and
                         completion dates are a 50/50 guesses

                                                                                        6/69
                                                                        Risk in Five Easy Pieces
Without Integrating $, Time, and TPM
you’re driving in the rearview mirror




                      Technical
                 Performance (TPM)


Addressing customer satisfaction means incorporating
product requirements and planned quality into the
Performance Measurement Baseline to assure the true
performance of the project is made visible.

                                                                7/69
                                                Risk in Five Easy Pieces
Without a model for risk management, you’re driving
                       in the dark with the headlights turn off



The Risk
Management
process to the right
is used by the US
DOD and differs
from the PMI
approach in how
the processes
areas are arranged.
The key is to
understand the
relationships
between these
areas.

                       Risk Management means using a proven risk management
                       process, adapting this to the project environment, and using this
                       process for everyday decision making.
                                                                                              8/69
                                                                              Risk in Five Easy Pieces
Risk Communication is …

           An interactive process of exchange
           of information and opinion among
           individuals, groups, and institutions;
           often involving multiple messages
           about the nature of risk or
           expressing concerns, opinions, or
           reactions to risk messages or to
           legal or institutional arrangements for
           risk management.
Bad news is not wine. It does not improve with age — Colin Powell


                                                                             9/69
                                                             Risk in Five Easy Pieces
Basic Statistics for Programmatic
Risk Management




Since all point estimates are wrong, statistical estimates will be needed
to construct a credible cost and schedule model
                                                                             10/69
                                                                        Basic Statistics
Uncertainty and Risk are not the
same thing – don’t confuse them
 Uncertainty stems from                 Risk stems from known
  unknown probability                     probability distributions
  distributions                           – Cost estimating methodology
  – Requirements change impacts             risk resulting from improper
  – Budget Perturbations                    models of cost
  – Re–work, and re–test                  – Cost factors such as inflation,
    phenomena                               labor rates, labor rate
                                            burdens, etc
  – Contractual arrangements
    (contract type, prime/sub             – Configuration risk (variation in
    relationships, etc)                     the technical inputs)
  – Potential for disaster (labor         – Schedule and technical risk
    troubles, shuttle loss, satellite       coupling
    “falls over”, war, hurricanes,        – Correlation between risk
    etc.)                                   distributions
  – Probability that if a discrete
    event occurs it will invoke a
    project delay



                                                                           11/69
                                                                      Basic Statistics
There are 2 types of Uncertainty
encountered in cost and schedule
 Static uncertainty is natural variation
  and foreseen risks
  – Uncertainty about the value of a
    parameter
 Dynamic uncertainty is unforeseen
  uncertainty and “chaos”
  – Stochastic changes in the underlying
    environment
  – System time delays, interactions
    between the network elements, positive
    and negative feedback loops
  – Internal dependencies
                                            12/69
                                       Basic Statistics
The Multiple Sources of Schedule Uncertainty
and Sorting Them Out is the Role of Planning
 Unknown interactions drive
  uncertainty
 Dynamic uncertainty can be
  addressed by flexibility in the
  schedule
  – On ramps
  – Off ramps
  – Alternative paths
  – Schedule “crashing” opportunities
 Modeling of this dynamic
  uncertainty requires simulation
  rather than static PERT based path
  assessment
  – Changes in critical path are
    dependent on time and state of the
    network
  – The result is a stochastic network



                                              13/69
                                          Basic Statistics
Statistics at a Glance

 Probability distribution – A          Bias –The expected deviation of
  function that describes the            the expected value of a statistical
  probabilities of possible outcomes     estimate from the quantity it
  in a "sample space.”                   estimates.
 Random variable – variable a          Correlation – A measure of the
  function of the result of a            joint impact of two variables upon
  statistical experiment in which        each other that reflects the
  each outcome has a definite            simultaneous variation of
  probability of occurrence.             quantities.
 Determinism – a theory that           Percentile – A value on a scale of
  phenomena are causally                 100 indicating the percent of a
  determined by preceding events         distribution that is equal to or
  or natural laws.                       below it.
 Standard deviation (sigma             Monte Carlo sampling – A
  value) – An index that                 modeling technique that employs
  characterizes the dispersion           random sampling to simulate a
  among the values in a population.      population being studied.


                                                                           14/69
                                                                       Basic Statistics
Statistics Versus Probability

            In building a risk tolerant
             schedule, we’re interested in the
             probability of a successful
             outcome
              – “What is the probability of making a
                desired completion date?”
            But the underlying statistics of the
             tasks influence this probability
            The statistics of the tasks, their
             arrangement in a network of tasks
             and correlation define how this
             probability based estimated
             developed.


                                                    15/69
                                               Basic Statistics
Each path and each task along that path has a
           probability distribution

 Any path could be critical depending on the convolution of the
  underlying task completion time probability distribution functions
 The independence or
  dependency of each task
  with others in the network,
  greatly influences the
  outcome of the total project
  duration
 Understanding this
  dependence is critical to
  assessing the credibility of
  the plan as well as the total
  completion time of that plan



                                                                           16/69
                                                                       Basic Statistics
Probability Distribution Functions are the Life
           Blood of good planning

 Probability of
  occurrence as a
  function of the
  number of
  samples
 “The number of
  times a task
  duration appears
  in a Monte Carlo
  simulation”



                                                 17/69
                                             Basic Statistics
Statistics of a Triangle Distribution


Triangle                                    50% of all possible values are under
distributions are                           this area of the curve. This is the
useful when                                 definition of the median
there is limited
information
about the
characteristics of
the random
variables are all
that is available.
This is common
in project cost        Minimum                                      Maximum
and schedule           1000 hrs                                     6830 hrs
estimates.
                        Mode = 2000 hrs      Mean = 3879 hrs
                                          Median = 3415 hrs

                                                                                        18/69
                                                                                   Basic Statistics
Basics of Monte Carlo Simulation




Far better an approximate answer to the right question, which is often
vague, than an exact answer to the wrong question, which can always
be made precise. — John W. Tukey, 1962
                                                                              19/69
                                                                   Basics of Monte Carlo
Monte Carlo Simulation

 Yes Monte Carlo is named after the
  country full of casinos located on
  the French Rivera
 Advantages of Monte Carlo over
  PERT is that Monte Carlo…
 – Examines all paths, not just the critical
   path
 – Provides an accurate (true) estimate of
   completion
   • Overall duration distribution
   • Confidence interval (accuracy range)
 – Sensitivity analysis of interacting tasks
 – Varied activity distribution types – not restricted to Beta
 – Schedule logic can include branching – both probabilistic and conditional
 – When resource loaded schedules are used – provides integrated cost and schedule
   probabilistic model


                                                                                         20/69
                                                                              Basics of Monte Carlo
First let’s be convinced that PERT
has limited usefulness
 The original paper (Malcolm 1959) states
   – The method is “the best that could be done in a real
     situation within tight time constraints.”
   – The time constraint was One Month
 The PERT time made the assumption that the
  standard deviation was about 1/6 of the range
  (b–a), resulting in the PERT formula.
 It has been shown that the PERT mean and
  standard deviation formulas are poor
  approximations for most Beta distributions
  (Keefer 1983 and Keefer 1993).
   – Errors up to 40% are possible for the PERT mean
   – Errors up to 550% are possible for the PERT
     standard deviation
                                                             21/69
                                                  Basics of Monte Carlo
Critical Path and Mostly Likelies

 Critical Path’s are Deterministic
 – At least one path exists through
   the network
 – The critical path is identified by
   adding the “single point” estimates
 – The critical predicts the completion
   date only if everything goes
   according to plan (we all know this
   of course)
 Schedule execution is Probabilistic
 – There is a likelihood that some durations will comprise a path that is off the critical
   path
 – The single number for the estimate – the “single point estimate” is in fact a most
   likely estimate
 – The completion date is not the most likely date, but is a confidence interval in the
   probability distribution function resulting from the convolution of all the distributions
   along all the paths to the completion of the project



                                                                                                      22/69
                                                                                           Basics of Monte Carlo
Deterministic PERT Uses Three Point
           Estimates In A Static Manner
 Durations are defined as three point estimates
 – These estimates are very subjective if captured individually by asking…
 – “What is the Minimum, Maximum, and Most Likely”
 Critical path is defined from these
  estimates is the algebraic addition of
  three point estimates
 Project duration is based on the
  algebraic addition of the times along
  the critical path
 This approach has some serious
  problems from the outset
 – Durations must be independent
 – Most likely is not the same as the
   average




                                                                                        23/69
                                                                             Basics of Monte Carlo
Foundation of Monte Carlo Theory

George Louis Leclerc, Comte de Buffon,
asked what was the probability that the
needle would fall across one of the lines,
marked in green.
That outcome occurs only if: A  l sin




                                                 24/69
                                      Basics of Monte Carlo
Mechanics of Risk+ integrated with
Microsoft Project




Any credible schedule is a credible model of its dynamic behavior. This
starts with a Monte Carlo model of the schedule’s network of tasks
                                                                            25/69
                                                                    Mechanics of Risk+
The Simplest Risk+ elements




 Task to “watch”         Most Likely     Distribution
   (Number3)             (Duration3)     (Number1)



                    Optimistic Pessimistic
                   (Duration1) (Duration2)




                                                                26/69
                                                        Mechanics of Risk+
The output of Risk+

                               Date: 9/26/2005 2:14:02 PM                                          Completion Std Deviation: 4.83 days
                               Samples: 500                                                        95% Confidence Interval: 0.42 days
 Task to “watch”               Unique ID: 10                                                       Each bar represents 2 days
                               Name: Task 10
                                0.16                                                      1.0         Completion Probability Table




                                         Cumulative Probability
                                                                                          0.9
                                0.14                                                               Prob   Date        Prob    Date
                                                                                          0.8
                                0.12                                                               0.05   2/17/06     0.55    3/1/06
                                                                                          0.7
                   Frequency


                                                                                                   0.10   2/21/06     0.60    3/2/06
                                0.10                                                      0.6      0.15   2/22/06     0.65    3/3/06
                                0.08                                                      0.5      0.20   2/22/06     0.70    3/3/06
                                                                                          0.4      0.25   2/23/06     0.75    3/6/06
                                0.06
                                                                                          0.3      0.30   2/24/06     0.80    3/7/06     80% confidence
                                0.04                                                               0.35   2/27/06     0.85    3/8/06
                                                                                          0.2
                                                                                                   0.40   2/27/06     0.90    3/9/06     that task will
                                0.02                                                      0.1      0.45   2/28/06     0.95    3/13/06    complete by
                                   2/10/06                             3/1/06       3/17/06
                                                                                                   0.50   3/1/06      1.00    3/17/06
                                                                  Completion Date
                                                                                                                                         3/7/06

