SlideShare a Scribd company logo
1 of 29
ENVIRONMENTAL
MANAGEMENT PLAN
(EMP)
INTRODUCTION
• Environmental laws have to be forward-looking
in anticipation of advancement in socio-
technological development affecting the
environment.
• Consistent with this, Malaysian Environmental
laws were amended to further protect the
environment and improve on the quality of life.
• The Environmental Quality (Amendment) Act
1996 was gazette on the 1st of August 1996.
• The amendment to the Act may require
central audit, which means a periodic,
systematic, documented and objective
evaluation to determine compliance to
environmental regulatory requirement,
environmental management system and
overall environmental risk of the premises.
ENVIRONMENTAL
MANAGEMENT PLAN (EMP)
• Prior to starting the project, an EMP must
be submitted to the DOE for approval.
• In this EMP, the operator should include
strategies for the management of
important issues associated with the
construction and operation of the station.
• This plan should include an administrative
setting such as the Environmental Safety
and Health Department that is responsible
for environmental management.
• This should include the structure,
manpower and specific responsibilities of
the personnel concerned.
• Among these responsibilities are: -
– liasing with the Malaysian authorities on
environmental related matters
– submission of reports on environmental
performance
– co-ordinating environmental training and
awareness
– prevent non-compliance
– identifying and recording environmental
problems and issues
– controlling non conformance until the
condition has been mitigated and corrected
– implementation of corrective actions
• The EMP also includes the legislative requirement to be
observed and complied with.
• These are given below but not necessarily are limited to
it:
– Compliance to the Environmental Quality Act
(Amendment) 1996.
– Contamination as given in the Environmental Quality
Act 1974 (Act 127) and subsidiary legislation made
thereunder.
– To adopt wherever necessary and applicable the
Environmental Impact Assessment Guidelines
produced by the DOE that are relevant to the project.
– Compliance to the Terms and Conditions of Approval
that are issued by Authorities for the duration of this
project.
– Compliance wherever possible with all the Malaysian
Environmental guidelines produced by the DOE and
other relevant authorities.
• The EMP should have a comprehensive monitoring
programme, which should take into account the
following:
– Monitoring and measurement shall be carried out by
trained qualified Technician or accredited laboratory
under ISO Guide 25/SAMM 1.
– Monitoring and measuring equipment shall be
controlled and maintained and a copy of the report
shall be handed over to the Employers’
Representative and DOE.
• The purpose of monitoring is to identify any changes
caused by the Project activities. It will also establish
whether mitigating measures adopted are sufficient to
reduce impact.
Environmental Monitoring
Programme
(a) Noise Monitoring Programme
• The proposed noise monitoring programme (to
be discussed and agreed by DOE) is as follows:
• Location:Five stations (Refer to Figure 7.2.1).
Table 7.2.1 provides the locations of these
sampling stations.
• Parameter: LAmax, LAmin, LAeq , LA10, LA90
• Frequency: Quarterly
(b) Marine and Riverine Water Quality
Monitoring Programme
• The proposed air quality monitoring programme
(to be discussed and agreed by DOE) is as
follows:
• Location: 16 Station.(Refer to Figure
7.2.2).
• Parameters: Parameter listed in the Interim
National Marine Water Quality Standard and
Water Quality standard
• Frequency: Quarterly
(c) Air Quality Monitoring Programme
• The proposed air quality monitoring programme
(to be discussed and agreed by DOE) is as
follows:
• Location: 3 locations (Refer to Figure
7.2.3). Table 7.2.2 provides the locations of
these sampling stations.
• Parameters: Total suspended particulates,
NOx, CO and SOx
• Frequency: Quarterly
Table 7.2.1 Noise monitoring stations
Station Ref.
GPS Reading Description
N1 N 01˚25.77
E 103 40.21˚
Kg. Tebing Runtuh
N2 N 01° 28.105′
E 103° 34.891′
Nearby Sekolah Menengah Kebangsaan
Taman Nusantara
N3 N 01° 28.813′
E 103° 38.486′
Nearby Sekolah Menengah Kebangsaan
Bukit Indah
N4 N 01° 27.111′
E 103° 34.807′
Nearby Kampung Bukit Tempurung
N5 N 01° 23.393′
E 103° 35.114′
Nearby Kampung Tiram Duku
Table 7.2.2 Air monitoring stations
Station Ref.
GPS Reading Description
N1 N 01˚25.77
E 103 40.21˚
Kg. Tebing Runtuh
N2 N 01° 28.105′
E 103° 34.891′
Nearby Sekolah Menengah Kebangsaan
Taman Nusantara
N5 N 01° 23.393′
E 103° 35.114′
