SlideShare a Scribd company logo
1 of 12
ADOPTING THE 
QUADRATIC MEAN 
PROCESS TO QUANTIFY 
THE QUALITATIVE RISK 
ANALYSIS 
Accepted for publication at 
PMI Global Congress 2013 – North America 
New Orleans – Louisiana – USA – 2013
2 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis 
Abstract 
The objective of this paper is to propose a mathematical process to turn the re-sults 
of a qualitative risk analysis into numeric indicators to support better deci-sions 
regarding risk response strategies. 
Using a five-level scale for probability and a set of scales to measure different 
aspects of the impact and time horizon, a simple mathematical process is devel-oped 
using the quadratic mean (also known as root mean square) to calculate 
the numerical exposition of the risk and consequently, the numerical exposition 
of the project risks. 
This paper also supports the reduction of intuitive thinking when evaluating 
risks, often subject to illusions, which can cause perception errors. These predict-able 
mental errors, such as overconfidence, confirmation traps, optimism bias, 
zero-risk bias, sunk-cost effect, and others often lead to the underestimation of 
costs and effort, poor resource planning, and other low-quality decisions (VIRINE, 
2010). 
Related Podcasts 
♫♫Using the Quadratic Average 
(Mean) in the Qualitative Risk 
Analysis 
http://rvarg.as/bd 
♫♫Understanding the Risk 
Attitude 
http://rvarg.as/6j 
♫♫RBS – Risk Breakdown Struc-ture 
http://rvarg.as/be 
♫♫Risk Management Special 
Playlist 
http://rvarg.as/bc
ricardo-vargas.com 3 
Qualitative X Quantitative Risk Analysis 
One of the main challenges during the analysis of a risk is to define the right ap-proach 
to assess the amount of the exposure/opportunity. The two basic steps 
to determine the right level of risk are based on the qualitative and quantitative 
analysis (Exhibit 1). 
Assessment 
of Risk Level 
Updated 
Risk Register 
Output 
Risk 
Prioritisation 
Qualitative 
Quantitative 
Risk 
Analysis 
Exhibit 1 – Analysis of Risk Process Flow (ROSSI, 2007). 
A qualitative risk analysis prioritizes the identified project risks using a predefined 
scale. Risks will be scored based on their probability or likelihood of occurrence 
and the impact on project objectives if they occur (Exhibit 2 and 3). 
LEVEL SCORE FOR THREATS 
High 
Very High 5 
Red 
High 4 
Medium 
Medium 3 
Yellow 
Low 2 
Low Very Low 1 Green 
Exhibit 2 – Example of scales used in the qualitative risk analysis 
Qualitative Risk Matrix 
Risk Levels are Relative to Regions Connected by Arrows 
Consequence 
Low Medium High 
Low Medium High 
Frequency 
3 4 5 
2 3’ 4’ 
1 2’ 3” 
Highest 
Risk 
Lowest 
Risk 
Exhibit 3 – Example of Qualitative Risk Matrix with 3 x 3 Levels (ALTENBACH, 1995)
4 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis 
A quantitative risk analysis is based on simulation models and probabilistic analy-sis, 
where the possible outcomes for the project are evaluated, providing a quan-titative, 
numeric and many times financial risk exposure to support decisions 
when there is uncertainty (PMI, 2013). Some quantitative processes are simple 
and direct like rolling a dice (Exhibit 4), but most of them involve very complex 
simulation scenarios like the Monte Carlo Simulation. 
Exhibit 4 – Diagram showing the deterministic probability of rolling a dice 
“Monte Carlo” was a nickname of a top-secret project related to the drawing and 
to the project of atomic weapons developed by the mathematician John von 
Neumann (POUNDSTONE, 1993 and VARGAS, 2013). He discovered that a sim-ple 
model of random samples could solve certain mathematical problems, which 
couldn’t be solved up to that moment. 
The simulation refers, however, to a method by which the distribution of possible 
results is produced from successive recalculations of project data, allowing the 
development of multiple scenarios. In each one of the calculations, new random 
data is used to represent a repetitive and interactive process. The combination of 
all these results creates a probabilistic distribution of the results (Exhibit 5 and 6). 
A B E 
C 
D 
Start Finish 
Forecast of Final Cost 
% 
Exhibit 5 – Construction of model of distribution of costs and activities or work packages 
making up a final distribution from random data of the project (PRITCHARD, 2001).
ricardo-vargas.com 5 
Exhibit 6 – Example of Monte Carlo simulation to assess the cost impact of a potential 
threat to the project 
Because quantitative analysis is based on mathematics and statistics supported 
by objective metrics, such analyses are considered to be more rigorous (SMOCK, 
2002). The main challenges of a solid quantitative analysis are the time and effort 
it requires to be executed and the required technical background in statistics to 
make the proper parameterization of the data. The main advantages and disad-vantages 
of each method are presented in the Exhibit 7. 
QUANTITATIVE METHODS QUALITATIVE METHODS 
Advantages 
Facilitates the cost benefit analysis 
Gives a more accurate value of the risk 
More valuable 
Relatively simple to be implemented 
Easily determine risk categories with greater 
impact in the project 
Visually impactful 
Disadvantages 
Results of the method may not be precise 
Numbers can give a false perception of 
precision 
More expensive and time consuming 
A lack of understanding of the parameters 
used in the scale can lead to different 
interpretations 
Results can be biased 
Less valuable 
Exhibit 7 – Example of Monte Carlo simulation to assess the cost impact of a potential threat to the project (based on ROT, 
2008) 
The risk model proposed hereafter is a qualitative process with numerical results, 
reducing the ambiguity of the qualitative process without adds the time and 
effort to determine with precision the probability and the impact of uncertain 
events in the project. 
Assessing Probability 
The proposed qualitative probability assessment is based on a scale with their 
respective scores (Exhibit 8).
6 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis 
LEVEL SCORE DESCRIPTION 
Very High 5 It is expected that the event will occur. If it 
does not occurs it will be a surprise. 
High 4 The event has a great chance of occurring. 
Medium 3 The event can occur. 
Low 2 It will be a surprise if the event occurs. 
Very Low 1 Very remote chance of the event to happen. 
Practically impossible. 
Exhibit 8 – 5 Scales to assess the risk probability 
For each identified risk a score from 1 (one) to 5 (five) should be determined. 
5 Dimensions of the Impact 
The impact of the event, in case it occurs, can be perceived in different dimen-sions 
of the project objectives. For example, one risk can have a major impact on 
costs but not necessarily an important impact in quality. It is very important to 
highlight that threats and opportunities should be analyzed separately. 
The basic groups where impact should be evaluated are (Exhibit 9): 
• impact on time and deadlines 
• impact on costs 
• impact on quality 
• impact in safety and security 
• other impacts 
TIME 
OTHER COST 
QUALITY 
SAFETY 
& SECURITY 
Exhibit 9 – Basic impact groups showing the different impact dimensions of one specific 
risk 
Each project may develop different impact groups based on the nature of the 
project, including groups like: impact on reputation, regulatory impact, environ-mental 
impact, social impact, and stakeholder’s impact, among several others. 
Following is the presentation of the 5 basic groups.
ricardo-vargas.com 7 
Impact on Time and Deadlines 
One should assess the level of impact on the conclusion of the project. It can be 
positive or negative for opportunities and threats, respectively. Threats that im-pact 
the conclusion of the project must be considered as a priority if compared 
to other events. 
Because each project differs in size, complexity and several other factors, the 
project team needs to agree on the level of tolerance that they consider appro-priate 
for each level of impact, like the example shown in Exhibit 10. 
LEVEL SCORE DESCRIPTION 
Very High 5 Delays/Anticipation above 180 days or 6 
months. 
High 4 Delays/Anticipation between 120 and 180 
calendar days. 
Medium 3 Delays/Anticipation between 60 and 120 
calendar days. 
Low 2 Delays/Anticipation between 15 and 60 
calendar days. 
Very Low 1 Less than 15 calendar days of delays/ 
anticipation. 
Exhibit 10 – Example of impact scale and score for time and deadlines 
Impact on Costs 
One should also assess the level of impact that the event may bring to the total 
project cost. It can be positive (savings) or negative (additional expenditures) for 
opportunities and threats, respectively. 
Like mentioned for time and deadlines, the project team needs to agree on the 
level of tolerance that they consider appropriate for each level of impact, like in 
the example for costs presented in the Exhibit 11. 
LEVEL SCORE DESCRIPTION 
Very High 5 Variation (positive or negative) above 
$1,000,000. 
High 4 Variation (positive or negative) between 
$500,000 and $1,000,000. 
Medium 3 Variation (positive or negative) between 
$250,000 and $500,000. 
Low 2 Variation (positive or negative) between 
$100,000 and $250,000. 
Very Low 1 Variation (positive or negative) lower than 
$100,000. 
Exhibit 11 – Example of impact scale and score for costs
8 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis 
Impact on Quality 
Assesses the level of impact on the quality required for the project. It can be pos-itive 
or negative for opportunities and threats, respectively. 
As presented in the other groups, the project team needs to agree on the level 
of tolerance that they consider appropriate for each level of impact like in the 
example in Exhibit 12 for negative risk events. 
LEVEL SCORE DESCRIPTION 
Very High 5 Client rejects the delivery or product. 
High 4 Client asks for immediate corrective actions. 
Medium 3 Client perceives and asks for action/ 
information. 
Low 2 Client perceives but forgives and no action 
is needed. 
Very Low 1 Imperceptible impact (most of the time not 
even perceived by the stakeholders). 
Exhibit 12 – Example of impact scale and score for quality (only negative events) 
Impact in Safety and Security 
Assesses the level of impact that the event can incur in safety at work and se-curity. 
This impact group could include or not aspects related to environment, 
physical security of the work in the project, data security (IT), and reputation, 
among others. 
In the Exhibit 13, an example of scale is presented to assess impacts in safety and 
security. 
LEVEL SCORE DESCRIPTION 
Very High 5 Crisis. Impact is so evident and public that 
the project could not proceed as planned. 
High 4 Evident impact on environment/reputation. 
Medium 3 Impact is perceived and raises concerns. 
Low 2 Perceived impact on environment/ 
reputation but without relevance. 
Very Low 1 No impact on environment and reputation. 
Exhibit 13 – Example of impact scale and score for safety and security, with focus in 
environment and reputation 
Other impacts 
This group is an optional group and aims to include any other specific impact of a 
risk that was not covered in the previous groups. It is important that the score of 
the other impacts, if it exists, should be from 1 to 5 like the other impact groups.
ricardo-vargas.com 9 
Proximity: The 6th Impact Dimension 
Another dimension of the impact is the time horizon or proximity of the event 
(Exhibit 14). An event that may happen in hours requires different actions than 
another event that could impact the project in 2 years. If an event is close to 
happen, it has a higher priority if compared with future events (in the proximity 
aspect). 
VERY LONGͳTERM LONGͳTERM 
MEDIUM TERM 
NEAR 
IMMEDIATE 
Exhibit 14 – Understanding the time horizon 
The proximity scale should be compatible with the other impact groups (1 to 5 
score for different time horizons). It is important that the project team defines 
what are immediate events, short-term events, medium-term events, long-term 
events and very long-term events (Exhibit 15). 
It is important to highlight that immediate events will score higher than very 
long-term events when assessing their proximity. 
LEVEL SCORE DESCRIPTION 
Very High 5 Event can happen anytime in the next 15 
days. 
High 4 Event can happen between 15 days and 3 
months. 
Medium 3 Event can happen between 3 and 6 months. 
Low 2 Event can happen between 6 months and 1 
year. 
Very Low 1 Event can happen more than 1 year ahead. 
Exhibit 15 – Example of proximity scale and score
10 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis 
Calculating the expected value and final risk assessment 
The expected value is a risk measurement used to assess and prioritize risk events 
(Exhibit 16). 
Tabela 1. Exemplo dos resultados do impacto e a fórmula de cálculo. 
Área 
impactada Tempo Custos Qualidade Proteção e Segurança Outras Proximidade 
Risco A 3 2 1 1 1 4 
Impact = 
32 + 22 + 12 + 12 + 12 + 42 
6 
= 
 
