                  BASIC PRINCIPLES OF SHUTDOWN
                        SCHEDULING IN SAP

           ______________________________________________________________________




Printed: February 5, 2011
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc
Last Modified: 2/3/2011 01:07:00 AM                            Draft
Gentile Consulting Inc.


Table of Contents
1.0Purpose                                                                               2

2.0Scope                                                                                 2

3.0Discussion                                                                            3

4.0Summary/Conclusions                                                                  12




1.0 Purpose
The purpose of this document is to introduce the concepts and techniques required to
effectively schedule shutdown work entirely within SAP. It is not intended to be a step by
step instruction manual. Specific business processes are developed in detail for each
organization however, it is important for everyone to understand the concepts involved and
how their everyday activities affect the schedule. Using SAP will allow live real-time
schedule reports and status to be available to everyone with access to SAP.
2.0      Scope

This document will cover the following topics:

    •    Why it is necessary to schedule work in SAP
    •    Introduction to the “WINDOWS” concept of scheduling.
    •    Introduction to SAP “Networks”
    •    Integration of SAP Networks and Work Orders to create a schedule.
    •    Introduction to on-line reports for all levels of the organization.




Printed: February 5, 2011                                   2
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




3.0      Discussion


Why schedule in SAP

SAP is a fully integrated software system in which various modules share a common
database. This means that the information that a planner puts on a work order provides
data that is used by all modules of the program. The system will automatically order parts
and services, make demands on work groups resources, provide input to the financial
planning groups, all based on the dates of the work order operations.

If the dates on the work order are incorrect, the basic functionality of SAP is diminished
and the company cannot realize the improvements and benefits it expected when it made
the investment in SAP. Incorrect dates on the work order will supply incorrect data to all
the modules seen below.




Printed: February 5, 2011                                   3
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




The “WINDOWS” concept of scheduling

Window scheduling is a technique that is used by many industries regardless of the
scheduling tool being used. Consider the following sequence of events.


       Reduce Steam Demand to                Secure Boiler Feed Pump                                     Reduce Steam Demand to
                           50%                                         #1                                                    10%




                                                                                           Boiler Feed
                                                                                         Pump #1 Work
                                                                                              Window




  Secure Main Steam Header            Hydro Main Steam Header               Increase Steam Demand to
                                                                                                                                   Start Boiler Feed Pump #1
                             #1                                 #1                                50%




The scenario in the above illustration describes reducing the output of a boiler to facilitate
the hydrostatic testing of a steam header. The “Work Window” depicted in red is that
period in time when #1 Boiler Feed Pump is available for maintenance without effecting
the overall duration of the hydrostatic testing evolution.




Printed: February 5, 2011                                   4
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Project Systems Networks

A network is a structure the Project Systems module that contains specific work
instructions similar to the work order in the Plant Maintenance module. These work
instructions are referred to as activities. The network activities may be logic tied and
scheduled. A simple network is illustrated graphically below.




Printed: February 5, 2011                                   5
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Subnetworks


It is possible to add more details to your network by creating subnetworks to
network activities. In the example below a project network was created with the
high level network consisting of design, installation and closeout activities. More
detail was added by adding a subnetwork to the installation activity.




You can use subnetworks to refine and detail your networks as planning
progresses. You create subnetworks by breaking down a network activity into one
or more subnetworks. The system treats subnetworks and networks the same, that
is, you can plan dates, capacities, costs, materials and production resource/tools
also with a subnetwork.




Printed: February 5, 2011                                   6
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Network Activities

Network Activities are discrete tasks similar to work order operations with the following
characteristics:

•   They have duration.
•   They have a defined start and a defined finish.
•   Resources are needed to execute them.
•   They incur costs.
•   They are worked without interruption.

There are the following types of activities in Project Systems:

• Internal processed activities (work performed by internal employees)
• Externally processed activities (work performed by external employees)
• Primary costs activities (activity costs that are expected to arise through the
  consumption of goods and services that originate from outside the company




Printed: February 5, 2011                                   7
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


         Integration of SAP Networks and Work Orders

         PM work orders can be linked to any network or subnetwork activity. When they are
         linked the dates on the work order will be derived from the activity date. When the
         network is scheduled all work orders attached will also be scheduled. This allows
         scheduling personnel to maintain the dates of many orders at once by using a single
         transaction.




Operative Network
Operative Network



Sub Networks
Sub Networks


PM Orders
PM Orders




Printed: February 5, 2011                                   8
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.