 The height of each box indicates                                                               The standard deviation of the
  how often the project complete in a                                                             completion date and the 95%
  given interval during the run                                                                   confidence interval of the expected
 The S–Curve shows the cumulative                                                                completion date are in the same
  probability of completing on or                                                                 units as the “most likely remaining
  before a given date.                                                                            duration” field in the schedule


                                                                                                                                                       27/69
                                                                                                                                                Mechanics of Risk+
A Well Formed Risk+ Schedule




For Risk+ to provide useful information, the underlying schedule must
be well formed on some simple way.
                                                                            28/69
                                                                    Mechanics of Risk+
A Well formed Risk+ Schedule

 A good critical path network
 – No constraint dates
 – Lowest level tasks have predecessors and
   successors
 – 80% of relationships are finish to start
 Identify risk tasks
    – These are “reporting tasks”
    – Identify the preview task to watch during
      simulation runs
 Defining the probability distribution profile for each task
 – Bulk assignment is an easy way to start
 – A – F ranking is another approach
 – Individual risk profile assignments is best but tedious


                                                                       29/69
                                                                Mechanics of Risk+
Analyzing the Risk+ Simulation

 Risk+ generates one or more of
  the following outputs:
 – Earliest, expected, and latest
   completion date for each reporting
   task
 – Graphical and tabular displays of the
   completion date distribution for each
   reporting task
 – The standard deviation and
   confidence interval for the
   completion date distribution for each
   reporting task
 – The criticality index (percentage of
   time on the critical path) for each
   task
 – The duration mean and standard deviation for each task
 – Minimum, expected, and maximum cost for the total project
 – Graphical and tabular displays of cost distribution for the total project
 – The standard deviation and confidence interval for cost at the total project level



                                                                                               30/69
                                                                                        Mechanics of Risk+
Programmatic Risk Ranking




The variance in task duration must be defined in some systematic way.
Capturing three point values is the least desirable.
                                                                               31/69
                                                               Programmatic Risk Ranking
Thinking about risk ranking

              These classifications can be used to avoid
               asking the “3 point” question for each task
              This information will be maintained in the IMS
              When updates are made the percentage
               change can be applied across all tasks
    Classification                                  Uncertainty   Overrun
A   Routine, been done before                       Low           0% to 2%
B   Routine, but possible difficulties              Medium to Low 2% to 5%
C   Development, with little technical difficulty   Medium        5% to 10%
D   Development, but some technical difficulty      Medium High   10% to 15%
E   Significant effort, technical challenge         High          15% to 25%
F   No experience in this area                      Very High     25% to 50%



                                                                                   32/69
                                                                   Programmatic Risk Ranking
Steps in characterizing uncertainty

 Use an “envelope” method to characterize the
  minimum, maximum and “most likely”
 Fit this data to a statistical distribution
 Use conservative assumptions
 Apply greater uncertainty to less mature
  technologies
 Confirm analysis matches intuition
  Remember Sir Francis Bacon’s quote
  about beginning with uncertainty and
  ending with certainty.
  If we start with a what we think is a
  valid number we will tend to continue
  with that valid number.
  When in fact we should speak only in
  terms of confidence intervals and
  probabilities of success.
                                                          33/69
                                          Programmatic Risk Ranking
Sobering observations about 3 point
estimates when asking engineers
 In 1979, Tversky and Kahneman proposed an alternative
  to Utility theory. Prospect theory asserts that people
  make predictably irrational decisions.
 The way that a choice of decisions is presented can sway
  a person to choose the less rational decision from a set of
  options.
 Once a problem is clearly and reasonably presented,
  rarely does a person think outside the bounds of the
  frame.
 Source:
 – “The Causes of Risk Taking By Project Managers,”
   Proceedings of the Project Management Institute Annual
   Seminars & Symposium November 1–10, 2001 • Nashville,
   Tenn
 – Tversky, Amos, and Daniel Kahneman. 1981. The Framing of
   Decisions and the Psychology of Choice. Science 211
   (January 30): 453–458

                                                                  34/69
                                                  Programmatic Risk Ranking
Building a Credible Schedule




A credible schedule contains a well formed network, explicit risk
mitigations, proper margin for these risks, and a clear and concise
critical path(s). All of this is prologue to analyzing the schedule.
                                                                                     35/69
                                                                  Building a Credible Schedule
Good schedules have a contingency plans

 The schedule contingency
  needed to make the plan credible
  can be derived from the Risk+
  analysis
 The schedule contingency is the                      Is This Our
  amount of time added (or                             Contingency
  subtracted) from the baseline                        Plan ?
  schedule necessary to achieve
  the desired probability of an under
  run or over run.
 The schedule contingency can be determined through
 – Monte Carlo simulations (Risk+)
 – Best judgment from previous experience
 – Percentage factors based on historical experience
 – Correlation analysis for dependency impacts


                                                                             36/69
                                                           Building a Credible Schedule
Schedule quality and accuracy

 Accuracy range
    – Similar for each estimate class
   Consistent with estimate
    – Level of project definition
    – Purpose
    – Preparation effort
 Monte Carlo simulation
    – Analysis of results shows quality attained versus the quality sought
      (expected accuracy ranges)
 Achieving specified accuracy requirements
    – Select value at end points of confidence interval
    – Calculate percentages from base schedule completion date, including
      the contingency


                                                                                         37/69
                                                                       Building a Credible Schedule
Technical Performance Measures

 Technical Performance Measures are one method of showing risk by
  done
 – Specific actions taken in the IMS to move the compliance forward toward the
   goal
 Activities that
  assessing the
  increasing compliance
  to the technical
  performance measure
  can be show in the
  IMS
 – These can be
   Accomplishment
   Criteria




                                                                                                   38/69
                                                                                 Building a Credible Schedule
The Monte Carlo Process starts with
                     the 3 point estimates
                      Estimates of the task duration are still needed,
                       just like they are in PERT
These three             – Three point estimates could be used
point estimates
are not the PERT
                        – But risk ranking and algorithmic generation of the
ones.                     “spreads” is a better approach
They are derived      Duration estimates must be parametric rather
from the ordinal
risk ranking           than numeric values
process.                – A geometric scale of parametric risk is one approach
This allows them
to be “calibrated”    Branching probabilities need to be defined
for the domain,         – Conditional paths through the schedule can be
correlated with
the technical risk
                          evaluated using Monte Carlo tools
model.                  – This also demonstrate explicit risk mitigation
                          planning to answer the question “what if this
                          happens?”
                                                                                        39/69
                                                                     Building a Credible Schedule
Expert Judgment is required to build
                  a Risk Management approach
                   Expert judgment is typically the basis of cost and
                    schedule estimates
                      – Expert judgment is usually the weakest area of process
Building the
                        and quantification
variance values
for the ordinal       – Translating from English (SOW) to mathematics
risk rank is a          (probabilistic risk model) is usually inconsistent at best and
technical               erroneous at worst
process,
requiring          One approach
engineering           – Plan for the “best case” and preclude a self–fulfilling
judgment.               prophesy
                      – Budget for the “most likely” and recognize risks and
                        uncertainties
                      – Protect for the “worst case” and acknowledge the
                        conceivable in the risk mitigation plan
                   The credibility of the “best case” estimates if crucial to
                    the success of this approach
                                                                                             40/69
                                                                          Building a Credible Schedule
Guiding the Risk Factor Process requires
       careful weighting of each level of risk
 For tasks marked “Low” a reasonable
  approach is to score the maximum 10%                         Min   Most Max
  greater than the minimum.                                          Likely
 The “Most Likely” is then scored as a
  geometric progression for the remaining               Low    1.0   1.04          1.10
  categories with a common ratio of 1.5                Low+    1.0   1.06          1.15
 Tasks marked “Very High” are bound at            Moderate    1.0   1.09          1.24
  200% of minimum.                                Moderate+    1.0   1.14          1.36
  – No viable project manager would like a task
    grow to three times the planned duration           High    1.0   1.20          1.55
    without intervention                              High+    1.0   1.30          1.85
 The geometric progress is somewhat               Very High   1.0   1.46          2.30
  arbitrary but it should be used instead of
                                                  Very High+   1.0   1.68          3.00
  a linear progression



                                                                                        41/69
                                                                      Building a Credible Schedule
Assume now we have a well formed
                   schedule – now what?

                    With all the “bone head” elements
For the role of      removed, we can say we have a
PP&C is to
move “reporting
                     well formed schedule
past
performance” to
                    But the real role of Planning is to
“forecasting         forecast the future, provide
future
performance” it      alternative Plan’s for this forecast
must break the
mold of using        and actively engage all the
static models of
cost and             participants in the projects in the
schedule
                     Planning Process

                                                                      42/69
                                                   Building a Credible Schedule
We’re really after the management of schedule
          margin as part of planning
  Plan the risk alternatives that                      Assign duration and resource
   “might” be needed                                     estimates to both branches
         – Each mitigation has a Plan B                 Turn off for alternative for a
           branch                                        “success” path assessment
         – Keep alternatives as simple as               Turn off primary for a “failure” path
           possible (maybe one task)
                                                         assessment
  Assess probability of the alternative
   occurring
                              Plan B

30% Probability
     of failure
                                                                          80% Confidence for completion
                                                                          with current margin



70% Probability
    of success

                                            Plan A               Current Margin     Future Margin

                  Duration of Plan B    Plan A + Margin
                                                                                                                  43/69
                                                                                                Building a Credible Schedule
Successful margin management requires the
        reuse of unused durations
 Programmatic Margin is added between                                  Margin that is not used in the IMS for risk
  Development, Production and Integration                                mitigation will be moved to the next
  & Test phases                                                          sequence of risk alternatives
 Risk Margin is added to the IMS where                                 – This enables us to buy back schedule margin
  risk alternatives are identified                                        for activities further downstream
                                                                        – This enables us to control the ripple effect of
                                                                          schedule shifts on Margin activities
                                                                          Downstream
                Duration of Plan B < Plan A + Margin                      Activities shifted to
       Plan B                                                             left 2 days

                                                                                  Plan B
                                  3 Days Margin Used




                 Plan A
                                                       5 Days Margin


     First Identified Risk Alternative in IMS                                                     Plan A   5 Days Margin



                                                                           Second Identified Risk           2 days will be added
                                                                                                            to this margin task
                                                                           Alternative in IMS               to bring schedule
                                                                                                            back on track



                                                                                                                                        44/69
                                                                                                                      Building a Credible Schedule
Simulation Considerations