32 
6 
= 2, 31 
Expected Value = Probability x Impact 
Quadratic Mean2 = Arithmetic Mean2+ Variance 
Impact = 
 
Imp. on Time2 + Imp. on Costs2 + Imp. on Quality2 + Imp. on SSecurity2 + Imp. on Other2 + Proximity2 
6 
Figura 3. Fórmula de cálculo da média quadrática. 
Alguns processos quantitativas são simples e diretos, como rolar um dado (Figura ??), mas a maioria en-volve 
uma complexa simulação de cenários como a Simulação de Monte Carlo. Monte Carlo foi uma 
alcunha para um projeto ultra-secreto relacionado ao desenho e ao desenvolvimento de armas atômicas 
criadas pelo matemático John von Neumann (POUNDSTONE, 1993 e VARGAS, 2013). Ele descobriu que 
um simples modelo de amostras randômicas poderia solucionar certos problemas matemáticos, que não 
podiam ser solucionados até aquele momento. 
A simulação se refere, no entanto, a um método pelo qual a distribuição dos resultados possíveis é pro-duzidas 
através de sucessivos recálculos dos dados do projeto, permitindo o desenvolvimento de múltiplos 
cenários. Em cada um dos cálculos, novos dados randômicos são usados para representar um processo 
repetitivo e interativo. A combinação de todos estes resultados cria uma distribuição probabilística dos 
resultados (Figuras 5 e 6). 
**Figura 5** – Construção de um modelo de distribuição de custos e atividades, ou pacotes de trabalho, 
gerando uma distribuição nal a partir de dados aleatórios do projeto (PRITCHARD, 2001). 
**Figura 6** – Exemplo da simulação de Monte Carlo para avaliar o impacto no custo de uma possível 
ameaça ao projeto. 
Em razão da análise quantitativa ser baseada na matemática e na estatística suportadas por métricas obje-tivas, 
tais análises são consideradas mais rigorosas (SMOCK, 2020). Os principais desaos de uma análise 
quantitativa sólida são o tempo e o esforço requeridos para a sua execução e também o requerido conhec- 
Exhibit 16 
Using the qualitative method, the probability will range from 1 to 5 (Exhibit 8). 
The impact is based on the impact in different aspects of the project and the 
proximity using a quadratic mean (root square mean) calculation (Exhibit 17). 
Copyright 2014 by Ricardo Viana Vargas. All Rights Reseved 
Tabela 1. Exemplo dos resultados do impacto e a fórmula de cálculo. 
Área 
impactada Tempo Custos Qualidade Proteção e Segurança Outras Proximidade 
Risco A 3 2 1 1 1 4 
Impact = 
32 + 22 + 12 + 12 + 12 + 42 
6 
= 
 
32 
6 
= 2, 31 
Expected Value = Probability x Impact 
Quadratic Mean2 = Arithmetic Mean2+ Variance 
Impact = 
 
Imp. on Time2 + Imp. on Costs2 + Imp. on Quality2 + Imp. on SSecurity2 + Imp. on Other2 + Proximity2 
6 
Figura 3. Fórmula de cálculo da média quadrática. 
Alguns processos quantitativas são simples e diretos, como rolar um dado (Figura ??), mas a maioria en-volve 
uma complexa simulação de cenários como a Simulação de Monte Carlo. Monte Carlo foi uma 
alcunha para um projeto ultra-secreto relacionado ao desenho e ao desenvolvimento de armas atômicas 
criadas pelo matemático John von Neumann (POUNDSTONE, 1993 e VARGAS, 2013). Ele descobriu que 
um simples modelo de amostras randômicas poderia solucionar certos problemas matemáticos, que não 
podiam ser solucionados até aquele momento. 
A simulação se refere, no entanto, a um método pelo qual a distribuição dos resultados possíveis é pro-duzidas 
através de sucessivos recálculos dos dados do projeto, permitindo o desenvolvimento de múltiplos 
cenários. Em cada um dos cálculos, novos dados randômicos são usados para representar um processo 
repetitivo e interativo. A combinação de todos estes resultados cria uma distribuição probabilística dos 
resultados (Figuras 5 e 6). 
**Figura 5** – Construção de um modelo de distribuição de custos e atividades, ou pacotes de trabalho, 
gerando uma distribuição nal a partir de dados aleatórios do projeto (PRITCHARD, 2001). 
**Figura 6** – Exemplo da simulação de Monte Carlo para avaliar o impacto no custo de uma possível 
ameaça ao projeto. 
Em razão da análise quantitativa ser baseada na matemática e na estatística suportadas por métricas obje-tivas, 
tais análises são consideradas mais rigorosas (SMOCK, 2020). Os principais desaos de uma análise 
quantitativa sólida são o tempo e o esforço requeridos para a sua execução e também o requerido conhec- 
3 
Exhibit 17 
The decision for the quadratic mean instead of the arithmetic mean is based on 
the concept that different levels of impact add additional exposure to the project 
and this variance should be considered as a risk factor to the project. 
The relationship between the quadratic mean and the arithmetic mean is 
Copyright 2014 by Ricardo Viana Vargas. All Rights Reseved 
Tabela 1. Exemplo dos resultados do impacto e a fórmula de cálculo. 
Área 
impactada Tempo Custos Qualidade Proteção e Segurança Outras Proximidade 
Risco A 3 2 1 1 1 4 
Impact = 
32 + 22 + 12 + 12 + 12 + 42 
6 
= 
 
