More Related Content
Similar to Market Briefing. Japan part 2. 28th January
Similar to Market Briefing. Japan part 2. 28th January (20)
Market Briefing. Japan part 2. 28th January
- 1. Civil Nuclear Export Showcase 2014
Market Briefings & Seminars
Organization Outline & Present Activities
of
International Research Institute for
Nuclear Decommissioning (IRID)
Kiyoshi OIKAWA Director, IRID
無断複製・転載禁止 技術研究組合 国際廃炉研究開発機構
©International Research Institute for Nuclear Decommissioning
- 2. IRID is a Research & Development Consortium
Basic role is:
Fully committing to technology R&D that helps the
decommissioning project of Fukushima Daiichi NPS as an
urgent subject, based on which enhancing the technological
basis for nuclear decommissioning for the future.
Contents of operation are:
✓R&D for nuclear decommissioning
✓Promoting the international/domestic alliance
for decommissioning
✓Human resource development for R&D
Establishment: August 1, 2013
2
©International Research Institute for Nuclear Decommissioning
- 3. Overall Relationship
Electric Utilities &
Plant Manufacturers
Council for the Decommissioning of Fukushima Daiichi NPS
(Chaired by the Minister of METI)
Implementation of
Mid-and-long-term Roadmap
Outputs/Outcomes of R&D
program
Expertise for future
decommissioning projects
IRID
Management Functions
TEPCO
Headquarters
F1 Site Operation
Integrated management of R&D projects
Project Group A
Project Group B
Project Group C
R&D project A-1
R&D project B-1
R&D project C-1
R&D project A-2
R&D project B-2
R&D project C-2
Contractors &
Sub-contractors
Advice from international community
3
Joint study/research with partners
©International Research Institute for Nuclear Decommissioning
- 4. IRID as “Open Platform” for Collaboration
Board of Directors
Integrated management of
R&D projects
Alliance/
collaborative study
Technological
vendors
Research institutes,
etc.
✓Planning of overall research strategy
✓Coordination & optimization
Needs at site/
Supply of
equipment
Collaborative
study
Project -A
Project -B
International Advisors
Advices from organizational governance &
management aspects
Joint Research/
International
Collaboration
Joint
business
Sharing
results
Technological
advices
✓Discussion on innovative ideas, technologies
and projects
Innovative ideas/
OECD/NEA
- Accident analysis
- Others
IAEA
- Review mission
- Others
International
Expert Group
technology proposals
Business and research institutions all over the world
4
©International Research Institute for Nuclear Decommissioning
- 5. Overview of Fukushima Daiichi Units 1-4
The state of progress for decommissioning varies with each unit.
Unit1: Hydrogen explosion. Cover was installed. *Most of the fuel has fallen down into the PCV.
Unit2: *Fuel debris exist the core part, lower plenum and PCV.
Unit3: Hydrogen explosion. *Fuel debris exist the core part, lower plenum and PCV.
Unit4: Hydrogen explosion. Cover for fuel removal was installed. Started fuel removal at 18 Nov. 2013.
*Fuel debris location is estimated location.
Unit 1
Covering Structure
Spent Fuel Pool
Reactor Building
Primary (SFP)
Containment
Water
Vessel (PCV)
Reactor Pressure Injection
Vessel (RPV)
Fuel Debris
Vent
Contaminated
Water
Unit 2
Unit 4
Unit 3
Blow-out Panel
(now closed)
gantry
Water
Injection
Crawler Crane
Covering Structure
Finished removing rubbles
on the building
Started removing fuels
Water
Injection
5
©International Research Institute for Nuclear Decommissioning
- 6. Outline of Mid and Long Term Roadmap
Mid and long term roadmap was revised in June 2013.
Phased approach was confirmed.
The roadmap has shifted into the Phase-2, by having started fuel removal from Unit 4 SFP.
1st half of 2020 30 to 40 years in
2011
2013
(fast case)
December
November
the future
Step 1
Step 2
Phase 1
Phase 2
Phase 3
Period up to the
Period up to the
Cold shutdown
commencement of the Period up to the
completion of
achieved
commencement of the
removal of the fuel
decommissioning
•Achieve cold shutdown
retrieval of the fuel debris
from the spent fuel
measures
(within 10 years)
•Significantly reduce
pool
(30 to 40 years in the
radiation releases
future)
(within 2 years)
Started first fuel removal
from Unit 4 SFP on Nov. 18, 2013
6
©International Research Institute for Nuclear Decommissioning
- 7. Planned Schedule for Unit 1-4
Removal of fuel at Unit 4 was started from November 2013 (one month earlier than the initial plan).
Retrieval of fuel debris will be started from the first half of FY 2020 (the earliest case).
