SlideShare a Scribd company logo
1 of 21
Download to read offline
2014 Construction Law Conference:
Case Law Developments over 2013
Thursday, 6 February 2014

Kathryn Noble, Associate
kathryn.noble@olswang.com | +44 20 7067 3343
Today’s cases
DAMAGES/REMOTENESS OF LOSS
John Grimes Partnership Limited v Gubbins
[2013] EWCA Civ 37
IS A COLLATERAL WARRANTY A CONSTRUCTION CONTRACT?
Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited
[2013] EWHC 2665
DELAYED COMPLETION / BREACH OF SALE AGREEMENT
Urban I (Blonk Street) Limited v Simon Martin Ayres and Nicola Jane Ayres
[2013] EWCA Civ 816
#olswangconstruction

www.constructiveblog.com
John Grimes Partnership v
Gubbins
The case is about:
Developer’s recoverability of a loss in rental value following late completion of a
construction project due to delays caused by a consultant
Principle:
Court of Appeal decision: Engineer was held to be liable for damages having
caused a delay in the completion of a development. By the time of completion,
there had been a drop in the market value of the property and the developer loss
suffered because the property was less valuable than if the development had been
completed on schedule.

#olswangconstruction

www.constructiveblog.com
John Grimes Partnership v
Gubbins
What was agreed:
Mr Gubbins: Land Developer
John Grimes Partnership Limited (JGP): engineering and geological services
Proposed development: development of field for residential purposes (“affordable
dwellings”) - included a road to access the dwellings. The design of the road
required the county council’s approval as it was intended to be adopted by the
highway authority
JGP instructed by Mr Gubbins to design road and drainage for the site and obtain
the council’s approval
Express oral agreement that the works should be completed by March 2007
Parties originally agreed fees of £15,000 to be paid to JGP for the above works

#olswangconstruction

www.constructiveblog.com
John Grimes Partnership v
Gubbins
What actually happened:
The work remained incomplete at March 2007. An initial part-approval was obtained
in February 2008
April 2008: Mr Gubbins engaged Joint Technical Partnership Limited (JTPL) to
carry out the work that JGP should have completed
June 2008: JTPL redesigned the road and drainage layout and submitted it for
council approval, which was provided on 18 June 2008
JGP had received c.£20,000 in fees but issued an invoice for £2,893 and
commenced proceedings following Mr Gubbins’ refusal to pay

#olswangconstruction

www.constructiveblog.com
John Grimes Partnership v
Gubbins
Mr Gubbins’ counterclaim:
= for sums previously paid to JGP + damages for JGP’s failure to complete on time
Damages for:
(i)

reduction in market value of the residential dwellings;

(ii)

reduction in offer from Housing Association; and

(iii)

increase in building costs.

First Instance decision:
Delay was caused by JGP’s breach of contract and this resulted in loss to Mr
Gubbins. This loss was reasonably foreseeable to JGP and JGP was “responsible
for loss flowing from the property market decline”

#olswangconstruction

www.constructiveblog.com
John Grimes Partnership v
Gubbins
Court of Appeal’s decision:
Upheld the first instance decision: JGP liable for damages for losses caused by its
breach of contract and which arose in the context of the decline in property values
Mr Grimes’ losses were not too remote and CA considered there was an implied
responsibility on the parties for reasonably foreseeable losses
CA agreed with Trial Judge that losses arising from movement in the property
market were reasonably foreseeable at the time of contract as a consequence of
delay by JGP
JGP’s delay of 15 months gave rise to a quantifiable loss over a prolonged period
of time
Mr Gubbin’s scale of loss was not disproportionate to the £15,000 fee payable to
JGP

#olswangconstruction

www.constructiveblog.com
John Grimes Partnership v
Gubbins
Practical considerations in light of this case:
•  Considered exclusion/limitation clauses to expressly exclude liability for particular
circumstances or specified events?
•  Demonstrate not responsible for particular types of losses?
•  Losses within the consultant’s control?
•  Losses suffered over a prolonged period of time
•  Increase in claims for damages where property values fall?

#olswangconstruction

www.constructiveblog.com
Parkwood Leisure Limited v
Laing O’Rourke Wales and
West Limited
The case is about:
Mr Justice Akenhead: “In what circumstances a collateral warranty can amount to a
construction contract for the carrying out of construction operations” for the
purposes of the Housing Grants, Construction and Regeneration Act 1996
(Construction Act)
“Construction Contract” under the Construction Act = subject to statutory
adjudication rules!
Principle:
Surprise result: The collateral warranty in this case was deemed a contract for the
carrying out of construction operations and therefore fell within the Construction Act

#olswangconstruction

www.constructiveblog.com
Parkwood Leisure Limited v
Laing O’Rourke Wales and
West Limited
The facts:
April 2006: Laing O’Rourke Wales and West Limited entered into a contract as
contractor to design and build a swimming and leisure facility in Cardiff
Around April 2006: Parkwood entered into an Agreement for Lease for the facility
December 2007: Laing O’Rourke entered into a deed of warranty in favour of
Parkwood
January 2008: Parkwood Leisure Limited took a ten year lease of the property
Practical Completion was achieved in 2008
Parkwood took occupation and various Construction and commissioning defects
were complained of once the facility had been opened to the public
Parkwood issued a Pre-Action Protocol Letter of Claim in February 2011

#olswangconstruction

www.constructiveblog.com
Parkwood Leisure Limited v
Laing O’Rourke Wales and
West Limited
What the Court considered:
Parkwood sought a declaration that the collateral warranty fell within the remit of
the Construction Act for the purpose of bringing adjudication proceedings against
Laing
The wording of the collateral warranty:
Laing “warrants, acknowledges and undertakes that it has carried out and shall
carry out and complete the Works in accordance with the Contract..”
Did the warranty amount to the carrying out of “construction operations”?