32 
6 
= 2, 31 
Expected Value = Probability x Impact 
Quadratic Mean2 = Arithmetic Mean2+ Variance 
Impact = 
 
Imp. on Time2 + Imp. on Costs2 + Imp. on Quality2 + Imp. on SSecurity2 + Imp. on Other2 + Proximity2 
6 
Figura 3. Fórmula de cálculo da média quadrática. 
Alguns processos quantitativas são simples e diretos, como rolar um dado (Figura ??), mas a maioria en-volve 
uma complexa simulação de cenários como a Simulação de Monte Carlo. Monte Carlo foi uma 
alcunha para um projeto ultra-secreto relacionado ao desenho e ao desenvolvimento de armas atômicas 
criadas pelo matemático John von Neumann (POUNDSTONE, 1993 e VARGAS, 2013). Ele descobriu que 
um simples modelo de amostras randômicas poderia solucionar certos problemas matemáticos, que não 
podiam ser solucionados até aquele momento. 
A simulação se refere, no entanto, a um método pelo qual a distribuição dos resultados possíveis é pro-duzidas 
através de sucessivos recálculos dos dados do projeto, permitindo o desenvolvimento de múltiplos 
cenários. Em cada um dos cálculos, novos dados randômicos são usados para representar um processo 
repetitivo e interativo. A combinação de todos estes resultados cria uma distribuição probabilística dos 
resultados (Figuras 5 e 6). 
Exhibit 18 
where the variance is a measure of how far a set of numbers is spread out 
The variance concept is directly related to the dispersion of the different impact 
groups. If the impact ranges are very wide, the variance will also be high and the 
difference between the proposed quadratic mean and the traditional arithmetic 
mean will increase, increasing the risk impact. 
One example of the impact results is presented in the Exhibit 19. 
IMPACT 
TIME 
IMPACT 
COST 
IMPACT 
QUALITY 
IMPACT 
SS 
OTHER 
IMPACT PROXIMITY 
Risk A 3 2 1 1 1 4 
Copyright 2014 by Ricardo Viana Vargas. All Rights Reseved 
Tabela 1. Exemplo dos resultados do impacto e a fórmula de cálculo. 
Área 
impactada Tempo Custos Qualidade Proteção e Segurança Outras Proximidade 
Risco A 3 2 1 1 1 4 
Impact = 
32 + 22 + 12 + 12 + 12 + 42 
6 
= 
 
32 
6 
= 2, 31 
Expected Value = Probability x Impact 
Quadratic Mean2 = Arithmetic Mean2+ Variance 
Impact = 
 
Imp. on Time2 + Imp. on Costs2 + Imp. on Quality2 + Imp. on SSecurity2 + Imp. on Other2 + Proximity2 
6 
Figura 3. Fórmula de cálculo da média quadrática. 
Exhibit 19 
It is important to highlight that the threats and opportunities can be calculated 
using the same formula, but with different signals (+ for opportunities and – for 
threats). The total qualitative risk exposure of the project is determined by the 
sum of the expected values of all threats and opportunities. An example of this 
process is presented on the Exhibit 20.
ricardo-vargas.com 11 
TYPE 
PROBA-BILITY 
PROXI-MITY 
IMPACT 
TIME 
IMPACT 
COST 
IMPACT 
QUALITY 
IMPACT 
SAFETY 
AND 
SECURITY 
OTHER 
IMPACTS 
TOTAL 
IMPACT 
EXPECTED 
VALUE 
Threat 1 3 2 1 1 1 4 2,31 (2,31) 
Threat 2 4 4 3 3 4 3 3,54 (7,07) 
Threat 2 3 5 4 4 5 1 3,92 (7,83) 
Opportunity 3 2 4 3 5 4 2 3,51 10,54 
Opportunity 4 1 3 2 4 3 2 2,68 10,71 
Threat 5 2 2 1 3 1 1 1,83 (9,13) 
Total Risk Expected Value (5,10) 
Exhibit 20 – Example of a project expected risk value considering opportunities and threats. 
The results from the process will be always a number between 1 and 25. In the 
example of Exhibit 20, the value -5,10 is equivalent to 20,4% negative exposure 
(5,10/25) for the Project. 
Based on this result and the tolerance thresholds (HILSON  MURRAY-WEBSTER, 
2007), the total exposure can be compared with other projects and the corporate 
limits to define potential risk response plans. 
Conclusions 
The qualitative risk method is always a simplified model if compared with the 
quantitative methods. The approach of this paper suggests an alternative model 
that can be tailored to include different kinds of impacts and scales in order to 
produce a reliable quantitative result. 
This result allows opportunities and threats to be compared in order to deter-mine 
the total risk exposure. The concept that an opportunity can cancel a threat 
of the same level is not possible with the traditional qualitative risk management 
approach. 
References 
ALTENBACH, T. J. (1995). A Comparison of Risk Assessment Techniques from Quali-tative 
to Quantitative. Honolulu, ASME Preassure Vessels and Piping Conference. 
Available at http://www.osti.gov/bridge/servlets/purl/67753-dsZ0vB/webview-able/ 
67753.pdf 
HILSON, D.  MURRAY-WEBSTER, R. (2007). Understanding and Managing Risk Atti-tude. 
London: Gower Publishing. 
PMI (2013). The Project Management Body of Knowledge: Fifth Edition. Newtown 
Square: Project Management Institute.
12 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis 
POUNDSTONE, W (1993). Prisoner’s Dillema. Flushing: Anchor Publishing Group. 
PRITCHARD, C. L. (2001). Risk Management: Concepts and Guidance. 2ª Ed. Arling-ton: 
ESI International. 
ROSSI, P. (2007). How to link the qualitative and the quantitative risk assessment. 
Budapest: Project Management Institute Global Congress EMEA. 
ROT, A. (2008). IT Risk Assessment: Quantitative and Qualitative Approach. San 
Francisco: World Congress on Engineering and Computer Science. 
SMOCK, R. (2002). Reducing Subjectivity in Qualitative Risk Assessments. Bethesda, 
SANS Institute. Available at http://www.giac.org/paper/gsec/2014/reducing-sub-jectivity- 
qualitative-risk-assessments/103489 
VARGAS, R. V. (2013). Determining the Mathematical ROI of a Project Management 
Implementation. New Orleans, Project Management Institute Global Congress 
North America. 
VIRINE, L. (2010). Project Risk Analysis: How Ignoring It Will Lead to Project Failures. 
Washington: Project Management Institute Global Congress North America.

More Related Content

What's hot

Managing cost and schedule risk
Managing cost and schedule riskManaging cost and schedule risk
Managing cost and schedule riskGlen Alleman
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk toleranceGlen Alleman
 
Options based decisions processes
Options based decisions processesOptions based decisions processes
Options based decisions processesGlen Alleman
 
Decision and risk analysis
Decision and risk analysisDecision and risk analysis
Decision and risk analysisIndra Biswakarma
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk ManagementIRJET Journal
 
Framework criteria-appraisal-socioeconomic-justification-education-projects
Framework criteria-appraisal-socioeconomic-justification-education-projectsFramework criteria-appraisal-socioeconomic-justification-education-projects
Framework criteria-appraisal-socioeconomic-justification-education-projectsAdili Zella
 
SEPG_2010_RiskKnowItAll_REV2
SEPG_2010_RiskKnowItAll_REV2SEPG_2010_RiskKnowItAll_REV2
SEPG_2010_RiskKnowItAll_REV2pbaxter
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Association for Project Management
 
Risk management of the performance measurement baseline
Risk management of the performance measurement baselineRisk management of the performance measurement baseline
Risk management of the performance measurement baselineGlen Alleman
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)Serdar Temiz
 
Risk analysis and management
Risk analysis and managementRisk analysis and management
Risk analysis and managementgnitu
 
Acumen Risk Workshops Overview
Acumen Risk Workshops OverviewAcumen Risk Workshops Overview
Acumen Risk Workshops OverviewAcumen
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsIJMER
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)Glen Alleman
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy PiecesGlen Alleman
 