         Project Systems Reporting



         Now that the PS and PM modules are linked through the networks reports
         can be generated through the PS module that can be used by all levels and
         departments in the organization via a single source. Illustrated below are
         some reports generated by the system.


                                                         Gant Charts




Printed: February 5, 2011                                   9
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




                                          Work Center Schedules




                                                    Material Reports



Printed: February 5, 2011                                   10
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




                                              Real Time Cost Reports



Printed: February 5, 2011                                   11
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




         Hundreds of reports involving all work groups can be generated from a
         single transaction in the PS module. Any report generated by external
         scheduling software can be duplicated in SAP.




4.0      Summary/Conclusions

The integration of the PS and PM modules will provide a scheduling capability
previously impossible in the company. This scheduling capability will require little or
no input from the individuals performing the work since all schedule updates occur
through the already implemented conformation process.

The critical success factors involved in this process are:



Printed: February 5, 2011                                   12
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.



            • All work planned and managed within SAP (Capital, Maintenance,
              Operations)
            • Work orders must contain detailed planning
            • Accurate and timely confirmations of all operations




Printed: February 5, 2011                                   13
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM

More Related Content

What's hot

Scheduled Shutdown Maintenance
Scheduled Shutdown MaintenanceScheduled Shutdown Maintenance
Scheduled Shutdown Maintenance
jdparfett
 
MuleSoft: How to Engage Partners/Customers and API Led with Alexa
MuleSoft: How to Engage Partners/Customers and  API Led with Alexa MuleSoft: How to Engage Partners/Customers and  API Led with Alexa
MuleSoft: How to Engage Partners/Customers and API Led with Alexa
Angel Alberici
 
Sachin 5 Yrs Telecom Ba Pmp Resume
Sachin 5 Yrs Telecom Ba Pmp ResumeSachin 5 Yrs Telecom Ba Pmp Resume
Sachin 5 Yrs Telecom Ba Pmp Resume
Sachin P, PMP®
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
TW Carl
 

What's hot (20)

Reliability Centered Maintenance Case Study
 Reliability Centered Maintenance Case Study Reliability Centered Maintenance Case Study
Reliability Centered Maintenance Case Study
 
Mulesoft Connections to different companies, and different services
Mulesoft Connections to different companies, and different servicesMulesoft Connections to different companies, and different services
Mulesoft Connections to different companies, and different services
 
Scheduled Shutdown Maintenance
Scheduled Shutdown MaintenanceScheduled Shutdown Maintenance
Scheduled Shutdown Maintenance
 
F.M.E.C.A pdf
F.M.E.C.A pdfF.M.E.C.A pdf
F.M.E.C.A pdf
 
SAP Integration with MuleSoft | MuleSoft Mysore Meetup #14
SAP Integration with MuleSoft | MuleSoft Mysore Meetup #14 SAP Integration with MuleSoft | MuleSoft Mysore Meetup #14
SAP Integration with MuleSoft | MuleSoft Mysore Meetup #14
 
Scope of work
Scope of workScope of work
Scope of work
 
Audit Vault Database Firewall 12.2.0.1.0 installation
Audit Vault Database Firewall 12.2.0.1.0 installationAudit Vault Database Firewall 12.2.0.1.0 installation
Audit Vault Database Firewall 12.2.0.1.0 installation
 
NEC Engineering and Construction Short Contract (ECSC) webinar
NEC Engineering and Construction Short Contract (ECSC) webinarNEC Engineering and Construction Short Contract (ECSC) webinar
NEC Engineering and Construction Short Contract (ECSC) webinar
 
MuleSoft: How to Engage Partners/Customers and API Led with Alexa
MuleSoft: How to Engage Partners/Customers and  API Led with Alexa MuleSoft: How to Engage Partners/Customers and  API Led with Alexa
MuleSoft: How to Engage Partners/Customers and API Led with Alexa
 
Unit 1: Apply the Twelve-Factor App to Microservices Architectures
Unit 1: Apply the Twelve-Factor App to Microservices ArchitecturesUnit 1: Apply the Twelve-Factor App to Microservices Architectures
Unit 1: Apply the Twelve-Factor App to Microservices Architectures
 
Contracting Strategy
Contracting StrategyContracting Strategy
Contracting Strategy
 
