SlideShare a Scribd company logo
1 of 39
Download to read offline
2008 PM Challenge
NASA’s Business Systems
Are they working for you?




                              Sandra Smalley
                            OCIO IEMP Integration Manager
                                 ssmalley@nasa.gov
                                   202-358-4731




        PM Challenge 2008                               1
Contents

•   M/BSIG
     – Background
     – Membership
     – Overview of Requirements Governance
•   Gap Analysis Activity
     –   Gap Definition, Scope and Depth
     –   GAP Corrective Action Plan development process
     –   Identification Process Summary
     –   Gap Statement Summary
     –   M/BSIG integration and prioritization results
     –   Gap relationships and corrective action strategy
     –   CAP Schedule
•   Concept of Operations (ConOps) Overview
     –   Overview
     –   Background
     –   ConOps Development Approach
     –   ConOps Schedule
     –   Integration into CIO’s management strategy
     –   Business system portfolio examples

                    PM Challenge 2008                       2
Background - Management/Business System
                   Integration Group (M/B SIG)

•   IPAO/PA&E White Paper presented to OMC resulted in OMC action
    to perform gap analysis and establish M/BSIG – July 2006

•   M/BSIG Kick-Off Meeting Held - January 2007

•   Charter signed - February 2007
    – The charter of the M/BSIG is to assess and prioritize future business system
      requirements to ensure integration and alignment with Agency goals and
      objectives
    – Participants included PA&E, OCE, MD’s, OCFO, OCIO, NSSC, OHCM, I&A, OP,
      OPII, MSFC, GRC, GSFC, and IEMP (ex-officio)

•   Charter updated – October 12, 2007 to:
    –   include all ten centers
    –   reflect decision authority of the associate deputy administrator
    –   reflect scope expansion to include all agency-wide business systems
    –   include records retention process
                                    PM Challenge 2008                                3
M/B SIG Membership as of November 2007


•   ARMD – John Scholtz          •       GRC – Harvey Schabes
•   ESMD – Marlana Dorman        •       GSFC – George Barth
•   SMD – Craig Tupper           •       DFRC – John Wonacott
•   SOMD – Toni Mumford          •       LaRC – Dan Tenny
•   MSFC – Johnny Stephenson     •       SSC – Kern Witcher
•   PA&E- Cherish Johnson        •       JSC – Lucy Kranz
•   OCE – Mike Blythe            •       KSC – Vanessa Stromer
•   OCFO – Daphne Jefferson      •       JPL – Joanne Kennedy
•   OCIO – Gary Cox              •       ARC – Trish Morrissey
•   OCHM – Candy Irwin           •       HQ(Center) – Michele O’Connell
•   I&A – Jim Wright             •       IEMP – Bobby German
•   OP – Ken Stepka              •       NSSC – Joyce Short
•   OPII – Rita Svarcas          •       Facilitator – Sandra Smalley

                     PM Challenge 2008                              4
M/BSIG Responsibilities

• Ensuring the management and business system needs, goals, and objectives of all relevant
  stakeholders (e.g., internal NASA stakeholders as well as external authority stakeholders) are
  proactively elicited and considered when new or revised systems are developed.

• Ensuring the management and business system requirements are developed with an integrated
  Agency-wide perspective.

• Ensuring the management and business system priorities and the sequencing or phasing of
  implementation efforts (e.g. policy updates, process re-engineering, IEMP projects) are developed
  in recognition of budgeting, resource, and other constraints (e.g., compliance with Federal laws,
  regulations, and policies; other externally mandated requirements).

• Ensuring integration of Agency-wide business system requirements and alignment with Agency
  priorities.

• Ensuring Agency-wide business system requirements are traceable throughout the entire
  requirements chain.

• Ensuring major stakeholder proposals relating to new or changing business system scope,
  content, and priorities are appropriately reviewed from an integrated Agency-wide perspective.

• Ensuring oversight and direction of management and business system initiatives are appropriately
  focused on cross system integration and the reduction of stove-piped and redundant data silos.



                                        PM Challenge 2008                                          5
Overview of Requirements Governance


                Operations Management Council

                                           OCIO IT Strategy and
                    IT DM&E
                                            Investment Board
Requirements                                         Planning & Execution                                      IT DM&E Performance
Management                                               Management                                                 Assessment
                                                                                                                        Status Briefings &
           Recommended Actions      Implement             Implement                                                     Recommendations for
           & Requirements via the   Non-IT                 IT-DM&E                                                      (1) Significant
           Associate Deputy         DM&E                     Actions                                                    Changes to Project
           Administrator            Actions                                                                             Baseline, or
                                                                                                                        (2) Termination of
                                                                                                                        Projects

                                                          System                        Program Execution Status

                                      Coordination     Implementers
   M/BSIG                                                   (IEMP, NSSC, etc.)                                     OCIO PMB
                                                              •Projects       Project Performance Reporting
                                                       •Sustaining Operations
                                      Lower Level
                                      Requirements
                                      Priorities &
 Needs &                              Decisions
 Requirements for
 Cross-Functional
                                                         Lower Level    Lower Level
 Review and
 Prioritization          Process/                       Requirements    Requirements Governed
                                                               Issues
                        Functional                                      by the Requirements
                                                                        Management
                         Owners                                         Framework




Customers
(Mission & Mission
  Support Orgs)




                                                     PM Challenge 2008                                                                        6
Gap Analysis




   PM Challenge 2008   7
Gap Definition, Scope and Depth

• Gaps exist when the contents or behaviors of systems, in this case NASA’s
  Management and Business Systems, are different from what is needed.
• Four general types of system Gaps:
        1. Data                                2. Process
            • Incomplete data                      • Non-congruent with local processes
            • Missing data                         • Work-around solutions
            • Redundant data                       • Outside post-processing of the
            • Incorrect data                         system data
        2. Application                         3. Human
            • Inability to retrieve data           • Changing roles and responsibilities
            • Inability to input data              • Training and knowledge of the
            • Inability to modify data               system
                                                   • Non-standard practices
• Scope:
    – Includes all Agency-wide systems which process and/or provide management and
      business related information
• Depth:
    – Includes gaps associated with the data, applications, processes, and the human
      aspects of the management and business systems

                                    PM Challenge 2008                                      8
Gap Corrective Action Plan (CAP) Development
                         Process

GAP Identification and                                                            OMC/OCIO SIB
Prioritization Phase                                                                Approval
• Plan
• Collect & characterize
  data activity            CAP Development                       Is IT DM&E
• Analyze & Process data   Phase                                 Required? *
• Prioritize gaps                                                                                                   N
                           • Identify stakeholders
                           • Design workshop                            Y
                           • Perform causal analysis
                           • Develop corrective        Concept Identification                         CAP Implementation
                             action plan (including    Phase                                          Phase
                             identification of
                                                       • Develop candidate concepts,
                             requirements)
                                                         cost estimates, and
                           • Brief M/BSIG
                                                         schedules
                                                       • Perform trade studies
                                                       • Develop cost estimates
                                                       • Develop M/BSIG
                                                         implementation
                                                         recommendation
                                                       • Present to the OCIO SIB
                                                       • Submit approved
                                                         recommendation for inclusion
                                                         in the PPBE




                               M/BSIG Oversight            * IT DM&E: Information Technology Development, Modernization, or Enhancement



                                          PM Challenge 2008                                                                               9
Gap Identification & Ranking
                    Process Summary

• Project Management Gaps were collected from 5 representative
  projects
   – 58 Gaps were prioritized utilizing by the M/BSIG in July 2007
     using a Delphi process
   – 8 Project Management Gaps were identified as relatively high
     priority
• Functional Gaps were collected from Procurement, Human Capital,
  Institutions and Administration, and Finance
   – 19 Gaps were prioritized by the M/BSIG in September 2007 using
     a Delphi process
   – 4 Functional Gaps were identified as relatively high priority
• The M/BSIG integrated and prioritized the resulting top 12 project
  management and functional gaps on October 1 & 2, 2007 using an
  Analytic Hierarchy Process (AHP)

                           PM Challenge 2008                      10
Gap Statements Summary
                          The Relatively High Priority Gaps
                    Project Management                                        Functional/Mission Support
Priority   Gap #     Gap Description                            Priority   Gap #    Gap Description
  1        Gap-16    The Projects do not always receive           1        Gap-64   The OCFO does not have an
                     funding in a timely manner.                                    automated process and standardized
  2        Gap-51    Projects have concerns over the                                tools necessary to facilitate timely and
                     integrity of data in the system.                               accurate reconciliation of the SAP
  3        Gap-2     The projects are limited by system                             funds balance with the Treasury
                     configuration to obligate and cost funds                       general ledger account.
                     at the same WBS level.                       2        Gap-66   The missions and mission support
  4        Gap-49    The Projects have difficulty maintaining                       organizations do not have a
                     effective planning and control during                          standardized, integrated set of tools
                     the end-of-year closeout period.                               and processes to create, maintain,
  5        Gap-1     The Projects occasionally need more                            track and report phasing plans.
                     WBS elements (levels) than are               3        Gap-59   The OCFO and the Center Property
                     available.                                                     Custodians do not have a real property
  6        Gap-18    The Projects receive conflicting data                          system, integrated with NASA’s
                     when pulling reports on the same                               financial system, to track the value of
                     information but from different systems.                        NASA’s real property portfolio.
  7        Gap-4     The projects can not use SAP/BW to           4        Gap-67   NASA does not have the capability to
                     meet the current set of reporting                              load the next fiscal year budget
                     requirements.                                                  structure prior to current fiscal year end
  8        Gap-27    Projects report that the integration of                        close.
                     WBS, financial, manpower planning,
                     and scheduling data is a problematic
                     and manual process.


                                                    PM Challenge 2008                                                    11
M/BSIG Integrated Gap Prioritization
based upon “Benefit to the Agency”


Priority   Gap                                              Statement
   1       Gap 51   Projects have concerns over the integrity of data in the system.
   2       Gap 2    The projects must obligate and cost funds at the same WBS level.
                    The OCFO and the Center Property Custodians do not have a real property system,
   3       Gap 59
                    integrated with NASA's financial system, to track the value of NASA's real property portfolio.
   4       Gap 16   The Projects do not always receive funding in a timely manner.
   5       Gap 1    The Projects occasionally need more WBS elements (levels) than are available.
                    The Projects receive conflicting data when pulling reports on the same information but from
   6       Gap 18
                    different systems.
                    The OCFO does not have an automated process and standardized tools necessary to
   7       Gap 64   facilitate timely and accurate reconciliation of the SAP funds balance with the Treasury
                    general ledger account.
                    Projects report that the integration of WBS, financial, manpower planning, and scheduling
   8       Gap 27
                    data is a problematic and manual process.
                    NASA does not have the capability to load the next fiscal year budget structures prior to
   9       Gap 67
                    current fiscal year end close.
                    The missions and mission support organizations do not have a standardized, integrated set
  10       Gap 66
                    of tools and processes to create, maintain, track and report phasing plans.
  11       Gap 4    The projects can not use SAP/BW to meet the current set of reporting requirements.
                    The Projects have difficulty maintaining effective planning and control during the end of year
  12       Gap 49
                    closeout period.