Iwsm2014 defining technical risk in software development (vard antinyan)
Iwsm2014   defining technical risk in software development (vard antinyan)Iwsm2014   defining technical risk in software development (vard antinyan)
Iwsm2014 defining technical risk in software development (vard antinyan)Nesma
 
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Liana Underwood
 
Software IT risk-management
Software IT risk-managementSoftware IT risk-management
Software IT risk-managementgufranresearcher
 

What's hot (20)

Managing cost and schedule risk
Managing cost and schedule riskManaging cost and schedule risk
Managing cost and schedule risk
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk tolerance
 
Options based decisions processes
Options based decisions processesOptions based decisions processes
Options based decisions processes
 
Decision and risk analysis
Decision and risk analysisDecision and risk analysis
Decision and risk analysis
 
Pmi 19 26
Pmi 19 26Pmi 19 26
Pmi 19 26
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk Management
 
Framework criteria-appraisal-socioeconomic-justification-education-projects
Framework criteria-appraisal-socioeconomic-justification-education-projectsFramework criteria-appraisal-socioeconomic-justification-education-projects
Framework criteria-appraisal-socioeconomic-justification-education-projects
 
SEPG_2010_RiskKnowItAll_REV2
SEPG_2010_RiskKnowItAll_REV2SEPG_2010_RiskKnowItAll_REV2
SEPG_2010_RiskKnowItAll_REV2
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
 
Risk management of the performance measurement baseline
Risk management of the performance measurement baselineRisk management of the performance measurement baseline
Risk management of the performance measurement baseline
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
Risk analysis and management
Risk analysis and managementRisk analysis and management
Risk analysis and management
 
Acumen Risk Workshops Overview
Acumen Risk Workshops OverviewAcumen Risk Workshops Overview
Acumen Risk Workshops Overview
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction Projects
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy Pieces
 
Iwsm2014 defining technical risk in software development (vard antinyan)
Iwsm2014   defining technical risk in software development (vard antinyan)Iwsm2014   defining technical risk in software development (vard antinyan)
Iwsm2014 defining technical risk in software development (vard antinyan)
 
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
 
Software IT risk-management
Software IT risk-managementSoftware IT risk-management
Software IT risk-management
 

Viewers also liked

Avoiding Mistakes During the Team Acquisition
Avoiding Mistakes During the Team AcquisitionAvoiding Mistakes During the Team Acquisition
Avoiding Mistakes During the Team AcquisitionRicardo Viana Vargas
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationRicardo Viana Vargas
 
Entrevista Revista Mundo PM com Ricardo Vargas.
Entrevista Revista Mundo PM com Ricardo Vargas.Entrevista Revista Mundo PM com Ricardo Vargas.
Entrevista Revista Mundo PM com Ricardo Vargas.Ricardo Viana Vargas
 
Identifying and Recovering Troubled Projects - Chinese Version
Identifying and Recovering Troubled Projects - Chinese VersionIdentifying and Recovering Troubled Projects - Chinese Version
Identifying and Recovering Troubled Projects - Chinese VersionRicardo Viana Vargas
 
Flow of PMBOK 4th edition in Portuguese - Color
Flow of PMBOK 4th edition in Portuguese - ColorFlow of PMBOK 4th edition in Portuguese - Color
Flow of PMBOK 4th edition in Portuguese - ColorRicardo Viana Vargas
 
Managing ERP Implementation Using Basic Software Tools
Managing ERP Implementation Using Basic Software ToolsManaging ERP Implementation Using Basic Software Tools
Managing ERP Implementation Using Basic Software ToolsRicardo Viana Vargas
 
Evintando Erros Durante a Formacao do Time - Disponivel Apenas em Ingles
Evintando Erros Durante a Formacao do Time - Disponivel Apenas em InglesEvintando Erros Durante a Formacao do Time - Disponivel Apenas em Ingles
Evintando Erros Durante a Formacao do Time - Disponivel Apenas em InglesRicardo Viana Vargas
 
Ricardo vargas identifying_recovering_troubled_projects_rus
Ricardo vargas identifying_recovering_troubled_projects_rusRicardo vargas identifying_recovering_troubled_projects_rus
Ricardo vargas identifying_recovering_troubled_projects_rusRicardo Viana Vargas
 
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...Ricardo Viana Vargas
 
Análise de Valor Agregado no Controle de Projetos: Sucesso ou Fracasso?
Análise de Valor Agregado no Controle de Projetos: Sucesso ou Fracasso?Análise de Valor Agregado no Controle de Projetos: Sucesso ou Fracasso?
Análise de Valor Agregado no Controle de Projetos: Sucesso ou Fracasso?Ricardo Viana Vargas
 
RFlow of PMBOK 4th edition in Portuguese - Black and White
RFlow of PMBOK 4th edition in Portuguese - Black and WhiteRFlow of PMBOK 4th edition in Portuguese - Black and White
RFlow of PMBOK 4th edition in Portuguese - Black and WhiteRicardo Viana Vargas
 
Ricardo vargas ahp_project_selection_esp
Ricardo vargas ahp_project_selection_espRicardo vargas ahp_project_selection_esp
Ricardo vargas ahp_project_selection_espRicardo Viana Vargas
 
Ricardo vargas identifying_recovering_troubled_projects_germ
Ricardo vargas identifying_recovering_troubled_projects_germRicardo vargas identifying_recovering_troubled_projects_germ
Ricardo vargas identifying_recovering_troubled_projects_germRicardo Viana Vargas
 
PMBOK® Guide 4th edition Processes Flow in German (Ablaufplan des PMBOK® Guid...
PMBOK® Guide 4th edition Processes Flow in German (Ablaufplan des PMBOK® Guid...PMBOK® Guide 4th edition Processes Flow in German (Ablaufplan des PMBOK® Guid...
PMBOK® Guide 4th edition Processes Flow in German (Ablaufplan des PMBOK® Guid...Ricardo Viana Vargas
 
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...Ricardo Viana Vargas
 
Processos de Gerenciamento de Portfólio
Processos de Gerenciamento de PortfólioProcessos de Gerenciamento de Portfólio
Processos de Gerenciamento de PortfólioRicardo Viana Vargas
 
Earned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of ProjectsEarned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of ProjectsRicardo Viana Vargas
 
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Ricardo Viana Vargas
 
PMBOK® Guide 4th edition Processes Flow in Spanish (Flujo de Procesos del Guí...
PMBOK® Guide 4th edition Processes Flow in Spanish (Flujo de Procesos del Guí...PMBOK® Guide 4th edition Processes Flow in Spanish (Flujo de Procesos del Guí...
PMBOK® Guide 4th edition Processes Flow in Spanish (Flujo de Procesos del Guí...Ricardo Viana Vargas
 

Viewers also liked (19)

Avoiding Mistakes During the Team Acquisition
Avoiding Mistakes During the Team AcquisitionAvoiding Mistakes During the Team Acquisition
Avoiding Mistakes During the Team Acquisition
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
Entrevista Revista Mundo PM com Ricardo Vargas.
Entrevista Revista Mundo PM com Ricardo Vargas.Entrevista Revista Mundo PM com Ricardo Vargas.
Entrevista Revista Mundo PM com Ricardo Vargas.
 
Identifying and Recovering Troubled Projects - Chinese Version
Identifying and Recovering Troubled Projects - Chinese VersionIdentifying and Recovering Troubled Projects - Chinese Version
Identifying and Recovering Troubled Projects - Chinese Version
 
Flow of PMBOK 4th edition in Portuguese - Color
Flow of PMBOK 4th edition in Portuguese - ColorFlow of PMBOK 4th edition in Portuguese - Color
Flow of PMBOK 4th edition in Portuguese - Color
 
Managing ERP Implementation Using Basic Software Tools
Managing ERP Implementation Using Basic Software ToolsManaging ERP Implementation Using Basic Software Tools
Managing ERP Implementation Using Basic Software Tools
 
Evintando Erros Durante a Formacao do Time - Disponivel Apenas em Ingles
Evintando Erros Durante a Formacao do Time - Disponivel Apenas em InglesEvintando Erros Durante a Formacao do Time - Disponivel Apenas em Ingles
Evintando Erros Durante a Formacao do Time - Disponivel Apenas em Ingles
 
Ricardo vargas identifying_recovering_troubled_projects_rus
Ricardo vargas identifying_recovering_troubled_projects_rusRicardo vargas identifying_recovering_troubled_projects_rus
Ricardo vargas identifying_recovering_troubled_projects_rus
 
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
 
Análise de Valor Agregado no Controle de Projetos: Sucesso ou Fracasso?
Análise de Valor Agregado no Controle de Projetos: Sucesso ou Fracasso?Análise de Valor Agregado no Controle de Projetos: Sucesso ou Fracasso?
Análise de Valor Agregado no Controle de Projetos: Sucesso ou Fracasso?
 