 Schedule logic and constraints
   – Simplify logic – model only paths which, by
     inspection, may have a significant bearing on
     the final result
   – Correlate similar activities
   – No open ends
   – Use only finish–to–start relationships with no
     lags
   – Model relationships other than finish–to–start
     as activities with base durations equal to the lag
     value
   – Eliminate all date constraints
   – Consider using branching for known
     alternatives

                                                                45/69
                                             Building a Credible Schedule
The contents of the schedule

   Constraints
   Lead/Lag
   Task relationships
   Durations
   Network topology




                                                  46/69
                               Building a Credible Schedule
Simulation Considerations

 Selection of Probability Distributions
   – Develop schedule simulation inputs
     concurrently with the cost estimate
      • Early in process – use same subject matter
        experts
      • Convert confidence intervals into probability
        duration distributions
   – Number of distributions vary depending on
     software
   – Difficult to develop inputs required for
     distributions
   – Beta and Lognormal better than triangular;
     avoid exclusive use of Normal distribution
                                                                   47/69
                                                Building a Credible Schedule
Sensitivity Analysis describes which
tasks drive the completion times
 Concentrates on inputs most likely
  to improve quality (accuracy)
 Identifies most promising
  opportunities where additional
  work will help to narrow input
  ranges
 Methods
  – Run multiple simulations
  – Use criticality index
  – “Tornado” or Pareto graph
                                                   48/69
                                Building a Credible Schedule
What we get in the end is a Credible
        Model of the schedule




All models are wrong. Some
models are useful.
– George Box (1919 – )


                             Concept generator from Ramon
                               Lull’s Ars Magna (C. 1300)




                                                                      49/69
                                                   Building a Credible Schedule
Conclusion




At this point there is too much information. Processing this information
will take time, patience, and most of all practice with the tools and the
results they produce.
                                                                             50/69
                                                                            Conclusion
Conclusions

 Project schedule status must be
  assessed in terms of a critical path
  through the schedule network
 Because the actual durations of
  each task in the network are
  uncertain (they are random
  variables following a probability
  distribution function), the project
  schedule duration must be
  modeled statistically
                                     51/69
                                    Conclusion
Conclusions

 Quality (accuracy) is measured at the
  end points of achieved confidence
  interval (suggest 80% level)
 Simulation results depend on:
  – Accuracy and care taken with base
    schedule logic
  – Use of subject matter experts to establish
    inputs
  – Selection of appropriate distribution types
  – Through analysis of multiple critical paths
  – Understanding which activities and paths
    have the greatest potential impact

                                               52/69
                                              Conclusion
Conclusions

 Cost and schedule estimates are made up of
  many independent elements.
   – When each element is planned as best case – e.g. a
     probability of achievement of 10%
   – The probability of achieving best case for a two–
     element estimate is 1%
   – For three elements, 0.01%
   – For many elements, infinitesimal
   – In effect, it is zero.
 In the beginning no attempt should be made to
  distinguish between risk and uncertainty
   – Risk involves uncertainty but it is indeed more
   – For initial purposes it is unimportant
   – The effect is combined into one statistical factor
     called “risk,” which can be described by a single
     probability distribution function
                                                           53/69
                                                          Conclusion
What are we really after in the end?

 As the program
  proceeds so
  does:
   – Increasing
     accuracy
   – Reduced
     schedule risk
   – Increasing
     visual
     confirmation     Current Estimate Accuracy
     that success
     can be reached



                                                  54/69
                                                  Conclusion
Points to remember

 Good project management is good risk
  management
 Risk management is how adults manage
  projects
 The only thing we manage is project risk
 Risks impact objectives
 Risks come from the decisions we make while
  trying to achieve the objectives
 Risks require a factual condition and have
  potential negative consequences that must be
  mitigated in the schedule


                                             55/69
                                            Conclusion
Usage is needed before
         understanding is acquired



Here and elsewhere, we shall not
obtain the best insights into things
until we actually see them growing
from the beginning.
— Aristotle




                                        56/69
                                       Conclusion
The End

                                A planning algorithm from
                                Aristotle’s De Motu Animalium
                                c. 400 BC



This is actually the beginning, since building a risk tolerant, credible,
robust schedule requires constant “execution” of the plan.
                                                                             57/69
                                                                            Conclusion
Resources
1. “The Parameters of the Classical PERT: An Assessment of its
   Success,” Rafael Herrerias Pleguezuelo,
   http://www.cyta.com.ar/biblioteca/bddoc/bdlibros/pert_van/PARAMET
   ROS.PDF
2. “Advanced Quantitative Schedule Risk Analysis,” David T. Hulett,
   Hulett & Associates, http://www.projectrisk.com/index.html
3. “Schedule Risk Analysis Simplified,” David T. Hulett, Hulett &
   Associates, http://www.projectrisk.com/index.html
4. “Project Risk Management: A Combined Analytical Hierarchy Process
   and Decision Tree Approach,” Prasanta Kumar Dey, Cost
   Engineering, Vol. 44, No. 3, March 2002.
5. “Adding Probability to Your ‘Swiss Army Knife’,” John C. Goodpasture,
   Proceedings of the 30th Annual Project Management Institute 1999
   Seminars and Symposium, October, 1999.
6. “Modeling Uncertainty in Project Scheduling,” Patrick Leach,
   Proceedings of the 2005 Crystal Ball User Conference
7. “Near Critical Paths Create Violations in the PERT Assumptions of
   Normality,” Frank Pokladnik and Robert Hill, University of Houston,
   Clear Lake, http://www.sbaer.uca.edu/research/dsi/2003/procs/237–
   4203.pdf


                                                                    58/69
                                                                    Resources
Resources
8. “Teaching SuPERT,” Kenneth R. MacLeod and Paul F. Petersen,
    Proceedings of the Decision Sciences 2003 Annual Meeting,
    Washington DC,
    http://www.sbaer.uca.edu/research/dsi/2003/by_track_paper.html
9. “The Beginning of the Monte Carlo Method,” N. Metropolis, Los
    Alamos Science, Special Issue, 1987.
    http://www.fas.org/sgp/othergov/doe/lanl/pubs/00326866.pdf
10. “Defining a Beta Distribution Function for Construction Simulation,”
    Javier Fente, Kraig Knutson, Cliff Schexnayder, Proceedings of the
    1999 Winter Simulation Conference.
11. “The Basics of Monte Carlo Simulation: A Tutorial,” S. Kandaswamy,
    Proceedings of the Project Management Institute Annual Seminars &
    Symposium, November, 2001.
12. “The Mother of All Guesses: A User Friendly Guide to Statistical
    Estimation,” Francois Melese and David Rose, Armed Forces
    Comptroller, 1998, http://www.nps.navy.mil/drmi/graphics/StatGuide–
    web.pdf
13. “Inverse Statistical Estimation via Order Statistics: A Resolution of the
    Ill–Posed Inverse problem of PERT Scheduling,” William F. Pickard,
    Inverse Problems 20, pp. 1565–1581, 2004


                                                                          59/69
                                                                          Resources
Resources
14. “Schedule Risk Analysis: Why It Is Important and How to Do It,
    “Stephen A. Book, Proceedings of the Ground Systems Architecture
    Workshop (GSAW 2002), Aerospace Corporation, March 2002,
    http://sunset.usc.edu/GSAW/gsaw2002/s11a/book.pdf
15. “Evaluation of the Risk Analysis and Cost Management (RACM)
    Model,” Matthew S. Goldberg, Institute for Defense Analysis, 1998.
    http://www.thedacs.com/topics/earnedvalue/racm.pdf
16. “PERT Completion Times Revisited,” Fred E. Williams, School of
    Management, University of Michigan–Flint, July 2005,
    http://som.umflint.edu/yener/PERT%20Completion%20Revisited.htm
17. “Overcoming Project Risk: Lessons from the PERIL Database,” Tom
    Hendrick , Program Manager, Hewlett Packard, 2003,
    http://www.failureproofprojects.com/Risky.pdf
18. “The Heart of Risk Management: Teaching Project Teams to Combat
    Risk,” Bruce Chadbourne, 30th Annual Project Management Institute
    1999 Seminara and Symposium, October 1999,
    http://www.risksig.com/Articles/pmi1999/rkalt01.pdf




                                                                   60/69
                                                                   Resources
Resources
20. Project Risk Management Resource List, NASA Headquarters Library,
    http://www.hq.nasa.gov/office/hqlibrary/ppm/ppm22.htm#art
21. “Quantify Risk to Manage Cost and Schedule,” Fred Raymond,
    Acquisition Quarterly, Spring 1999,
    http://www.dau.mil/pubs/arq/99arq/raymond.pdf
22. “Continuous Risk Management,” Cost Analysis Symposium, April
    2005,
    http://www1.jsc.nasa.gov/bu2/conferences/NCAS2005/papers/5C_–
    _Cockrell_CRM_v1_0.ppt
23. “A Novel Extension of the Triangular Distribution and its Parameter
    Estimation,” J. Rene van Dorp and Samuel Kotz, The Statistician
    51(1), pp. 63 – 79, 2002.
    http://www.seas.gwu.edu/~dorpjr/Publications/JournalPapers/TheStati
    stician2002.pdf
24. “Distribution of Modeling Dependence Cause by Common Risk
    Factors,”
     J. Rene van Dorp, European Safety and Reliability 2003 Conference
    Proceedings, March 2003,
    http://www.seas.gwu.edu/~dorpjr/Publications/ConferenceProceeding
    s/Esrel2003.pdf
                                                                   61/69
                                                                   Resources
Resources
25. “Improved Three Point Approximation To Distribution Functions For
    Application In Financial Decision Analysis,” Michele E. Pfund, Jennifer
    E. McNeill, John W. Fowler and Gerald T. Mackulak, Department of
    Industrial Engineering, Arizona State University, Tempe, Arizona,
    http://www.eas.asu.edu/ie/workingpaper/pdf/cdf_estimation_submissio
    n.pdf
26. “Analysis Of Resource–constrained Stochastic Project Networks
    Using Discrete–event Simulation,” Sucharith Vanguri, Masters Thesis,
    Mississippi State University, May 2005,
    http://sun.library.msstate.edu/ETD–db/theses/available/etd–
    04072005–123743/restricted/SucharithVanguriThesis.pdf
27. “Integrated Cost / Schedule Risk Analysis,” David T. Hulett and Bill
    Campbell, Fifth European Project Management Conference, June
    2002.
28. “Risk Interrelation Management – Controlling the Snowball Effect,” Olli
    Kuismanen, Tuomo Saari and Jussi Vähäkylä, Fifth European Project
    Management Conference, June 2002.
29. The Lady Tasting Tea: How Statistics Revolutionized Science in the
    Twentieth Century, David Salsburg, W. H. Freeman, 2001