Singapore MuleSoft Meetup - 24 Aug 2022
Singapore MuleSoft Meetup - 24 Aug 2022Singapore MuleSoft Meetup - 24 Aug 2022
Singapore MuleSoft Meetup - 24 Aug 2022
 
Sachin 5 Yrs Telecom Ba Pmp Resume
Sachin 5 Yrs Telecom Ba Pmp ResumeSachin 5 Yrs Telecom Ba Pmp Resume
Sachin 5 Yrs Telecom Ba Pmp Resume
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Europe User Conference: ADNOC optimization of hydrocracking process as a func...
Europe User Conference: ADNOC optimization of hydrocracking process as a func...Europe User Conference: ADNOC optimization of hydrocracking process as a func...
Europe User Conference: ADNOC optimization of hydrocracking process as a func...
 
Introduction to MuleSoft Anytime Platform
Introduction to MuleSoft Anytime PlatformIntroduction to MuleSoft Anytime Platform
Introduction to MuleSoft Anytime Platform
 
MuleSoft Surat Meetup#45 - Anypoint Flex Gateway as a Kubernetes Ingress Cont...
MuleSoft Surat Meetup#45 - Anypoint Flex Gateway as a Kubernetes Ingress Cont...MuleSoft Surat Meetup#45 - Anypoint Flex Gateway as a Kubernetes Ingress Cont...
MuleSoft Surat Meetup#45 - Anypoint Flex Gateway as a Kubernetes Ingress Cont...
 
How To Drive A Successful ServiceNow Implementation
How To Drive A Successful ServiceNow ImplementationHow To Drive A Successful ServiceNow Implementation
How To Drive A Successful ServiceNow Implementation
 
Anypoint platform architecture and components
Anypoint platform architecture and componentsAnypoint platform architecture and components
Anypoint platform architecture and components
 

Viewers also liked

Planning for Shutdowns, Turnarounds and Outages Workshop
Planning for Shutdowns, Turnarounds and Outages WorkshopPlanning for Shutdowns, Turnarounds and Outages Workshop
Planning for Shutdowns, Turnarounds and Outages Workshop
Life Cycle Engineering
 
Managing A Synergistic Shutdown Team
Managing A Synergistic Shutdown TeamManaging A Synergistic Shutdown Team
Managing A Synergistic Shutdown Team
jdparfett
 
Employee benefits in oil & energy industry
Employee benefits in oil & energy industryEmployee benefits in oil & energy industry
Employee benefits in oil & energy industry
raghunathan janarthanan
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1
Jahanzeb Khan
 
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPSBGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
Jonathan Danker
 
Ibm turn around strategy
Ibm turn around strategyIbm turn around strategy
Ibm turn around strategy
Karan Shah
 

Viewers also liked (20)

Turnaround Project Planner Primer
Turnaround Project Planner PrimerTurnaround Project Planner Primer
Turnaround Project Planner Primer
 
Plant shutdown
Plant shutdownPlant shutdown
Plant shutdown
 
technical services for turnarounds in petrochemical plants in western europe
technical services for turnarounds in petrochemical plants in western europetechnical services for turnarounds in petrochemical plants in western europe
technical services for turnarounds in petrochemical plants in western europe
 
Planning for Shutdowns, Turnarounds and Outages Workshop
Planning for Shutdowns, Turnarounds and Outages WorkshopPlanning for Shutdowns, Turnarounds and Outages Workshop
Planning for Shutdowns, Turnarounds and Outages Workshop
 
Managing A Synergistic Shutdown Team
Managing A Synergistic Shutdown TeamManaging A Synergistic Shutdown Team
Managing A Synergistic Shutdown Team
 
Turnarounds for process plants/ Industry Services
Turnarounds for process plants/ Industry ServicesTurnarounds for process plants/ Industry Services
Turnarounds for process plants/ Industry Services
 
Employee benefits in oil & energy industry
Employee benefits in oil & energy industryEmployee benefits in oil & energy industry
Employee benefits in oil & energy industry
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1
 
MAOP Process Validation
MAOP Process ValidationMAOP Process Validation
MAOP Process Validation
 
Smart Asset Solution for Oil and Gas
Smart Asset Solution for Oil and GasSmart Asset Solution for Oil and Gas
Smart Asset Solution for Oil and Gas
 
Arcadis capabillity statement summary feb 2017
Arcadis capabillity statement summary feb 2017Arcadis capabillity statement summary feb 2017
Arcadis capabillity statement summary feb 2017
 
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPSBGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
 
IBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industryIBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industry
 