RFlow of PMBOK 4th edition in Portuguese - Black and White
RFlow of PMBOK 4th edition in Portuguese - Black and WhiteRFlow of PMBOK 4th edition in Portuguese - Black and White
RFlow of PMBOK 4th edition in Portuguese - Black and White
 
Ricardo vargas ahp_project_selection_esp
Ricardo vargas ahp_project_selection_espRicardo vargas ahp_project_selection_esp
Ricardo vargas ahp_project_selection_esp
 
Ricardo vargas identifying_recovering_troubled_projects_germ
Ricardo vargas identifying_recovering_troubled_projects_germRicardo vargas identifying_recovering_troubled_projects_germ
Ricardo vargas identifying_recovering_troubled_projects_germ
 
PMBOK® Guide 4th edition Processes Flow in German (Ablaufplan des PMBOK® Guid...
PMBOK® Guide 4th edition Processes Flow in German (Ablaufplan des PMBOK® Guid...PMBOK® Guide 4th edition Processes Flow in German (Ablaufplan des PMBOK® Guid...
PMBOK® Guide 4th edition Processes Flow in German (Ablaufplan des PMBOK® Guid...
 
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
PMBOK® Guide 4th edition Processes Flow in Arabic (دليل بمبوك ® 4 عمليات تدفق...
 
Processos de Gerenciamento de Portfólio
Processos de Gerenciamento de PortfólioProcessos de Gerenciamento de Portfólio
Processos de Gerenciamento de Portfólio
 
Earned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of ProjectsEarned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of Projects
 
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
 
PMBOK® Guide 4th edition Processes Flow in Spanish (Flujo de Procesos del Guí...
PMBOK® Guide 4th edition Processes Flow in Spanish (Flujo de Procesos del Guí...PMBOK® Guide 4th edition Processes Flow in Spanish (Flujo de Procesos del Guí...
PMBOK® Guide 4th edition Processes Flow in Spanish (Flujo de Procesos del Guí...
 

Similar to Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis

PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Running head RISK MANAGEMENT PLAN 1RISK MANAGE.docx
Running head RISK MANAGEMENT PLAN          1RISK MANAGE.docxRunning head RISK MANAGEMENT PLAN          1RISK MANAGE.docx
Running head RISK MANAGEMENT PLAN 1RISK MANAGE.docxtoltonkendal
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownAcumen
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - PaperDaniel Ackermann
 
Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Loren Schwappach
 
Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project ManagementVenkatesh Ganapathy
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222nashaat algrara
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesIRJET Journal
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaPankaj K Sinha
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual EssayPrince Bertrand
 
Risk Calculator PowerPoint Presentation Slides
Risk Calculator PowerPoint Presentation SlidesRisk Calculator PowerPoint Presentation Slides
Risk Calculator PowerPoint Presentation SlidesSlideTeam
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Pedram Danesh-Mand
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleGlen Alleman
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMIMudassir Iqbal
 
Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyAcumen
 
Comprehensive Overview Of Risk Management
Comprehensive Overview Of Risk ManagementComprehensive Overview Of Risk Management
Comprehensive Overview Of Risk ManagementAndrew Valenti
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleGlen Alleman
 
Use of Causeand Effect Diagrams for Risk Management
Use of Causeand Effect Diagrams for Risk ManagementUse of Causeand Effect Diagrams for Risk Management
Use of Causeand Effect Diagrams for Risk ManagementProcept Associates
 

Similar to Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis (20)

PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Running head RISK MANAGEMENT PLAN 1RISK MANAGE.docx
Running head RISK MANAGEMENT PLAN          1RISK MANAGE.docxRunning head RISK MANAGEMENT PLAN          1RISK MANAGE.docx
Running head RISK MANAGEMENT PLAN 1RISK MANAGE.docx
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - Paper
 
Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6
 
Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project Management
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction Industries
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual Essay
 
Risk Calculator PowerPoint Presentation Slides
Risk Calculator PowerPoint Presentation SlidesRisk Calculator PowerPoint Presentation Slides
Risk Calculator PowerPoint Presentation Slides
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range Certainty
 
Risk analysis
Risk analysis Risk analysis
Risk analysis
 
Comprehensive Overview Of Risk Management
Comprehensive Overview Of Risk ManagementComprehensive Overview Of Risk Management
Comprehensive Overview Of Risk Management
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and Schedule
 
Use of Causeand Effect Diagrams for Risk Management
Use of Causeand Effect Diagrams for Risk ManagementUse of Causeand Effect Diagrams for Risk Management
Use of Causeand Effect Diagrams for Risk Management
 

More from Ricardo Viana Vargas

PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionRicardo Viana Vargas
 
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)Ricardo Viana Vargas
 
Fluxo de Processos do Guia PMBOK® – 6ª Edição
Fluxo de Processos do Guia PMBOK® – 6ª EdiçãoFluxo de Processos do Guia PMBOK® – 6ª Edição
Fluxo de Processos do Guia PMBOK® – 6ª EdiçãoRicardo Viana Vargas
 
Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)
Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)
Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)Ricardo Viana Vargas
 
Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...
Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...
Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...Ricardo Viana Vargas
 
Applying Neural Networks and Analogous Estimating to Determine the Project Bu...
Applying Neural Networks and Analogous Estimating to Determine the Project Bu...Applying Neural Networks and Analogous Estimating to Determine the Project Bu...
Applying Neural Networks and Analogous Estimating to Determine the Project Bu...Ricardo Viana Vargas
 
Modelando Linhas de Balanço com Relacionamentos “Início-Término”
Modelando Linhas de Balanço com Relacionamentos “Início-Término”Modelando Linhas de Balanço com Relacionamentos “Início-Término”
Modelando Linhas de Balanço com Relacionamentos “Início-Término”Ricardo Viana Vargas
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsScheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsRicardo Viana Vargas
 
Sustainability Marker to Support the Project Selection Process: the UNOPS Case
Sustainability Marker to Support the Project Selection Process: the UNOPS CaseSustainability Marker to Support the Project Selection Process: the UNOPS Case
Sustainability Marker to Support the Project Selection Process: the UNOPS CaseRicardo Viana Vargas
 
Milestones Trend Analysis (MTA) - Conceitos Básicos
Milestones Trend Analysis (MTA) - Conceitos BásicosMilestones Trend Analysis (MTA) - Conceitos Básicos
Milestones Trend Analysis (MTA) - Conceitos BásicosRicardo Viana Vargas
 
Milestones Trend Analysis (MTA) - Fundamentals
Milestones Trend Analysis (MTA) - FundamentalsMilestones Trend Analysis (MTA) - Fundamentals
Milestones Trend Analysis (MTA) - FundamentalsRicardo Viana Vargas
 
Diagrammes de Flux Guide PMBOK® 5e Édition en Français
Diagrammes de Flux Guide PMBOK® 5e Édition en FrançaisDiagrammes de Flux Guide PMBOK® 5e Édition en Français
Diagrammes de Flux Guide PMBOK® 5e Édition en FrançaisRicardo Viana Vargas
 
Diagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiée
Diagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiéeDiagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiée
Diagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiéeRicardo Viana Vargas
 
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in ItalianoDiagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in ItalianoRicardo Viana Vargas
 
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...Ricardo Viana Vargas
 
Ricardo vargas pmbok_flow_5ed_color_es
Ricardo vargas pmbok_flow_5ed_color_esRicardo vargas pmbok_flow_5ed_color_es
Ricardo vargas pmbok_flow_5ed_color_esRicardo Viana Vargas
 
Flujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificada
Flujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificadaFlujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificada
Flujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificadaRicardo Viana Vargas
 
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)Ricardo Viana Vargas
 
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch
Ablaufplan des PMBOK® Guide 5. Auflage auf DeutschAblaufplan des PMBOK® Guide 5. Auflage auf Deutsch
Ablaufplan des PMBOK® Guide 5. Auflage auf DeutschRicardo Viana Vargas
 
Understanding Opportunities, Challenges and Strategies to Build Your Career i...
Understanding Opportunities, Challenges and Strategies to Build Your Career i...Understanding Opportunities, Challenges and Strategies to Build Your Career i...
Understanding Opportunities, Challenges and Strategies to Build Your Career i...Ricardo Viana Vargas
 

More from Ricardo Viana Vargas (20)

PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th Edition
 
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
 
Fluxo de Processos do Guia PMBOK® – 6ª Edição
Fluxo de Processos do Guia PMBOK® – 6ª EdiçãoFluxo de Processos do Guia PMBOK® – 6ª Edição
Fluxo de Processos do Guia PMBOK® – 6ª Edição
 
Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)
Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)
Fluxo de Processos do Guia PMBOK® – 6ª Edição (Versão simplificada)
 
Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...
Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...
Aplicando Redes Neurais e Estimativa Análoga para Determinar o Orçamento do P...
 