                               PM Challenge 2008                                                                     12
Gap Relationships
                                             Data Integrity

                 Planning and Control                                 Funds balance
                 during year end close
                                                Gap                   with Treasury
                                                51                                        Funds distribution
                        Gap                                              Gap                                         Independent Gaps
                        49                                               64                    Gap
                                                                                               16
                                                                                               67
           Separation of       Gap                                  Gap     Integration
                                                                                                                     Gap                     Gap
      Obligations from Costs
                                2                                   27      of data                                   59                      66
                                                Gap                                                            Real Property
                                                                                               Gap                                           Phasing Plans
                                                18                                                                             Gap Status:
                                         Conflicting report data
                                                                                               67
                                                                                               16
                                                                                                                               Closed
                                         from different systems                            Loading Budget
                Additional     Gap                                  Gap     Reporting        structures                        In Progress
               WBS levels       1                                    4      standards &                                        Pending
                                                                            automation


• Aspects of gaps 49, 2, 18, 27, 64, 1 & 4 all contribute to the data integrity concerns identified in gap
  51. Contributing gaps will be evaluated prior to gap 51.
• Gaps 1 and 2 both relate to WBS structures and will be evaluated in unison.
• Gaps 4 and 27 both relate to performance assessment/reporting and will be evaluated in unison.
• Resolution of gap 67 will further improve the funds distribution process identified in gap 16.
• Gaps 59 and 66 stand alone.
• Gap 49 was attributed to SVU and corrective actions have been implemented. M/BSIG will verify for
  closure.
• OCFO has developed CAPs and work is in progress for Gaps 64, 16 & 67. No additional workshops
  are scheduled as part of the CAP planning phase for these gaps.
• The CAP development schedule takes into consideration Agency priority, gap relationships and work
  in progress.


                                                                   PM Challenge 2008                                                                         13
Revised - Gap Identification and CAP
                                                              Development Schedule
                            FY07                                                                            FY08                                                            FY09



Mar      Apr      May       Jun    Jul      Aug       Sep     Oct      Nov     Dec     Jan        Feb    Mar        Apr    May        Jun    Jul      Aug     Sep     Oct        Nov

      Gap Identification & Prioritization Phase                                    CAP Development Phase

                                                                                                            Concept Identification Phase


                                                                                   CAP Implementation Phase (Dependent upon approval, $, & human resource availability)
 Decision Point
                                                                                 Decision Point                                                                Decision Point


GAP                                      PM          MSO       M/BSIG       OMC       Evaluate          Evaluate             OMC                                    OMC         PPBE
Identification                          Gaps         Gaps Integration Status           Process          Process             Status                               Approval     Insertion
ATP                                   Identified   Identified      &                      &                &                                                      Concept       Point
                                                             Prioritization           Schedule          Schedule                                               Implementation
                                                                          M/BSIG Cap Review
      Plan                                                                    CAP 1&2               Concepts: 1&2                 M/BSIG Concept Review

                                                                               M/BSIG Cap Review
             Collect Data                                                         CAP 59                   Concepts: 59                 M/BSIG Concept Review

                                                                                       M/BSIG Cap Review
                  Analyze & Process          Prioritization                                CAP 18                  Concepts: 18                    M/BSIG Concept Review
                                                   M/BSIG Prioritization                          M/BSIG Cap Review
                                                   & Integration
                                                                                                  CAP 4&27          Concepts: 4&27                             M/BSIG Concept Review

                                                                                                        M/BSIG Cap Review
                                                                                                           CAP 51                 Concepts: 51                   M/BSIG Concept Review

                                                                                                                   M/BSIG Cap Review
                                                                                                                     CAP 66              Concepts: 66                       M/BSIG
                                                                                                                                                                            Concept
                                                                                                                                                                            Review
                                                                                                                           Optional – CAPS 16, 64, 67 & 49

                                                                                                                                            Optional Concepts: 16, 64, 67 & 49

                                                                              PM Challenge 2008                                                                              14
Agency wide
Business System Concept of Operations
Development




                      PM Challenge 2008   15
ConOps Overview – What is it?


•   A systems engineering tool typically developed early in formulation to describe how a system will
    operate from a users perspective
     –   Not a technical specification; described in layman’s terms:
     –   Describes what exists currently
     –   Describes where the Agency is heading

•   Overview of NASA’s ConOps for agencywide business systems:
     –   Describes the desired operational state of NASA’s Agency-wide business management systems.
            • Will address the business system needs of both the programmatic and institutional communities.
     – Provides a framework to focus future business management systems initiatives by
            • describing agency business functions, processes, and needs
            • defining system boundaries and major system components.
     Note: Detailed process re-engineering and systems modifications will only occur when the Agency makes a
         strategic investment decision to address gaps between the “as is” and “to be” state.

•   Expected Outcomes
     –   Provide a description of the system characteristics from an operational perspective.
     –   Facilitate understanding of the overall system goals with users (including recipients of the products of the
         system, where applicable), buyers, implementers, architects, testers, and managers.
     –   Form an overall basis for long-range operations planning and provide guidance for development and/or
         update of subsequent system definition documents such as the system specification and the interface
         specification.
     –   Describe the user organization and mission from an integrated user/system point of view.
     –   Provide information for strategic and tactical decisions regarding Agency-wide business systems which in
         turn will ultimately improve the availability of management information necessary for mission success.


                                        PM Challenge 2008                                                      16
Background – Why do we need one?


•   Addresses recommendations in the GAO report on business modernization (GAO-
    07-691)
     –   “We recommend that the NASA Administrator establish as a high priority the completion of a
         concept of operations that addresses NASA’s business operations for both its mission
         offices and administrative offices (such as financial management and human capital) before
         any new implementation efforts begin.” (pg. 25)
     –   “For NASA, an effective concept of operations would describe, at a high level, (1) how all of
         the various elements of NASA’s business systems relate to each other and (2) how
         information flows among these systems. Further, a concept of operations would provide a
         useful tool to explain how business systems at the agency can operate cohesively.” (pg. 17)
     –   “As part of an agencywide concept of operations, to best leverage its investment in IEMP,
         NASA should also analyze the agency’s current business process and determine how these
         processes can be made more efficient and effective.” (pg. 28)

•   Key initiative in the NASA plan for improvement in the GAO High-Risk area of
    Contract Management (Initiative F1)
     –   Commitment to baseline ConOps by Sep 08

•   NASA concurs and recognizes the need for an integrated vision for agency wide
    business processes to:
     –   form an overall basis for long-range planning
     –   support business modernization investment decisions
     –   provide Operations’ guidance for system definition and design

                                   PM Challenge 2008                                           17
ConOps informs Decision Making


                         OMC:
                   • Decision Authority




                       M/BSIG:
      • Assess integration and alignment with Agency
                           Priorities
  • Ensure agencywide perspective for new investments
    • Support prioritization of needs, goals, objectives &
                         requirements




                        ConOps


                      PM Challenge 2008                      18
Concept of Operations Approach to Development

•   Development planned through a series of workshops
•   IEEE Standard 1362-1998 provides content guidance
•   SCOPE: Reflects all users needs (including the PM community)
    from agency business functions (including finance, procurement,
    human capital, institutions and administration, and other
    agencywide MSO business systems (as identified))
    – Interfaces to other functions will be documented (e.g. science and engineering,
      project management, and IT infrastructure)
•   Workshops include all NASA stakeholders
    – Information Providers                 – Information Consumers
        • CFO                                    • MDs       • Internal Controls
        • CIO                                    • Centers • Strategic
        • Human Capital                          • OSMA        Communications
        • Institutions and                       • PA&E      • Innovative
          Management                             • OCE         Partnership Program
        • Procurement                            • OPII      • External Relations
    – Information Service Providers              • GC        • Chief Health and
        • IEMP                                                 Medical Officer
                                                 • IG
        • NSSC           All users are information consumers • Others?
                             PM Challenge 2008                                  19
Preliminary Concept of Operations
                              Development Schedule

                                                                         FY08

Oct      Nov      Dec            Jan             Feb              Mar            Apr           May          Jun              Jul            Aug    Sep



         CIT                                                                                1st               2nd                    Baselined
                  Data Gathering               Data Gathering
       Kick-Off                 Integration                     Integration                Draft             Draft                     Draft


Plan    Define
        Scope



                                                                                                                                   Formal
                   Document                            Document                                                      Final
                                                                                 First Draft       Second Draft                     Doc.
                  Current State                        To-Be State                                                   Draft
                                                                                                                                   Review


                                                    Dev.
                                                    Ops.
                                                  Scenario




                                              Development

                                                                   Walkthrough



                                                            PM Challenge 2008                                                                     20
Integration into Agency Management Strategy

                    Integration into Agency IT Strategy for Managing Service
                                          Investments


                                                     The ConOps will describe the future state for the
                                                     Agency’s Business Management Applications Portfolio



                               NPR 2800
NPR 7120.5                        NPR 7120.7                                                    Governance &      Enterprise
                                                                                 Compliance        Policy        Architecture
                                                                                                                                 IT Security
  Highly
Specialized
              Science and        Project        Business
                                                                Infrastructure
Examples:
              Engineering      Management      Management
                                                                 Applications
              Applications     Applications    Applications
Avionics                                                                                        Relationship      Resource        Innovation
software                                                                         Alignment      Management       Management      Management
Real-time
Control                           Infrastructure Services
Systems
Onboard
Processors                                                                                         Service          Project
                    End User         Communications           Data Center    Service Delivery                                    Performance
Deep Space                                                                                         Mgmt. &        Management
                                                                                                                                 Management
Network                                                                                         Delivery (Ops)   (Development)



                    NASA’s IT Portfolios                                                                 CIO Core Functions
                                                              PM Challenge 2008                                                        21
Business Management Portfolio Examples

 Owner
  OCE
  MD’s




  OCE
  MD’s



   ADA
  OCFO
  OHCM
    OP
   I&A
Other MSO’s


   OCIO
   MD’s
  Centers



         OCIO facilitates and provides stewardship for this portfolio management process

                                         PM Challenge 2008                            22
Backup




PM Challenge 2008   23
Projects Selected

Coordinated with 9 M/B SIG organizations to select representative sample of
5 NASA Projects - set includes projects from all four Mission Directorates -
Used formal selection methods with 30 Characteristics in 8 groups

 • Hypersonic Boundary Layer Transition Experiment (Hy-BoLT/HSA) ARMD,
   Workshop and Interviews

 • Geostationary Operational Environmental Satellite (GOES-N)
    – SMD, Workshop and Interviews

 • James Webb Space Telescope (JWST)
    – SMD, Workshop and Interviews

 • International Space Station
    – SOMD, Workshop and Interviews

 • ORION
    – ESMD, Workshop and Interviews
                                PM Challenge 2008                         24
Project Management Gaps
                                                                 Relative Priority Clustering (M/B SIG)

                               Objective: to determine the relative priority thresholds
                                                                                                      Gap-Numbers
                                                                                                                                                                            Clustered Distribution of Priority for Normalized Gaps
                                                                                                                                                                                         (as prioritized by M/B SIG)
                                              6
                                                                                                                                                                                                                                                                                                                            TOP 8 Relatively High
                                                                          15,24,37,52




                                                                                                                                                              12,17,40,41
                                              5
                                                                                                                                                                                                                                                                                                                             Priority PM GAPS
                                                          29,56,58




                                                                                               25,33,48
                                                                                               32,39,57




                                                                                                                                                                                 28,30,31
                                                                                                                                                                                 3,26,'36




                                                                                                                                                                                                                                         6,10,21
                                              4
                             Number of Gaps




                                                                                                                     7,9,55




                                              3
                                                  42,53




                                                                                                             14,35

                                                                                                                              23,46




                                                                                                                                                                                                   11,20




                                                                                                                                                                                                                          43,44
                                                                                        8,50