#olswangconstruction

www.constructiveblog.com
Parkwood Leisure Limited v
Laing O’Rourke Wales and
West Limited
Court’s decision:
The collateral warranty was a contract for the carrying out of construction
operations and therefore was a Construction Contract for the purposes of the
Construction Act
•  Warranty recognised works were yet to be completed under the contract
•  Warranty expressly related to the design, carrying out and completion of the
construction of a pool development
•  Warranty was not “merely warranting or guaranteeing a past state of affairs”
BUT…

#olswangconstruction

www.constructiveblog.com
Parkwood Leisure Limited v
Laing O’Rourke Wales and
West Limited
Not all collateral warranties are construction contracts:
Court’s relevant factors include:
•  Wording of the document and factual background
•  Is the contractor “undertaking to the beneficiary of the warranty to carry out
operations”?
•  Have “all the works completed and the contractor simply warranting a past state
of affairs as reaching a certain level, quality or standard”?

#olswangconstruction

www.constructiveblog.com
Parkwood Leisure Limited v
Laing O’Rourke Wales and
West Limited
Practical considerations in light of this case:
•  Third Party Rights v collateral warranties
•  Not all collateral warranties are construction contracts
•  Timing of warranties
•  Increase in claims under collateral warranties being referred to adjudication
•  What about payment/suspension rights that are implied into a Construction
Contract?
•  Limitation of warranties entered into?
•  NB the position on settlement agreements

#olswangconstruction

www.constructiveblog.com
Urban I (Blonk Street) Limited v
Simon Martin Ayres & Nicola
Jane Ayres
The case is about:
The consequences of time being (or not being) of the essence in contracts for sale
of land (particularly where a purchase is mortgage funded)
Notices to complete in circumstances where there has been delay in complying with
the terms of the contract for sale

Principle:
The delay in completing a new build apartment caused by the developer did not
entitle the buyer to terminate the agreement between the parties as the buyer was
not substantially deprived of the whole benefit of the contract for the lease of the
apartment.

#olswangconstruction

www.constructiveblog.com
Urban I (Blonk Street) Limited v
Simon Martin Ayres & Nicola
Jane Ayres
The contract:
25 January 2007: Contract between Urban I (Developer) and Mr & Mrs Ayres for
the purchase of the leasehold of a flat in a mixed commercial and residential
development in Blonk Street, Sheffield
The contract did not specify a fixed completion date but did provide that the
Developer would issue to the buyers a written notice once the development had
completed
Contract provided that a Notice to Complete may be issued by either party at any
time after the completion date and the contract would be completed within ten
working days of the notice. The contract added: “For this purpose, time is of the
essence”
Developer was obliged to take all reasonable steps to prevent any delay arising

#olswangconstruction

www.constructiveblog.com
Urban I (Blonk Street) Limited v
Simon Martin Ayres & Nicola
Jane Ayres
What happened:
The Developer aimed to start the development on 26 February 2007 and complete
in December 2008
The development started late (March 2007) and quickly fell further behind schedule
after a series of delays
June 2008: Mr & Mrs Ayres were advised that completion would be in December
2008
September 2008: Mr & Mrs Ayres received a mortgage offer of 90% of the
purchase price of the flat (subject to conditions - the mortgage had to be
commenced by 31 December 2008)
October 2008: Buyers were advised that the flat would be completed in February
2009
November/December 2008: Mr & Mrs Ayres lost their 90% mortgage offer
#olswangconstruction

www.constructiveblog.com
Urban I (Blonk Street) Limited v
Simon Martin Ayres & Nicola
Jane Ayres
What happened next:
January/February 2009: on-going delays with the development but the Developer
thought it may be finished by May 2009
March 2009: Mr & Mrs Ayres terminated the contract on grounds of unreasonable
delay and stated:
•  there had been breach of an implied term that the completion would take place
within a reasonable time
•  the anticipated completion date had been December 2008
•  they had lost their 90% mortgage offer and the decline in property values resulted
in them not being able to obtain another like product
•  the Developer was in repudiatory breach of the contract and they requested
repayment of their deposit plus interest
July 2009: the development completed and the Developer served a notice to
complete in September 2009
#olswangconstruction

www.constructiveblog.com
Urban I (Blonk Street) Limited v
Simon Martin Ayres & Nicola
Jane Ayres
The Claim:
August 2011: The Developer issued a claim for specific performance of the contract
and/or damages for late completion, interest and costs.
August 2011: Mr & Mrs Ayres served a Defence that the Developer had repudiated
the contract and that they had successfully terminated. They served a counterclaim
for their reservation fee/deposit, plus other costs (including legal fees).
First Instance decision:
It was implied that the development would be completed within a reasonable time
The delays to the development overall amounted to a repudiation of the contract
and Mr & Mrs Ayres were entitled to refuse to complete having been served with
the notice to complete by the Developer in September 2009