Data - the Oil & Gas asset that isn’t managed like one
Data  - the Oil & Gas asset that isn’t managed like oneData  - the Oil & Gas asset that isn’t managed like one
Data - the Oil & Gas asset that isn’t managed like one
 
Maintenance Management Certification
Maintenance Management CertificationMaintenance Management Certification
Maintenance Management Certification
 
Shutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramShutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement Program
 
Introduction to Reliability Excellence
Introduction to Reliability ExcellenceIntroduction to Reliability Excellence
Introduction to Reliability Excellence
 
Heat-exchanger-manual
Heat-exchanger-manualHeat-exchanger-manual
Heat-exchanger-manual
 
Ibm turn around strategy
Ibm turn around strategyIbm turn around strategy
Ibm turn around strategy
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivity
 

Similar to Shutdown Scheduling

SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
BIWUG
 
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
Knut Relbe-Moe [MVP, MCT]
 
Paremus service fabric
Paremus service fabricParemus service fabric
Paremus service fabric
pjhInovex
 
Convio Summit 2011 - CG Admin Without Tears
Convio Summit 2011 - CG Admin Without TearsConvio Summit 2011 - CG Admin Without Tears
Convio Summit 2011 - CG Admin Without Tears
judisohn
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...
p6academy
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
jeanettehully
 

Similar to Shutdown Scheduling (20)

SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
 
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practices
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practicesSPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practices
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practices
 
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
 
resume
resumeresume
resume
 
Lotusphere 2012: BP110 Performance Boost for your Notes Client
Lotusphere 2012: BP110 Performance Boost for your Notes ClientLotusphere 2012: BP110 Performance Boost for your Notes Client
Lotusphere 2012: BP110 Performance Boost for your Notes Client
 
Tyco IS Oracle Apps Support Project
Tyco IS Oracle Apps Support ProjectTyco IS Oracle Apps Support Project
Tyco IS Oracle Apps Support Project
 
IETM Development Process.pdf
IETM Development Process.pdfIETM Development Process.pdf
IETM Development Process.pdf
 
Paremus service fabric
Paremus service fabricParemus service fabric
Paremus service fabric
 
Task Management for OpenNTF
Task Management for OpenNTFTask Management for OpenNTF
Task Management for OpenNTF
 
Convio Summit 2011 - CG Admin Without Tears
Convio Summit 2011 - CG Admin Without TearsConvio Summit 2011 - CG Admin Without Tears
Convio Summit 2011 - CG Admin Without Tears
 
Report final
Report finalReport final
Report final
 
J Bdemo101215
J Bdemo101215J Bdemo101215
J Bdemo101215
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...
 
Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2
 
Database performance management
Database performance managementDatabase performance management
Database performance management
 
Understanding the basic need of Service Oriented Architecture and getting sta...
Understanding the basic need of Service Oriented Architecture and getting sta...Understanding the basic need of Service Oriented Architecture and getting sta...
Understanding the basic need of Service Oriented Architecture and getting sta...
 
Easy oracle & weblogic provisioning and deployment
Easy oracle & weblogic provisioning and deploymentEasy oracle & weblogic provisioning and deployment
Easy oracle & weblogic provisioning and deployment
 
M tierney res
M tierney resM tierney res
M tierney res
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
 
Why your SAP PI/PO system should be updated
Why your SAP PI/PO system should be updatedWhy your SAP PI/PO system should be updated
Why your SAP PI/PO system should be updated
 