                                                                                                                                                                                                                                                                                                       4,27
                                              2
                                                                     34




                                                                                                                                                       22

                                                                                                                                                                            19


                                                                                                                                                                                            54


                                                                                                                                                                                                              47


                                                                                                                                                                                                                                  13


                                                                                                                                                                                                                                                          38


                                                                                                                                                                                                                                                                    45




                                                                                                                                                                                                                                                                                                               18




                                                                                                                                                                                                                                                                                                                                                               49




                                                                                                                                                                                                                                                                                                                                                                                                                51


                                                                                                                                                                                                                                                                                                                                                                                                                                16
                                                                                                                                                                                                                                                                    5




                                                                                                                                                                                                                                                                                                                                   1




                                                                                                                                                                                                                                                                                                                                                               2
                                              1

                                              0
                                                   0.1-
                                                             0.2-
                                                                      0.3-
                                                                                    0.4-
                                                                                               0.5-
                                                                                                      0.6-
                                                                                                              0.7-
                                                                                                                        0.8-
                                                                                                                                  0.9-
                                                                                                                                         1.0-
                                                                                                                                                1.1-
                                                                                                                                                       1.2-
                                                                                                                                                                   1.3-
                                                                                                                                                                             1.4-
                                                                                                                                                                                    1.5-
                                                                                                                                                                                            1.6-
                                                                                                                                                                                                    1.7-
                                                                                                                                                                                                           1.8-
                                                                                                                                                                                                                  1.9-
                                                                                                                                                                                                                         2.0-
                                                                                                                                                                                                                                  2.1-
                                                                                                                                                                                                                                         2.2-
                                                                                                                                                                                                                                                   2.3-
                                                                                                                                                                                                                                                           2.4-
                                                                                                                                                                                                                                                                  2.5-
                                                                                                                                                                                                                                                                         2.6-
                                                                                                                                                                                                                                                                                2.7-
                                                                                                                                                                                                                                                                                       2.8-
                                                                                                                                                                                                                                                                                              2.9-
                                                                                                                                                                                                                                                                                                     3.0-
                                                                                                                                                                                                                                                                                                              3.1-
                                                                                                                                                                                                                                                                                                                     3.2-
                                                                                                                                                                                                                                                                                                                            3.3-
                                                                                                                                                                                                                                                                                                                                   3.4-
                                                                                                                                                                                                                                                                                                                                          3.5-
                                                                                                                                                                                                                                                                                                                                                 3.6-
                                                                                                                                                                                                                                                                                                                                                        3.7-
                                                                                                                                                                                                                                                                                                                                                               3.8-
                                                                                                                                                                                                                                                                                                                                                                      3.9-
                                                                                                                                                                                                                                                                                                                                                                             4.0-
                                                                                                                                                                                                                                                                                                                                                                                    4.1-
                                                                                                                                                                                                                                                                                                                                                                                           4.2-
                                                                                                                                                                                                                                                                                                                                                                                                  4.3-
                                                                                                                                                                                                                                                                                                                                                                                                         4.4-
                                                                                                                                                                                                                                                                                                                                                                                                                 4.5-
                                                                                                                                                                                                                                                                                                                                                                                                                        4.6-
                                                                                                                                                                                                                                                                                                                                                                                                                               4.7-
Source File: Gap Priority Distribution 070719-D.xls
                                                                                                                                                                                                                                             Average Priority Weight Assigned by M/B SIG


                                              Low Relative Priority                                                                                                              Medium Relative Priority                                                                                                                                        High Relative Priority


             How to interpret this graph – Gap-16 has average priority weight of 5.6 and is ranked the highest
             by the M/B SIG – Gaps 42 and 53 both have average priority weight of 0.1 and are ranked the lowest
             – based on the apparent cluster groups, the 25 gaps ranked between 0.1 and 1.0 are deemed of
             relatively low priority, the 25 gaps ranked between 1.4 and 3.1 are deemed of relatively medium
             priority, and the 8 gaps ranked between 3.6 and 5.6 are deemed of relatively high priority

                                                                                                                                                                                                   PM Challenge 2008                                                                                                                                                                                                                  25
Functional/Missions Support Gaps
                         Relative Priority Clustering (M/B SIG)

                                    Priority Distributions (High, Medium, Low)

                3

                                                                                                                                      TOP 4 Relatively
                                                                                                                                       High Priority


                                                            61, 72
                                                                                                                                        Functional
Numbere oGaps
   Nm offG s




                2                                                                                                                         GAPS
    u br  ap




                                                  70
                                                       69
                                                               78
                                                                     76
                                                                          60


                                                                                    68
                                                                                         73


                                                                                              77


                                                                                                       75




                                                                                                                 79
                          63
                               62




                                             71




                                                                                                                                                67

                                                                                                                                                     59




                                                                                                                                                                 66
                                                                                                                                                                       64
                1




                0




                                                                                                                                                       0

                                                                                                                                                             5

                                                                                                                                                                   0

                                                                                                                                                                              5
                     0

                          5

                                 0

                                         5

                                                   0

                                                             5

                                                                       0

                                                                                5

                                                                                          0

                                                                                               5

                                                                                                       0


                                                                                                             5

                                                                                                                  0

                                                                                                                        5

                                                                                                                             0

                                                                                                                                  5

                                                                                                                                       0

                                                                                                                                            5
                    1.

                         1.

                                2.

                                        2.

                                                  3.

                                                            3.

                                                                      4.

                                                                               4.

                                                                                         5.

                                                                                              5.

                                                                                                      6.


                                                                                                            6.

                                                                                                                 7.

                                                                                                                       7.

                                                                                                                            8.

                                                                                                                                 8.

                                                                                                                                      9.

                                                                                                                                           9.

                                                                                                                                                     1.
                                                                                                                                                      0

                                                                                                                                                           1.
                                                                                                                                                            0

                                                                                                                                                                 1.
                                                                                                                                                                  1

                                                                                                                                                                            1.
                                                                                                                                                                             1
                                                                                         We ighte d Priority




                                     Relatively Low                                                Relatively Medium                       Relatively High
                                     Priority Gaps                                                   Priority Gaps                          Priority Gaps




                                                                                PM Challenge 2008                                                                                 26
Gap-51 (Ranked Overall Priority 1)

Gap Statement:
• Projects have concerns over the integrity of data in the system
Gap Elaboration:
• The Projects do not have control over charges placed against their WBS so cost data in the system may not reflect the true work performed
  for the Project labor costs, particularly for pool type labor and for comp-credit-over time, are not always timely - the charges may be legitimate
  but not recorded in the period when the work was performed - also, the pooled labor charges may reflect work performed for some other
  Project.
• There are issues with the level of detail in contractor data. In some cases contractors report data at lower levels of detail than the system can
  track (e.g., reports labor and material costs separately but the system can not track them separately). Reports of the "same data" from
  different systems (ALDS, WIMS, WebTADS, etc...) are sometimes different.
• There is a lack of guidance and standardization in which reports and filters to use for which business processes, some reports have built in
  filters or exclusions that are not apparent.
• There is ambiguity and a lack of confidence in the system's data during the several weeks which the system is closed for end-of-year
  processing, and several weeks after the system returns on-line before the data stabilizes.
• After system updates or fixes are installed there often seems to be a large number of errors until the user's figure out what has changed and
  if everything is working properly.
• Projects reported that given the same set of filters, but requesting different levels of drill down, may result in different report totals.
• Project and Center participation in the SVU implementation testing and associated bug fixes did not appear well planned or coordinated (very
  little visibility into the test procedures, no apparent "full system" testing).
• Project can not control costing of funds to a shared contract.
• SAP is configured to require obligations and costing at the same WBS Level, this is apparently based on an Agency Policy. However, it
  forces the Projects to accept a trade off between having a detailed enough WBS (working to low enough WBS levels in SAP to sufficiently
  plan, track, and manage work) against the high level or effort necessary to manipulate SAP at those detailed WBS levels (shifting funds
  across lower level WBS elements requires significant SAP transactions to 'roll back' previous transactions, redistribute guidelines across the
  affected WBS elements, then reenter all the SAP transactions). As a result the projects often accept a higher WBS level of obligation in SAP
  then manually tracking costs at lower WBS levels with spreadsheets or other tools outside the system.
Team Observations:
• There are apparent inconsistencies in some cases when the "same data" is retrieved through different system interfaces or from different
  system reports. Also, the reported labor does not necessarily reflect work actually performed for the project during the reporting period.
• This is a multifaceted issue that includes concerns with the data as well as the applications and processes which handle the data.
• This gap reduces confidence in the accuracy and reliability of the data. It diverts effort from other priorities as Projects cross check and
  manually verify reported data. It can increase the frequency of queries to support organizations trying to reconcile the discrepancies. It may
  also negatively impact a Project's performance trends and will certainly be an issue as the Agency implements EVM.
• NOTE: This is related to Gap-18 but is more focused on issues with data accuracy and level of data resolution where as Gap-18 is more
  focused on issues between data from different reports and system interfaces.
Relative Gap Complexity Factor
• 7-28;28;28;14
                                                          PM Challenge 2008                                                                    27
Gap-2 (Ranked Overall Priority 2)

Gap Statement:
• The projects must obligate and cost funds at the same WBS level
Gap Elaboration:
• SAP is configured to require obligations and costing at the same WBS Level, this is
  apparently based on an Agency Policy. However, it forces the Projects to accept a trade off
  between having a detailed enough WBS (working to low enough WBS levels in SAP to
  sufficiently plan, track, and manage work) against the high level or effort necessary to
  manipulate SAP at those detailed WBS levels (shifting funds across lower level WBS
  elements requires significant SAP transactions to 'roll back' previous transactions,
  redistribute guidelines across the affected WBS elements, then reenter all the SAP
  transactions).
• As a result the projects often accept a higher WBS level of obligation in SAP then manually
  tracking costs at lower WBS levels with spreadsheets or other tools outside the system.
Team Observations:
• The projects indicated that requirements to obligate and cost at the same WBS level
  significantly increases the effort necessary to manage within the system
• This is primarily an Agency policy issue which drove application design constraints.
• This gap forces the Projects to choose between spending the additional effort necessary to
  maintain sufficiently detailed data in the system or spending less effort but maintaining the
  more detailed data outside of the system. The Projects usually chose the path of least effort
  which means some Projects choose to manage critical data outside of the system.
Relative Gap Complexity Factor:
• 5-20;40;20;20


                                    PM Challenge 2008                                      28
Gap-59 (Ranked Overall Priority 3)

Gap Statement:
• The OCFO and the Center Property Custodians do not have a real property
  system, integrated with NASA's financial system, to track the value of
  NASA's real property portfolio.
Gap Elaboration:
• This is necessary to achieve a "clean audit"
• Need a single integrated system that tracks all capital assets for the agency.
• Standardizes real property classifications and ledger accounts (e.g. buildings
  vs. structures)
Projected Benefits:
• Improves NASA's financial integrity
• Eliminates reconciliation data entry resulting in improved efficiency and
  accuracy of the function.