                                                                       62/69
                                                                       Resources
Resources
30. “Triangular Approximations for Continuous Random Variables in Risk
    Analysis,” David G. Johnson, The Business School, Loughborough
    University, Liecestershire.
31. “Statistical Dependence through Common Risk Factors: With
    Applications in Uncertainty Analysis,” J. Rene van Dorp, European
    Journal of Operations Research, Volume 161(1), pp. 240–255.
32. “Statistical Dependence in the risk analysis for Project Networks Using
    Monte Carlo Methods,” J. Rene van Dorp and M. R. Dufy,
    International Journal of Production Economics, 58, pp. 17–29, 1999.
    http://www.seas.gwu.edu/~dorpjr/Publications/JournalPapers/Prodeco
    n1999.pdf
33. “Risk Analysis for Large Engineering Projects: Modeling Cost
    Uncertainty for Ship Production Activities,” M. R. Dufy and J. Rene
    van Dorp, Journal of Engineering Valuation and Cost Analysis,
    Volume 2. pp. 285–301,
    http://www.seas.gwu.edu/~dorpjr/Publications/JournalPapers/EVCA19
    99.pdf
34. “Risk Based Decision Support techniques for Programs and Projects,”
    Barney Roberts and David Frost, Futron Risk Management Center of
    Excellence, http://www.futron.com/pdf/RBDSsupporttech.pdf
                                                                       63/69
                                                                       Resources
Resources
35. Probabilistic Risk Assessment Procedures Guide for NASA Managers
    and Practitioners, Office of Safety and Mission Assurance, April 2002.
    http://www.hq.nasa.gov/office/codeq/doctree/praguide.pdf
36. “Project Planning: Improved Approach Incorporating Uncertainty,”
    Vahid Khodakarami, Norman Fenton, and Martin Neil, Track 15
    EURAM2005: “Reconciling Uncertainty and Responsibility” European
    Academy of Management.
    http://www.dcs.qmw.ac.uk/~norman/papers/project_planning_khodake
    rami.pdf
37. “A Distribution for Modeling Dependence Caused by Common Risk
    Factors,” J. Rene van Dorp, European Safety and Reliability 2003
    Conference Proceedings, March 2003.
38. “Probabilistic PERT,” Arthur Nadas, IBM Journal of Research and
    Development, 23(3), May 1979, pp. 339–347.
39. “Ranked Nodes: A Simple and effective way to model qualitative in
    large–scale Bayesian Networks,” Norman Fenton and Martin Neil,
    Risk Assessment and Decision Analysis Research Group, Department
    of Computer Science, Queen Mary, University of London, February
    21, 2005.

                                                                      64/69
                                                                      Resources
Resources
40. “Quantify Risk to Manage Cost and Schedule,” Fred Raymond,
    Acquisition Review Quarterly, Spring 1999, pp. 147–154
41. “The Causes of Risk Taking by Project Managers,” Michael Wakshull,
    Proceedings of the Project Management Institute Annual Seminars &
    Symposium, November 2001.
42. “Stochastic Project Duration Analysis Using PERT–Beta Distributions,”
    Ron Davis.
43. “Triangular Approximation for Continuous Random Variables in Risk
    Analysis,” David G. Johnson, Decision Sciences Institute Proceedings
    1998.
    http://www.sbaer.uca.edu/research/dsi/1998/Pdffiles/Papers/1114.pdf
44. “The Cause of Risk Taking by Managers,” Michael N.Wakshull,
    Proceedings of the Project Management Institute Annual Seminars &
    Symposium November 1–10, 2001, Nashville Tennessee ,
    http://www.risksig.com/Articles/pmi2001/21261.pdf
45. “The Framing of Decisions and the Psychology of Choice,” Tversky,
    Amos, and Daniel Kahneman. 1981, Science 211 (January 30): 453–
    458, http://www.cs.umu.se/kurser/TDBC12/HT99/Tversky.html


                                                                     65/69
                                                                     Resources
Resources
46. “Three Point Approximations for Continuous Random Variables,”
    Donald Keefer and Samuel Bodily, Management Science, 29(5), pp.
    595 – 609.
47. “Better Estimation of PERT Activity Time Parameters,” Donald Keefer
    and William Verdini, Management Science, 39(9), pp. 1086 – 1091.
48. “The Benefits of Integrated, Quantitative Risk Management,” Barney
    B. Roberts, Futron Corporation, 12th Annual International Symposium
    of the International Council on Systems Engineering, July 1–5, 2001,
    http://www.futron.com/pdf/benefits_QuantIRM.pdf
49. “Sources of Schedule Risk in Complex Systems Development,” Tyson
    R. Browning, INCOSE Systems Engineering Journal, Volume 2, Issue
    3, pp. 129 – 142, 14 September 1999,
    http://sbufaculty.tcu.edu/tbrowning/Publications/Browning%20(1999)–
    –SE%20Sch%20Risk%20Drivers.pdf
50. “Sources of Performance Risk in Complex System Development,”
    Tyson R. Browning, 9th Annual International Symposium of INCOSE,
    June 1999,
    http://sbufaculty.tcu.edu/tbrowning/Publications/Browning%20(1999)–
    –INCOSE%20Perf%20Risk%20Drivers.pdf

                                                                    66/69
                                                                    Resources
Resources
51. “Experiences in Improving Risk Management Processes Using the
    Concepts of the Riskit Method,” Jyrki Konito, Gerhard Getto, and
    Dieter Landes, ACM SIGSOFT Software Engineering Notes ,
    Proceedings of the 6th ACM SIGSOFT international symposium on
    Foundations of software engineering SIGSOFT '98/FSE-6, Volume 23
    Issue 6, November 1998.
52. “Anchoring and Adjustment in Software Estimation,” Jorge Aranda and
    Steve Easterbrook, Proceedings of the 10th European software
    engineering conference held jointly with 13th ACM SIGSOFT
    international symposium on Foundations of software engineering
    ESEC/FSE-13
53. “The Monte Carlo Method,” W. F. Bauer, Journal of the Society of
    Industrial Mathematics, Volume 6, Number 4, December 1958,
    http://www.cs.fsu.edu/~mascagni/Bauer_1959_Journal_SIAM.pdf.
54. “A Retrospective and Prospective Survey of the Monte Carlo Method,”
    John H. Molton, SIAM Journal, Volume 12, Number 1, January 1970,
    http://www.cs.fsu.edu/~mascagni/Halton_SIAM_Review_1970.pdf.




                                                                   67/69
                                                                   Resources
68/69
Resources
Lewis & Fowler
        8310 South Valley Highway
                Suite 300
        Englewood, Colorado 80112
         www.lewisandfowler.com
              303.524.1610
      Deliverables Based Planningsm
              Integrated Master Plan
           Integrated Master Schedule
                   Earned Value
                 Risk Management
            Proposal Support Service

Glen B. Alleman, VP, Program Planning and Controls
           galleman@lewisandfowler.com
                   303.437 5226


                                                     69/69

More Related Content

What's hot

S thomas sfield
S thomas sfieldS thomas sfield
S thomas sfieldNASAPMC
 
The role of events in simulation modeling
The role of events in simulation modelingThe role of events in simulation modeling
The role of events in simulation modelingWeibull AS
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk toleranceGlen Alleman
 
IT Risk managment combined
IT Risk managment combinedIT Risk managment combined
IT Risk managment combinedGlen Alleman
 
Stephen.book
Stephen.bookStephen.book
Stephen.bookNASAPMC
 
Ignou 10 no. project
Ignou 10 no. projectIgnou 10 no. project
Ignou 10 no. projectAnupamDubey34
 
Eric.druker
Eric.drukerEric.druker
Eric.drukerNASAPMC
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleGlen Alleman
 
Managing cost and schedule risk
Managing cost and schedule riskManaging cost and schedule risk
Managing cost and schedule riskGlen Alleman
 
Outsourcing
OutsourcingOutsourcing
OutsourcingNgoc Dep
 
Factors Affecting Risk Management For Construction By Analytic Hierarchy Proc...
Factors Affecting Risk Management For Construction By Analytic Hierarchy Proc...Factors Affecting Risk Management For Construction By Analytic Hierarchy Proc...
Factors Affecting Risk Management For Construction By Analytic Hierarchy Proc...A Makwana
 
Building a Risk Tolerant IMS
Building a Risk Tolerant IMSBuilding a Risk Tolerant IMS
Building a Risk Tolerant IMSGlen Alleman
 
Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)Glen Alleman
 

What's hot (20)

S thomas sfield
S thomas sfieldS thomas sfield
S thomas sfield
 
Risk ppt1672
Risk ppt1672Risk ppt1672
Risk ppt1672
 
The role of events in simulation modeling
The role of events in simulation modelingThe role of events in simulation modeling
The role of events in simulation modeling
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk tolerance
 
IT Risk managment combined
IT Risk managment combinedIT Risk managment combined
IT Risk managment combined
 
Stephen.book
Stephen.bookStephen.book
Stephen.book
 
Ignou 10 no. project
Ignou 10 no. projectIgnou 10 no. project
Ignou 10 no. project
 
Eric.druker
Eric.drukerEric.druker
Eric.druker
 
Chap5
Chap5Chap5
Chap5
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and Schedule
 
Managing cost and schedule risk
Managing cost and schedule riskManaging cost and schedule risk
Managing cost and schedule risk
 
Pmi 19 26
Pmi 19 26Pmi 19 26
Pmi 19 26
 
Killion
KillionKillion
Killion
 
Outsourcing
OutsourcingOutsourcing
Outsourcing
 
Factors Affecting Risk Management For Construction By Analytic Hierarchy Proc...
Factors Affecting Risk Management For Construction By Analytic Hierarchy Proc...Factors Affecting Risk Management For Construction By Analytic Hierarchy Proc...
Factors Affecting Risk Management For Construction By Analytic Hierarchy Proc...
 