Nearby Kampung Tiram Duku
Environmental Audit Checklist
• This section provides a checklist of the
mitigating measures that must be taken to
ensure that the mitigating measures are
adequately carried out to meet various
conditions stipulated by the authorities.
(i) Planning and Design
• Has the machinery been incorporated with
the required noise control equipment?
• Has adequate air pollution control
equipment been incorporated to meet the
Standard C, Environmental Quality (Clean
Air) Regulations, 1978?
(ii) Damage and Interference (on
Structure, Roads, and Other Property)
• Have all precautions been taken to avoid
damages and interference (other than to the
extent that is necessary for them to be removed
or diverted to permit the execution of the works)
to:
a.watercourses or drainage systems?
b.utilities?
c. structures, roads, including street furniture, or
other property?
d. public or private vehicular or pedestrian
accesses?
• Have all items, which are damaged or interfered
with as a result of the works, and items which
are removed to enable work to be carried out,
been reinstated to at least the same condition as
existed before the work started?
• Has written permission been obtained prior to
any excavation or performance of any other
work directly or indirectly affecting any utility
(underground, overhead or on the surface)?
• Has appropriate remedial action been taken for
any damage to structures, roads or other
property?
• Has alternative access been provided if
interference with existing public or private
vehicular or pedestrian access is
necessary to enable the works to be
carried out?
• Has the arrangements for the alternative
access been agreed by the relevant
authorities?
(iii)Access
• Are the permanent accesses reinstated as soon
as practicable after work is completed and the
alternative access removed immediately if it is
no longer required, and the ground surfaces
properly reinstated?
• Are all necessary precautions been taken to
protect structures or works being carried out by
others adjacent to and, for the time being, within
the site from the effects of vibrations,
undermining and any other earth movements, or
the diversion of water flow arising from the
work?
(iv)Noise
• Is noise monitoring carried out at locations and
frequency determined by the DOE?
• Does the noise level comply with all
requirements of the authorities?
• If any noise level gives rise to public complaints,
has the contractor taken immediate steps to
mitigate the problem such as limiting noise
intense works to 0800 to 1800 hours?
• If it is necessary to work beyond 2000 hour, has
the approval from relevant authorities been
obtained?
(v) Water Quality and Silt Trap
• Is water containing soil particles or muddy water
flowing as surface run-off or from other areas of
the worksite being drained into a suitably
designed silt trap before it is discharged into an
outlet drain, ditch, stream, or sea?
• Is silt trap size designed to conform to the total
catchment area?
• Is the silt trap regularly inspected and de-silted?
• Has the sites for deposition of desilting material
been determined and approved by the
authorities?
• Is the water drained from the silt trap
being frequently monitored (weekly) for
TSS, and other relevant parameters?
• If the desilting material has to be disposed
outside the construction area, is strict
procedure taken to avoid leakage of
material along the transportation route?
• Are the sampling locations and frequency
complying with the DOE requirement?
(vi) Site Cleaning and Disposal of
Waste Material
• Have all debris, spoil material, rubbish and other
waste being cleared regularly from the site?
• Is the disposal site for dumping of the waste
material approved by the local authorities?
• Is the access to the work sites free of all debris,
waste and excavated material and other
obstructions?
• Are the waste oil and other scheduled wastes
being handled and disposed according to
procedures for scheduled wastes?
(vii) Air Quality
• Is air monitoring carried out at locations
and frequency determined by the DOE?
• Does the air quality comply with Standard
C, Environmental Quality (Clean Air)
Regulations, 1978?
(viii) Safety
• Have the contractors ensured that all workers
understand and comply with the standard safety
procedures for handling heavy machinery,
vehicles and equipment?
• Is there a safety officer to oversee that the
overall safety compliance has been adhered to?
• Are first aid facilities available at all times at the
construction site?
• Is there available immediate transportation to
hospital for medical treatment, if required?
THANK YOU