                               PM Challenge 2008                             29
Gap-16 (Ranked Overall Priority 4)

Gap Statement:
• The Projects do not always receive funding in a timely manner.
Gap Elaboration:
• Even after approval of the Agency's operating plan there is often a several week
  delay before projects receive funding.
• The problem appears to be before funds are distributed to the Mission Directorates
  as the MDs seem to quickly distribute funds once received.
• Project must accommodate these delays with work stoppages/delays, contractors
  working at risk, or additional effort to realign remaining prior year budget to cover the
  delayed funds.
Team Observations:
• The Projects indicated that a delay in receiving funds significantly increases the risk
  of not completing as planned.
• This is primarily a process issue.
• This gap can prevent the start of new work and interfere with the timely payment for
  work already in progress. It may result in contractors deciding to begin work at their
  own risk. Projects often divert efforts from other priorities in order to redistribute work
  and available funds. This can negatively impact a Project's performance trends and
  will certainly complicate the ability to produce reliable and accurate EVM reports.
Relative Gap Complexity Factor:
• 2-0;0;50;50

                                    PM Challenge 2008                                      30
Gap-1 (Ranked Overall Priority 5)

Gap Statement:
• The Projects occasionally need more WBS elements (levels) than are available.
Gap Elaboration:
• The projects often use spreadsheets or other tools to establish lower level
  structures for tracking work below the lowest WBS level allowed in SAP.
• This is sometimes related to the need for more visibility into tracking contractor's
  work and cost.
• This also applies to cases where in-house sub project type work is distributed
  across different Centers.
Team Observations:
• Several projects report that the current number of WBS levels available in SAP
  does not provide a sufficiently detailed level of information to effectively manage
  the work.
• This is primarily a policy issue which drove application constraints that limited
  the resolution of data a project can maintain in the system
• This gap results in Projects maintaining necessary levels of WBS detail in other
  tools outside the system. This additional detail is most likely necessary for the
  Agency to implement effective EVM but such data is not available to the SAP
  system.
Relative Gap Complexity Factor:
• 2-50;50;0;0
                                  PM Challenge 2008                                 31
Gap-18 (Ranked Overall Priority 6)

Gap Statement:
• The Projects receive conflicting data when pulling reports on the same information but from different
  systems.
Gap Elaboration:
• Reports on civil servant manpower actuals from different sources (i.e., ALDS, BRIO, WISP, Web TADS)
  can have different numbers - There is ambiguity over the source authority and which system has
  precedence.
• The lag time between pay date and ALDS reporting of charges to the project make it difficult to reconcile
  or make Web TADS changes within the allowed three pay period window.
• This is compounded by the lack of standard reporting policy and templates, each project pulls data from
  the various systems according to their own favorite report, filters, and bookmarks.
• The Agency seems to have multiple systems/interfaces performing the same (or similar) functions (the
  variety of labor and workforce related systems is a prime example). There is ambiguity regarding the
  overlapping roles, responsibilities, and data contents of these systems.
Team Observations:
• Several projects indicated that the data reported from different systems is not always consistent. This
  may be a timing issue related to a lack of some user's awareness about how batch oriented transactions
  propagate data through the systems. It may also be related to confusion over specific roles and
  responsibilities of systems with similar functions.
• This is primarily an application interface issue. However, the lack of a strong Agency policy regarding
  development of a uniform system architecture has allowed multiple and partially redundant systems and
  interfaces to emerge.
• This gap reduces confidence in the system. It diverts efforts from other priorities as Projects evaluate
  multiple reports before selecting which data to report,
• NOTE: This gap is related to Gap-51 but is more specific to the system's labor reports where as Gap-51
  is more specific to the system's data accuracy and data resolution
Relative Gap Complexity Factor:
• 4-25;50;25;0
                                          PM Challenge 2008                                              32
Gap-64 (Ranked Overall Priority 7)

Gap Statement:
• The OCFO does not have an automated process and standardized tools
  necessary to facilitate timely and accurate reconciliation of the SAP funds
  balance with the Treasury general ledger account.
Gap Elaboration:
• NASA's inability to balance funds with Treasury has been an annual audit
  deficiency for years.
• Achievement of a clean audit is a high priority to the administrator.
Projected Benefits:
• Improve NASA's credibility with Congress, OMB, and the general public.
• Improve NASA's efficiency to better utilize the Agency's funds to support
  the mission.
• Increase likelihood of obtaining a clean opinion




                              PM Challenge 2008                             33
Gap-27 (Ranked Overall Priority 8)

Gap Statement:
• Projects report that the integration of WBS, financial, manpower planning, and scheduling data is a
  problematic and manual process.
Gap Elaboration:
• There is no Agency-wide resources/budget integration and planning tool that can be used by different
  Centers working on the same project.
• The IBOT tool works well within JSC but doesn't integrate and provide detail info for work at other
  Centers, the system can't capture actuals across all stakeholders (marrying phasing plan with actuals).
• There is no Agency designated system of record for scheduling data, configuration management data,
  and other critical but non-SAP data - however, there are numerous external and ad-hoc systems which
  Projects and Centers have developed around SAP/BW to provide this integration - such systems provide
  only limited and sometimes questionable integration.
• How to do EVM on large, multi-center, multi-contractor projects using Agency provided tools and a
  standard process hasn't been developed/communicated (No standard process or tools to establish and
  manage EVM baselines).
Team Observations:
• Most Projects indicated there is a lack of guidance and standards for integrated cost, schedule, and work
  planning. There is also a lack of appropriate tools for developing integrated reports.
• This is fundamentally a policy issue. However, the lack of a strong Agency policy regarding the
  development and implementation of a uniform system architecture, has allowed multiple and partially
  redundant systems and interfaces to emerge.
• This gap has contributed to the proliferation of local "integration" tools across then Centers, tools which
  may serve a local need but often do not integrate effectively with other Agency systems. The lack of
  integration across cost, schedule, and work systems will negatively impact the Agency's ability to
  implement effective EVM.
Relative Gap Complexity Factor:
• 4-0;50;50;0

                                          PM Challenge 2008                                               34
Gap-67 (Ranked Overall Priority 9)

Gap Statement:
• NASA does not have the capability to load the next
  fiscal year budget structures prior to current fiscal year
  end close.
Gap Elaboration:
• Delays funds distribution process
• Biggest impact to new initiatives but also delays funding
  to existing projects
Projected Benefits:
• Seamless transition between fiscal years from a funding
  perspective.


                      PM Challenge 2008                  35
Gap-66 (Ranked Overall Priority 10)

Gap Statement:
• The missions and mission support organizations do not have a
  standardized, integrated set of tools and processes to create,
  maintain, track and report phasing plans.
Gap Elaboration:
• Better insight into unobligated balances is necessary to more
  effectively manage funds distribution agency-wide.
• In the year of execution, better insight into our phasing plans and
  performance against those plans will ensure NASA is adequately
  expending appropriated funds.
• An enhanced phasing plan processes and tools also provide
  missions enhanced capability to assess performance.
Projected Benefits:
• Benefits both missions, the CFO, and other institutional
  organizations by allowing CFO to more effectively manage the flow
  of funds.
                           PM Challenge 2008                        36
Gap-4 (Ranked Overall Priority 11)

Gap Statement:
• The projects can not use SAP/BW to meet the current set of reporting requirements.
Gap Elaboration:
• There seems to be no Agency standard process or tools to implement the reporting requirements.
• Projects frequently export data from multiple systems into Excel. The data is then integrated in Excel
  to generate the required reports.
• There are lots of related systems containing data, but the projects can't get integrated reports across
  all the related systems - significant effort is required to manually integrate the data and compile the
  reports.
• Different people/organizations want to see data in different formats - no two seem to have the same
  format requirements - there is no standardization in the reporting format - requires manual translation
  and extra effort.
• The required reporting format often doesn't match the output capabilities of the commonly used tools -
  requiring manual "cut & paste" to create the necessary charts and reports.
Team Observations:
• The existing reporting capabilities of SAP/BW seldom meet the reporting requirements levied on the
  Projects.
• This is primarily an application issue which has been compounded by the lack of reporting standards
  across the Agency.
• This gap causes Projects to spend time and effort exporting and manually integrating relevant data
  into the multiple formats necessary to meet all the different reporting requirements. As a result, it is
  very difficult to maintain consistency in the reporting format and contents across Projects.
Relative Gap Complexity Factor:
• 4-0;50;50;0


                                         PM Challenge 2008                                            37
Gap-49 (Ranked Overall Priority 12)

Gap Statement:
• The Projects have difficulty maintaining effective planning and control during the end-of-year closeout period.
Gap Elaboration:
• SAP is unavailable for a long period of time during end of year closeout/startup.
• When the system comes back on line after the end-of-year closeout the data in the system is often not stable until late
  December or early January. Also, after start-up, a surge of effort is necessary to enter the backlog of manually
  processed transactions.
• Re-bills from pool related charges can cause unexpected changed in a Project's actual costs. The changes sometimes
  occur several weeks after the Project thought the books were closed - there are no reports available to track the re-
  billing activity during the shut down period.
• The Procurement system shuts down (stops accepting non-emergency PRs) several weeks prior to the End-of-Year
  SAP/BW shutdown - This, in conjunction with the efforts to recall and reallocate uncommitted funds, makes it very
  difficult for a Project to maintain stable operations during the last and first quarter of each FY.
• There is an issue with changing WBS numbers each new FY - apparently some types of funds, particularly grant and
  reimbursable funds, may be assigned new WBS numbers which significantly complicates and sometimes prevents the
  year-to-year traceability of the funds.
• Pooling un-obligated funds from previous FYs into a current year WBS makes it difficult to track and manage total
  project costs and reconcile multi year project expenditures.
Team Observations:
• The Projects indicated that the length of time required for year-end closeout seems excessive, especially compared to
  what is heard regarding industry norms. The Projects indicated they are often "working blind" for more than a month
  and have serious concerns about effectively maintaining and reporting project control during this period.
• This is fundamentally a policy issue but from a practical perspective it is more a process and resource issue. (lack of
  resources to more quickly process the volume of end of year transactions).
• This gap increases the use of manual processes and temporary workarounds, causes a surge in the demands placed
  on support organizations, and prevents the Projects from pulling accurate and timely reports for more than a month.
Relative Gap Complexity Factor:
• 28-18;29;35;18


                                               PM Challenge 2008                                                    38
Concept of Operations Document

      IEEE Standard 1362-1998 defines the content of ConOps as:
1. Scope                                              5. Concepts for the proposed system
    a) Identification                                         a)   Background, objectives and scope
    b) Document Overview                                      b)   Operational policies and constraints
    c) System Overview                                        c)   Description of current system
2. Referenced Documents                                       d)   Modes of operation
                                                              e)   User classes and other involved personnel
3. Current system
                                                              f)   Support Environment
    a)   Background, objectives and scope
    b)   Operational policies and constraints
                                                      6. Operational Scenarios
    c)   Description of current system                7. Summary of impacts
    d)   Modes of operation                                   a) Operational Impacts
    e)   User classes and other involved personnel            b) Organizational Impacts
    f)   Support Environment                                  c) Impacts during development
4. Justification for and nature of changes            8. Analysis of the proposed system
    a)   Justification of changes                     9. Notes
    b)   Description of desired changes
    c)   Priorities among changes
    d)   Changes considered but not included

                                          PM Challenge 2008                                            39

More Related Content

What's hot

ITIL® im Microsoft-Umfeld: Einführung in das MOF
ITIL® im Microsoft-Umfeld: Einführung in das MOFITIL® im Microsoft-Umfeld: Einführung in das MOF
ITIL® im Microsoft-Umfeld: Einführung in das MOF
Digicomp Academy AG
 
Mohamad Afshar Moving Beyond Project Level S O A
Mohamad  Afshar    Moving Beyond Project Level S O AMohamad  Afshar    Moving Beyond Project Level S O A
Mohamad Afshar Moving Beyond Project Level S O A
SOA Symposium
 
Конфигурация и соответствие: две половины единого целого.
 Конфигурация и соответствие: две половины единого целого. Конфигурация и соответствие: две половины единого целого.
Конфигурация и соответствие: две половины единого целого.
Cisco Russia
 
Cobit, itil and cmmi - a tutorial
Cobit, itil and cmmi  - a tutorialCobit, itil and cmmi  - a tutorial
Cobit, itil and cmmi - a tutorial
seveman
 

What's hot (20)

COBIT 5 & 4.1 Comparison
COBIT 5 & 4.1 ComparisonCOBIT 5 & 4.1 Comparison
COBIT 5 & 4.1 Comparison
 
What is EA In a Nutshell
What is EA In a NutshellWhat is EA In a Nutshell
What is EA In a Nutshell
 
MEEA Technical Webinar: A New Approach to Estimating Free Ridership in Upstre...
MEEA Technical Webinar: A New Approach to Estimating Free Ridership in Upstre...MEEA Technical Webinar: A New Approach to Estimating Free Ridership in Upstre...
MEEA Technical Webinar: A New Approach to Estimating Free Ridership in Upstre...
 