Building a Risk Tolerant IMS
Building a Risk Tolerant IMSBuilding a Risk Tolerant IMS
Building a Risk Tolerant IMS
 
Savi chapter9
Savi chapter9Savi chapter9
Savi chapter9
 
targeting process part 1
targeting process part 1targeting process part 1
targeting process part 1
 
Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)
 
Wagster
WagsterWagster
Wagster
 

Viewers also liked

Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentationGlen Alleman
 
Applying risk radar (v2)
Applying risk radar (v2)Applying risk radar (v2)
Applying risk radar (v2)Glen Alleman
 
Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Glen Alleman
 
Project Performance Evaluations
Project Performance EvaluationsProject Performance Evaluations
Project Performance Evaluationssvandegrift
 
Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellGlen Alleman
 
Requirements elicitation
Requirements elicitationRequirements elicitation
Requirements elicitationGlen Alleman
 
The Sustainable Project Management Maturity Model
The Sustainable Project Management Maturity ModelThe Sustainable Project Management Maturity Model
The Sustainable Project Management Maturity ModelGilbert Silvius
 

Viewers also liked (7)

Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentation
 
Applying risk radar (v2)
Applying risk radar (v2)Applying risk radar (v2)
Applying risk radar (v2)
 
Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)
 
Project Performance Evaluations
Project Performance EvaluationsProject Performance Evaluations
Project Performance Evaluations
 
Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut Shell
 
Requirements elicitation
Requirements elicitationRequirements elicitation
Requirements elicitation
 
The Sustainable Project Management Maturity Model
The Sustainable Project Management Maturity ModelThe Sustainable Project Management Maturity Model
The Sustainable Project Management Maturity Model
 

Similar to Programmatic risk management workshop (handbook)

Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project ManagementVenkatesh Ganapathy
 
Risk management of the performance measurement baseline
Risk management of the performance measurement baselineRisk management of the performance measurement baseline
Risk management of the performance measurement baselineGlen Alleman
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownAcumen
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)Glen Alleman
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk ManagementGlen Alleman
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertaintyGlen Alleman
 
Risk management 4th in a series
Risk management 4th in a seriesRisk management 4th in a series
Risk management 4th in a seriesGlen Alleman
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy PiecesGlen Alleman
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy PiecesGlen Alleman
 
Project examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersProject examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersJohn Goodpasture
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - PaperDaniel Ackermann
 
Risk management (Denver PM))
Risk management (Denver PM))Risk management (Denver PM))
Risk management (Denver PM))Glen Alleman
 
Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngbloodNASAPMC
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaPankaj K Sinha
 
Advantages of Regression Models Over Expert Judgement for Characterizing Cybe...
Advantages of Regression Models Over Expert Judgement for Characterizing Cybe...Advantages of Regression Models Over Expert Judgement for Characterizing Cybe...
Advantages of Regression Models Over Expert Judgement for Characterizing Cybe...Thomas Lee
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Glen Alleman
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment templateGlen Alleman
 

Similar to Programmatic risk management workshop (handbook) (20)

Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project Management
 
Risk management of the performance measurement baseline
Risk management of the performance measurement baselineRisk management of the performance measurement baseline
Risk management of the performance measurement baseline
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)
 
Stephen cresswell risk are we missing a trick - 25th june
Stephen cresswell   risk are we missing a trick - 25th juneStephen cresswell   risk are we missing a trick - 25th june
Stephen cresswell risk are we missing a trick - 25th june
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertainty
 
Risk management 4th in a series
Risk management 4th in a seriesRisk management 4th in a series
Risk management 4th in a series
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy Pieces
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy Pieces
 
Project examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersProject examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbers
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - Paper
 
Risk management (Denver PM))
Risk management (Denver PM))Risk management (Denver PM))
Risk management (Denver PM))
 
Risk Adjusted Estimating Techniques
Risk Adjusted Estimating TechniquesRisk Adjusted Estimating Techniques
Risk Adjusted Estimating Techniques
 
Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngblood
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
 
Advantages of Regression Models Over Expert Judgement for Characterizing Cybe...
Advantages of Regression Models Over Expert Judgement for Characterizing Cybe...Advantages of Regression Models Over Expert Judgement for Characterizing Cybe...
Advantages of Regression Models Over Expert Judgement for Characterizing Cybe...
 
Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Recently uploaded

Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Delhi Call girls
 
20240429 Calibre April 2024 Investor Presentation.pdf
20240429 Calibre April 2024 Investor Presentation.pdf20240429 Calibre April 2024 Investor Presentation.pdf
20240429 Calibre April 2024 Investor Presentation.pdfAdnet Communications
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfThe Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfGale Pooley
 
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...Call Girls in Nagpur High Profile
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...ssifa0344
 
Basic concepts related to Financial modelling
Basic concepts related to Financial modellingBasic concepts related to Financial modelling
Basic concepts related to Financial modellingbaijup5
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptxFinTech Belgium
 
The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfGale Pooley
 
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...dipikadinghjn ( Why You Choose Us? ) Escorts
 
Booking open Available Pune Call Girls Wadgaon Sheri 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Wadgaon Sheri  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Wadgaon Sheri  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Wadgaon Sheri 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
The Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfThe Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfGale Pooley
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure servicePooja Nehwal
 
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Pooja Nehwal
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfGale Pooley
 
Pooja 9892124323 : Call Girl in Juhu Escorts Service Free Home Delivery
Pooja 9892124323 : Call Girl in Juhu Escorts Service Free Home DeliveryPooja 9892124323 : Call Girl in Juhu Escorts Service Free Home Delivery
Pooja 9892124323 : Call Girl in Juhu Escorts Service Free Home DeliveryPooja Nehwal
 

Recently uploaded (20)

Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
 
20240429 Calibre April 2024 Investor Presentation.pdf
20240429 Calibre April 2024 Investor Presentation.pdf20240429 Calibre April 2024 Investor Presentation.pdf
20240429 Calibre April 2024 Investor Presentation.pdf
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
 
The Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfThe Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdf
 
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
 
Basic concepts related to Financial modelling
Basic concepts related to Financial modellingBasic concepts related to Financial modelling
Basic concepts related to Financial modelling
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx
 
The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdf
 
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
 
Booking open Available Pune Call Girls Wadgaon Sheri 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Wadgaon Sheri  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Wadgaon Sheri  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Wadgaon Sheri 6297143586 Call Hot Ind...
 
The Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfThe Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdf
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
 
(INDIRA) Call Girl Mumbai Call Now 8250077686 Mumbai Escorts 24x7
(INDIRA) Call Girl Mumbai Call Now 8250077686 Mumbai Escorts 24x7(INDIRA) Call Girl Mumbai Call Now 8250077686 Mumbai Escorts 24x7
(INDIRA) Call Girl Mumbai Call Now 8250077686 Mumbai Escorts 24x7
 
Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024
 
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdf
 
Pooja 9892124323 : Call Girl in Juhu Escorts Service Free Home Delivery
Pooja 9892124323 : Call Girl in Juhu Escorts Service Free Home DeliveryPooja 9892124323 : Call Girl in Juhu Escorts Service Free Home Delivery
Pooja 9892124323 : Call Girl in Juhu Escorts Service Free Home Delivery
 

Programmatic risk management workshop (handbook)