Applying Neural Networks and Analogous Estimating to Determine the Project Bu...
Applying Neural Networks and Analogous Estimating to Determine the Project Bu...Applying Neural Networks and Analogous Estimating to Determine the Project Bu...
Applying Neural Networks and Analogous Estimating to Determine the Project Bu...
 
Modelando Linhas de Balanço com Relacionamentos “Início-Término”
Modelando Linhas de Balanço com Relacionamentos “Início-Término”Modelando Linhas de Balanço com Relacionamentos “Início-Término”
Modelando Linhas de Balanço com Relacionamentos “Início-Término”
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsScheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
 
Sustainability Marker to Support the Project Selection Process: the UNOPS Case
Sustainability Marker to Support the Project Selection Process: the UNOPS CaseSustainability Marker to Support the Project Selection Process: the UNOPS Case
Sustainability Marker to Support the Project Selection Process: the UNOPS Case
 
Milestones Trend Analysis (MTA) - Conceitos Básicos
Milestones Trend Analysis (MTA) - Conceitos BásicosMilestones Trend Analysis (MTA) - Conceitos Básicos
Milestones Trend Analysis (MTA) - Conceitos Básicos
 
Milestones Trend Analysis (MTA) - Fundamentals
Milestones Trend Analysis (MTA) - FundamentalsMilestones Trend Analysis (MTA) - Fundamentals
Milestones Trend Analysis (MTA) - Fundamentals
 
Diagrammes de Flux Guide PMBOK® 5e Édition en Français
Diagrammes de Flux Guide PMBOK® 5e Édition en FrançaisDiagrammes de Flux Guide PMBOK® 5e Édition en Français
Diagrammes de Flux Guide PMBOK® 5e Édition en Français
 
Diagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiée
Diagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiéeDiagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiée
Diagrammes de Flux Guide PMBOK® 5e Édition en Français - Version simplifiée
 
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in ItalianoDiagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano
 
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...
Diagrammi di Flusso della Guida PMBOK® 5ª Edizione in Italiano - Versione sem...
 
Ricardo vargas pmbok_flow_5ed_color_es
Ricardo vargas pmbok_flow_5ed_color_esRicardo vargas pmbok_flow_5ed_color_es
Ricardo vargas pmbok_flow_5ed_color_es
 
Flujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificada
Flujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificadaFlujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificada
Flujo de Procesos de la Guía PMBOK® 5ª edición en Español - Versión simplificada
 
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch (vereinfachte Version)
 
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch
Ablaufplan des PMBOK® Guide 5. Auflage auf DeutschAblaufplan des PMBOK® Guide 5. Auflage auf Deutsch
Ablaufplan des PMBOK® Guide 5. Auflage auf Deutsch
 
Understanding Opportunities, Challenges and Strategies to Build Your Career i...
Understanding Opportunities, Challenges and Strategies to Build Your Career i...Understanding Opportunities, Challenges and Strategies to Build Your Career i...
Understanding Opportunities, Challenges and Strategies to Build Your Career i...
 

Recently uploaded

The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 

Recently uploaded (20)