#olswangconstruction

www.constructiveblog.com
Urban I (Blonk Street) Limited v
Simon Martin Ayres & Nicola
Jane Ayres
Court of Appeal:
Agreed with the First Instance trial that it was an implied term that completion of the
development and the contract was to be within a reasonable time. What is
reasonable? “A mixed question of fact and law”…
Allowed the Developer’s appeal = a “severe disappointment” to Mr & Mrs Ayres
•  The Developer’s breach of contract did not cause Mr & Mrs Ayres’ unfortunate
financial position
•  The contract did not have a fixed long-stop date for construction of their
apartment
•  Contract did not expressly provide for the buyers to cancel the contract if the
building was not handed over by a specified date
•  The delay did not cause Mr & Mrs Ayres to lose substantially the whole benefit of
the contract.
#olswangconstruction

www.constructiveblog.com
Urban I (Blonk Street) Limited v
Simon Martin Ayres & Nicola
Jane Ayres
Practical considerations in light of this case:
•  Buyers’ risks where financing a purchase by way of mortgage
•  Consideration of what is a reasonable time for completion of construction where
the contract does not specify a date for completion
•  Meaning of substantially depriving a party of the whole of the benefit of a contract
•  Provisions relating to timing in contracts
•  When a repudiatory breach will be considered to have occurred

#olswangconstruction

www.constructiveblog.com

More Related Content

Viewers also liked

Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction ContractsFrancis Ho
 
Study Of Human Physiology Dr Shriniwas Kashalikar
Study Of Human Physiology Dr Shriniwas KashalikarStudy Of Human Physiology Dr Shriniwas Kashalikar
Study Of Human Physiology Dr Shriniwas Kashalikarshriniwaskashalikar
 
N E W S T U D Y O F G I T A N O V 9 D R
N E W  S T U D Y  O F  G I T A  N O V 9   D RN E W  S T U D Y  O F  G I T A  N O V 9   D R
N E W S T U D Y O F G I T A N O V 9 D Rshriniwaskashalikar
 
Berpikir Kreatif I
Berpikir Kreatif IBerpikir Kreatif I
Berpikir Kreatif Iguest361b2c
 
R E M E D I E S I F O U N D U S E F U L I N J O I N T P A I N S D R S...
R E M E D I E S  I  F O U N D  U S E F U L  I N  J O I N T  P A I N S  D R  S...R E M E D I E S  I  F O U N D  U S E F U L  I N  J O I N T  P A I N S  D R  S...
R E M E D I E S I F O U N D U S E F U L I N J O I N T P A I N S D R S...shriniwaskashalikar
 
150411政策分析ネットワーク シェア
150411政策分析ネットワーク シェア150411政策分析ネットワーク シェア
150411政策分析ネットワーク シェア河井 孝仁
 
S H R I L A X M I N A R A Y A N D R
S H R I  L A X M I  N A R A Y A N  D RS H R I  L A X M I  N A R A Y A N  D R
S H R I L A X M I N A R A Y A N D Rshriniwaskashalikar
 
Why, What, and of How Marketing Measurement
Why, What, and of How Marketing MeasurementWhy, What, and of How Marketing Measurement
Why, What, and of How Marketing MeasurementKathy Herrmann
 
Bibliotecas universitarias tendencias_mo
Bibliotecas universitarias tendencias_moBibliotecas universitarias tendencias_mo
Bibliotecas universitarias tendencias_moPaula Saraiva
 
Webinar: The Power of Normalized Inventory
Webinar: The Power of Normalized InventoryWebinar: The Power of Normalized Inventory
Webinar: The Power of Normalized InventoryFlexera
 
顧客満足度の向上、顧客情報の取得、電子ソフトウェア更新を通じた顧客とのつながり、アプリ ケーション内メッセージおよび詳細レポート
顧客満足度の向上、顧客情報の取得、電子ソフトウェア更新を通じた顧客とのつながり、アプリ ケーション内メッセージおよび詳細レポート顧客満足度の向上、顧客情報の取得、電子ソフトウェア更新を通じた顧客とのつながり、アプリ ケーション内メッセージおよび詳細レポート
顧客満足度の向上、顧客情報の取得、電子ソフトウェア更新を通じた顧客とのつながり、アプリ ケーション内メッセージおよび詳細レポートFlexera
 

Viewers also liked (20)

Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction Contracts
 
Study Of Human Physiology Dr Shriniwas Kashalikar
Study Of Human Physiology Dr Shriniwas KashalikarStudy Of Human Physiology Dr Shriniwas Kashalikar
Study Of Human Physiology Dr Shriniwas Kashalikar
 
為人的藝術
為人的藝術為人的藝術
為人的藝術
 
N E W S T U D Y O F G I T A N O V 9 D R
N E W  S T U D Y  O F  G I T A  N O V 9   D RN E W  S T U D Y  O F  G I T A  N O V 9   D R
N E W S T U D Y O F G I T A N O V 9 D R
 
Belchfire Torch Seo Ranking Report
Belchfire Torch Seo Ranking ReportBelchfire Torch Seo Ranking Report
Belchfire Torch Seo Ranking Report
 
Splinternetmarketing Keyword Rankings 3 5 2011 Vs 3 28 2011
Splinternetmarketing Keyword Rankings 3 5 2011 Vs 3 28 2011Splinternetmarketing Keyword Rankings 3 5 2011 Vs 3 28 2011
Splinternetmarketing Keyword Rankings 3 5 2011 Vs 3 28 2011
 
Berpikir Kreatif I
Berpikir Kreatif IBerpikir Kreatif I
Berpikir Kreatif I
 
Superliving Dr
Superliving  DrSuperliving  Dr
Superliving Dr
 
R E M E D I E S I F O U N D U S E F U L I N J O I N T P A I N S D R S...
R E M E D I E S  I  F O U N D  U S E F U L  I N  J O I N T  P A I N S  D R  S...R E M E D I E S  I  F O U N D  U S E F U L  I N  J O I N T  P A I N S  D R  S...
R E M E D I E S I F O U N D U S E F U L I N J O I N T P A I N S D R S...
 