  • 1. Programmatic Risk Management Work (Handbook) Programmatic Risk Management: A “not so simple” introduction to the complex but critical process of building a “credible” schedule Program Planning and Controls Workshop, Denver, Colorado October 6th and October 14th 2008 1/69
  • 2. Agenda Duration Topic 20 Minutes Risk Management in Five Easy Pieces 15 Minutes Basic Statistics for programmatic risk management 15 Minutes Monte Carlo Simulation (MCS) theory 20 Minutes Mechanics of MSFT Project and Risk+ 15 Minutes Programmatic Risk Ranking 15 Minutes Building a Credible schedule 20 Minutes Conclusion 120 Minutes 2/69
  • 3. When we say “Risk Management” What do we really mean? 3/69
  • 4. Five Easy Pieces†: The Essentials of Managing Programmatic Risk Managing the risk to cost, schedule, and technical performance is the basis of a successful project management method. † With apologies to Carole Eastman and Bob Rafelson for their 1970 film staring Jack Nicholson 4/69 Risk in Five Easy Pieces
  • 5. Hope is Not a Strategy When General Custer was completely surrounded, his chief scout asked, “General what's our strategy?” Custer replied, “The first thing we need to do is make a note to ourselves – never get in this situation again.” Hope is not a strategy! A Strategy is the plan to successfully complete the project If the project’s success factors, the processes that deliver them, the alternatives when they fail, and the measurement of this success are not defined in meaningful ways for both the customer and managers of the project – Hope is the only strategy left. 5/69 Risk in Five Easy Pieces
  • 6. No Single Point Estimate can be correct without knowing the variance  Single Point Estimates use sample data to calculate a single value (a statistic) that serves as a When estimating "best guess" for an unknown (fixed or random) cost and duration population parameter for planning purposes using  Bayesian Inference is a statistical inference where Point Estimates evidence or observations are used to infer the results in the probability that a hypothesis may be true least likely result. A result with a  Identifying underlying statistical behavior of the cost 50/50 chance of and schedule parameters of the project is the first being true. step in forecasting future behavior  Without this information and the model in which it is used any statements about cost, schedule and completion dates are a 50/50 guesses 6/69 Risk in Five Easy Pieces
  • 7. Without Integrating $, Time, and TPM you’re driving in the rearview mirror Technical Performance (TPM) Addressing customer satisfaction means incorporating product requirements and planned quality into the Performance Measurement Baseline to assure the true performance of the project is made visible. 7/69 Risk in Five Easy Pieces
  • 8. Without a model for risk management, you’re driving in the dark with the headlights turn off The Risk Management process to the right is used by the US DOD and differs from the PMI approach in how the processes areas are arranged. The key is to understand the relationships between these areas. Risk Management means using a proven risk management process, adapting this to the project environment, and using this process for everyday decision making. 8/69 Risk in Five Easy Pieces
  • 9. Risk Communication is … An interactive process of exchange of information and opinion among individuals, groups, and institutions; often involving multiple messages about the nature of risk or expressing concerns, opinions, or reactions to risk messages or to legal or institutional arrangements for risk management. Bad news is not wine. It does not improve with age — Colin Powell 9/69 Risk in Five Easy Pieces
  • 10. Basic Statistics for Programmatic Risk Management Since all point estimates are wrong, statistical estimates will be needed to construct a credible cost and schedule model 10/69 Basic Statistics
  • 11. Uncertainty and Risk are not the same thing – don’t confuse them  Uncertainty stems from  Risk stems from known unknown probability probability distributions distributions – Cost estimating methodology – Requirements change impacts risk resulting from improper – Budget Perturbations models of cost – Re–work, and re–test – Cost factors such as inflation, phenomena labor rates, labor rate burdens, etc – Contractual arrangements (contract type, prime/sub – Configuration risk (variation in relationships, etc) the technical inputs) – Potential for disaster (labor – Schedule and technical risk troubles, shuttle loss, satellite coupling “falls over”, war, hurricanes, – Correlation between risk etc.) distributions – Probability that if a discrete event occurs it will invoke a project delay 11/69 Basic Statistics
  • 12. There are 2 types of Uncertainty encountered in cost and schedule  Static uncertainty is natural variation and foreseen risks – Uncertainty about the value of a parameter  Dynamic uncertainty is unforeseen uncertainty and “chaos” – Stochastic changes in the underlying environment – System time delays, interactions between the network elements, positive and negative feedback loops – Internal dependencies 12/69 Basic Statistics
  • 13. The Multiple Sources of Schedule Uncertainty and Sorting Them Out is the Role of Planning  Unknown interactions drive uncertainty  Dynamic uncertainty can be addressed by flexibility in the schedule – On ramps – Off ramps – Alternative paths – Schedule “crashing” opportunities  Modeling of this dynamic uncertainty requires simulation rather than static PERT based path assessment – Changes in critical path are dependent on time and state of the network – The result is a stochastic network 13/69 Basic Statistics
  • 14. Statistics at a Glance  Probability distribution – A  Bias –The expected deviation of function that describes the the expected value of a statistical probabilities of possible outcomes estimate from the quantity it in a "sample space.” estimates.  Random variable – variable a  Correlation – A measure of the function of the result of a joint impact of two variables upon statistical experiment in which each other that reflects the each outcome has a definite simultaneous variation of probability of occurrence. quantities.  Determinism – a theory that  Percentile – A value on a scale of phenomena are causally 100 indicating the percent of a determined by preceding events distribution that is equal to or or natural laws. below it.  Standard deviation (sigma  Monte Carlo sampling – A value) – An index that modeling technique that employs characterizes the dispersion random sampling to simulate a among the values in a population. population being studied. 14/69 Basic Statistics
  • 15. Statistics Versus Probability  In building a risk tolerant schedule, we’re interested in the probability of a successful outcome – “What is the probability of making a desired completion date?”  But the underlying statistics of the tasks influence this probability  The statistics of the tasks, their arrangement in a network of tasks and correlation define how this probability based estimated developed. 15/69 Basic Statistics
  • 16. Each path and each task along that path has a probability distribution  Any path could be critical depending on the convolution of the underlying task completion time probability distribution functions  The independence or dependency of each task with others in the network, greatly influences the outcome of the total project duration  Understanding this dependence is critical to assessing the credibility of the plan as well as the total completion time of that plan 16/69 Basic Statistics
  • 17. Probability Distribution Functions are the Life Blood of good planning  Probability of occurrence as a function of the number of samples  “The number of times a task duration appears in a Monte Carlo simulation” 17/69 Basic Statistics
  • 18. Statistics of a Triangle Distribution Triangle 50% of all possible values are under distributions are this area of the curve. This is the useful when definition of the median there is limited information about the characteristics of the random variables are all that is available. This is common in project cost Minimum Maximum and schedule 1000 hrs 6830 hrs estimates. Mode = 2000 hrs Mean = 3879 hrs Median = 3415 hrs 18/69 Basic Statistics
  • 19. Basics of Monte Carlo Simulation Far better an approximate answer to the right question, which is often vague, than an exact answer to the wrong question, which can always be made precise. — John W. Tukey, 1962 19/69 Basics of Monte Carlo
  • 20. Monte Carlo Simulation  Yes Monte Carlo is named after the country full of casinos located on the French Rivera  Advantages of Monte Carlo over PERT is that Monte Carlo… – Examines all paths, not just the critical path – Provides an accurate (true) estimate of completion • Overall duration distribution • Confidence interval (accuracy range) – Sensitivity analysis of interacting tasks – Varied activity distribution types – not restricted to Beta – Schedule logic can include branching – both probabilistic and conditional – When resource loaded schedules are used – provides integrated cost and schedule probabilistic model 20/69 Basics of Monte Carlo
  • 21. First let’s be convinced that PERT has limited usefulness  The original paper (Malcolm 1959) states – The method is “the best that could be done in a real situation within tight time constraints.” – The time constraint was One Month  The PERT time made the assumption that the standard deviation was about 1/6 of the range (b–a), resulting in the PERT formula.  It has been shown that the PERT mean and standard deviation formulas are poor approximations for most Beta distributions (Keefer 1983 and Keefer 1993). – Errors up to 40% are possible for the PERT mean – Errors up to 550% are possible for the PERT standard deviation 21/69 Basics of Monte Carlo
  • 22. Critical Path and Mostly Likelies  Critical Path’s are Deterministic – At least one path exists through the network – The critical path is identified by adding the “single point” estimates – The critical predicts the completion date only if everything goes according to plan (we all know this of course)  Schedule execution is Probabilistic – There is a likelihood that some durations will comprise a path that is off the critical path – The single number for the estimate – the “single point estimate” is in fact a most likely estimate – The completion date is not the most likely date, but is a confidence interval in the probability distribution function resulting from the convolution of all the distributions along all the paths to the completion of the project 22/69 Basics of Monte Carlo
  • 23. Deterministic PERT Uses Three Point Estimates In A Static Manner  Durations are defined as three point estimates – These estimates are very subjective if captured individually by asking… – “What is the Minimum, Maximum, and Most Likely”  Critical path is defined from these estimates is the algebraic addition of three point estimates  Project duration is based on the algebraic addition of the times along the critical path  This approach has some serious problems from the outset – Durations must be independent – Most likely is not the same as the average 23/69 Basics of Monte Carlo
  • 24. Foundation of Monte Carlo Theory George Louis Leclerc, Comte de Buffon, asked what was the probability that the needle would fall across one of the lines, marked in green. That outcome occurs only if: A  l sin 24/69 Basics of Monte Carlo
  • 25. Mechanics of Risk+ integrated with Microsoft Project Any credible schedule is a credible model of its dynamic behavior. This starts with a Monte Carlo model of the schedule’s network of tasks 25/69 Mechanics of Risk+
  • 26. The Simplest Risk+ elements Task to “watch” Most Likely Distribution (Number3) (Duration3) (Number1) Optimistic Pessimistic (Duration1) (Duration2) 26/69 Mechanics of Risk+
  • 27. The output of Risk+ Date: 9/26/2005 2:14:02 PM Completion Std Deviation: 4.83 days Samples: 500 95% Confidence Interval: 0.42 days Task to “watch” Unique ID: 10 Each bar represents 2 days Name: Task 10 0.16 1.0 Completion Probability Table Cumulative Probability 0.9 0.14 Prob Date Prob Date 0.8 0.12 0.05 2/17/06 0.55 3/1/06 0.7 Frequency 0.10 2/21/06 0.60 3/2/06 0.10 0.6 0.15 2/22/06 0.65 3/3/06 0.08 0.5 0.20 2/22/06 0.70 3/3/06 0.4 0.25 2/23/06 0.75 3/6/06 0.06 0.3 0.30 2/24/06 0.80 3/7/06 80% confidence 0.04 0.35 2/27/06 0.85 3/8/06 0.2 0.40 2/27/06 0.90 3/9/06 that task will 0.02 0.1 0.45 2/28/06 0.95 3/13/06 complete by 2/10/06 3/1/06 3/17/06 0.50 3/1/06 1.00 3/17/06 Completion Date 3/7/06  The height of each box indicates  The standard deviation of the how often the project complete in a completion date and the 95% given interval during the run confidence interval of the expected  The S–Curve shows the cumulative completion date are in the same probability of completing on or units as the “most likely remaining before a given date. duration” field in the schedule 27/69 Mechanics of Risk+