More Related Content

Viewers also liked

Environment Protection Act, 1986
Environment Protection Act, 1986Environment Protection Act, 1986
Environment Protection Act, 1986Prashant Sakariya
 
Environment Protection Act , 1986.
Environment Protection Act , 1986.Environment Protection Act , 1986.
Environment Protection Act , 1986.Yuvraj Tomar
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrithvi Ghag
 
The environmental (protection) act, 1986
The environmental (protection) act, 1986The environmental (protection) act, 1986
The environmental (protection) act, 1986ACS Shalu Saraf
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentNigel Gardner
 
Environment protection act
Environment protection actEnvironment protection act
Environment protection actPadmapriyaG
 

Viewers also liked (8)

Environment Protection Act, 1986
Environment Protection Act, 1986Environment Protection Act, 1986
Environment Protection Act, 1986
 
Environment Protection Act , 1986.
Environment Protection Act , 1986.Environment Protection Act , 1986.
Environment Protection Act , 1986.
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
The environmental (protection) act, 1986
The environmental (protection) act, 1986The environmental (protection) act, 1986
The environmental (protection) act, 1986
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Environment protection act
Environment protection actEnvironment protection act
Environment protection act
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 

Similar to Emergency Management Plan

CET 415 Module IV.pptx
CET 415 Module IV.pptxCET 415 Module IV.pptx
CET 415 Module IV.pptxFARSANA26
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projectsSandeep Kumar
 
EIA-for-Proposed-Development-at-Kampung-Sungai-Buah.pptx
EIA-for-Proposed-Development-at-Kampung-Sungai-Buah.pptxEIA-for-Proposed-Development-at-Kampung-Sungai-Buah.pptx
EIA-for-Proposed-Development-at-Kampung-Sungai-Buah.pptxSITI NORSITA MOHD RAWI
 
EIA of offshore drilling and dredging
EIA of  offshore drilling and dredgingEIA of  offshore drilling and dredging
EIA of offshore drilling and dredgingbivin ebenezer
 
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2Sadique Khan
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptxthanga2
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptxthanga2
 
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA ProjectRegulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA ProjectDrAbdulRahmanMahmud
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfChandanLawrence
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment Pramoda Raj
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentSonikaPawar
 
Environmental Impact Assignment
Environmental Impact Assignment Environmental Impact Assignment
Environmental Impact Assignment Hemant Thakur
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentBahadur Prasad
 
Environmental Risk Assessment - BOSH
Environmental Risk Assessment - BOSH Environmental Risk Assessment - BOSH
Environmental Risk Assessment - BOSH Abirami V Veeramani
 
Environmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit IIIEnvironmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit IIIGAURAV. H .TANDON
 

Similar to Emergency Management Plan (20)

CET 415 Module IV.pptx
CET 415 Module IV.pptxCET 415 Module IV.pptx
CET 415 Module IV.pptx
 
IMM PRESENTATION
IMM  PRESENTATIONIMM  PRESENTATION
IMM PRESENTATION
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projects
 
PEISS
PEISSPEISS
PEISS
 
EIA-for-Proposed-Development-at-Kampung-Sungai-Buah.pptx
EIA-for-Proposed-Development-at-Kampung-Sungai-Buah.pptxEIA-for-Proposed-Development-at-Kampung-Sungai-Buah.pptx
EIA-for-Proposed-Development-at-Kampung-Sungai-Buah.pptx
 
EIA of offshore drilling and dredging
EIA of  offshore drilling and dredgingEIA of  offshore drilling and dredging
EIA of offshore drilling and dredging
 
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
 
Ecw 579 week 13
Ecw 579 week 13Ecw 579 week 13
Ecw 579 week 13
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA ProjectRegulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdf
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
PEISS
PEISSPEISS
PEISS
 
Environmental Impact Assignment
Environmental Impact Assignment Environmental Impact Assignment
Environmental Impact Assignment
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Iee
IeeIee
Iee
 