Understanding
UnderstandingUnderstanding
Understanding
 
Telling your story
Telling your story Telling your story
Telling your story
 
150411政策分析ネットワーク シェア
150411政策分析ネットワーク シェア150411政策分析ネットワーク シェア
150411政策分析ネットワーク シェア
 
S H R I L A X M I N A R A Y A N D R
S H R I  L A X M I  N A R A Y A N  D RS H R I  L A X M I  N A R A Y A N  D R
S H R I L A X M I N A R A Y A N D R
 
Local Search Seo Ranking Report
Local Search Seo Ranking ReportLocal Search Seo Ranking Report
Local Search Seo Ranking Report
 
Prezentimi
Prezentimi Prezentimi
Prezentimi
 
P R O P G A G A N D A D R
P R O P G A G A N D A  D RP R O P G A G A N D A  D R
P R O P G A G A N D A D R
 
Why, What, and of How Marketing Measurement
Why, What, and of How Marketing MeasurementWhy, What, and of How Marketing Measurement
Why, What, and of How Marketing Measurement
 
Bibliotecas universitarias tendencias_mo
Bibliotecas universitarias tendencias_moBibliotecas universitarias tendencias_mo
Bibliotecas universitarias tendencias_mo
 
Webinar: The Power of Normalized Inventory
Webinar: The Power of Normalized InventoryWebinar: The Power of Normalized Inventory
Webinar: The Power of Normalized Inventory
 
顧客満足度の向上、顧客情報の取得、電子ソフトウェア更新を通じた顧客とのつながり、アプリ ケーション内メッセージおよび詳細レポート
顧客満足度の向上、顧客情報の取得、電子ソフトウェア更新を通じた顧客とのつながり、アプリ ケーション内メッセージおよび詳細レポート顧客満足度の向上、顧客情報の取得、電子ソフトウェア更新を通じた顧客とのつながり、アプリ ケーション内メッセージおよび詳細レポート
顧客満足度の向上、顧客情報の取得、電子ソフトウェア更新を通じた顧客とのつながり、アプリ ケーション内メッセージおよび詳細レポート
 

Similar to Recent Case Law Developments - 2014 Olswang Construction Law Conference

Playing Nice with the Neighbors Dealing with Adjoining Properties During Cons...
Playing Nice with the Neighbors Dealing with Adjoining Properties During Cons...Playing Nice with the Neighbors Dealing with Adjoining Properties During Cons...
Playing Nice with the Neighbors Dealing with Adjoining Properties During Cons...Ryan Slack
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterSeanGibbs12
 
Planning Review 2009
Planning Review 2009Planning Review 2009
Planning Review 2009Graham Gover
 
Project ppt riverside condo
Project ppt riverside condoProject ppt riverside condo
Project ppt riverside condoSAIFULLAH MAHMUD
 
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Alec Rendell [NBPR-2]
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceFrancis Ho
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptNesrElhandasa1
 
March 2015 presentation to ASBC on slab heave and damages
March 2015 presentation to ASBC on slab heave and damagesMarch 2015 presentation to ASBC on slab heave and damages
March 2015 presentation to ASBC on slab heave and damagesAndrew Downie
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterSeanGibbs12
 
Obtaining Title Insurance on Construction Loans: Avoiding Pitfalls Regarding ...
Obtaining Title Insurance on Construction Loans: Avoiding Pitfalls Regarding ...Obtaining Title Insurance on Construction Loans: Avoiding Pitfalls Regarding ...
Obtaining Title Insurance on Construction Loans: Avoiding Pitfalls Regarding ...Bradley Arant Boult Cummings LLP
 
UKA Newsletter Apr 2022.pdf
UKA Newsletter Apr 2022.pdfUKA Newsletter Apr 2022.pdf
UKA Newsletter Apr 2022.pdfSeanGibbs12
 
Building contract introduction
Building contract  introductionBuilding contract  introduction
Building contract introductionHafizul Mukhlis
 

Similar to Recent Case Law Developments - 2014 Olswang Construction Law Conference (20)

Playing Nice with the Neighbors Dealing with Adjoining Properties During Cons...
Playing Nice with the Neighbors Dealing with Adjoining Properties During Cons...Playing Nice with the Neighbors Dealing with Adjoining Properties During Cons...
Playing Nice with the Neighbors Dealing with Adjoining Properties During Cons...
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 
Planning Review 2009
Planning Review 2009Planning Review 2009
Planning Review 2009
 
Project ppt riverside condo
Project ppt riverside condoProject ppt riverside condo
Project ppt riverside condo
 
Dispute resolution & dispute avoidance
Dispute resolution & dispute avoidanceDispute resolution & dispute avoidance
Dispute resolution & dispute avoidance
 
Recent NEC3 Case Review and its Application
Recent NEC3 Case Review and its ApplicationRecent NEC3 Case Review and its Application
Recent NEC3 Case Review and its Application
 
UK Adjudicators December 2019 Newsletter
UK Adjudicators December 2019 NewsletterUK Adjudicators December 2019 Newsletter
UK Adjudicators December 2019 Newsletter
 