  • 28. A Well Formed Risk+ Schedule For Risk+ to provide useful information, the underlying schedule must be well formed on some simple way. 28/69 Mechanics of Risk+
  • 29. A Well formed Risk+ Schedule  A good critical path network – No constraint dates – Lowest level tasks have predecessors and successors – 80% of relationships are finish to start  Identify risk tasks – These are “reporting tasks” – Identify the preview task to watch during simulation runs  Defining the probability distribution profile for each task – Bulk assignment is an easy way to start – A – F ranking is another approach – Individual risk profile assignments is best but tedious 29/69 Mechanics of Risk+
  • 30. Analyzing the Risk+ Simulation  Risk+ generates one or more of the following outputs: – Earliest, expected, and latest completion date for each reporting task – Graphical and tabular displays of the completion date distribution for each reporting task – The standard deviation and confidence interval for the completion date distribution for each reporting task – The criticality index (percentage of time on the critical path) for each task – The duration mean and standard deviation for each task – Minimum, expected, and maximum cost for the total project – Graphical and tabular displays of cost distribution for the total project – The standard deviation and confidence interval for cost at the total project level 30/69 Mechanics of Risk+
  • 31. Programmatic Risk Ranking The variance in task duration must be defined in some systematic way. Capturing three point values is the least desirable. 31/69 Programmatic Risk Ranking
  • 32. Thinking about risk ranking  These classifications can be used to avoid asking the “3 point” question for each task  This information will be maintained in the IMS  When updates are made the percentage change can be applied across all tasks Classification Uncertainty Overrun A Routine, been done before Low 0% to 2% B Routine, but possible difficulties Medium to Low 2% to 5% C Development, with little technical difficulty Medium 5% to 10% D Development, but some technical difficulty Medium High 10% to 15% E Significant effort, technical challenge High 15% to 25% F No experience in this area Very High 25% to 50% 32/69 Programmatic Risk Ranking
  • 33. Steps in characterizing uncertainty  Use an “envelope” method to characterize the minimum, maximum and “most likely”  Fit this data to a statistical distribution  Use conservative assumptions  Apply greater uncertainty to less mature technologies  Confirm analysis matches intuition Remember Sir Francis Bacon’s quote about beginning with uncertainty and ending with certainty. If we start with a what we think is a valid number we will tend to continue with that valid number. When in fact we should speak only in terms of confidence intervals and probabilities of success. 33/69 Programmatic Risk Ranking
  • 34. Sobering observations about 3 point estimates when asking engineers  In 1979, Tversky and Kahneman proposed an alternative to Utility theory. Prospect theory asserts that people make predictably irrational decisions.  The way that a choice of decisions is presented can sway a person to choose the less rational decision from a set of options.  Once a problem is clearly and reasonably presented, rarely does a person think outside the bounds of the frame.  Source: – “The Causes of Risk Taking By Project Managers,” Proceedings of the Project Management Institute Annual Seminars & Symposium November 1–10, 2001 • Nashville, Tenn – Tversky, Amos, and Daniel Kahneman. 1981. The Framing of Decisions and the Psychology of Choice. Science 211 (January 30): 453–458 34/69 Programmatic Risk Ranking
  • 35. Building a Credible Schedule A credible schedule contains a well formed network, explicit risk mitigations, proper margin for these risks, and a clear and concise critical path(s). All of this is prologue to analyzing the schedule. 35/69 Building a Credible Schedule
  • 36. Good schedules have a contingency plans  The schedule contingency needed to make the plan credible can be derived from the Risk+ analysis  The schedule contingency is the Is This Our amount of time added (or Contingency subtracted) from the baseline Plan ? schedule necessary to achieve the desired probability of an under run or over run.  The schedule contingency can be determined through – Monte Carlo simulations (Risk+) – Best judgment from previous experience – Percentage factors based on historical experience – Correlation analysis for dependency impacts 36/69 Building a Credible Schedule
  • 37. Schedule quality and accuracy  Accuracy range – Similar for each estimate class  Consistent with estimate – Level of project definition – Purpose – Preparation effort  Monte Carlo simulation – Analysis of results shows quality attained versus the quality sought (expected accuracy ranges)  Achieving specified accuracy requirements – Select value at end points of confidence interval – Calculate percentages from base schedule completion date, including the contingency 37/69 Building a Credible Schedule
  • 38. Technical Performance Measures  Technical Performance Measures are one method of showing risk by done – Specific actions taken in the IMS to move the compliance forward toward the goal  Activities that assessing the increasing compliance to the technical performance measure can be show in the IMS – These can be Accomplishment Criteria 38/69 Building a Credible Schedule
  • 39. The Monte Carlo Process starts with the 3 point estimates  Estimates of the task duration are still needed, just like they are in PERT These three – Three point estimates could be used point estimates are not the PERT – But risk ranking and algorithmic generation of the ones. “spreads” is a better approach They are derived  Duration estimates must be parametric rather from the ordinal risk ranking than numeric values process. – A geometric scale of parametric risk is one approach This allows them to be “calibrated”  Branching probabilities need to be defined for the domain, – Conditional paths through the schedule can be correlated with the technical risk evaluated using Monte Carlo tools model. – This also demonstrate explicit risk mitigation planning to answer the question “what if this happens?” 39/69 Building a Credible Schedule
  • 40. Expert Judgment is required to build a Risk Management approach  Expert judgment is typically the basis of cost and schedule estimates – Expert judgment is usually the weakest area of process Building the and quantification variance values for the ordinal – Translating from English (SOW) to mathematics risk rank is a (probabilistic risk model) is usually inconsistent at best and technical erroneous at worst process, requiring  One approach engineering – Plan for the “best case” and preclude a self–fulfilling judgment. prophesy – Budget for the “most likely” and recognize risks and uncertainties – Protect for the “worst case” and acknowledge the conceivable in the risk mitigation plan  The credibility of the “best case” estimates if crucial to the success of this approach 40/69 Building a Credible Schedule
  • 41. Guiding the Risk Factor Process requires careful weighting of each level of risk  For tasks marked “Low” a reasonable approach is to score the maximum 10% Min Most Max greater than the minimum. Likely  The “Most Likely” is then scored as a geometric progression for the remaining Low 1.0 1.04 1.10 categories with a common ratio of 1.5 Low+ 1.0 1.06 1.15  Tasks marked “Very High” are bound at Moderate 1.0 1.09 1.24 200% of minimum. Moderate+ 1.0 1.14 1.36 – No viable project manager would like a task grow to three times the planned duration High 1.0 1.20 1.55 without intervention High+ 1.0 1.30 1.85  The geometric progress is somewhat Very High 1.0 1.46 2.30 arbitrary but it should be used instead of Very High+ 1.0 1.68 3.00 a linear progression 41/69 Building a Credible Schedule
  • 42. Assume now we have a well formed schedule – now what?  With all the “bone head” elements For the role of removed, we can say we have a PP&C is to move “reporting well formed schedule past performance” to  But the real role of Planning is to “forecasting forecast the future, provide future performance” it alternative Plan’s for this forecast must break the mold of using and actively engage all the static models of cost and participants in the projects in the schedule Planning Process 42/69 Building a Credible Schedule
  • 43. We’re really after the management of schedule margin as part of planning  Plan the risk alternatives that  Assign duration and resource “might” be needed estimates to both branches – Each mitigation has a Plan B  Turn off for alternative for a branch “success” path assessment – Keep alternatives as simple as  Turn off primary for a “failure” path possible (maybe one task) assessment  Assess probability of the alternative occurring Plan B 30% Probability of failure 80% Confidence for completion with current margin 70% Probability of success Plan A Current Margin Future Margin Duration of Plan B  Plan A + Margin 43/69 Building a Credible Schedule
  • 44. Successful margin management requires the reuse of unused durations  Programmatic Margin is added between  Margin that is not used in the IMS for risk Development, Production and Integration mitigation will be moved to the next & Test phases sequence of risk alternatives  Risk Margin is added to the IMS where – This enables us to buy back schedule margin risk alternatives are identified for activities further downstream – This enables us to control the ripple effect of schedule shifts on Margin activities Downstream Duration of Plan B < Plan A + Margin Activities shifted to Plan B left 2 days Plan B 3 Days Margin Used Plan A 5 Days Margin First Identified Risk Alternative in IMS Plan A 5 Days Margin Second Identified Risk 2 days will be added to this margin task Alternative in IMS to bring schedule back on track 44/69 Building a Credible Schedule
  • 45. Simulation Considerations  Schedule logic and constraints – Simplify logic – model only paths which, by inspection, may have a significant bearing on the final result – Correlate similar activities – No open ends – Use only finish–to–start relationships with no lags – Model relationships other than finish–to–start as activities with base durations equal to the lag value – Eliminate all date constraints – Consider using branching for known alternatives 45/69 Building a Credible Schedule
  • 46. The contents of the schedule  Constraints  Lead/Lag  Task relationships  Durations  Network topology 46/69 Building a Credible Schedule
  • 47. Simulation Considerations  Selection of Probability Distributions – Develop schedule simulation inputs concurrently with the cost estimate • Early in process – use same subject matter experts • Convert confidence intervals into probability duration distributions – Number of distributions vary depending on software – Difficult to develop inputs required for distributions – Beta and Lognormal better than triangular; avoid exclusive use of Normal distribution 47/69 Building a Credible Schedule
  • 48. Sensitivity Analysis describes which tasks drive the completion times  Concentrates on inputs most likely to improve quality (accuracy)  Identifies most promising opportunities where additional work will help to narrow input ranges  Methods – Run multiple simulations – Use criticality index – “Tornado” or Pareto graph 48/69 Building a Credible Schedule
  • 49. What we get in the end is a Credible Model of the schedule All models are wrong. Some models are useful. – George Box (1919 – ) Concept generator from Ramon Lull’s Ars Magna (C. 1300) 49/69 Building a Credible Schedule
  • 50. Conclusion At this point there is too much information. Processing this information will take time, patience, and most of all practice with the tools and the results they produce. 50/69 Conclusion
  • 51. Conclusions  Project schedule status must be assessed in terms of a critical path through the schedule network  Because the actual durations of each task in the network are uncertain (they are random variables following a probability distribution function), the project schedule duration must be modeled statistically 51/69 Conclusion
  • 52. Conclusions  Quality (accuracy) is measured at the end points of achieved confidence interval (suggest 80% level)  Simulation results depend on: – Accuracy and care taken with base schedule logic – Use of subject matter experts to establish inputs – Selection of appropriate distribution types – Through analysis of multiple critical paths – Understanding which activities and paths have the greatest potential impact 52/69 Conclusion