Environmental Risk Assessment - BOSH
Environmental Risk Assessment - BOSH Environmental Risk Assessment - BOSH
Environmental Risk Assessment - BOSH
 
Environmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit IIIEnvironmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit III
 

Emergency Management Plan

  • 2. INTRODUCTION • Environmental laws have to be forward-looking in anticipation of advancement in socio- technological development affecting the environment. • Consistent with this, Malaysian Environmental laws were amended to further protect the environment and improve on the quality of life. • The Environmental Quality (Amendment) Act 1996 was gazette on the 1st of August 1996.
  • 3. • The amendment to the Act may require central audit, which means a periodic, systematic, documented and objective evaluation to determine compliance to environmental regulatory requirement, environmental management system and overall environmental risk of the premises.
  • 4. ENVIRONMENTAL MANAGEMENT PLAN (EMP) • Prior to starting the project, an EMP must be submitted to the DOE for approval. • In this EMP, the operator should include strategies for the management of important issues associated with the construction and operation of the station.
  • 5. • This plan should include an administrative setting such as the Environmental Safety and Health Department that is responsible for environmental management. • This should include the structure, manpower and specific responsibilities of the personnel concerned.
  • 6. • Among these responsibilities are: - – liasing with the Malaysian authorities on environmental related matters – submission of reports on environmental performance – co-ordinating environmental training and awareness – prevent non-compliance – identifying and recording environmental problems and issues – controlling non conformance until the condition has been mitigated and corrected – implementation of corrective actions
  • 7. • The EMP also includes the legislative requirement to be observed and complied with. • These are given below but not necessarily are limited to it: – Compliance to the Environmental Quality Act (Amendment) 1996. – Contamination as given in the Environmental Quality Act 1974 (Act 127) and subsidiary legislation made thereunder. – To adopt wherever necessary and applicable the Environmental Impact Assessment Guidelines produced by the DOE that are relevant to the project. – Compliance to the Terms and Conditions of Approval that are issued by Authorities for the duration of this project. – Compliance wherever possible with all the Malaysian Environmental guidelines produced by the DOE and other relevant authorities.
  • 8. • The EMP should have a comprehensive monitoring programme, which should take into account the following: – Monitoring and measurement shall be carried out by trained qualified Technician or accredited laboratory under ISO Guide 25/SAMM 1. – Monitoring and measuring equipment shall be controlled and maintained and a copy of the report shall be handed over to the Employers’ Representative and DOE. • The purpose of monitoring is to identify any changes caused by the Project activities. It will also establish whether mitigating measures adopted are sufficient to reduce impact.
  • 9. Environmental Monitoring Programme (a) Noise Monitoring Programme • The proposed noise monitoring programme (to be discussed and agreed by DOE) is as follows: • Location:Five stations (Refer to Figure 7.2.1). Table 7.2.1 provides the locations of these sampling stations. • Parameter: LAmax, LAmin, LAeq , LA10, LA90 • Frequency: Quarterly
  • 10. (b) Marine and Riverine Water Quality Monitoring Programme • The proposed air quality monitoring programme (to be discussed and agreed by DOE) is as follows: • Location: 16 Station.(Refer to Figure 7.2.2). • Parameters: Parameter listed in the Interim National Marine Water Quality Standard and Water Quality standard • Frequency: Quarterly
  • 11. (c) Air Quality Monitoring Programme • The proposed air quality monitoring programme (to be discussed and agreed by DOE) is as follows: • Location: 3 locations (Refer to Figure 7.2.3). Table 7.2.2 provides the locations of these sampling stations. • Parameters: Total suspended particulates, NOx, CO and SOx • Frequency: Quarterly
  • 12. Table 7.2.1 Noise monitoring stations Station Ref. GPS Reading Description N1 N 01˚25.77 E 103 40.21˚ Kg. Tebing Runtuh N2 N 01° 28.105′ E 103° 34.891′ Nearby Sekolah Menengah Kebangsaan Taman Nusantara N3 N 01° 28.813′ E 103° 38.486′ Nearby Sekolah Menengah Kebangsaan Bukit Indah N4 N 01° 27.111′ E 103° 34.807′ Nearby Kampung Bukit Tempurung N5 N 01° 23.393′ E 103° 35.114′ Nearby Kampung Tiram Duku