Unit 1
Nuclear Fuel removal from SFPs
(target schedule)
First half of FY2017(the earliest case)
~
Second half of FY2017
Unit 2
Second half of FY2017(the earliest case) ~
First half of FY2023
Unit 3
First half of 2015
Unit 4
November 2013
Fuel debris retrieval
(target schedule)
First half of FY2020
~
Second half of FY2022
First half of FY2020
~
Second half of FY2024
Second half of FY2021(the earliest case)
~
First half of FY2023
ー
(one month earlier than the initial plan)
7
©International Research Institute for Nuclear Decommissioning
- 8. Steps for Fuel Debris Retrieval
on the premise of the Existing Flooding Method
The most reliable method of fuel debris retrieval at present is considered to remove the fuel debris
by keeping them covered with water to reduce the risk of radiation exposure during the work
process.
HP :Technical holding points
Phase 1
2012
Phase 2
Phase 3
By 1st half
in 2020
2013
Step 1: Reactor Building Decontamination
Leaking Location
(Lower PCV) HP
Identified
Step 2:
Enough
Leaking Location
achieved
Identified
HP Water Level HP (Upper PCV)
Step 5:
PCV
Investigation
from outside
PCV Internal Inspection
and Sampling
Step 3:
Lower PCV
Repair
Step 4:
PCV Half
Flooding
Step 6:
Upper PCV
Repair
8
Enough
After
20-25
years
Defueling
HP Water Level
HP Method
achieved
Developed
Step 8:
RPV Internal Inspection
and Sampling
▽Open RPV
Step 7:
PCV/RPV
Full Flooding
Step 9:
Defueling
Debris processing/
disposal methods HP
developed
©International Research Institute for Nuclear Decommissioning
- 9. Building Internal Decontamination
DS pit
SFP
Equipment
hatch
RPV
Fuel debris
PCV
airlock
Torus
Steam dryer
Steam-water
separator
Turbine Building
Development of remotely operated
decontamination devices that meet the
contamination conditions in the field in
order to improve the work environment
such as surveying and repairing leaks in the
PCV to prepare for fuel debris retrieval.
Waterproofing
Leak
High-pressure water jet
decontamination device
Dry ice blast
decontamination device
9
Blasting/collecting
decontamination device
©International Research Institute for Nuclear Decommissioning
- 10. Open air Robot for Inspection and Repair of PCV
Device
① Survey robot of
Vent
pipe joint
② Quadruped walking robot
( &Flat vehicle )
③ Robot for surveying the
upper part of the S/C
Characteristics
Approach joints between bent pipes and the D/W from between the vent pipe and concrete wall with
adhering itself to the surface of the outside of the vent pipe
Be used to ascertain conditions inside the S/C, such as the presence of leaks from near the area
beneath the vent pipe.
Check for leaks from structures at the top of the S/C, which is high up (Approx. 3m at its highest), after
accessing it from the catwalk outside the Torus.
① Survey robot of Vent pipe joint
PCV
③ Robot for surveying the
upper part of the S/C
Close-up camera
(with platform)
Extendable mast
PCV
Vent pipe
ベント管
Robot ロボット
adhesion
location
吸着位置
② Quadruped walking robot
Quadruped
walking robot
Vent pipe sleeves
Sand cushion drain
lines
PCV
Ven
t
1
pipe
3
S/C
2
500
mm
900
~
3000
mm
crawlers
Torus survey
4
Flat vehicle
Bellows cover
Approx.
約
6
10
5
Survey robot
©International Research Institute for Nuclear Decommissioning
- 11. Submersible Robot
Develops device
Robot for ④ Submersible
robot
surveying
submersed ⑤ Floor walking
torus walls
robot
⑥ Robots for surveying the
bottom part of the S/C
⑥ Robots
for
Surveying the
bottom part of
the S/C
Characteristics
Be used to check for damages at building penetration seals with remotely operated (used in very
narrow places) by an operator viewing a video screen.
Walk on the floor underneath the water and uses ultrasound to check for leaks in distant places.
Check for damages on the outside of the S/C, on structures on the outside and on penetration
pipes, with adhering itself to the outer surface of the S/C ④ Submersible robot
to
Movable camera
Ascent/descent
thrusters
(front, back, left, right)
Magnetic
Observation camera wheels
S/C
Inner circumference of S/C
Seismic
resistant
support
m
Exa
ve
tra
bot
f ro ute
o o
r
ple ロボット
l
Up
down
Column
support
Outer circumference of S/C
Camera
PCV
Ven
t pip
e
1
3
S/C
⑤ Floor walking
robot
Vertical thrusters
Horizontal
Thrusters
2
4
6
11
Forward
thrusters
Horizontal
thrusters
5
Taurus
walls
S/C
Tracer
Ultrasound
Taurus
Walls
Ultrasonic
sensor (sonar)
Crawlers
Camera
S/C
Robot
Robot
©International Research Institute for Nuclear Decommissioning
- 12. Investigation of the PCV Interior
Inserting survey equipment through Unit 1 X-100B
✓ A crawler device that can transform and move along gratings stably after being inserted into the PCV
from narrow access pipe (X-100B penetration seal: inner diameterφ100mm).