  • 53. Conclusions  Cost and schedule estimates are made up of many independent elements. – When each element is planned as best case – e.g. a probability of achievement of 10% – The probability of achieving best case for a two– element estimate is 1% – For three elements, 0.01% – For many elements, infinitesimal – In effect, it is zero.  In the beginning no attempt should be made to distinguish between risk and uncertainty – Risk involves uncertainty but it is indeed more – For initial purposes it is unimportant – The effect is combined into one statistical factor called “risk,” which can be described by a single probability distribution function 53/69 Conclusion
  • 54. What are we really after in the end?  As the program proceeds so does: – Increasing accuracy – Reduced schedule risk – Increasing visual confirmation Current Estimate Accuracy that success can be reached 54/69 Conclusion
  • 55. Points to remember  Good project management is good risk management  Risk management is how adults manage projects  The only thing we manage is project risk  Risks impact objectives  Risks come from the decisions we make while trying to achieve the objectives  Risks require a factual condition and have potential negative consequences that must be mitigated in the schedule 55/69 Conclusion
  • 56. Usage is needed before understanding is acquired Here and elsewhere, we shall not obtain the best insights into things until we actually see them growing from the beginning. — Aristotle 56/69 Conclusion
  • 57. The End A planning algorithm from Aristotle’s De Motu Animalium c. 400 BC This is actually the beginning, since building a risk tolerant, credible, robust schedule requires constant “execution” of the plan. 57/69 Conclusion
  • 58. Resources 1. “The Parameters of the Classical PERT: An Assessment of its Success,” Rafael Herrerias Pleguezuelo, http://www.cyta.com.ar/biblioteca/bddoc/bdlibros/pert_van/PARAMET ROS.PDF 2. “Advanced Quantitative Schedule Risk Analysis,” David T. Hulett, Hulett & Associates, http://www.projectrisk.com/index.html 3. “Schedule Risk Analysis Simplified,” David T. Hulett, Hulett & Associates, http://www.projectrisk.com/index.html 4. “Project Risk Management: A Combined Analytical Hierarchy Process and Decision Tree Approach,” Prasanta Kumar Dey, Cost Engineering, Vol. 44, No. 3, March 2002. 5. “Adding Probability to Your ‘Swiss Army Knife’,” John C. Goodpasture, Proceedings of the 30th Annual Project Management Institute 1999 Seminars and Symposium, October, 1999. 6. “Modeling Uncertainty in Project Scheduling,” Patrick Leach, Proceedings of the 2005 Crystal Ball User Conference 7. “Near Critical Paths Create Violations in the PERT Assumptions of Normality,” Frank Pokladnik and Robert Hill, University of Houston, Clear Lake, http://www.sbaer.uca.edu/research/dsi/2003/procs/237– 4203.pdf 58/69 Resources
  • 59. Resources 8. “Teaching SuPERT,” Kenneth R. MacLeod and Paul F. Petersen, Proceedings of the Decision Sciences 2003 Annual Meeting, Washington DC, http://www.sbaer.uca.edu/research/dsi/2003/by_track_paper.html 9. “The Beginning of the Monte Carlo Method,” N. Metropolis, Los Alamos Science, Special Issue, 1987. http://www.fas.org/sgp/othergov/doe/lanl/pubs/00326866.pdf 10. “Defining a Beta Distribution Function for Construction Simulation,” Javier Fente, Kraig Knutson, Cliff Schexnayder, Proceedings of the 1999 Winter Simulation Conference. 11. “The Basics of Monte Carlo Simulation: A Tutorial,” S. Kandaswamy, Proceedings of the Project Management Institute Annual Seminars & Symposium, November, 2001. 12. “The Mother of All Guesses: A User Friendly Guide to Statistical Estimation,” Francois Melese and David Rose, Armed Forces Comptroller, 1998, http://www.nps.navy.mil/drmi/graphics/StatGuide– web.pdf 13. “Inverse Statistical Estimation via Order Statistics: A Resolution of the Ill–Posed Inverse problem of PERT Scheduling,” William F. Pickard, Inverse Problems 20, pp. 1565–1581, 2004 59/69 Resources
  • 60. Resources 14. “Schedule Risk Analysis: Why It Is Important and How to Do It, “Stephen A. Book, Proceedings of the Ground Systems Architecture Workshop (GSAW 2002), Aerospace Corporation, March 2002, http://sunset.usc.edu/GSAW/gsaw2002/s11a/book.pdf 15. “Evaluation of the Risk Analysis and Cost Management (RACM) Model,” Matthew S. Goldberg, Institute for Defense Analysis, 1998. http://www.thedacs.com/topics/earnedvalue/racm.pdf 16. “PERT Completion Times Revisited,” Fred E. Williams, School of Management, University of Michigan–Flint, July 2005, http://som.umflint.edu/yener/PERT%20Completion%20Revisited.htm 17. “Overcoming Project Risk: Lessons from the PERIL Database,” Tom Hendrick , Program Manager, Hewlett Packard, 2003, http://www.failureproofprojects.com/Risky.pdf 18. “The Heart of Risk Management: Teaching Project Teams to Combat Risk,” Bruce Chadbourne, 30th Annual Project Management Institute 1999 Seminara and Symposium, October 1999, http://www.risksig.com/Articles/pmi1999/rkalt01.pdf 60/69 Resources
  • 61. Resources 20. Project Risk Management Resource List, NASA Headquarters Library, http://www.hq.nasa.gov/office/hqlibrary/ppm/ppm22.htm#art 21. “Quantify Risk to Manage Cost and Schedule,” Fred Raymond, Acquisition Quarterly, Spring 1999, http://www.dau.mil/pubs/arq/99arq/raymond.pdf 22. “Continuous Risk Management,” Cost Analysis Symposium, April 2005, http://www1.jsc.nasa.gov/bu2/conferences/NCAS2005/papers/5C_– _Cockrell_CRM_v1_0.ppt 23. “A Novel Extension of the Triangular Distribution and its Parameter Estimation,” J. Rene van Dorp and Samuel Kotz, The Statistician 51(1), pp. 63 – 79, 2002. http://www.seas.gwu.edu/~dorpjr/Publications/JournalPapers/TheStati stician2002.pdf 24. “Distribution of Modeling Dependence Cause by Common Risk Factors,” J. Rene van Dorp, European Safety and Reliability 2003 Conference Proceedings, March 2003, http://www.seas.gwu.edu/~dorpjr/Publications/ConferenceProceeding s/Esrel2003.pdf 61/69 Resources
  • 62. Resources 25. “Improved Three Point Approximation To Distribution Functions For Application In Financial Decision Analysis,” Michele E. Pfund, Jennifer E. McNeill, John W. Fowler and Gerald T. Mackulak, Department of Industrial Engineering, Arizona State University, Tempe, Arizona, http://www.eas.asu.edu/ie/workingpaper/pdf/cdf_estimation_submissio n.pdf 26. “Analysis Of Resource–constrained Stochastic Project Networks Using Discrete–event Simulation,” Sucharith Vanguri, Masters Thesis, Mississippi State University, May 2005, http://sun.library.msstate.edu/ETD–db/theses/available/etd– 04072005–123743/restricted/SucharithVanguriThesis.pdf 27. “Integrated Cost / Schedule Risk Analysis,” David T. Hulett and Bill Campbell, Fifth European Project Management Conference, June 2002. 28. “Risk Interrelation Management – Controlling the Snowball Effect,” Olli Kuismanen, Tuomo Saari and Jussi Vähäkylä, Fifth European Project Management Conference, June 2002. 29. The Lady Tasting Tea: How Statistics Revolutionized Science in the Twentieth Century, David Salsburg, W. H. Freeman, 2001 62/69 Resources
  • 63. Resources 30. “Triangular Approximations for Continuous Random Variables in Risk Analysis,” David G. Johnson, The Business School, Loughborough University, Liecestershire. 31. “Statistical Dependence through Common Risk Factors: With Applications in Uncertainty Analysis,” J. Rene van Dorp, European Journal of Operations Research, Volume 161(1), pp. 240–255. 32. “Statistical Dependence in the risk analysis for Project Networks Using Monte Carlo Methods,” J. Rene van Dorp and M. R. Dufy, International Journal of Production Economics, 58, pp. 17–29, 1999. http://www.seas.gwu.edu/~dorpjr/Publications/JournalPapers/Prodeco n1999.pdf 33. “Risk Analysis for Large Engineering Projects: Modeling Cost Uncertainty for Ship Production Activities,” M. R. Dufy and J. Rene van Dorp, Journal of Engineering Valuation and Cost Analysis, Volume 2. pp. 285–301, http://www.seas.gwu.edu/~dorpjr/Publications/JournalPapers/EVCA19 99.pdf 34. “Risk Based Decision Support techniques for Programs and Projects,” Barney Roberts and David Frost, Futron Risk Management Center of Excellence, http://www.futron.com/pdf/RBDSsupporttech.pdf 63/69 Resources
  • 64. Resources 35. Probabilistic Risk Assessment Procedures Guide for NASA Managers and Practitioners, Office of Safety and Mission Assurance, April 2002. http://www.hq.nasa.gov/office/codeq/doctree/praguide.pdf 36. “Project Planning: Improved Approach Incorporating Uncertainty,” Vahid Khodakarami, Norman Fenton, and Martin Neil, Track 15 EURAM2005: “Reconciling Uncertainty and Responsibility” European Academy of Management. http://www.dcs.qmw.ac.uk/~norman/papers/project_planning_khodake rami.pdf 37. “A Distribution for Modeling Dependence Caused by Common Risk Factors,” J. Rene van Dorp, European Safety and Reliability 2003 Conference Proceedings, March 2003. 38. “Probabilistic PERT,” Arthur Nadas, IBM Journal of Research and Development, 23(3), May 1979, pp. 339–347. 39. “Ranked Nodes: A Simple and effective way to model qualitative in large–scale Bayesian Networks,” Norman Fenton and Martin Neil, Risk Assessment and Decision Analysis Research Group, Department of Computer Science, Queen Mary, University of London, February 21, 2005. 64/69 Resources
  • 65. Resources 40. “Quantify Risk to Manage Cost and Schedule,” Fred Raymond, Acquisition Review Quarterly, Spring 1999, pp. 147–154 41. “The Causes of Risk Taking by Project Managers,” Michael Wakshull, Proceedings of the Project Management Institute Annual Seminars & Symposium, November 2001. 42. “Stochastic Project Duration Analysis Using PERT–Beta Distributions,” Ron Davis. 43. “Triangular Approximation for Continuous Random Variables in Risk Analysis,” David G. Johnson, Decision Sciences Institute Proceedings 1998. http://www.sbaer.uca.edu/research/dsi/1998/Pdffiles/Papers/1114.pdf 44. “The Cause of Risk Taking by Managers,” Michael N.Wakshull, Proceedings of the Project Management Institute Annual Seminars & Symposium November 1–10, 2001, Nashville Tennessee , http://www.risksig.com/Articles/pmi2001/21261.pdf 45. “The Framing of Decisions and the Psychology of Choice,” Tversky, Amos, and Daniel Kahneman. 1981, Science 211 (January 30): 453– 458, http://www.cs.umu.se/kurser/TDBC12/HT99/Tversky.html 65/69 Resources
  • 66. Resources 46. “Three Point Approximations for Continuous Random Variables,” Donald Keefer and Samuel Bodily, Management Science, 29(5), pp. 595 – 609. 47. “Better Estimation of PERT Activity Time Parameters,” Donald Keefer and William Verdini, Management Science, 39(9), pp. 1086 – 1091. 48. “The Benefits of Integrated, Quantitative Risk Management,” Barney B. Roberts, Futron Corporation, 12th Annual International Symposium of the International Council on Systems Engineering, July 1–5, 2001, http://www.futron.com/pdf/benefits_QuantIRM.pdf 49. “Sources of Schedule Risk in Complex Systems Development,” Tyson R. Browning, INCOSE Systems Engineering Journal, Volume 2, Issue 3, pp. 129 – 142, 14 September 1999, http://sbufaculty.tcu.edu/tbrowning/Publications/Browning%20(1999)– –SE%20Sch%20Risk%20Drivers.pdf 50. “Sources of Performance Risk in Complex System Development,” Tyson R. Browning, 9th Annual International Symposium of INCOSE, June 1999, http://sbufaculty.tcu.edu/tbrowning/Publications/Browning%20(1999)– –INCOSE%20Perf%20Risk%20Drivers.pdf 66/69 Resources
  • 67. Resources 51. “Experiences in Improving Risk Management Processes Using the Concepts of the Riskit Method,” Jyrki Konito, Gerhard Getto, and Dieter Landes, ACM SIGSOFT Software Engineering Notes , Proceedings of the 6th ACM SIGSOFT international symposium on Foundations of software engineering SIGSOFT '98/FSE-6, Volume 23 Issue 6, November 1998. 52. “Anchoring and Adjustment in Software Estimation,” Jorge Aranda and Steve Easterbrook, Proceedings of the 10th European software engineering conference held jointly with 13th ACM SIGSOFT international symposium on Foundations of software engineering ESEC/FSE-13 53. “The Monte Carlo Method,” W. F. Bauer, Journal of the Society of Industrial Mathematics, Volume 6, Number 4, December 1958, http://www.cs.fsu.edu/~mascagni/Bauer_1959_Journal_SIAM.pdf. 54. “A Retrospective and Prospective Survey of the Monte Carlo Method,” John H. Molton, SIAM Journal, Volume 12, Number 1, January 1970, http://www.cs.fsu.edu/~mascagni/Halton_SIAM_Review_1970.pdf. 67/69 Resources
  • 69. Lewis & Fowler 8310 South Valley Highway Suite 300 Englewood, Colorado 80112 www.lewisandfowler.com 303.524.1610 Deliverables Based Planningsm Integrated Master Plan Integrated Master Schedule Earned Value Risk Management Proposal Support Service Glen B. Alleman, VP, Program Planning and Controls galleman@lewisandfowler.com 303.437 5226 69/69