2. Funding
Type of Funding
FY 2013
President’s Request
FY 2014
President’s Request
ACWA Program Total $778.7M $707.0M
PCAPP Project Total $340.0M $293.0M
Military Construction $36.0M $0
Research Development
Test & Evaluation
$304.0M $293.0M
Note: Figures do not contain reductions as a result of Sequestration.
2
3. Safety
As of April 30, 2013
PCAPP staff has accomplished:
369 Safe Work Days
1,885,761 Safe Work Hours
3
4. Staffing – 783 employees
Bechtel Pueblo Team
non-manual: 690
Pueblo – 689
–(181 Pueblo County hires
~ 26%)
(36 Colorado hires ~ 5%)
–Off-project locations—1
Construction Workers: 93
–Bechtel direct-hire – 87
–Subcontractor
personnel – 6
4
5. FCC Metrics
March 2013 Progress of 177 packages
as of April 12, 2013
In Box In Process
Hold
Comp'l or
Resolve Accepted HGS/Gov't
4 2
40
117 117
0
20
40
60
80
100
120
140
In Box In Process Holding Comp'l Accepted
Current Snap Shot
163 159
40
117 117
15 19
61 61
0
20
40
60
80
100
120
140
160
180
200
In Box In Process Holding Comp'l Accepted
FCC Cum Progress to Date
Processed To Go
5
8. Job Symposium
8
More than 400 people attended the PCAPP Job Symposium,
held at the Pueblo Convention Center on April 29.
9. CSEPP Exercise
9
Pueblo Chemical Depot and PCAPP personnel participate in the Chemical
Stockpile Emergency Preparedness Program annual exercise on May 8 to
simulate what would happen in the event of a real world incident.
10. Projectile Mortar Disassembly
System Testing
Initial testing of a Projectile Mortar Disassembly system took place on
May 9 in an Explosion Containment Room inside the Enhanced
Reconfiguration Building.
10