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
 
UK Adjudicators September 2021 Newsletter
UK Adjudicators  September 2021 Newsletter UK Adjudicators  September 2021 Newsletter
UK Adjudicators September 2021 Newsletter
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
March 2015 presentation to ASBC on slab heave and damages
March 2015 presentation to ASBC on slab heave and damagesMarch 2015 presentation to ASBC on slab heave and damages
March 2015 presentation to ASBC on slab heave and damages
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 Newsletter
 
2019 Edinburgh Adjudication & Arbitration Conference Slides
2019 Edinburgh Adjudication & Arbitration Conference Slides2019 Edinburgh Adjudication & Arbitration Conference Slides
2019 Edinburgh Adjudication & Arbitration Conference Slides
 
Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 
Obtaining Title Insurance on Construction Loans: Avoiding Pitfalls Regarding ...
Obtaining Title Insurance on Construction Loans: Avoiding Pitfalls Regarding ...Obtaining Title Insurance on Construction Loans: Avoiding Pitfalls Regarding ...
Obtaining Title Insurance on Construction Loans: Avoiding Pitfalls Regarding ...
 
UKA Newsletter Apr 2022.pdf
UKA Newsletter Apr 2022.pdfUKA Newsletter Apr 2022.pdf
UKA Newsletter Apr 2022.pdf
 
Building contract introduction
Building contract  introductionBuilding contract  introduction
Building contract introduction
 
UKA Newsletter May 2022.pdf
UKA Newsletter May 2022.pdfUKA Newsletter May 2022.pdf
UKA Newsletter May 2022.pdf
 

More from Francis Ho

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the PlanetFrancis Ho
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...Francis Ho
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...Francis Ho
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?Francis Ho
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Francis Ho
 
Construction Insolvency
Construction InsolvencyConstruction Insolvency
Construction InsolvencyFrancis Ho
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex ContractsFrancis Ho
 
Key Developments in Emerging Markets
Key Developments in Emerging MarketsKey Developments in Emerging Markets
Key Developments in Emerging MarketsFrancis Ho
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyFrancis Ho
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsFrancis Ho
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsFrancis Ho
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKFrancis Ho
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceFrancis Ho
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They MatterFrancis Ho
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015Francis Ho
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketFrancis Ho
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of IntentFrancis Ho
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsFrancis Ho
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryFrancis Ho
 

More from Francis Ho (20)

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the Planet
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
 
Construction Insolvency
Construction InsolvencyConstruction Insolvency
Construction Insolvency
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex Contracts
 
Key Developments in Emerging Markets
Key Developments in Emerging MarketsKey Developments in Emerging Markets
Key Developments in Emerging Markets
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and Tactics
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UK
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects Insurance
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They Matter
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom Market
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of Intent
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party Rights
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction Industry
 

Recently uploaded

Shapoorji Pallonji Parkwest Sequoia Tower Bangalore.pdf
Shapoorji Pallonji Parkwest Sequoia Tower Bangalore.pdfShapoorji Pallonji Parkwest Sequoia Tower Bangalore.pdf
Shapoorji Pallonji Parkwest Sequoia Tower Bangalore.pdfashiyadav24
 
Cashpay_Call Girls In Gaur City Mall Noida ❤️8860477959 Escorts Service In 24...
Cashpay_Call Girls In Gaur City Mall Noida ❤️8860477959 Escorts Service In 24...Cashpay_Call Girls In Gaur City Mall Noida ❤️8860477959 Escorts Service In 24...
Cashpay_Call Girls In Gaur City Mall Noida ❤️8860477959 Escorts Service In 24...lizamodels9
 
Nanke Area Estate commercial ( Dir. Kat Kuo)
Nanke Area Estate commercial ( Dir. Kat Kuo)Nanke Area Estate commercial ( Dir. Kat Kuo)
Nanke Area Estate commercial ( Dir. Kat Kuo)jessica288382
 
Partner With the Golden Life Community for Single Women Over 55
Partner With the Golden Life Community for Single Women Over 55Partner With the Golden Life Community for Single Women Over 55
Partner With the Golden Life Community for Single Women Over 55Ron Surz
 
Managed Farmland Brochures to get more in
Managed Farmland Brochures to get more inManaged Farmland Brochures to get more in
Managed Farmland Brochures to get more inknoxdigital1
 
Brigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- BrochureBrigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- Brochurefaheemali990101
 
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai  E-Brochure.pdfAjmera Prive at Juhu, Mumbai  E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai E-Brochure.pdfManishSaxena95
 
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxLCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxTom Blefko
 
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...lizamodels9
 
Call Girls In Sahibabad Ghaziabad ❤️8860477959 Low Rate Escorts Service In 24...
Call Girls In Sahibabad Ghaziabad ❤️8860477959 Low Rate Escorts Service In 24...Call Girls In Sahibabad Ghaziabad ❤️8860477959 Low Rate Escorts Service In 24...
Call Girls In Sahibabad Ghaziabad ❤️8860477959 Low Rate Escorts Service In 24...lizamodels9
 
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfExperion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfkratirudram
 
83770-87607 ۞Call Girls In Near The Park Hotel (Cp) Delhi
83770-87607 ۞Call Girls In Near The Park Hotel (Cp) Delhi83770-87607 ۞Call Girls In Near The Park Hotel (Cp) Delhi
83770-87607 ۞Call Girls In Near The Park Hotel (Cp) Delhidollysharma2066
 
Dynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft
 
Call Girls in Khan Market 9654467111 ESCORTS SERVICE
Call Girls in Khan Market 9654467111 ESCORTS SERVICECall Girls in Khan Market 9654467111 ESCORTS SERVICE
Call Girls in Khan Market 9654467111 ESCORTS SERVICESapana Sha
 
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdfRustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdfmonikasharma630
 
Call Girls In The Lalit New Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In The Lalit New Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...Call Girls In The Lalit New Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In The Lalit New Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...lizamodels9
 
Call Girls In Vasundhara Ghaziabad ❤️8860477959 Low Rate Escorts Service In 2...
Call Girls In Vasundhara Ghaziabad ❤️8860477959 Low Rate Escorts Service In 2...Call Girls In Vasundhara Ghaziabad ❤️8860477959 Low Rate Escorts Service In 2...
Call Girls In Vasundhara Ghaziabad ❤️8860477959 Low Rate Escorts Service In 2...lizamodels9
 

Recently uploaded (20)

Shapoorji Pallonji Parkwest Sequoia Tower Bangalore.pdf
Shapoorji Pallonji Parkwest Sequoia Tower Bangalore.pdfShapoorji Pallonji Parkwest Sequoia Tower Bangalore.pdf
Shapoorji Pallonji Parkwest Sequoia Tower Bangalore.pdf
 
Cashpay_Call Girls In Gaur City Mall Noida ❤️8860477959 Escorts Service In 24...
Cashpay_Call Girls In Gaur City Mall Noida ❤️8860477959 Escorts Service In 24...Cashpay_Call Girls In Gaur City Mall Noida ❤️8860477959 Escorts Service In 24...
Cashpay_Call Girls In Gaur City Mall Noida ❤️8860477959 Escorts Service In 24...
 
young call girls in Lajpat Nagar,🔝 9953056974 🔝 escort Service
young call girls in Lajpat Nagar,🔝 9953056974 🔝 escort Serviceyoung call girls in Lajpat Nagar,🔝 9953056974 🔝 escort Service
young call girls in Lajpat Nagar,🔝 9953056974 🔝 escort Service
 
Nanke Area Estate commercial ( Dir. Kat Kuo)
Nanke Area Estate commercial ( Dir. Kat Kuo)Nanke Area Estate commercial ( Dir. Kat Kuo)
Nanke Area Estate commercial ( Dir. Kat Kuo)
 
Partner With the Golden Life Community for Single Women Over 55
Partner With the Golden Life Community for Single Women Over 55Partner With the Golden Life Community for Single Women Over 55
Partner With the Golden Life Community for Single Women Over 55
 
Hot call girls in Moti Bagh🔝 9953056974 🔝 escort Service
Hot call girls in Moti Bagh🔝 9953056974 🔝 escort ServiceHot call girls in Moti Bagh🔝 9953056974 🔝 escort Service
Hot call girls in Moti Bagh🔝 9953056974 🔝 escort Service
 
Managed Farmland Brochures to get more in
Managed Farmland Brochures to get more inManaged Farmland Brochures to get more in
Managed Farmland Brochures to get more in
 
Brigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- BrochureBrigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- Brochure
 
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai  E-Brochure.pdfAjmera Prive at Juhu, Mumbai  E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
 
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxLCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
 
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
 
9953056974 Low Rate Call Girls In Saket, Delhi NCR
9953056974 Low Rate Call Girls In Saket, Delhi NCR9953056974 Low Rate Call Girls In Saket, Delhi NCR
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls In Sahibabad Ghaziabad ❤️8860477959 Low Rate Escorts Service In 24...
Call Girls In Sahibabad Ghaziabad ❤️8860477959 Low Rate Escorts Service In 24...Call Girls In Sahibabad Ghaziabad ❤️8860477959 Low Rate Escorts Service In 24...
Call Girls In Sahibabad Ghaziabad ❤️8860477959 Low Rate Escorts Service In 24...
 
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfExperion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
 
83770-87607 ۞Call Girls In Near The Park Hotel (Cp) Delhi
83770-87607 ۞Call Girls In Near The Park Hotel (Cp) Delhi83770-87607 ۞Call Girls In Near The Park Hotel (Cp) Delhi
83770-87607 ۞Call Girls In Near The Park Hotel (Cp) Delhi
 
Dynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management Software
 
Call Girls in Khan Market 9654467111 ESCORTS SERVICE
Call Girls in Khan Market 9654467111 ESCORTS SERVICECall Girls in Khan Market 9654467111 ESCORTS SERVICE
Call Girls in Khan Market 9654467111 ESCORTS SERVICE
 
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdfRustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
 
Call Girls In The Lalit New Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In The Lalit New Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...Call Girls In The Lalit New Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In The Lalit New Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
 
Call Girls In Vasundhara Ghaziabad ❤️8860477959 Low Rate Escorts Service In 2...
Call Girls In Vasundhara Ghaziabad ❤️8860477959 Low Rate Escorts Service In 2...Call Girls In Vasundhara Ghaziabad ❤️8860477959 Low Rate Escorts Service In 2...
Call Girls In Vasundhara Ghaziabad ❤️8860477959 Low Rate Escorts Service In 2...
 