ITIL® im Microsoft-Umfeld: Einführung in das MOF
ITIL® im Microsoft-Umfeld: Einführung in das MOFITIL® im Microsoft-Umfeld: Einführung in das MOF
ITIL® im Microsoft-Umfeld: Einführung in das MOF
 
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
Gestión de Gobierno, Riesgos y Reglamentaciones (GRC)
 
Microsoft Business Intelligence Performance Management Dan Bulos_2011
Microsoft Business Intelligence Performance Management Dan Bulos_2011Microsoft Business Intelligence Performance Management Dan Bulos_2011
Microsoft Business Intelligence Performance Management Dan Bulos_2011
 
Mohamad Afshar Moving Beyond Project Level S O A
Mohamad  Afshar    Moving Beyond Project Level S O AMohamad  Afshar    Moving Beyond Project Level S O A
Mohamad Afshar Moving Beyond Project Level S O A
 
Moving Beyond Project Level SOA
Moving Beyond Project Level SOAMoving Beyond Project Level SOA
Moving Beyond Project Level SOA
 
Configuration Management Best Practices
Configuration Management Best PracticesConfiguration Management Best Practices
Configuration Management Best Practices
 
Andre Tost S G M M
Andre  Tost    S G M MAndre  Tost    S G M M
Andre Tost S G M M
 
IBM Software Day 2013. Process innovation
IBM Software Day 2013. Process innovationIBM Software Day 2013. Process innovation
IBM Software Day 2013. Process innovation
 
iso 20000
iso 20000iso 20000
iso 20000
 
Ed Mayer- Getting from Good Requirements to Good Code
Ed Mayer- Getting from Good Requirements to Good CodeEd Mayer- Getting from Good Requirements to Good Code
Ed Mayer- Getting from Good Requirements to Good Code
 
Конфигурация и соответствие: две половины единого целого.
 Конфигурация и соответствие: две половины единого целого. Конфигурация и соответствие: две половины единого целого.
Конфигурация и соответствие: две половины единого целого.
 
Green EA
Green EAGreen EA
Green EA
 
Cobit, itil and cmmi - a tutorial
Cobit, itil and cmmi  - a tutorialCobit, itil and cmmi  - a tutorial
Cobit, itil and cmmi - a tutorial
 
Cobit 4.1 Highlights
Cobit 4.1 HighlightsCobit 4.1 Highlights
Cobit 4.1 Highlights
 
M2MSys ITIL Executive Summary
M2MSys ITIL Executive SummaryM2MSys ITIL Executive Summary
M2MSys ITIL Executive Summary
 
Business Process Managmenet & Intelligent BPM Suites
Business Process Managmenet & Intelligent BPM SuitesBusiness Process Managmenet & Intelligent BPM Suites
Business Process Managmenet & Intelligent BPM Suites
 
Day 3 p1 - itsm
Day 3   p1 - itsmDay 3   p1 - itsm
Day 3 p1 - itsm
 

Viewers also liked

Stambolianv2
Stambolianv2Stambolianv2
Stambolianv2
NASAPMC
 
Risk.panel handout
Risk.panel handoutRisk.panel handout
Risk.panel handout
NASAPMC
 
Augustin.debbie
Augustin.debbieAugustin.debbie
Augustin.debbie
NASAPMC
 
Project management roundtable summary final
Project management roundtable summary finalProject management roundtable summary final
Project management roundtable summary final
NASAPMC
 
Lou.wheatcraft
Lou.wheatcraftLou.wheatcraft
Lou.wheatcraft
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Snow lee
Snow leeSnow lee
Snow lee
NASAPMC
 

Viewers also liked (20)

Stambolianv2
Stambolianv2Stambolianv2
Stambolianv2
 
Risk.panel handout
Risk.panel handoutRisk.panel handout
Risk.panel handout
 
Augustin.debbie
Augustin.debbieAugustin.debbie
Augustin.debbie
 
Project management roundtable summary final
Project management roundtable summary finalProject management roundtable summary final
Project management roundtable summary final
 
Lou.wheatcraft
Lou.wheatcraftLou.wheatcraft
Lou.wheatcraft
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Wood frank
Wood frankWood frank
Wood frank
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Paradis william
Paradis williamParadis william
Paradis william
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
Yew manson
Yew mansonYew manson
Yew manson
 
Snow lee
Snow leeSnow lee
Snow lee
 

Similar to Sandra.smalley

Bush.stewart
Bush.stewartBush.stewart
Bush.stewart
NASAPMC
 
A model for optimizing process efficiency in multi stream data keying environ...
A model for optimizing process efficiency in multi stream data keying environ...A model for optimizing process efficiency in multi stream data keying environ...
A model for optimizing process efficiency in multi stream data keying environ...
Daniel Hillman
 
Governance Maturity Assessment Report
Governance Maturity Assessment ReportGovernance Maturity Assessment Report
Governance Maturity Assessment Report
smcasas
 
Bpr Process Modeling
Bpr Process ModelingBpr Process Modeling
Bpr Process Modeling
rlynes
 
Cmmi agile kulpa 2004meas cmmi[1]
Cmmi  agile kulpa 2004meas cmmi[1]Cmmi  agile kulpa 2004meas cmmi[1]
Cmmi agile kulpa 2004meas cmmi[1]
JULIO GONZALEZ SANZ
 
Strivent Service Offerings Differentiators Web 2 9
Strivent Service Offerings  Differentiators Web 2 9Strivent Service Offerings  Differentiators Web 2 9
Strivent Service Offerings Differentiators Web 2 9
John Streit
 

Similar to Sandra.smalley (20)

Quick Start Advantage
Quick Start AdvantageQuick Start Advantage
Quick Start Advantage
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
RequirementPro™ Architecture
RequirementPro™ ArchitectureRequirementPro™ Architecture
RequirementPro™ Architecture
 
ERP Implementation cycle
ERP Implementation cycleERP Implementation cycle
ERP Implementation cycle
 
Cisco Data Sheet SORM
Cisco Data Sheet SORM Cisco Data Sheet SORM
Cisco Data Sheet SORM
 
Case study development of share point service business architecture 2010 08-0...
Case study development of share point service business architecture 2010 08-0...Case study development of share point service business architecture 2010 08-0...
Case study development of share point service business architecture 2010 08-0...
 
Infusing EPM in people and process
Infusing EPM in people and processInfusing EPM in people and process
Infusing EPM in people and process
 
The road to System Center Service Manager 2012 - case study
The road to System Center Service Manager 2012 - case studyThe road to System Center Service Manager 2012 - case study
The road to System Center Service Manager 2012 - case study
 
Bush.stewart
Bush.stewartBush.stewart
Bush.stewart
 
A model for optimizing process efficiency in multi stream data keying environ...
A model for optimizing process efficiency in multi stream data keying environ...A model for optimizing process efficiency in multi stream data keying environ...
A model for optimizing process efficiency in multi stream data keying environ...
 
Outsourcing Best Practices - Process Efficiency
Outsourcing Best Practices - Process EfficiencyOutsourcing Best Practices - Process Efficiency
Outsourcing Best Practices - Process Efficiency
 
Considerations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentConsiderations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT Investment
 
Governance Maturity Assessment Report
Governance Maturity Assessment ReportGovernance Maturity Assessment Report
Governance Maturity Assessment Report
 
ISP
ISPISP
ISP
 
Enterprise Unified Process (EUP)
Enterprise Unified Process (EUP)Enterprise Unified Process (EUP)
Enterprise Unified Process (EUP)
 
An Exploration: Moving Your Enterprise to a Cloud Collaboration
An Exploration: Moving Your Enterprise to a Cloud CollaborationAn Exploration: Moving Your Enterprise to a Cloud Collaboration
An Exploration: Moving Your Enterprise to a Cloud Collaboration
 
PMI Presentation2
PMI Presentation2PMI Presentation2
PMI Presentation2
 
Bpr Process Modeling
Bpr Process ModelingBpr Process Modeling
Bpr Process Modeling
 
Cmmi agile kulpa 2004meas cmmi[1]
Cmmi  agile kulpa 2004meas cmmi[1]Cmmi  agile kulpa 2004meas cmmi[1]
Cmmi agile kulpa 2004meas cmmi[1]
 
Strivent Service Offerings Differentiators Web 2 9
Strivent Service Offerings  Differentiators Web 2 9Strivent Service Offerings  Differentiators Web 2 9
Strivent Service Offerings Differentiators Web 2 9
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
NASAPMC
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
NASAPMC
 
Martt anne
Martt anneMartt anne
Martt anne
NASAPMC
 
Manzer fred
Manzer fredManzer fred
Manzer fred
NASAPMC
 
Manthos jeff
Manthos jeffManthos jeff
Manthos jeff
NASAPMC
 
Lengyel dave
Lengyel daveLengyel dave
Lengyel dave
NASAPMC
 
Krahula john
Krahula johnKrahula john
Krahula john
NASAPMC
 
Kroeger lin
Kroeger linKroeger lin
Kroeger lin
NASAPMC
 
Krage jousha
Krage joushaKrage jousha
Krage jousha
NASAPMC
 
Kotnour tim
Kotnour timKotnour tim
Kotnour tim
NASAPMC
 

More from NASAPMC (15)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Wood frank
Wood frankWood frank
Wood frank
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
 
Martt anne
Martt anneMartt anne
Martt anne
 
Manzer fred
Manzer fredManzer fred
Manzer fred
 
Manthos jeff
Manthos jeffManthos jeff
Manthos jeff
 
Lengyel dave
Lengyel daveLengyel dave
Lengyel dave
 
Krahula john
Krahula johnKrahula john
Krahula john
 
Kroeger lin
Kroeger linKroeger lin
Kroeger lin
 
Krage jousha
Krage joushaKrage jousha
Krage jousha
 
Kotnour tim
Kotnour timKotnour tim
Kotnour tim
 

Recently uploaded

Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 

Recently uploaded (20)

Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 

Sandra.smalley

  • 1. 2008 PM Challenge NASA’s Business Systems Are they working for you? Sandra Smalley OCIO IEMP Integration Manager ssmalley@nasa.gov 202-358-4731 PM Challenge 2008 1
  • 2. Contents • M/BSIG – Background – Membership – Overview of Requirements Governance • Gap Analysis Activity – Gap Definition, Scope and Depth – GAP Corrective Action Plan development process – Identification Process Summary – Gap Statement Summary – M/BSIG integration and prioritization results – Gap relationships and corrective action strategy – CAP Schedule • Concept of Operations (ConOps) Overview – Overview – Background – ConOps Development Approach – ConOps Schedule – Integration into CIO’s management strategy – Business system portfolio examples PM Challenge 2008 2
  • 3. Background - Management/Business System Integration Group (M/B SIG) • IPAO/PA&E White Paper presented to OMC resulted in OMC action to perform gap analysis and establish M/BSIG – July 2006 • M/BSIG Kick-Off Meeting Held - January 2007 • Charter signed - February 2007 – The charter of the M/BSIG is to assess and prioritize future business system requirements to ensure integration and alignment with Agency goals and objectives – Participants included PA&E, OCE, MD’s, OCFO, OCIO, NSSC, OHCM, I&A, OP, OPII, MSFC, GRC, GSFC, and IEMP (ex-officio) • Charter updated – October 12, 2007 to: – include all ten centers – reflect decision authority of the associate deputy administrator – reflect scope expansion to include all agency-wide business systems – include records retention process PM Challenge 2008 3
  • 4. M/B SIG Membership as of November 2007 • ARMD – John Scholtz • GRC – Harvey Schabes • ESMD – Marlana Dorman • GSFC – George Barth • SMD – Craig Tupper • DFRC – John Wonacott • SOMD – Toni Mumford • LaRC – Dan Tenny • MSFC – Johnny Stephenson • SSC – Kern Witcher • PA&E- Cherish Johnson • JSC – Lucy Kranz • OCE – Mike Blythe • KSC – Vanessa Stromer • OCFO – Daphne Jefferson • JPL – Joanne Kennedy • OCIO – Gary Cox • ARC – Trish Morrissey • OCHM – Candy Irwin • HQ(Center) – Michele O’Connell • I&A – Jim Wright • IEMP – Bobby German • OP – Ken Stepka • NSSC – Joyce Short • OPII – Rita Svarcas • Facilitator – Sandra Smalley PM Challenge 2008 4
  • 5. M/BSIG Responsibilities • Ensuring the management and business system needs, goals, and objectives of all relevant stakeholders (e.g., internal NASA stakeholders as well as external authority stakeholders) are proactively elicited and considered when new or revised systems are developed. • Ensuring the management and business system requirements are developed with an integrated Agency-wide perspective. • Ensuring the management and business system priorities and the sequencing or phasing of implementation efforts (e.g. policy updates, process re-engineering, IEMP projects) are developed in recognition of budgeting, resource, and other constraints (e.g., compliance with Federal laws, regulations, and policies; other externally mandated requirements). • Ensuring integration of Agency-wide business system requirements and alignment with Agency priorities. • Ensuring Agency-wide business system requirements are traceable throughout the entire requirements chain. • Ensuring major stakeholder proposals relating to new or changing business system scope, content, and priorities are appropriately reviewed from an integrated Agency-wide perspective. • Ensuring oversight and direction of management and business system initiatives are appropriately focused on cross system integration and the reduction of stove-piped and redundant data silos. PM Challenge 2008 5
  • 6. Overview of Requirements Governance Operations Management Council OCIO IT Strategy and IT DM&E Investment Board Requirements Planning & Execution IT DM&E Performance Management Management Assessment Status Briefings & Recommended Actions Implement Implement Recommendations for & Requirements via the Non-IT IT-DM&E (1) Significant Associate Deputy DM&E Actions Changes to Project Administrator Actions Baseline, or (2) Termination of Projects System Program Execution Status Coordination Implementers M/BSIG (IEMP, NSSC, etc.) OCIO PMB •Projects Project Performance Reporting •Sustaining Operations Lower Level Requirements Priorities & Needs & Decisions Requirements for Cross-Functional Lower Level Lower Level Review and Prioritization Process/ Requirements Requirements Governed Issues Functional by the Requirements Management Owners Framework Customers (Mission & Mission Support Orgs) PM Challenge 2008 6
  • 7. Gap Analysis PM Challenge 2008 7
  • 8. Gap Definition, Scope and Depth • Gaps exist when the contents or behaviors of systems, in this case NASA’s Management and Business Systems, are different from what is needed. • Four general types of system Gaps: 1. Data 2. Process • Incomplete data • Non-congruent with local processes • Missing data • Work-around solutions • Redundant data • Outside post-processing of the • Incorrect data system data 2. Application 3. Human • Inability to retrieve data • Changing roles and responsibilities • Inability to input data • Training and knowledge of the • Inability to modify data system • Non-standard practices • Scope: – Includes all Agency-wide systems which process and/or provide management and business related information • Depth: – Includes gaps associated with the data, applications, processes, and the human aspects of the management and business systems PM Challenge 2008 8
  • 9. Gap Corrective Action Plan (CAP) Development Process GAP Identification and OMC/OCIO SIB Prioritization Phase Approval • Plan • Collect & characterize data activity CAP Development Is IT DM&E • Analyze & Process data Phase Required? * • Prioritize gaps N • Identify stakeholders • Design workshop Y • Perform causal analysis • Develop corrective Concept Identification CAP Implementation action plan (including Phase Phase identification of • Develop candidate concepts, requirements) cost estimates, and • Brief M/BSIG schedules • Perform trade studies • Develop cost estimates • Develop M/BSIG implementation recommendation • Present to the OCIO SIB • Submit approved recommendation for inclusion in the PPBE M/BSIG Oversight * IT DM&E: Information Technology Development, Modernization, or Enhancement PM Challenge 2008 9
  • 10. Gap Identification & Ranking Process Summary • Project Management Gaps were collected from 5 representative projects – 58 Gaps were prioritized utilizing by the M/BSIG in July 2007 using a Delphi process – 8 Project Management Gaps were identified as relatively high priority • Functional Gaps were collected from Procurement, Human Capital, Institutions and Administration, and Finance – 19 Gaps were prioritized by the M/BSIG in September 2007 using a Delphi process – 4 Functional Gaps were identified as relatively high priority • The M/BSIG integrated and prioritized the resulting top 12 project management and functional gaps on October 1 & 2, 2007 using an Analytic Hierarchy Process (AHP) PM Challenge 2008 10
  • 11. Gap Statements Summary The Relatively High Priority Gaps Project Management Functional/Mission Support Priority Gap # Gap Description Priority Gap # Gap Description 1 Gap-16 The Projects do not always receive 1 Gap-64 The OCFO does not have an funding in a timely manner. automated process and standardized 2 Gap-51 Projects have concerns over the tools necessary to facilitate timely and integrity of data in the system. accurate reconciliation of the SAP 3 Gap-2 The projects are limited by system funds balance with the Treasury configuration to obligate and cost funds general ledger account. at the same WBS level. 2 Gap-66 The missions and mission support 4 Gap-49 The Projects have difficulty maintaining organizations do not have a effective planning and control during standardized, integrated set of tools the end-of-year closeout period. and processes to create, maintain, 5 Gap-1 The Projects occasionally need more track and report phasing plans. WBS elements (levels) than are 3 Gap-59 The OCFO and the Center Property available. Custodians do not have a real property 6 Gap-18 The Projects receive conflicting data system, integrated with NASA’s when pulling reports on the same financial system, to track the value of information but from different systems. NASA’s real property portfolio. 7 Gap-4 The projects can not use SAP/BW to 4 Gap-67 NASA does not have the capability to meet the current set of reporting load the next fiscal year budget requirements. structure prior to current fiscal year end 8 Gap-27 Projects report that the integration of close. WBS, financial, manpower planning, and scheduling data is a problematic and manual process. PM Challenge 2008 11
  • 12. M/BSIG Integrated Gap Prioritization based upon “Benefit to the Agency” Priority Gap Statement 1 Gap 51 Projects have concerns over the integrity of data in the system. 2 Gap 2 The projects must obligate and cost funds at the same WBS level. The OCFO and the Center Property Custodians do not have a real property system, 3 Gap 59 integrated with NASA's financial system, to track the value of NASA's real property portfolio. 4 Gap 16 The Projects do not always receive funding in a timely manner. 5 Gap 1 The Projects occasionally need more WBS elements (levels) than are available. The Projects receive conflicting data when pulling reports on the same information but from 6 Gap 18 different systems. The OCFO does not have an automated process and standardized tools necessary to 7 Gap 64 facilitate timely and accurate reconciliation of the SAP funds balance with the Treasury general ledger account. Projects report that the integration of WBS, financial, manpower planning, and scheduling 8 Gap 27 data is a problematic and manual process. NASA does not have the capability to load the next fiscal year budget structures prior to 9 Gap 67 current fiscal year end close. The missions and mission support organizations do not have a standardized, integrated set 10 Gap 66 of tools and processes to create, maintain, track and report phasing plans. 11 Gap 4 The projects can not use SAP/BW to meet the current set of reporting requirements. The Projects have difficulty maintaining effective planning and control during the end of year 12 Gap 49 closeout period. PM Challenge 2008 12
  • 13. Gap Relationships Data Integrity Planning and Control Funds balance during year end close Gap with Treasury 51 Funds distribution Gap Gap Independent Gaps 49 64 Gap 16 67 Separation of Gap Gap Integration Gap Gap Obligations from Costs 2 27 of data 59 66 Gap Real Property Gap Phasing Plans 18 Gap Status: Conflicting report data 67 16 Closed from different systems Loading Budget Additional Gap Gap Reporting structures In Progress WBS levels 1 4 standards & Pending automation • Aspects of gaps 49, 2, 18, 27, 64, 1 & 4 all contribute to the data integrity concerns identified in gap 51. Contributing gaps will be evaluated prior to gap 51. • Gaps 1 and 2 both relate to WBS structures and will be evaluated in unison. • Gaps 4 and 27 both relate to performance assessment/reporting and will be evaluated in unison. • Resolution of gap 67 will further improve the funds distribution process identified in gap 16. • Gaps 59 and 66 stand alone. • Gap 49 was attributed to SVU and corrective actions have been implemented. M/BSIG will verify for closure. • OCFO has developed CAPs and work is in progress for Gaps 64, 16 & 67. No additional workshops are scheduled as part of the CAP planning phase for these gaps. • The CAP development schedule takes into consideration Agency priority, gap relationships and work in progress. PM Challenge 2008 13
  • 14. Revised - Gap Identification and CAP Development Schedule FY07 FY08 FY09 Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Gap Identification & Prioritization Phase CAP Development Phase Concept Identification Phase CAP Implementation Phase (Dependent upon approval, $, & human resource availability) Decision Point Decision Point Decision Point GAP PM MSO M/BSIG OMC Evaluate Evaluate OMC OMC PPBE Identification Gaps Gaps Integration Status Process Process Status Approval Insertion ATP Identified Identified & & & Concept Point Prioritization Schedule Schedule Implementation M/BSIG Cap Review Plan CAP 1&2 Concepts: 1&2 M/BSIG Concept Review M/BSIG Cap Review Collect Data CAP 59 Concepts: 59 M/BSIG Concept Review M/BSIG Cap Review Analyze & Process Prioritization CAP 18 Concepts: 18 M/BSIG Concept Review M/BSIG Prioritization M/BSIG Cap Review & Integration CAP 4&27 Concepts: 4&27 M/BSIG Concept Review M/BSIG Cap Review CAP 51 Concepts: 51 M/BSIG Concept Review M/BSIG Cap Review CAP 66 Concepts: 66 M/BSIG Concept Review Optional – CAPS 16, 64, 67 & 49 Optional Concepts: 16, 64, 67 & 49 PM Challenge 2008 14
  • 15. Agency wide Business System Concept of Operations Development PM Challenge 2008 15