[PCV cross-section]
X-100B
Existing Guide pipe
[D/W 1FL]
D/W 1F Grating
A enlarged view
X-100B
Existing guide pipe
Cable
Guide pipe
When traveling
along guide pipe
Dosimeter
CCD camera
Thermometer
Running device
A section
PCV
Grating
D/W subfloors
Transformation
X-6
: Survey route
( proposed )
High radiation level
PCV internal survey route (proposed)
12
When traveling on grating
Device concept image
©International Research Institute for Nuclear Decommissioning
- 13. Steps for Fuel Debris Retrieval
on the premise of the Existing Flooding Method
The most reliable method of fuel debris retrieval at present is considered to remove the fuel debris
by keeping them covered with water to reduce the risk of radiation exposure during the work
process.
HP :Technical holding points
Phase 1
2012
Phase 2
Phase 3
By 1st half
in 2020
2013
Step 1: Reactor Building Decontamination
Leaking Location
(Lower PCV) HP
Identified
Step 2:
Enough
Leaking Location
achieved
Identified
HP Water Level HP (Upper PCV)
Step 5:
PCV
Investigation
from outside
PCV Internal Inspection
and Sampling
Step 3:
Lower PCV
Repair
Step 4:
PCV Half
Flooding
Step 6:
Upper PCV
Repair
13
Enough
HP Water Level
achieved
After
20-25
years
Defueling
HP Method
Developed
Step 8:
RPV Internal Inspection
and Sampling
▽Open RPV
Step 7:
PCV/RPV
Full Flooding
Step 9:
Defueling
Debris processing/
disposal methods HP
developed
©International Research Institute for Nuclear Decommissioning
- 14. Request for Information (RFI) of
Innovative Approach for Fuel Debris Retrieval
Background of RFI:
To ensure multi-fold approach, as well as to enable
technological breakthroughs, collective knowledge and
experience via interactive platform is to be pursued. This will
also benefit enhancement of safety and decommissioning of
nuclear
Schedule: facilities all over the world.
2013
✓November 29 : Website is open
✓Mid December : Procedure for RFI is to be announced
2014
✓End of January : Deadline of RFI
✓Feb/March
: Review of responses
14
✓
©International Research Institute for Nuclear Decommissioning
- 15. Topics for RFI
Topic-A: Internal PCV/RPV Status Investigation
✓A-1: Conceptual study on innovative approaches
✓A-2: Technologies for internal PCV/RPV status investigation
Topic-B: Fuel-Debris Retrieval from PCV/RPV
✓B-1: Conceptual study on Innovative approaches
[Example]
Conceptual idea of retrieving fuel debris from PCV and RPV without submerging PCV, the comparison to
the submersion scenario, etc.
(a) Accessing and removal of fuel debris from Top side of PCV/RPV under water.
(b) Accessing and removal of fuel debris from Top side of PCV/RPV in atmospheric condition.
(c) Accessing and removal of fuel debris from lateral side of PCV/RPV in atmospheric condition.
Innovative approach
(d) Accessing and removal of fuel debris from bottom side of PCV/RPV in atmospheric condition.
✓B-2: Technologies for Fuel-Debris Retrieval
15
©International Research Institute for Nuclear Decommissioning
- 16. Program Structure
MAR/APR, 2014
PHASE 1
Theme
A-1
RFI for C/S
B-1
Theme RFI for F/S
A-2
B-2
MAR/APR, 2015
PHASE 2
RFP for C/S
Selection
RFP for F/S
Selection
PHASE 3
RFP
F/S
Funding
R&D project
RFP
Funding
Selection
Selection
(3 to 5 projects)
(3 to 5 projects)
if not selected
C/S or R&D
No Funding
Others
R&D project
Funding
C/S
Funding
Project Workshop #1
(potential)
(potential)
Preliminary/Design
Funding
Selection
RFP
(potential)
R&D project
Funding
Selection
(potential)
Project Workshop #2
RFP
Visit IRID WEB for more information!
http://www.irid.or.jp
http://www.irid.or.jp/fd (for RFI)
16
©International Research Institute for Nuclear Decommissioning
- 17. Thank you for your attention
無断複製・転載禁止 技術研究組合 国際廃炉研究開発機構
©International Research Institute for Nuclear Decommissioning