Recent Case Law Developments - 2014 Olswang Construction Law Conference

  • 1. 2014 Construction Law Conference: Case Law Developments over 2013 Thursday, 6 February 2014 Kathryn Noble, Associate kathryn.noble@olswang.com | +44 20 7067 3343
  • 2. Today’s cases DAMAGES/REMOTENESS OF LOSS John Grimes Partnership Limited v Gubbins [2013] EWCA Civ 37 IS A COLLATERAL WARRANTY A CONSTRUCTION CONTRACT? Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited [2013] EWHC 2665 DELAYED COMPLETION / BREACH OF SALE AGREEMENT Urban I (Blonk Street) Limited v Simon Martin Ayres and Nicola Jane Ayres [2013] EWCA Civ 816 #olswangconstruction www.constructiveblog.com
  • 3. John Grimes Partnership v Gubbins The case is about: Developer’s recoverability of a loss in rental value following late completion of a construction project due to delays caused by a consultant Principle: Court of Appeal decision: Engineer was held to be liable for damages having caused a delay in the completion of a development. By the time of completion, there had been a drop in the market value of the property and the developer loss suffered because the property was less valuable than if the development had been completed on schedule. #olswangconstruction www.constructiveblog.com
  • 4. John Grimes Partnership v Gubbins What was agreed: Mr Gubbins: Land Developer John Grimes Partnership Limited (JGP): engineering and geological services Proposed development: development of field for residential purposes (“affordable dwellings”) - included a road to access the dwellings. The design of the road required the county council’s approval as it was intended to be adopted by the highway authority JGP instructed by Mr Gubbins to design road and drainage for the site and obtain the council’s approval Express oral agreement that the works should be completed by March 2007 Parties originally agreed fees of £15,000 to be paid to JGP for the above works #olswangconstruction www.constructiveblog.com
  • 5. John Grimes Partnership v Gubbins What actually happened: The work remained incomplete at March 2007. An initial part-approval was obtained in February 2008 April 2008: Mr Gubbins engaged Joint Technical Partnership Limited (JTPL) to carry out the work that JGP should have completed June 2008: JTPL redesigned the road and drainage layout and submitted it for council approval, which was provided on 18 June 2008 JGP had received c.£20,000 in fees but issued an invoice for £2,893 and commenced proceedings following Mr Gubbins’ refusal to pay #olswangconstruction www.constructiveblog.com
  • 6. John Grimes Partnership v Gubbins Mr Gubbins’ counterclaim: = for sums previously paid to JGP + damages for JGP’s failure to complete on time Damages for: (i) reduction in market value of the residential dwellings; (ii) reduction in offer from Housing Association; and (iii) increase in building costs. First Instance decision: Delay was caused by JGP’s breach of contract and this resulted in loss to Mr Gubbins. This loss was reasonably foreseeable to JGP and JGP was “responsible for loss flowing from the property market decline” #olswangconstruction www.constructiveblog.com
  • 7. John Grimes Partnership v Gubbins Court of Appeal’s decision: Upheld the first instance decision: JGP liable for damages for losses caused by its breach of contract and which arose in the context of the decline in property values Mr Grimes’ losses were not too remote and CA considered there was an implied responsibility on the parties for reasonably foreseeable losses CA agreed with Trial Judge that losses arising from movement in the property market were reasonably foreseeable at the time of contract as a consequence of delay by JGP JGP’s delay of 15 months gave rise to a quantifiable loss over a prolonged period of time Mr Gubbin’s scale of loss was not disproportionate to the £15,000 fee payable to JGP #olswangconstruction www.constructiveblog.com
  • 8. John Grimes Partnership v Gubbins Practical considerations in light of this case: •  Considered exclusion/limitation clauses to expressly exclude liability for particular circumstances or specified events? •  Demonstrate not responsible for particular types of losses? •  Losses within the consultant’s control? •  Losses suffered over a prolonged period of time •  Increase in claims for damages where property values fall? #olswangconstruction www.constructiveblog.com
  • 9. Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited The case is about: Mr Justice Akenhead: “In what circumstances a collateral warranty can amount to a construction contract for the carrying out of construction operations” for the purposes of the Housing Grants, Construction and Regeneration Act 1996 (Construction Act) “Construction Contract” under the Construction Act = subject to statutory adjudication rules! Principle: Surprise result: The collateral warranty in this case was deemed a contract for the carrying out of construction operations and therefore fell within the Construction Act #olswangconstruction www.constructiveblog.com
  • 10. Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited The facts: April 2006: Laing O’Rourke Wales and West Limited entered into a contract as contractor to design and build a swimming and leisure facility in Cardiff Around April 2006: Parkwood entered into an Agreement for Lease for the facility December 2007: Laing O’Rourke entered into a deed of warranty in favour of Parkwood January 2008: Parkwood Leisure Limited took a ten year lease of the property Practical Completion was achieved in 2008 Parkwood took occupation and various Construction and commissioning defects were complained of once the facility had been opened to the public Parkwood issued a Pre-Action Protocol Letter of Claim in February 2011 #olswangconstruction www.constructiveblog.com
  • 11. Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited What the Court considered: Parkwood sought a declaration that the collateral warranty fell within the remit of the Construction Act for the purpose of bringing adjudication proceedings against Laing The wording of the collateral warranty: Laing “warrants, acknowledges and undertakes that it has carried out and shall carry out and complete the Works in accordance with the Contract..” Did the warranty amount to the carrying out of “construction operations”? #olswangconstruction www.constructiveblog.com
  • 12. Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited Court’s decision: The collateral warranty was a contract for the carrying out of construction operations and therefore was a Construction Contract for the purposes of the Construction Act •  Warranty recognised works were yet to be completed under the contract •  Warranty expressly related to the design, carrying out and completion of the construction of a pool development •  Warranty was not “merely warranting or guaranteeing a past state of affairs” BUT… #olswangconstruction www.constructiveblog.com