The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 

Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis

  • 1. ADOPTING THE QUADRATIC MEAN PROCESS TO QUANTIFY THE QUALITATIVE RISK ANALYSIS Accepted for publication at PMI Global Congress 2013 – North America New Orleans – Louisiana – USA – 2013
  • 2. 2 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis Abstract The objective of this paper is to propose a mathematical process to turn the re-sults of a qualitative risk analysis into numeric indicators to support better deci-sions regarding risk response strategies. Using a five-level scale for probability and a set of scales to measure different aspects of the impact and time horizon, a simple mathematical process is devel-oped using the quadratic mean (also known as root mean square) to calculate the numerical exposition of the risk and consequently, the numerical exposition of the project risks. This paper also supports the reduction of intuitive thinking when evaluating risks, often subject to illusions, which can cause perception errors. These predict-able mental errors, such as overconfidence, confirmation traps, optimism bias, zero-risk bias, sunk-cost effect, and others often lead to the underestimation of costs and effort, poor resource planning, and other low-quality decisions (VIRINE, 2010). Related Podcasts ♫♫Using the Quadratic Average (Mean) in the Qualitative Risk Analysis http://rvarg.as/bd ♫♫Understanding the Risk Attitude http://rvarg.as/6j ♫♫RBS – Risk Breakdown Struc-ture http://rvarg.as/be ♫♫Risk Management Special Playlist http://rvarg.as/bc
  • 3. ricardo-vargas.com 3 Qualitative X Quantitative Risk Analysis One of the main challenges during the analysis of a risk is to define the right ap-proach to assess the amount of the exposure/opportunity. The two basic steps to determine the right level of risk are based on the qualitative and quantitative analysis (Exhibit 1). Assessment of Risk Level Updated Risk Register Output Risk Prioritisation Qualitative Quantitative Risk Analysis Exhibit 1 – Analysis of Risk Process Flow (ROSSI, 2007). A qualitative risk analysis prioritizes the identified project risks using a predefined scale. Risks will be scored based on their probability or likelihood of occurrence and the impact on project objectives if they occur (Exhibit 2 and 3). LEVEL SCORE FOR THREATS High Very High 5 Red High 4 Medium Medium 3 Yellow Low 2 Low Very Low 1 Green Exhibit 2 – Example of scales used in the qualitative risk analysis Qualitative Risk Matrix Risk Levels are Relative to Regions Connected by Arrows Consequence Low Medium High Low Medium High Frequency 3 4 5 2 3’ 4’ 1 2’ 3” Highest Risk Lowest Risk Exhibit 3 – Example of Qualitative Risk Matrix with 3 x 3 Levels (ALTENBACH, 1995)
  • 4. 4 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis A quantitative risk analysis is based on simulation models and probabilistic analy-sis, where the possible outcomes for the project are evaluated, providing a quan-titative, numeric and many times financial risk exposure to support decisions when there is uncertainty (PMI, 2013). Some quantitative processes are simple and direct like rolling a dice (Exhibit 4), but most of them involve very complex simulation scenarios like the Monte Carlo Simulation. Exhibit 4 – Diagram showing the deterministic probability of rolling a dice “Monte Carlo” was a nickname of a top-secret project related to the drawing and to the project of atomic weapons developed by the mathematician John von Neumann (POUNDSTONE, 1993 and VARGAS, 2013). He discovered that a sim-ple model of random samples could solve certain mathematical problems, which couldn’t be solved up to that moment. The simulation refers, however, to a method by which the distribution of possible results is produced from successive recalculations of project data, allowing the development of multiple scenarios. In each one of the calculations, new random data is used to represent a repetitive and interactive process. The combination of all these results creates a probabilistic distribution of the results (Exhibit 5 and 6). A B E C D Start Finish Forecast of Final Cost % Exhibit 5 – Construction of model of distribution of costs and activities or work packages making up a final distribution from random data of the project (PRITCHARD, 2001).
  • 5. ricardo-vargas.com 5 Exhibit 6 – Example of Monte Carlo simulation to assess the cost impact of a potential threat to the project Because quantitative analysis is based on mathematics and statistics supported by objective metrics, such analyses are considered to be more rigorous (SMOCK, 2002). The main challenges of a solid quantitative analysis are the time and effort it requires to be executed and the required technical background in statistics to make the proper parameterization of the data. The main advantages and disad-vantages of each method are presented in the Exhibit 7. QUANTITATIVE METHODS QUALITATIVE METHODS Advantages Facilitates the cost benefit analysis Gives a more accurate value of the risk More valuable Relatively simple to be implemented Easily determine risk categories with greater impact in the project Visually impactful Disadvantages Results of the method may not be precise Numbers can give a false perception of precision More expensive and time consuming A lack of understanding of the parameters used in the scale can lead to different interpretations Results can be biased Less valuable Exhibit 7 – Example of Monte Carlo simulation to assess the cost impact of a potential threat to the project (based on ROT, 2008) The risk model proposed hereafter is a qualitative process with numerical results, reducing the ambiguity of the qualitative process without adds the time and effort to determine with precision the probability and the impact of uncertain events in the project. Assessing Probability The proposed qualitative probability assessment is based on a scale with their respective scores (Exhibit 8).
  • 6. 6 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis LEVEL SCORE DESCRIPTION Very High 5 It is expected that the event will occur. If it does not occurs it will be a surprise. High 4 The event has a great chance of occurring. Medium 3 The event can occur. Low 2 It will be a surprise if the event occurs. Very Low 1 Very remote chance of the event to happen. Practically impossible. Exhibit 8 – 5 Scales to assess the risk probability For each identified risk a score from 1 (one) to 5 (five) should be determined. 5 Dimensions of the Impact The impact of the event, in case it occurs, can be perceived in different dimen-sions of the project objectives. For example, one risk can have a major impact on costs but not necessarily an important impact in quality. It is very important to highlight that threats and opportunities should be analyzed separately. The basic groups where impact should be evaluated are (Exhibit 9): • impact on time and deadlines • impact on costs • impact on quality • impact in safety and security • other impacts TIME OTHER COST QUALITY SAFETY & SECURITY Exhibit 9 – Basic impact groups showing the different impact dimensions of one specific risk Each project may develop different impact groups based on the nature of the project, including groups like: impact on reputation, regulatory impact, environ-mental impact, social impact, and stakeholder’s impact, among several others. Following is the presentation of the 5 basic groups.
  • 7. ricardo-vargas.com 7 Impact on Time and Deadlines One should assess the level of impact on the conclusion of the project. It can be positive or negative for opportunities and threats, respectively. Threats that im-pact the conclusion of the project must be considered as a priority if compared to other events. Because each project differs in size, complexity and several other factors, the project team needs to agree on the level of tolerance that they consider appro-priate for each level of impact, like the example shown in Exhibit 10. LEVEL SCORE DESCRIPTION Very High 5 Delays/Anticipation above 180 days or 6 months. High 4 Delays/Anticipation between 120 and 180 calendar days. Medium 3 Delays/Anticipation between 60 and 120 calendar days. Low 2 Delays/Anticipation between 15 and 60 calendar days. Very Low 1 Less than 15 calendar days of delays/ anticipation. Exhibit 10 – Example of impact scale and score for time and deadlines Impact on Costs One should also assess the level of impact that the event may bring to the total project cost. It can be positive (savings) or negative (additional expenditures) for opportunities and threats, respectively. Like mentioned for time and deadlines, the project team needs to agree on the level of tolerance that they consider appropriate for each level of impact, like in the example for costs presented in the Exhibit 11. LEVEL SCORE DESCRIPTION Very High 5 Variation (positive or negative) above $1,000,000. High 4 Variation (positive or negative) between $500,000 and $1,000,000. Medium 3 Variation (positive or negative) between $250,000 and $500,000. Low 2 Variation (positive or negative) between $100,000 and $250,000. Very Low 1 Variation (positive or negative) lower than $100,000. Exhibit 11 – Example of impact scale and score for costs
  • 8. 8 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis Impact on Quality Assesses the level of impact on the quality required for the project. It can be pos-itive or negative for opportunities and threats, respectively. As presented in the other groups, the project team needs to agree on the level of tolerance that they consider appropriate for each level of impact like in the example in Exhibit 12 for negative risk events. LEVEL SCORE DESCRIPTION Very High 5 Client rejects the delivery or product. High 4 Client asks for immediate corrective actions. Medium 3 Client perceives and asks for action/ information. Low 2 Client perceives but forgives and no action is needed. Very Low 1 Imperceptible impact (most of the time not even perceived by the stakeholders). Exhibit 12 – Example of impact scale and score for quality (only negative events) Impact in Safety and Security Assesses the level of impact that the event can incur in safety at work and se-curity. This impact group could include or not aspects related to environment, physical security of the work in the project, data security (IT), and reputation, among others. In the Exhibit 13, an example of scale is presented to assess impacts in safety and security. LEVEL SCORE DESCRIPTION Very High 5 Crisis. Impact is so evident and public that the project could not proceed as planned. High 4 Evident impact on environment/reputation. Medium 3 Impact is perceived and raises concerns. Low 2 Perceived impact on environment/ reputation but without relevance. Very Low 1 No impact on environment and reputation. Exhibit 13 – Example of impact scale and score for safety and security, with focus in environment and reputation Other impacts This group is an optional group and aims to include any other specific impact of a risk that was not covered in the previous groups. It is important that the score of the other impacts, if it exists, should be from 1 to 5 like the other impact groups.