  • 13. Table 7.2.2 Air monitoring stations Station Ref. GPS Reading Description N1 N 01˚25.77 E 103 40.21˚ Kg. Tebing Runtuh N2 N 01° 28.105′ E 103° 34.891′ Nearby Sekolah Menengah Kebangsaan Taman Nusantara N5 N 01° 23.393′ E 103° 35.114′ Nearby Kampung Tiram Duku
  • 14.
  • 15.
  • 16.
  • 17. Environmental Audit Checklist • This section provides a checklist of the mitigating measures that must be taken to ensure that the mitigating measures are adequately carried out to meet various conditions stipulated by the authorities.
  • 18. (i) Planning and Design • Has the machinery been incorporated with the required noise control equipment? • Has adequate air pollution control equipment been incorporated to meet the Standard C, Environmental Quality (Clean Air) Regulations, 1978?
  • 19. (ii) Damage and Interference (on Structure, Roads, and Other Property) • Have all precautions been taken to avoid damages and interference (other than to the extent that is necessary for them to be removed or diverted to permit the execution of the works) to: a.watercourses or drainage systems? b.utilities? c. structures, roads, including street furniture, or other property? d. public or private vehicular or pedestrian accesses?
  • 20. • Have all items, which are damaged or interfered with as a result of the works, and items which are removed to enable work to be carried out, been reinstated to at least the same condition as existed before the work started? • Has written permission been obtained prior to any excavation or performance of any other work directly or indirectly affecting any utility (underground, overhead or on the surface)? • Has appropriate remedial action been taken for any damage to structures, roads or other property?
  • 21. • Has alternative access been provided if interference with existing public or private vehicular or pedestrian access is necessary to enable the works to be carried out? • Has the arrangements for the alternative access been agreed by the relevant authorities? (iii)Access
  • 22. • Are the permanent accesses reinstated as soon as practicable after work is completed and the alternative access removed immediately if it is no longer required, and the ground surfaces properly reinstated? • Are all necessary precautions been taken to protect structures or works being carried out by others adjacent to and, for the time being, within the site from the effects of vibrations, undermining and any other earth movements, or the diversion of water flow arising from the work?
  • 23. (iv)Noise • Is noise monitoring carried out at locations and frequency determined by the DOE? • Does the noise level comply with all requirements of the authorities? • If any noise level gives rise to public complaints, has the contractor taken immediate steps to mitigate the problem such as limiting noise intense works to 0800 to 1800 hours? • If it is necessary to work beyond 2000 hour, has the approval from relevant authorities been obtained?
  • 24. (v) Water Quality and Silt Trap • Is water containing soil particles or muddy water flowing as surface run-off or from other areas of the worksite being drained into a suitably designed silt trap before it is discharged into an outlet drain, ditch, stream, or sea? • Is silt trap size designed to conform to the total catchment area? • Is the silt trap regularly inspected and de-silted? • Has the sites for deposition of desilting material been determined and approved by the authorities?
  • 25. • Is the water drained from the silt trap being frequently monitored (weekly) for TSS, and other relevant parameters? • If the desilting material has to be disposed outside the construction area, is strict procedure taken to avoid leakage of material along the transportation route? • Are the sampling locations and frequency complying with the DOE requirement?
  • 26. (vi) Site Cleaning and Disposal of Waste Material • Have all debris, spoil material, rubbish and other waste being cleared regularly from the site? • Is the disposal site for dumping of the waste material approved by the local authorities? • Is the access to the work sites free of all debris, waste and excavated material and other obstructions? • Are the waste oil and other scheduled wastes being handled and disposed according to procedures for scheduled wastes?
  • 27. (vii) Air Quality • Is air monitoring carried out at locations and frequency determined by the DOE? • Does the air quality comply with Standard C, Environmental Quality (Clean Air) Regulations, 1978?
  • 28. (viii) Safety • Have the contractors ensured that all workers understand and comply with the standard safety procedures for handling heavy machinery, vehicles and equipment? • Is there a safety officer to oversee that the overall safety compliance has been adhered to? • Are first aid facilities available at all times at the construction site? • Is there available immediate transportation to hospital for medical treatment, if required?