  • 13. Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited Not all collateral warranties are construction contracts: Court’s relevant factors include: •  Wording of the document and factual background •  Is the contractor “undertaking to the beneficiary of the warranty to carry out operations”? •  Have “all the works completed and the contractor simply warranting a past state of affairs as reaching a certain level, quality or standard”? #olswangconstruction www.constructiveblog.com
  • 14. Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited Practical considerations in light of this case: •  Third Party Rights v collateral warranties •  Not all collateral warranties are construction contracts •  Timing of warranties •  Increase in claims under collateral warranties being referred to adjudication •  What about payment/suspension rights that are implied into a Construction Contract? •  Limitation of warranties entered into? •  NB the position on settlement agreements #olswangconstruction www.constructiveblog.com
  • 15. Urban I (Blonk Street) Limited v Simon Martin Ayres & Nicola Jane Ayres The case is about: The consequences of time being (or not being) of the essence in contracts for sale of land (particularly where a purchase is mortgage funded) Notices to complete in circumstances where there has been delay in complying with the terms of the contract for sale Principle: The delay in completing a new build apartment caused by the developer did not entitle the buyer to terminate the agreement between the parties as the buyer was not substantially deprived of the whole benefit of the contract for the lease of the apartment. #olswangconstruction www.constructiveblog.com
  • 16. Urban I (Blonk Street) Limited v Simon Martin Ayres & Nicola Jane Ayres The contract: 25 January 2007: Contract between Urban I (Developer) and Mr & Mrs Ayres for the purchase of the leasehold of a flat in a mixed commercial and residential development in Blonk Street, Sheffield The contract did not specify a fixed completion date but did provide that the Developer would issue to the buyers a written notice once the development had completed Contract provided that a Notice to Complete may be issued by either party at any time after the completion date and the contract would be completed within ten working days of the notice. The contract added: “For this purpose, time is of the essence” Developer was obliged to take all reasonable steps to prevent any delay arising #olswangconstruction www.constructiveblog.com
  • 17. Urban I (Blonk Street) Limited v Simon Martin Ayres & Nicola Jane Ayres What happened: The Developer aimed to start the development on 26 February 2007 and complete in December 2008 The development started late (March 2007) and quickly fell further behind schedule after a series of delays June 2008: Mr & Mrs Ayres were advised that completion would be in December 2008 September 2008: Mr & Mrs Ayres received a mortgage offer of 90% of the purchase price of the flat (subject to conditions - the mortgage had to be commenced by 31 December 2008) October 2008: Buyers were advised that the flat would be completed in February 2009 November/December 2008: Mr & Mrs Ayres lost their 90% mortgage offer #olswangconstruction www.constructiveblog.com
  • 18. Urban I (Blonk Street) Limited v Simon Martin Ayres & Nicola Jane Ayres What happened next: January/February 2009: on-going delays with the development but the Developer thought it may be finished by May 2009 March 2009: Mr & Mrs Ayres terminated the contract on grounds of unreasonable delay and stated: •  there had been breach of an implied term that the completion would take place within a reasonable time •  the anticipated completion date had been December 2008 •  they had lost their 90% mortgage offer and the decline in property values resulted in them not being able to obtain another like product •  the Developer was in repudiatory breach of the contract and they requested repayment of their deposit plus interest July 2009: the development completed and the Developer served a notice to complete in September 2009 #olswangconstruction www.constructiveblog.com
  • 19. Urban I (Blonk Street) Limited v Simon Martin Ayres & Nicola Jane Ayres The Claim: August 2011: The Developer issued a claim for specific performance of the contract and/or damages for late completion, interest and costs. August 2011: Mr & Mrs Ayres served a Defence that the Developer had repudiated the contract and that they had successfully terminated. They served a counterclaim for their reservation fee/deposit, plus other costs (including legal fees). First Instance decision: It was implied that the development would be completed within a reasonable time The delays to the development overall amounted to a repudiation of the contract and Mr & Mrs Ayres were entitled to refuse to complete having been served with the notice to complete by the Developer in September 2009 #olswangconstruction www.constructiveblog.com
  • 20. Urban I (Blonk Street) Limited v Simon Martin Ayres & Nicola Jane Ayres Court of Appeal: Agreed with the First Instance trial that it was an implied term that completion of the development and the contract was to be within a reasonable time. What is reasonable? “A mixed question of fact and law”… Allowed the Developer’s appeal = a “severe disappointment” to Mr & Mrs Ayres •  The Developer’s breach of contract did not cause Mr & Mrs Ayres’ unfortunate financial position •  The contract did not have a fixed long-stop date for construction of their apartment •  Contract did not expressly provide for the buyers to cancel the contract if the building was not handed over by a specified date •  The delay did not cause Mr & Mrs Ayres to lose substantially the whole benefit of the contract. #olswangconstruction www.constructiveblog.com
  • 21. Urban I (Blonk Street) Limited v Simon Martin Ayres & Nicola Jane Ayres Practical considerations in light of this case: •  Buyers’ risks where financing a purchase by way of mortgage •  Consideration of what is a reasonable time for completion of construction where the contract does not specify a date for completion •  Meaning of substantially depriving a party of the whole of the benefit of a contract •  Provisions relating to timing in contracts •  When a repudiatory breach will be considered to have occurred #olswangconstruction www.constructiveblog.com