  • 9. ricardo-vargas.com 9 Proximity: The 6th Impact Dimension Another dimension of the impact is the time horizon or proximity of the event (Exhibit 14). An event that may happen in hours requires different actions than another event that could impact the project in 2 years. If an event is close to happen, it has a higher priority if compared with future events (in the proximity aspect). VERY LONGͳTERM LONGͳTERM MEDIUM TERM NEAR IMMEDIATE Exhibit 14 – Understanding the time horizon The proximity scale should be compatible with the other impact groups (1 to 5 score for different time horizons). It is important that the project team defines what are immediate events, short-term events, medium-term events, long-term events and very long-term events (Exhibit 15). It is important to highlight that immediate events will score higher than very long-term events when assessing their proximity. LEVEL SCORE DESCRIPTION Very High 5 Event can happen anytime in the next 15 days. High 4 Event can happen between 15 days and 3 months. Medium 3 Event can happen between 3 and 6 months. Low 2 Event can happen between 6 months and 1 year. Very Low 1 Event can happen more than 1 year ahead. Exhibit 15 – Example of proximity scale and score
  • 10. 10 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis Calculating the expected value and final risk assessment The expected value is a risk measurement used to assess and prioritize risk events (Exhibit 16). Tabela 1. Exemplo dos resultados do impacto e a fórmula de cálculo. Área impactada Tempo Custos Qualidade Proteção e Segurança Outras Proximidade Risco A 3 2 1 1 1 4 Impact = 32 + 22 + 12 + 12 + 12 + 42 6 = 32 6 = 2, 31 Expected Value = Probability x Impact Quadratic Mean2 = Arithmetic Mean2+ Variance Impact = Imp. on Time2 + Imp. on Costs2 + Imp. on Quality2 + Imp. on SSecurity2 + Imp. on Other2 + Proximity2 6 Figura 3. Fórmula de cálculo da média quadrática. Alguns processos quantitativas são simples e diretos, como rolar um dado (Figura ??), mas a maioria en-volve uma complexa simulação de cenários como a Simulação de Monte Carlo. Monte Carlo foi uma alcunha para um projeto ultra-secreto relacionado ao desenho e ao desenvolvimento de armas atômicas criadas pelo matemático John von Neumann (POUNDSTONE, 1993 e VARGAS, 2013). Ele descobriu que um simples modelo de amostras randômicas poderia solucionar certos problemas matemáticos, que não podiam ser solucionados até aquele momento. A simulação se refere, no entanto, a um método pelo qual a distribuição dos resultados possíveis é pro-duzidas através de sucessivos recálculos dos dados do projeto, permitindo o desenvolvimento de múltiplos cenários. Em cada um dos cálculos, novos dados randômicos são usados para representar um processo repetitivo e interativo. A combinação de todos estes resultados cria uma distribuição probabilística dos resultados (Figuras 5 e 6). **Figura 5** – Construção de um modelo de distribuição de custos e atividades, ou pacotes de trabalho, gerando uma distribuição nal a partir de dados aleatórios do projeto (PRITCHARD, 2001). **Figura 6** – Exemplo da simulação de Monte Carlo para avaliar o impacto no custo de uma possível ameaça ao projeto. Em razão da análise quantitativa ser baseada na matemática e na estatística suportadas por métricas obje-tivas, tais análises são consideradas mais rigorosas (SMOCK, 2020). Os principais desaos de uma análise quantitativa sólida são o tempo e o esforço requeridos para a sua execução e também o requerido conhec- Exhibit 16 Using the qualitative method, the probability will range from 1 to 5 (Exhibit 8). The impact is based on the impact in different aspects of the project and the proximity using a quadratic mean (root square mean) calculation (Exhibit 17). Copyright 2014 by Ricardo Viana Vargas. All Rights Reseved Tabela 1. Exemplo dos resultados do impacto e a fórmula de cálculo. Área impactada Tempo Custos Qualidade Proteção e Segurança Outras Proximidade Risco A 3 2 1 1 1 4 Impact = 32 + 22 + 12 + 12 + 12 + 42 6 = 32 6 = 2, 31 Expected Value = Probability x Impact Quadratic Mean2 = Arithmetic Mean2+ Variance Impact = Imp. on Time2 + Imp. on Costs2 + Imp. on Quality2 + Imp. on SSecurity2 + Imp. on Other2 + Proximity2 6 Figura 3. Fórmula de cálculo da média quadrática. Alguns processos quantitativas são simples e diretos, como rolar um dado (Figura ??), mas a maioria en-volve uma complexa simulação de cenários como a Simulação de Monte Carlo. Monte Carlo foi uma alcunha para um projeto ultra-secreto relacionado ao desenho e ao desenvolvimento de armas atômicas criadas pelo matemático John von Neumann (POUNDSTONE, 1993 e VARGAS, 2013). Ele descobriu que um simples modelo de amostras randômicas poderia solucionar certos problemas matemáticos, que não podiam ser solucionados até aquele momento. A simulação se refere, no entanto, a um método pelo qual a distribuição dos resultados possíveis é pro-duzidas através de sucessivos recálculos dos dados do projeto, permitindo o desenvolvimento de múltiplos cenários. Em cada um dos cálculos, novos dados randômicos são usados para representar um processo repetitivo e interativo. A combinação de todos estes resultados cria uma distribuição probabilística dos resultados (Figuras 5 e 6). **Figura 5** – Construção de um modelo de distribuição de custos e atividades, ou pacotes de trabalho, gerando uma distribuição nal a partir de dados aleatórios do projeto (PRITCHARD, 2001). **Figura 6** – Exemplo da simulação de Monte Carlo para avaliar o impacto no custo de uma possível ameaça ao projeto. Em razão da análise quantitativa ser baseada na matemática e na estatística suportadas por métricas obje-tivas, tais análises são consideradas mais rigorosas (SMOCK, 2020). Os principais desaos de uma análise quantitativa sólida são o tempo e o esforço requeridos para a sua execução e também o requerido conhec- 3 Exhibit 17 The decision for the quadratic mean instead of the arithmetic mean is based on the concept that different levels of impact add additional exposure to the project and this variance should be considered as a risk factor to the project. The relationship between the quadratic mean and the arithmetic mean is Copyright 2014 by Ricardo Viana Vargas. All Rights Reseved Tabela 1. Exemplo dos resultados do impacto e a fórmula de cálculo. Área impactada Tempo Custos Qualidade Proteção e Segurança Outras Proximidade Risco A 3 2 1 1 1 4 Impact = 32 + 22 + 12 + 12 + 12 + 42 6 = 32 6 = 2, 31 Expected Value = Probability x Impact Quadratic Mean2 = Arithmetic Mean2+ Variance Impact = Imp. on Time2 + Imp. on Costs2 + Imp. on Quality2 + Imp. on SSecurity2 + Imp. on Other2 + Proximity2 6 Figura 3. Fórmula de cálculo da média quadrática. Alguns processos quantitativas são simples e diretos, como rolar um dado (Figura ??), mas a maioria en-volve uma complexa simulação de cenários como a Simulação de Monte Carlo. Monte Carlo foi uma alcunha para um projeto ultra-secreto relacionado ao desenho e ao desenvolvimento de armas atômicas criadas pelo matemático John von Neumann (POUNDSTONE, 1993 e VARGAS, 2013). Ele descobriu que um simples modelo de amostras randômicas poderia solucionar certos problemas matemáticos, que não podiam ser solucionados até aquele momento. A simulação se refere, no entanto, a um método pelo qual a distribuição dos resultados possíveis é pro-duzidas através de sucessivos recálculos dos dados do projeto, permitindo o desenvolvimento de múltiplos cenários. Em cada um dos cálculos, novos dados randômicos são usados para representar um processo repetitivo e interativo. A combinação de todos estes resultados cria uma distribuição probabilística dos resultados (Figuras 5 e 6). Exhibit 18 where the variance is a measure of how far a set of numbers is spread out The variance concept is directly related to the dispersion of the different impact groups. If the impact ranges are very wide, the variance will also be high and the difference between the proposed quadratic mean and the traditional arithmetic mean will increase, increasing the risk impact. One example of the impact results is presented in the Exhibit 19. IMPACT TIME IMPACT COST IMPACT QUALITY IMPACT SS OTHER IMPACT PROXIMITY Risk A 3 2 1 1 1 4 Copyright 2014 by Ricardo Viana Vargas. All Rights Reseved Tabela 1. Exemplo dos resultados do impacto e a fórmula de cálculo. Área impactada Tempo Custos Qualidade Proteção e Segurança Outras Proximidade Risco A 3 2 1 1 1 4 Impact = 32 + 22 + 12 + 12 + 12 + 42 6 = 32 6 = 2, 31 Expected Value = Probability x Impact Quadratic Mean2 = Arithmetic Mean2+ Variance Impact = Imp. on Time2 + Imp. on Costs2 + Imp. on Quality2 + Imp. on SSecurity2 + Imp. on Other2 + Proximity2 6 Figura 3. Fórmula de cálculo da média quadrática. Exhibit 19 It is important to highlight that the threats and opportunities can be calculated using the same formula, but with different signals (+ for opportunities and – for threats). The total qualitative risk exposure of the project is determined by the sum of the expected values of all threats and opportunities. An example of this process is presented on the Exhibit 20.
  • 11. ricardo-vargas.com 11 TYPE PROBA-BILITY PROXI-MITY IMPACT TIME IMPACT COST IMPACT QUALITY IMPACT SAFETY AND SECURITY OTHER IMPACTS TOTAL IMPACT EXPECTED VALUE Threat 1 3 2 1 1 1 4 2,31 (2,31) Threat 2 4 4 3 3 4 3 3,54 (7,07) Threat 2 3 5 4 4 5 1 3,92 (7,83) Opportunity 3 2 4 3 5 4 2 3,51 10,54 Opportunity 4 1 3 2 4 3 2 2,68 10,71 Threat 5 2 2 1 3 1 1 1,83 (9,13) Total Risk Expected Value (5,10) Exhibit 20 – Example of a project expected risk value considering opportunities and threats. The results from the process will be always a number between 1 and 25. In the example of Exhibit 20, the value -5,10 is equivalent to 20,4% negative exposure (5,10/25) for the Project. Based on this result and the tolerance thresholds (HILSON MURRAY-WEBSTER, 2007), the total exposure can be compared with other projects and the corporate limits to define potential risk response plans. Conclusions The qualitative risk method is always a simplified model if compared with the quantitative methods. The approach of this paper suggests an alternative model that can be tailored to include different kinds of impacts and scales in order to produce a reliable quantitative result. This result allows opportunities and threats to be compared in order to deter-mine the total risk exposure. The concept that an opportunity can cancel a threat of the same level is not possible with the traditional qualitative risk management approach. References ALTENBACH, T. J. (1995). A Comparison of Risk Assessment Techniques from Quali-tative to Quantitative. Honolulu, ASME Preassure Vessels and Piping Conference. Available at http://www.osti.gov/bridge/servlets/purl/67753-dsZ0vB/webview-able/ 67753.pdf HILSON, D. MURRAY-WEBSTER, R. (2007). Understanding and Managing Risk Atti-tude. London: Gower Publishing. PMI (2013). The Project Management Body of Knowledge: Fifth Edition. Newtown Square: Project Management Institute.
  • 12. 12 Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis POUNDSTONE, W (1993). Prisoner’s Dillema. Flushing: Anchor Publishing Group. PRITCHARD, C. L. (2001). Risk Management: Concepts and Guidance. 2ª Ed. Arling-ton: ESI International. ROSSI, P. (2007). How to link the qualitative and the quantitative risk assessment. Budapest: Project Management Institute Global Congress EMEA. ROT, A. (2008). IT Risk Assessment: Quantitative and Qualitative Approach. San Francisco: World Congress on Engineering and Computer Science. SMOCK, R. (2002). Reducing Subjectivity in Qualitative Risk Assessments. Bethesda, SANS Institute. Available at http://www.giac.org/paper/gsec/2014/reducing-sub-jectivity- qualitative-risk-assessments/103489 VARGAS, R. V. (2013). Determining the Mathematical ROI of a Project Management Implementation. New Orleans, Project Management Institute Global Congress North America. VIRINE, L. (2010). Project Risk Analysis: How Ignoring It Will Lead to Project Failures. Washington: Project Management Institute Global Congress North America.