  • 16. ConOps Overview – What is it? • A systems engineering tool typically developed early in formulation to describe how a system will operate from a users perspective – Not a technical specification; described in layman’s terms: – Describes what exists currently – Describes where the Agency is heading • Overview of NASA’s ConOps for agencywide business systems: – Describes the desired operational state of NASA’s Agency-wide business management systems. • Will address the business system needs of both the programmatic and institutional communities. – Provides a framework to focus future business management systems initiatives by • describing agency business functions, processes, and needs • defining system boundaries and major system components. Note: Detailed process re-engineering and systems modifications will only occur when the Agency makes a strategic investment decision to address gaps between the “as is” and “to be” state. • Expected Outcomes – Provide a description of the system characteristics from an operational perspective. – Facilitate understanding of the overall system goals with users (including recipients of the products of the system, where applicable), buyers, implementers, architects, testers, and managers. – Form an overall basis for long-range operations planning and provide guidance for development and/or update of subsequent system definition documents such as the system specification and the interface specification. – Describe the user organization and mission from an integrated user/system point of view. – Provide information for strategic and tactical decisions regarding Agency-wide business systems which in turn will ultimately improve the availability of management information necessary for mission success. PM Challenge 2008 16
  • 17. Background – Why do we need one? • Addresses recommendations in the GAO report on business modernization (GAO- 07-691) – “We recommend that the NASA Administrator establish as a high priority the completion of a concept of operations that addresses NASA’s business operations for both its mission offices and administrative offices (such as financial management and human capital) before any new implementation efforts begin.” (pg. 25) – “For NASA, an effective concept of operations would describe, at a high level, (1) how all of the various elements of NASA’s business systems relate to each other and (2) how information flows among these systems. Further, a concept of operations would provide a useful tool to explain how business systems at the agency can operate cohesively.” (pg. 17) – “As part of an agencywide concept of operations, to best leverage its investment in IEMP, NASA should also analyze the agency’s current business process and determine how these processes can be made more efficient and effective.” (pg. 28) • Key initiative in the NASA plan for improvement in the GAO High-Risk area of Contract Management (Initiative F1) – Commitment to baseline ConOps by Sep 08 • NASA concurs and recognizes the need for an integrated vision for agency wide business processes to: – form an overall basis for long-range planning – support business modernization investment decisions – provide Operations’ guidance for system definition and design PM Challenge 2008 17
  • 18. ConOps informs Decision Making OMC: • Decision Authority M/BSIG: • Assess integration and alignment with Agency Priorities • Ensure agencywide perspective for new investments • Support prioritization of needs, goals, objectives & requirements ConOps PM Challenge 2008 18
  • 19. Concept of Operations Approach to Development • Development planned through a series of workshops • IEEE Standard 1362-1998 provides content guidance • SCOPE: Reflects all users needs (including the PM community) from agency business functions (including finance, procurement, human capital, institutions and administration, and other agencywide MSO business systems (as identified)) – Interfaces to other functions will be documented (e.g. science and engineering, project management, and IT infrastructure) • Workshops include all NASA stakeholders – Information Providers – Information Consumers • CFO • MDs • Internal Controls • CIO • Centers • Strategic • Human Capital • OSMA Communications • Institutions and • PA&E • Innovative Management • OCE Partnership Program • Procurement • OPII • External Relations – Information Service Providers • GC • Chief Health and • IEMP Medical Officer • IG • NSSC All users are information consumers • Others? PM Challenge 2008 19
  • 20. Preliminary Concept of Operations Development Schedule FY08 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep CIT 1st 2nd Baselined Data Gathering Data Gathering Kick-Off Integration Integration Draft Draft Draft Plan Define Scope Formal Document Document Final First Draft Second Draft Doc. Current State To-Be State Draft Review Dev. Ops. Scenario Development Walkthrough PM Challenge 2008 20
  • 21. Integration into Agency Management Strategy Integration into Agency IT Strategy for Managing Service Investments The ConOps will describe the future state for the Agency’s Business Management Applications Portfolio NPR 2800 NPR 7120.5 NPR 7120.7 Governance & Enterprise Compliance Policy Architecture IT Security Highly Specialized Science and Project Business Infrastructure Examples: Engineering Management Management Applications Applications Applications Applications Avionics Relationship Resource Innovation software Alignment Management Management Management Real-time Control Infrastructure Services Systems Onboard Processors Service Project End User Communications Data Center Service Delivery Performance Deep Space Mgmt. & Management Management Network Delivery (Ops) (Development) NASA’s IT Portfolios CIO Core Functions PM Challenge 2008 21
  • 22. Business Management Portfolio Examples Owner OCE MD’s OCE MD’s ADA OCFO OHCM OP I&A Other MSO’s OCIO MD’s Centers OCIO facilitates and provides stewardship for this portfolio management process PM Challenge 2008 22
  • 24. Projects Selected Coordinated with 9 M/B SIG organizations to select representative sample of 5 NASA Projects - set includes projects from all four Mission Directorates - Used formal selection methods with 30 Characteristics in 8 groups • Hypersonic Boundary Layer Transition Experiment (Hy-BoLT/HSA) ARMD, Workshop and Interviews • Geostationary Operational Environmental Satellite (GOES-N) – SMD, Workshop and Interviews • James Webb Space Telescope (JWST) – SMD, Workshop and Interviews • International Space Station – SOMD, Workshop and Interviews • ORION – ESMD, Workshop and Interviews PM Challenge 2008 24
  • 25. Project Management Gaps Relative Priority Clustering (M/B SIG) Objective: to determine the relative priority thresholds Gap-Numbers Clustered Distribution of Priority for Normalized Gaps (as prioritized by M/B SIG) 6 TOP 8 Relatively High 15,24,37,52 12,17,40,41 5 Priority PM GAPS 29,56,58 25,33,48 32,39,57 28,30,31 3,26,'36 6,10,21 4 Number of Gaps 7,9,55 3 42,53 14,35 23,46 11,20 43,44 8,50 4,27 2 34 22 19 54 47 13 38 45 18 49 51 16 5 1 2 1 0 0.1- 0.2- 0.3- 0.4- 0.5- 0.6- 0.7- 0.8- 0.9- 1.0- 1.1- 1.2- 1.3- 1.4- 1.5- 1.6- 1.7- 1.8- 1.9- 2.0- 2.1- 2.2- 2.3- 2.4- 2.5- 2.6- 2.7- 2.8- 2.9- 3.0- 3.1- 3.2- 3.3- 3.4- 3.5- 3.6- 3.7- 3.8- 3.9- 4.0- 4.1- 4.2- 4.3- 4.4- 4.5- 4.6- 4.7- Source File: Gap Priority Distribution 070719-D.xls Average Priority Weight Assigned by M/B SIG Low Relative Priority Medium Relative Priority High Relative Priority How to interpret this graph – Gap-16 has average priority weight of 5.6 and is ranked the highest by the M/B SIG – Gaps 42 and 53 both have average priority weight of 0.1 and are ranked the lowest – based on the apparent cluster groups, the 25 gaps ranked between 0.1 and 1.0 are deemed of relatively low priority, the 25 gaps ranked between 1.4 and 3.1 are deemed of relatively medium priority, and the 8 gaps ranked between 3.6 and 5.6 are deemed of relatively high priority PM Challenge 2008 25
  • 26. Functional/Missions Support Gaps Relative Priority Clustering (M/B SIG) Priority Distributions (High, Medium, Low) 3 TOP 4 Relatively High Priority 61, 72 Functional Numbere oGaps Nm offG s 2 GAPS u br ap 70 69 78 76 60 68 73 77 75 79 63 62 71 67 59 66 64 1 0 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 1. 1. 2. 2. 3. 3. 4. 4. 5. 5. 6. 6. 7. 7. 8. 8. 9. 9. 1. 0 1. 0 1. 1 1. 1 We ighte d Priority Relatively Low Relatively Medium Relatively High Priority Gaps Priority Gaps Priority Gaps PM Challenge 2008 26
  • 27. Gap-51 (Ranked Overall Priority 1) Gap Statement: • Projects have concerns over the integrity of data in the system Gap Elaboration: • The Projects do not have control over charges placed against their WBS so cost data in the system may not reflect the true work performed for the Project labor costs, particularly for pool type labor and for comp-credit-over time, are not always timely - the charges may be legitimate but not recorded in the period when the work was performed - also, the pooled labor charges may reflect work performed for some other Project. • There are issues with the level of detail in contractor data. In some cases contractors report data at lower levels of detail than the system can track (e.g., reports labor and material costs separately but the system can not track them separately). Reports of the "same data" from different systems (ALDS, WIMS, WebTADS, etc...) are sometimes different. • There is a lack of guidance and standardization in which reports and filters to use for which business processes, some reports have built in filters or exclusions that are not apparent. • There is ambiguity and a lack of confidence in the system's data during the several weeks which the system is closed for end-of-year processing, and several weeks after the system returns on-line before the data stabilizes. • After system updates or fixes are installed there often seems to be a large number of errors until the user's figure out what has changed and if everything is working properly. • Projects reported that given the same set of filters, but requesting different levels of drill down, may result in different report totals. • Project and Center participation in the SVU implementation testing and associated bug fixes did not appear well planned or coordinated (very little visibility into the test procedures, no apparent "full system" testing). • Project can not control costing of funds to a shared contract. • SAP is configured to require obligations and costing at the same WBS Level, this is apparently based on an Agency Policy. However, it forces the Projects to accept a trade off between having a detailed enough WBS (working to low enough WBS levels in SAP to sufficiently plan, track, and manage work) against the high level or effort necessary to manipulate SAP at those detailed WBS levels (shifting funds across lower level WBS elements requires significant SAP transactions to 'roll back' previous transactions, redistribute guidelines across the affected WBS elements, then reenter all the SAP transactions). As a result the projects often accept a higher WBS level of obligation in SAP then manually tracking costs at lower WBS levels with spreadsheets or other tools outside the system. Team Observations: • There are apparent inconsistencies in some cases when the "same data" is retrieved through different system interfaces or from different system reports. Also, the reported labor does not necessarily reflect work actually performed for the project during the reporting period. • This is a multifaceted issue that includes concerns with the data as well as the applications and processes which handle the data. • This gap reduces confidence in the accuracy and reliability of the data. It diverts effort from other priorities as Projects cross check and manually verify reported data. It can increase the frequency of queries to support organizations trying to reconcile the discrepancies. It may also negatively impact a Project's performance trends and will certainly be an issue as the Agency implements EVM. • NOTE: This is related to Gap-18 but is more focused on issues with data accuracy and level of data resolution where as Gap-18 is more focused on issues between data from different reports and system interfaces. Relative Gap Complexity Factor • 7-28;28;28;14 PM Challenge 2008 27
  • 28. Gap-2 (Ranked Overall Priority 2) Gap Statement: • The projects must obligate and cost funds at the same WBS level Gap Elaboration: • SAP is configured to require obligations and costing at the same WBS Level, this is apparently based on an Agency Policy. However, it forces the Projects to accept a trade off between having a detailed enough WBS (working to low enough WBS levels in SAP to sufficiently plan, track, and manage work) against the high level or effort necessary to manipulate SAP at those detailed WBS levels (shifting funds across lower level WBS elements requires significant SAP transactions to 'roll back' previous transactions, redistribute guidelines across the affected WBS elements, then reenter all the SAP transactions). • As a result the projects often accept a higher WBS level of obligation in SAP then manually tracking costs at lower WBS levels with spreadsheets or other tools outside the system. Team Observations: • The projects indicated that requirements to obligate and cost at the same WBS level significantly increases the effort necessary to manage within the system • This is primarily an Agency policy issue which drove application design constraints. • This gap forces the Projects to choose between spending the additional effort necessary to maintain sufficiently detailed data in the system or spending less effort but maintaining the more detailed data outside of the system. The Projects usually chose the path of least effort which means some Projects choose to manage critical data outside of the system. Relative Gap Complexity Factor: • 5-20;40;20;20 PM Challenge 2008 28
  • 29. Gap-59 (Ranked Overall Priority 3) Gap Statement: • The OCFO and the Center Property Custodians do not have a real property system, integrated with NASA's financial system, to track the value of NASA's real property portfolio. Gap Elaboration: • This is necessary to achieve a "clean audit" • Need a single integrated system that tracks all capital assets for the agency. • Standardizes real property classifications and ledger accounts (e.g. buildings vs. structures) Projected Benefits: • Improves NASA's financial integrity • Eliminates reconciliation data entry resulting in improved efficiency and accuracy of the function. PM Challenge 2008 29
  • 30. Gap-16 (Ranked Overall Priority 4) Gap Statement: • The Projects do not always receive funding in a timely manner. Gap Elaboration: • Even after approval of the Agency's operating plan there is often a several week delay before projects receive funding. • The problem appears to be before funds are distributed to the Mission Directorates as the MDs seem to quickly distribute funds once received. • Project must accommodate these delays with work stoppages/delays, contractors working at risk, or additional effort to realign remaining prior year budget to cover the delayed funds. Team Observations: • The Projects indicated that a delay in receiving funds significantly increases the risk of not completing as planned. • This is primarily a process issue. • This gap can prevent the start of new work and interfere with the timely payment for work already in progress. It may result in contractors deciding to begin work at their own risk. Projects often divert efforts from other priorities in order to redistribute work and available funds. This can negatively impact a Project's performance trends and will certainly complicate the ability to produce reliable and accurate EVM reports. Relative Gap Complexity Factor: • 2-0;0;50;50 PM Challenge 2008 30
  • 31. Gap-1 (Ranked Overall Priority 5) Gap Statement: • The Projects occasionally need more WBS elements (levels) than are available. Gap Elaboration: • The projects often use spreadsheets or other tools to establish lower level structures for tracking work below the lowest WBS level allowed in SAP. • This is sometimes related to the need for more visibility into tracking contractor's work and cost. • This also applies to cases where in-house sub project type work is distributed across different Centers. Team Observations: • Several projects report that the current number of WBS levels available in SAP does not provide a sufficiently detailed level of information to effectively manage the work. • This is primarily a policy issue which drove application constraints that limited the resolution of data a project can maintain in the system • This gap results in Projects maintaining necessary levels of WBS detail in other tools outside the system. This additional detail is most likely necessary for the Agency to implement effective EVM but such data is not available to the SAP system. Relative Gap Complexity Factor: • 2-50;50;0;0 PM Challenge 2008 31
  • 32. Gap-18 (Ranked Overall Priority 6) Gap Statement: • The Projects receive conflicting data when pulling reports on the same information but from different systems. Gap Elaboration: • Reports on civil servant manpower actuals from different sources (i.e., ALDS, BRIO, WISP, Web TADS) can have different numbers - There is ambiguity over the source authority and which system has precedence. • The lag time between pay date and ALDS reporting of charges to the project make it difficult to reconcile or make Web TADS changes within the allowed three pay period window. • This is compounded by the lack of standard reporting policy and templates, each project pulls data from the various systems according to their own favorite report, filters, and bookmarks. • The Agency seems to have multiple systems/interfaces performing the same (or similar) functions (the variety of labor and workforce related systems is a prime example). There is ambiguity regarding the overlapping roles, responsibilities, and data contents of these systems. Team Observations: • Several projects indicated that the data reported from different systems is not always consistent. This may be a timing issue related to a lack of some user's awareness about how batch oriented transactions propagate data through the systems. It may also be related to confusion over specific roles and responsibilities of systems with similar functions. • This is primarily an application interface issue. However, the lack of a strong Agency policy regarding development of a uniform system architecture has allowed multiple and partially redundant systems and interfaces to emerge. • This gap reduces confidence in the system. It diverts efforts from other priorities as Projects evaluate multiple reports before selecting which data to report, • NOTE: This gap is related to Gap-51 but is more specific to the system's labor reports where as Gap-51 is more specific to the system's data accuracy and data resolution Relative Gap Complexity Factor: • 4-25;50;25;0 PM Challenge 2008 32
  • 33. Gap-64 (Ranked Overall Priority 7) Gap Statement: • The OCFO does not have an automated process and standardized tools necessary to facilitate timely and accurate reconciliation of the SAP funds balance with the Treasury general ledger account. Gap Elaboration: • NASA's inability to balance funds with Treasury has been an annual audit deficiency for years. • Achievement of a clean audit is a high priority to the administrator. Projected Benefits: • Improve NASA's credibility with Congress, OMB, and the general public. • Improve NASA's efficiency to better utilize the Agency's funds to support the mission. • Increase likelihood of obtaining a clean opinion PM Challenge 2008 33
  • 34. Gap-27 (Ranked Overall Priority 8) Gap Statement: • Projects report that the integration of WBS, financial, manpower planning, and scheduling data is a problematic and manual process. Gap Elaboration: • There is no Agency-wide resources/budget integration and planning tool that can be used by different Centers working on the same project. • The IBOT tool works well within JSC but doesn't integrate and provide detail info for work at other Centers, the system can't capture actuals across all stakeholders (marrying phasing plan with actuals). • There is no Agency designated system of record for scheduling data, configuration management data, and other critical but non-SAP data - however, there are numerous external and ad-hoc systems which Projects and Centers have developed around SAP/BW to provide this integration - such systems provide only limited and sometimes questionable integration. • How to do EVM on large, multi-center, multi-contractor projects using Agency provided tools and a standard process hasn't been developed/communicated (No standard process or tools to establish and manage EVM baselines). Team Observations: • Most Projects indicated there is a lack of guidance and standards for integrated cost, schedule, and work planning. There is also a lack of appropriate tools for developing integrated reports. • This is fundamentally a policy issue. However, the lack of a strong Agency policy regarding the development and implementation of a uniform system architecture, has allowed multiple and partially redundant systems and interfaces to emerge. • This gap has contributed to the proliferation of local "integration" tools across then Centers, tools which may serve a local need but often do not integrate effectively with other Agency systems. The lack of integration across cost, schedule, and work systems will negatively impact the Agency's ability to implement effective EVM. Relative Gap Complexity Factor: • 4-0;50;50;0 PM Challenge 2008 34
  • 35. Gap-67 (Ranked Overall Priority 9) Gap Statement: • NASA does not have the capability to load the next fiscal year budget structures prior to current fiscal year end close. Gap Elaboration: • Delays funds distribution process • Biggest impact to new initiatives but also delays funding to existing projects Projected Benefits: • Seamless transition between fiscal years from a funding perspective. PM Challenge 2008 35
  • 36. Gap-66 (Ranked Overall Priority 10) Gap Statement: • The missions and mission support organizations do not have a standardized, integrated set of tools and processes to create, maintain, track and report phasing plans. Gap Elaboration: • Better insight into unobligated balances is necessary to more effectively manage funds distribution agency-wide. • In the year of execution, better insight into our phasing plans and performance against those plans will ensure NASA is adequately expending appropriated funds. • An enhanced phasing plan processes and tools also provide missions enhanced capability to assess performance. Projected Benefits: • Benefits both missions, the CFO, and other institutional organizations by allowing CFO to more effectively manage the flow of funds. PM Challenge 2008 36
  • 37. Gap-4 (Ranked Overall Priority 11) Gap Statement: • The projects can not use SAP/BW to meet the current set of reporting requirements. Gap Elaboration: • There seems to be no Agency standard process or tools to implement the reporting requirements. • Projects frequently export data from multiple systems into Excel. The data is then integrated in Excel to generate the required reports. • There are lots of related systems containing data, but the projects can't get integrated reports across all the related systems - significant effort is required to manually integrate the data and compile the reports. • Different people/organizations want to see data in different formats - no two seem to have the same format requirements - there is no standardization in the reporting format - requires manual translation and extra effort. • The required reporting format often doesn't match the output capabilities of the commonly used tools - requiring manual "cut & paste" to create the necessary charts and reports. Team Observations: • The existing reporting capabilities of SAP/BW seldom meet the reporting requirements levied on the Projects. • This is primarily an application issue which has been compounded by the lack of reporting standards across the Agency. • This gap causes Projects to spend time and effort exporting and manually integrating relevant data into the multiple formats necessary to meet all the different reporting requirements. As a result, it is very difficult to maintain consistency in the reporting format and contents across Projects. Relative Gap Complexity Factor: • 4-0;50;50;0 PM Challenge 2008 37
  • 38. Gap-49 (Ranked Overall Priority 12) Gap Statement: • The Projects have difficulty maintaining effective planning and control during the end-of-year closeout period. Gap Elaboration: • SAP is unavailable for a long period of time during end of year closeout/startup. • When the system comes back on line after the end-of-year closeout the data in the system is often not stable until late December or early January. Also, after start-up, a surge of effort is necessary to enter the backlog of manually processed transactions. • Re-bills from pool related charges can cause unexpected changed in a Project's actual costs. The changes sometimes occur several weeks after the Project thought the books were closed - there are no reports available to track the re- billing activity during the shut down period. • The Procurement system shuts down (stops accepting non-emergency PRs) several weeks prior to the End-of-Year SAP/BW shutdown - This, in conjunction with the efforts to recall and reallocate uncommitted funds, makes it very difficult for a Project to maintain stable operations during the last and first quarter of each FY. • There is an issue with changing WBS numbers each new FY - apparently some types of funds, particularly grant and reimbursable funds, may be assigned new WBS numbers which significantly complicates and sometimes prevents the year-to-year traceability of the funds. • Pooling un-obligated funds from previous FYs into a current year WBS makes it difficult to track and manage total project costs and reconcile multi year project expenditures. Team Observations: • The Projects indicated that the length of time required for year-end closeout seems excessive, especially compared to what is heard regarding industry norms. The Projects indicated they are often "working blind" for more than a month and have serious concerns about effectively maintaining and reporting project control during this period. • This is fundamentally a policy issue but from a practical perspective it is more a process and resource issue. (lack of resources to more quickly process the volume of end of year transactions). • This gap increases the use of manual processes and temporary workarounds, causes a surge in the demands placed on support organizations, and prevents the Projects from pulling accurate and timely reports for more than a month. Relative Gap Complexity Factor: • 28-18;29;35;18 PM Challenge 2008 38
  • 39. Concept of Operations Document IEEE Standard 1362-1998 defines the content of ConOps as: 1. Scope 5. Concepts for the proposed system a) Identification a) Background, objectives and scope b) Document Overview b) Operational policies and constraints c) System Overview c) Description of current system 2. Referenced Documents d) Modes of operation e) User classes and other involved personnel 3. Current system f) Support Environment a) Background, objectives and scope b) Operational policies and constraints 6. Operational Scenarios c) Description of current system 7. Summary of impacts d) Modes of operation a) Operational Impacts e) User classes and other involved personnel b) Organizational Impacts f) Support Environment c) Impacts during development 4. Justification for and nature of changes 8. Analysis of the proposed system a) Justification of changes 9. Notes b) Description of desired changes c) Priorities among changes d) Changes considered but not included PM Challenge 2008 39