Shutdown Scheduling

  • 1. Draft BASIC PRINCIPLES OF SHUTDOWN SCHEDULING IN SAP ______________________________________________________________________ Printed: February 5, 2011 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM Draft
  • 2. Gentile Consulting Inc. Table of Contents 1.0Purpose 2 2.0Scope 2 3.0Discussion 3 4.0Summary/Conclusions 12 1.0 Purpose The purpose of this document is to introduce the concepts and techniques required to effectively schedule shutdown work entirely within SAP. It is not intended to be a step by step instruction manual. Specific business processes are developed in detail for each organization however, it is important for everyone to understand the concepts involved and how their everyday activities affect the schedule. Using SAP will allow live real-time schedule reports and status to be available to everyone with access to SAP. 2.0 Scope This document will cover the following topics: • Why it is necessary to schedule work in SAP • Introduction to the “WINDOWS” concept of scheduling. • Introduction to SAP “Networks” • Integration of SAP Networks and Work Orders to create a schedule. • Introduction to on-line reports for all levels of the organization. Printed: February 5, 2011 2 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 3. Gentile Consulting Inc. 3.0 Discussion Why schedule in SAP SAP is a fully integrated software system in which various modules share a common database. This means that the information that a planner puts on a work order provides data that is used by all modules of the program. The system will automatically order parts and services, make demands on work groups resources, provide input to the financial planning groups, all based on the dates of the work order operations. If the dates on the work order are incorrect, the basic functionality of SAP is diminished and the company cannot realize the improvements and benefits it expected when it made the investment in SAP. Incorrect dates on the work order will supply incorrect data to all the modules seen below. Printed: February 5, 2011 3 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 4. Gentile Consulting Inc. The “WINDOWS” concept of scheduling Window scheduling is a technique that is used by many industries regardless of the scheduling tool being used. Consider the following sequence of events. Reduce Steam Demand to Secure Boiler Feed Pump Reduce Steam Demand to 50% #1 10% Boiler Feed Pump #1 Work Window Secure Main Steam Header Hydro Main Steam Header Increase Steam Demand to Start Boiler Feed Pump #1 #1 #1 50% The scenario in the above illustration describes reducing the output of a boiler to facilitate the hydrostatic testing of a steam header. The “Work Window” depicted in red is that period in time when #1 Boiler Feed Pump is available for maintenance without effecting the overall duration of the hydrostatic testing evolution. Printed: February 5, 2011 4 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 5. Gentile Consulting Inc. Project Systems Networks A network is a structure the Project Systems module that contains specific work instructions similar to the work order in the Plant Maintenance module. These work instructions are referred to as activities. The network activities may be logic tied and scheduled. A simple network is illustrated graphically below. Printed: February 5, 2011 5 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 6. Gentile Consulting Inc. Subnetworks It is possible to add more details to your network by creating subnetworks to network activities. In the example below a project network was created with the high level network consisting of design, installation and closeout activities. More detail was added by adding a subnetwork to the installation activity. You can use subnetworks to refine and detail your networks as planning progresses. You create subnetworks by breaking down a network activity into one or more subnetworks. The system treats subnetworks and networks the same, that is, you can plan dates, capacities, costs, materials and production resource/tools also with a subnetwork. Printed: February 5, 2011 6 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 7. Gentile Consulting Inc. Network Activities Network Activities are discrete tasks similar to work order operations with the following characteristics: • They have duration. • They have a defined start and a defined finish. • Resources are needed to execute them. • They incur costs. • They are worked without interruption. There are the following types of activities in Project Systems: • Internal processed activities (work performed by internal employees) • Externally processed activities (work performed by external employees) • Primary costs activities (activity costs that are expected to arise through the consumption of goods and services that originate from outside the company Printed: February 5, 2011 7 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 8. Gentile Consulting Inc. Integration of SAP Networks and Work Orders PM work orders can be linked to any network or subnetwork activity. When they are linked the dates on the work order will be derived from the activity date. When the network is scheduled all work orders attached will also be scheduled. This allows scheduling personnel to maintain the dates of many orders at once by using a single transaction. Operative Network Operative Network Sub Networks Sub Networks PM Orders PM Orders Printed: February 5, 2011 8 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 9. Gentile Consulting Inc. Project Systems Reporting Now that the PS and PM modules are linked through the networks reports can be generated through the PS module that can be used by all levels and departments in the organization via a single source. Illustrated below are some reports generated by the system. Gant Charts Printed: February 5, 2011 9 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 10. Gentile Consulting Inc. Work Center Schedules Material Reports Printed: February 5, 2011 10 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 11. Gentile Consulting Inc. Real Time Cost Reports Printed: February 5, 2011 11 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 12. Gentile Consulting Inc. Hundreds of reports involving all work groups can be generated from a single transaction in the PS module. Any report generated by external scheduling software can be duplicated in SAP. 4.0 Summary/Conclusions The integration of the PS and PM modules will provide a scheduling capability previously impossible in the company. This scheduling capability will require little or no input from the individuals performing the work since all schedule updates occur through the already implemented conformation process. The critical success factors involved in this process are: Printed: February 5, 2011 12 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 13. Gentile Consulting Inc. • All work planned and managed within SAP (Capital, Maintenance, Operations) • Work orders must contain detailed planning • Accurate and timely confirmations of all operations Printed: February 5, 2011 13 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM