SlideShare a Scribd company logo
1 of 14
Download to read offline
The Realities of Successful Project Management
     Project Management Challenge 2008
             Daytona Beach, Florida


                 Phil Sabelhaus
              JWST Project Manager
                February 27, 2008
Who am I?
ā€¢ Currently the James Webb Space Telescope (JWST) Project
  Manager
   ā€¢ Graduated from the University of Maryland in 1978
   ā€¢ Over 25 years of experience in the Aerospace business
      ā€¢ Mostly at GSFC/NASA and as a manager (as apposed to engineering)
ā€¢ Previous project or program management positions:
   ā€¢ Total Ozone Mapping Spectrometer (TOMS) Project Manager
   ā€¢ Geostationary Operational Environmental Satellite (GOES) Deputy
     Project Manager
   ā€¢ Landsat 7 Project Manager
   ā€¢ Earth Observing System (EOS) Deputy Program Manager plus
      ā€¢ Aura Project Manager
      ā€¢ Vegetation Canopy Lidar (VCL) Project Manager
      ā€¢ Aqua Project Manager
   ā€¢ Earth Observing System (EOS) Program Manager


                                                                           2
Project Management Objective

ā€¢   Achieve mission success while looking for opportunities to share
    the blame for any additional required time and money
     ā€“ Share blame on factors not under the projectā€™s control, ie. budget
       cuts, launch vehicles, ground system, requirement changes, etc.
     ā€“ Ask for more money and time when you first take over a project, not
       after you have been there for awhile
ā€¢   ā€œThe difference between a successful project manager and an
    unsuccessful project manager is recognizing and exploiting
    opportunity.ā€
ā€¢   ā€œItā€™s better to be lucky than good.ā€
ā€¢   Itā€™s even better to be lucky and good. You make your own luck
    by being good




                                                                         3
Obvious Project Management Tools

ā€¢   Organization with clear lines of authority and accountability
ā€¢   De-scope plan as a function of project life cycle
ā€¢   Critical path schedule with identified and budgeted schedule
    contingency
ā€¢   Grass roots budget with adequate properly phased contingency
ā€¢   Risk management process that is used. Process does not have
    to be complicated




                                                                4
My Projects
ā€¢   TOMS-EP
     ā€“    Pegasus launch failures delayed the launch by 2 years. Some of that time was used to
          better train the FOT and fix latent satellite problems. We didnā€™t need the 2 years, but a
          couple of months helped
ā€¢   Landsat 7
     ā€“    ETM+ delays blamed on heritage design inherited from the Air Force. Detailed example of
          using schedule work arounds to reduce risk and minimize launch delays
ā€¢   Aura
     ā€“    EOS Program office needed the Aura projectā€™s launch vehicle money for another project in
          FY01. The Aura project needed more time for instrument development. The program
          office got $12M loaned to them and the Aura project got 6 months of schedule slip and the
          loaned money paid back with interest. Everyone was happy
ā€¢   VCL
     ā€“    Nothing seemed to work, the project was eventually cancelled due to immature laser
          technology
ā€¢   Aqua
     ā€“    Asked for and received 5 months of schedule slip and $22M shortly after taking over the
          project. Used time to move up fault management testing while fixing latent problems with
          the satellite hardware. This reduced the over all risk to meeting the new LRD. More time
          should become available due to the missions in front slipping the Delta II manifest
ā€¢   JWST
     ā€“    Used projected cost growth as the catalyst to simplify the I&T program. The technical team
          was able to come up with creative solutions to achieve almost all of the original testing
          requirements while reducing hardware interdependencies and moving the need date of
          some critical path hardware and money to the right                                        5
Evolution of JWST Testing Approach
increasing
Cost/Risk




             ā€œCup-downā€ test configuration
             within Johnson Space Flight Center
             (JSC) cryogenic test chamber
decreasing




                                                                6
                       2003                       2005   2007
Landsat 7 Example

ā€¢   The Landsat 7 launch was only delayed by 11 months from
    May 1998 to April 1999 even though the delivery of the only
    instrument on the satellite was delayed by 2 years due to a
    series of design heritage and workmanship problems that were
    not uncovered until system level testing
    ā€“ Satellite was ready for launch in February 1999
ā€¢   The Landsat 7 Program Plan was highly dependent on a
    heritage ā€˜build to printā€™ instrument for management approach,
    budget and schedule. The project used a ā€˜light touchā€™ in
    managing the instrument contractor (SBRS) in the early stages
    of development as part of a new way of doing business
    ā€“ The Landsat 6/ETM had been commercially procured and its
      development problems were not really understood. Landsat 6
      never reached orbit and ended up in the drink. The last significant
      NASA involvement was on the Landsat 5/TM which was launched
      in 1984
                                                                            7
Landsat 7 Example (Continued)

ā€“ NASA took over the Landsat 7 program from the Air Force after
  the Enhanced Thematic Mapper Plus (ETM+) CDR
ā€“ The Landsat 6 launch failure was attributed to the satelliteā€™s
  propulsion system and the projectā€™s early energy was focused on
  LMMS




                                                                    8
Landsat 7 Adjusted Development
                     Approach
ā€¢   Due to the ETM+ problems and resultant delivery delays, the
    project developed an approach to test the available flight
    hardware and software as early and as often as possible
    ā€“ Satellite test flow altered several times to retire risk and minimize
      the schedule impacts of the ETM+ late delivery
        ā€¢ Spacecraft Comprehensive Performance Tests (CPTā€™s), phase 1
          EMI/EMC and thermal vacuum, sine vibration, acoustics were initially
          performed with various combinations of ETM+ flight and mass
          model/electrical simulator hardware
        ā€¢ ETM+ installed early on satellite to check interfaces and generate data
          to check out the ground system
    ā€“ System test programs for both the ETM+ and satellite were not
      compromised due to the use of heritage designs
    ā€“ Testing approach was effective in uncovering problems early


                                                                                    9
10
ETM+ Schedule Slips

ā€¢   ETM+ delivery slipped (~24 months) from August 1996 to late
    August 1998 due to a combination of workmanship and
    heritage design problems
    ā€“ Workmanship problems:
        ā€¢ reworked poorly manufactured optical cavity video cables
        ā€¢ reworked Main Electronics Module (MEM) power supply 2A to remove
          52 kHz noise
        ā€¢ repaired bad solder joint on band 7 channel 13 detector amplifier
    ā€“ Heritage design problems:
        ā€¢ power supply failures in the instrument level thermal vacuum test
        ā€¢ low pass electronic filters and ground system software algorithm
          required to remove heritage power supply 104 kHz noise in pan band
        ā€¢ reworked scan mirror to eliminate start up problems
        ā€¢ reworked both power supplies to remove short/potential shorts
        ā€¢ using unreliable Landsat 4/5 heritage test equipment
        ā€¢ lost key SBRS ā€œheritageā€ people due threaten plant closure

                                                                           11
ETM+ Power Supply Failures

ā€¢   ETM+ experienced two separate power supply failures early during
    the instrument thermal vacuum testing
    ā€“ Tiger team made up of GSFC, SBRS, LMMS and Aerospace
      Corporation experts was formed to spearhead the recovery effort
    ā€“ Power supplies were not thermal vacuum tested at the unit level
    ā€“ Problem was isolated to switching diodes with poor ā€˜reverse recovery
      timeā€™ (RRT) performance. Lack of air in T/V test was enough to cause
      failures
    ā€“ Part change from previous units due to Air Force imposed Grade 1
      parts requirement. RRT is not a mil spec measured parameter. Parts
      appeared to be better
    ā€“ New parts with acceptable RRT performance were found, tested and
      installed in the power supplies. 108 diodes had to be replaced in each
      power supply
    ā€“ Power supplies have operated successfully on obit for over two years

                                                                         12
L7 Lessons Learned
ā€¢   Whenever NASA takes over an ā€˜in progressā€™ program like Landsat
    7, a detailed critical design system review of all elements should
    be held as part of formulating the baseline
     ā€“ ETM+ did not have a GSFC chaired review until the Pre-
       Environmental Review (PER) was held in the fall of 1997
ā€¢   Be careful with the promise of heritage. Heritage that is 20 years
    old and without the original people is not heritage
     ā€“ 20 year old designs really can not be reproduced. At a minimum,
       electronic parts are not available, processes have changed and the
       people who put it together are no longer around
     ā€“ Change in application of heritage designs were not completely
       reanalyzed
     ā€“ Since ETM/L6 was a commercial buy, a gap existed in NASAā€™s
       understanding of the heritage design
ā€¢   Donā€™t comprise the test program when using hardware and
    software based on heritage designs
                                                                       13
Final Thoughts
ā€¢   Get good people and let them do their jobs
ā€¢   Build good chemistry between all contractor and government team members.
    This ensures that everyone is a stakeholder in the success of the mission
ā€¢   Never forget who is ultimately accountable
ā€¢   Attack your problems early and aggressively. Donā€™t put your head in the sand
    and hope things will get better. They donā€™t!
ā€¢   Always tell the truth, but do it at the right moment. Give your problems a little
    time to age. Follow the 24-48 hour gestation rule
ā€¢   Donā€™t constantly ask for direction or guidance. If you do, you will get it. Itā€™s your
    project, manage it
ā€¢   Communicate communicate communicate. Canā€™t over communicate
ā€¢   A test is worth a thousand analyses. Get operating time on the hardware and
    software. Test as you fly. Donā€™t forget to test with the ground system
ā€¢   Take care of yourself. Nobody else will. This means eat well and exercise.
    Project management is more of a marathon than a sprint
ā€¢   The reward for doing a good job (at least at GSFC) is the opportunity to do it
    again
ā€¢   Above all else ā€œMission Successā€. Make the right technical decisions. This
    achieves mission safety


                                                                                       14

More Related Content

What's hot

D brown gbezos_shirshorn
D brown gbezos_shirshornD brown gbezos_shirshorn
D brown gbezos_shirshornNASAPMC
Ā 
Barth simpkins
Barth simpkinsBarth simpkins
Barth simpkinsNASAPMC
Ā 
K ingoldsby
K ingoldsbyK ingoldsby
K ingoldsbyNASAPMC
Ā 
Keer.beth
Keer.bethKeer.beth
Keer.bethNASAPMC
Ā 
Sand.steven
Sand.stevenSand.steven
Sand.stevenNASAPMC
Ā 
Nick.chrissotimos
Nick.chrissotimosNick.chrissotimos
Nick.chrissotimosNASAPMC
Ā 
Tim.honeycutt
Tim.honeycuttTim.honeycutt
Tim.honeycuttNASAPMC
Ā 
Dusterwald
DusterwaldDusterwald
DusterwaldNASAPMC
Ā 
Fred.ouellette
Fred.ouelletteFred.ouellette
Fred.ouelletteNASAPMC
Ā 
Taylor.randall
Taylor.randallTaylor.randall
Taylor.randallNASAPMC
Ā 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.johnNASAPMC
Ā 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vinceNASAPMC
Ā 
Kelly crumbley
Kelly crumbleyKelly crumbley
Kelly crumbleyNASAPMC
Ā 
David.oberhettinger
David.oberhettingerDavid.oberhettinger
David.oberhettingerNASAPMC
Ā 
Lemack_Resume 2015
Lemack_Resume 2015Lemack_Resume 2015
Lemack_Resume 2015Bruce Lemack
Ā 
Rider.stephen
Rider.stephenRider.stephen
Rider.stephenNASAPMC
Ā 
Sean carter dan_deans
Sean carter dan_deansSean carter dan_deans
Sean carter dan_deansNASAPMC
Ā 
Ed.mango
Ed.mangoEd.mango
Ed.mangoNASAPMC
Ā 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylorNASAPMC
Ā 
Geyer.m.sasaki.c
Geyer.m.sasaki.cGeyer.m.sasaki.c
Geyer.m.sasaki.cNASAPMC
Ā 

What's hot (20)

D brown gbezos_shirshorn
D brown gbezos_shirshornD brown gbezos_shirshorn
D brown gbezos_shirshorn
Ā 
Barth simpkins
Barth simpkinsBarth simpkins
Barth simpkins
Ā 
K ingoldsby
K ingoldsbyK ingoldsby
K ingoldsby
Ā 
Keer.beth
Keer.bethKeer.beth
Keer.beth
Ā 
Sand.steven
Sand.stevenSand.steven
Sand.steven
Ā 
Nick.chrissotimos
Nick.chrissotimosNick.chrissotimos
Nick.chrissotimos
Ā 
Tim.honeycutt
Tim.honeycuttTim.honeycutt
Tim.honeycutt
Ā 
Dusterwald
DusterwaldDusterwald
Dusterwald
Ā 
Fred.ouellette
Fred.ouelletteFred.ouellette
Fred.ouellette
Ā 
Taylor.randall
Taylor.randallTaylor.randall
Taylor.randall
Ā 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
Ā 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
Ā 
Kelly crumbley
Kelly crumbleyKelly crumbley
Kelly crumbley
Ā 
David.oberhettinger
David.oberhettingerDavid.oberhettinger
David.oberhettinger
Ā 
Lemack_Resume 2015
Lemack_Resume 2015Lemack_Resume 2015
Lemack_Resume 2015
Ā 
Rider.stephen
Rider.stephenRider.stephen
Rider.stephen
Ā 
Sean carter dan_deans
Sean carter dan_deansSean carter dan_deans
Sean carter dan_deans
Ā 
Ed.mango
Ed.mangoEd.mango
Ed.mango
Ā 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
Ā 
Geyer.m.sasaki.c
Geyer.m.sasaki.cGeyer.m.sasaki.c
Geyer.m.sasaki.c
Ā 

Similar to Phil.sabelhaus

Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.updateNASAPMC
Ā 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.updateNASAPMC
Ā 
How DOORS Helps JPL Get to Mars & Beyond
How DOORS Helps JPL Get to Mars & BeyondHow DOORS Helps JPL Get to Mars & Beyond
How DOORS Helps JPL Get to Mars & BeyondBill Duncan
Ā 
Keer.beth
Keer.bethKeer.beth
Keer.bethNASAPMC
Ā 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
Ā 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylorNASAPMC
Ā 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylorNASAPMC
Ā 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
Ā 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
Ā 
Report on loss of Mars Polar Lander
Report on loss of Mars Polar LanderReport on loss of Mars Polar Lander
Report on loss of Mars Polar LanderNabilahmed Patel
Ā 
Robertson.brent
Robertson.brentRobertson.brent
Robertson.brentNASAPMC
Ā 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
Ā 
Lascas Failure Learn A Big Lession From The Most Terrible Problems In The W...
Lascas Failure   Learn A Big Lession From The Most Terrible Problems In The W...Lascas Failure   Learn A Big Lession From The Most Terrible Problems In The W...
Lascas Failure Learn A Big Lession From The Most Terrible Problems In The W...guestc990b6
Ā 
Sean Blanchette Resume - Summary
Sean Blanchette Resume - SummarySean Blanchette Resume - Summary
Sean Blanchette Resume - Summarysean blanchette
Ā 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsScottMadden, Inc.
Ā 
Complexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementComplexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementMDCSystems
Ā 
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power PlantLessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power PlantBrock Palen
Ā 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec domsBabasab Patil
Ā 
COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13Dmitry Tseitlin
Ā 

Similar to Phil.sabelhaus (20)

Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
Ā 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
Ā 
How DOORS Helps JPL Get to Mars & Beyond
How DOORS Helps JPL Get to Mars & BeyondHow DOORS Helps JPL Get to Mars & Beyond
How DOORS Helps JPL Get to Mars & Beyond
Ā 
Keer.beth
Keer.bethKeer.beth
Keer.beth
Ā 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
Ā 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
Ā 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
Ā 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
Ā 
PERT
PERTPERT
PERT
Ā 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
Ā 
Report on loss of Mars Polar Lander
Report on loss of Mars Polar LanderReport on loss of Mars Polar Lander
Report on loss of Mars Polar Lander
Ā 
Robertson.brent
Robertson.brentRobertson.brent
Robertson.brent
Ā 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
Ā 
Lascas Failure Learn A Big Lession From The Most Terrible Problems In The W...
Lascas Failure   Learn A Big Lession From The Most Terrible Problems In The W...Lascas Failure   Learn A Big Lession From The Most Terrible Problems In The W...
Lascas Failure Learn A Big Lession From The Most Terrible Problems In The W...
Ā 
Sean Blanchette Resume - Summary
Sean Blanchette Resume - SummarySean Blanchette Resume - Summary
Sean Blanchette Resume - Summary
Ā 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
Ā 
Complexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementComplexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project Management
Ā 
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power PlantLessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Ā 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
Ā 
COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13
Ā 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
Ā 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
Ā 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
Ā 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
Ā 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
Ā 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
Ā 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
Ā 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
Ā 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
Ā 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
Ā 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
Ā 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
Ā 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
Ā 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
Ā 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
Ā 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
Ā 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
Ā 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
Ā 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
Ā 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
Ā 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
Ā 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
Ā 
Yew manson
Yew mansonYew manson
Yew manson
Ā 
Wood frank
Wood frankWood frank
Wood frank
Ā 
Wood frank
Wood frankWood frank
Wood frank
Ā 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
Ā 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
Ā 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
Ā 
Stock gahm
Stock gahmStock gahm
Stock gahm
Ā 
Snow lee
Snow leeSnow lee
Snow lee
Ā 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
Ā 
Seftas krage
Seftas krageSeftas krage
Seftas krage
Ā 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
Ā 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
Ā 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
Ā 
Rackley mike
Rackley mikeRackley mike
Rackley mike
Ā 
Paradis william
Paradis williamParadis william
Paradis william
Ā 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
Ā 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
Ā 
Muller ralf
Muller ralfMuller ralf
Muller ralf
Ā 

Recently uploaded

Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
Ā 
šŸ¬ The future of MySQL is Postgres šŸ˜
šŸ¬  The future of MySQL is Postgres   šŸ˜šŸ¬  The future of MySQL is Postgres   šŸ˜
šŸ¬ The future of MySQL is Postgres šŸ˜RTylerCroy
Ā 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
Ā 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
Ā 
Scaling API-first ā€“ The story of a global engineering organization
Scaling API-first ā€“ The story of a global engineering organizationScaling API-first ā€“ The story of a global engineering organization
Scaling API-first ā€“ The story of a global engineering organizationRadu Cotescu
Ā 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
Ā 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfhans926745
Ā 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
Ā 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
Ā 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdfChristopherTHyatt
Ā 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
Ā 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
Ā 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
Ā 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
Ā 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
Ā 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
Ā 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
Ā 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
Ā 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
Ā 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
Ā 

Recently uploaded (20)

Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
Ā 
šŸ¬ The future of MySQL is Postgres šŸ˜
šŸ¬  The future of MySQL is Postgres   šŸ˜šŸ¬  The future of MySQL is Postgres   šŸ˜
šŸ¬ The future of MySQL is Postgres šŸ˜
Ā 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
Ā 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
Ā 
Scaling API-first ā€“ The story of a global engineering organization
Scaling API-first ā€“ The story of a global engineering organizationScaling API-first ā€“ The story of a global engineering organization
Scaling API-first ā€“ The story of a global engineering organization
Ā 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Ā 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
Ā 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Ā 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
Ā 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
Ā 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
Ā 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
Ā 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
Ā 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
Ā 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
Ā 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
Ā 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Ā 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
Ā 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Ā 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Ā 

Phil.sabelhaus

  • 1. The Realities of Successful Project Management Project Management Challenge 2008 Daytona Beach, Florida Phil Sabelhaus JWST Project Manager February 27, 2008
  • 2. Who am I? ā€¢ Currently the James Webb Space Telescope (JWST) Project Manager ā€¢ Graduated from the University of Maryland in 1978 ā€¢ Over 25 years of experience in the Aerospace business ā€¢ Mostly at GSFC/NASA and as a manager (as apposed to engineering) ā€¢ Previous project or program management positions: ā€¢ Total Ozone Mapping Spectrometer (TOMS) Project Manager ā€¢ Geostationary Operational Environmental Satellite (GOES) Deputy Project Manager ā€¢ Landsat 7 Project Manager ā€¢ Earth Observing System (EOS) Deputy Program Manager plus ā€¢ Aura Project Manager ā€¢ Vegetation Canopy Lidar (VCL) Project Manager ā€¢ Aqua Project Manager ā€¢ Earth Observing System (EOS) Program Manager 2
  • 3. Project Management Objective ā€¢ Achieve mission success while looking for opportunities to share the blame for any additional required time and money ā€“ Share blame on factors not under the projectā€™s control, ie. budget cuts, launch vehicles, ground system, requirement changes, etc. ā€“ Ask for more money and time when you first take over a project, not after you have been there for awhile ā€¢ ā€œThe difference between a successful project manager and an unsuccessful project manager is recognizing and exploiting opportunity.ā€ ā€¢ ā€œItā€™s better to be lucky than good.ā€ ā€¢ Itā€™s even better to be lucky and good. You make your own luck by being good 3
  • 4. Obvious Project Management Tools ā€¢ Organization with clear lines of authority and accountability ā€¢ De-scope plan as a function of project life cycle ā€¢ Critical path schedule with identified and budgeted schedule contingency ā€¢ Grass roots budget with adequate properly phased contingency ā€¢ Risk management process that is used. Process does not have to be complicated 4
  • 5. My Projects ā€¢ TOMS-EP ā€“ Pegasus launch failures delayed the launch by 2 years. Some of that time was used to better train the FOT and fix latent satellite problems. We didnā€™t need the 2 years, but a couple of months helped ā€¢ Landsat 7 ā€“ ETM+ delays blamed on heritage design inherited from the Air Force. Detailed example of using schedule work arounds to reduce risk and minimize launch delays ā€¢ Aura ā€“ EOS Program office needed the Aura projectā€™s launch vehicle money for another project in FY01. The Aura project needed more time for instrument development. The program office got $12M loaned to them and the Aura project got 6 months of schedule slip and the loaned money paid back with interest. Everyone was happy ā€¢ VCL ā€“ Nothing seemed to work, the project was eventually cancelled due to immature laser technology ā€¢ Aqua ā€“ Asked for and received 5 months of schedule slip and $22M shortly after taking over the project. Used time to move up fault management testing while fixing latent problems with the satellite hardware. This reduced the over all risk to meeting the new LRD. More time should become available due to the missions in front slipping the Delta II manifest ā€¢ JWST ā€“ Used projected cost growth as the catalyst to simplify the I&T program. The technical team was able to come up with creative solutions to achieve almost all of the original testing requirements while reducing hardware interdependencies and moving the need date of some critical path hardware and money to the right 5
  • 6. Evolution of JWST Testing Approach increasing Cost/Risk ā€œCup-downā€ test configuration within Johnson Space Flight Center (JSC) cryogenic test chamber decreasing 6 2003 2005 2007
  • 7. Landsat 7 Example ā€¢ The Landsat 7 launch was only delayed by 11 months from May 1998 to April 1999 even though the delivery of the only instrument on the satellite was delayed by 2 years due to a series of design heritage and workmanship problems that were not uncovered until system level testing ā€“ Satellite was ready for launch in February 1999 ā€¢ The Landsat 7 Program Plan was highly dependent on a heritage ā€˜build to printā€™ instrument for management approach, budget and schedule. The project used a ā€˜light touchā€™ in managing the instrument contractor (SBRS) in the early stages of development as part of a new way of doing business ā€“ The Landsat 6/ETM had been commercially procured and its development problems were not really understood. Landsat 6 never reached orbit and ended up in the drink. The last significant NASA involvement was on the Landsat 5/TM which was launched in 1984 7
  • 8. Landsat 7 Example (Continued) ā€“ NASA took over the Landsat 7 program from the Air Force after the Enhanced Thematic Mapper Plus (ETM+) CDR ā€“ The Landsat 6 launch failure was attributed to the satelliteā€™s propulsion system and the projectā€™s early energy was focused on LMMS 8
  • 9. Landsat 7 Adjusted Development Approach ā€¢ Due to the ETM+ problems and resultant delivery delays, the project developed an approach to test the available flight hardware and software as early and as often as possible ā€“ Satellite test flow altered several times to retire risk and minimize the schedule impacts of the ETM+ late delivery ā€¢ Spacecraft Comprehensive Performance Tests (CPTā€™s), phase 1 EMI/EMC and thermal vacuum, sine vibration, acoustics were initially performed with various combinations of ETM+ flight and mass model/electrical simulator hardware ā€¢ ETM+ installed early on satellite to check interfaces and generate data to check out the ground system ā€“ System test programs for both the ETM+ and satellite were not compromised due to the use of heritage designs ā€“ Testing approach was effective in uncovering problems early 9
  • 10. 10
  • 11. ETM+ Schedule Slips ā€¢ ETM+ delivery slipped (~24 months) from August 1996 to late August 1998 due to a combination of workmanship and heritage design problems ā€“ Workmanship problems: ā€¢ reworked poorly manufactured optical cavity video cables ā€¢ reworked Main Electronics Module (MEM) power supply 2A to remove 52 kHz noise ā€¢ repaired bad solder joint on band 7 channel 13 detector amplifier ā€“ Heritage design problems: ā€¢ power supply failures in the instrument level thermal vacuum test ā€¢ low pass electronic filters and ground system software algorithm required to remove heritage power supply 104 kHz noise in pan band ā€¢ reworked scan mirror to eliminate start up problems ā€¢ reworked both power supplies to remove short/potential shorts ā€¢ using unreliable Landsat 4/5 heritage test equipment ā€¢ lost key SBRS ā€œheritageā€ people due threaten plant closure 11
  • 12. ETM+ Power Supply Failures ā€¢ ETM+ experienced two separate power supply failures early during the instrument thermal vacuum testing ā€“ Tiger team made up of GSFC, SBRS, LMMS and Aerospace Corporation experts was formed to spearhead the recovery effort ā€“ Power supplies were not thermal vacuum tested at the unit level ā€“ Problem was isolated to switching diodes with poor ā€˜reverse recovery timeā€™ (RRT) performance. Lack of air in T/V test was enough to cause failures ā€“ Part change from previous units due to Air Force imposed Grade 1 parts requirement. RRT is not a mil spec measured parameter. Parts appeared to be better ā€“ New parts with acceptable RRT performance were found, tested and installed in the power supplies. 108 diodes had to be replaced in each power supply ā€“ Power supplies have operated successfully on obit for over two years 12
  • 13. L7 Lessons Learned ā€¢ Whenever NASA takes over an ā€˜in progressā€™ program like Landsat 7, a detailed critical design system review of all elements should be held as part of formulating the baseline ā€“ ETM+ did not have a GSFC chaired review until the Pre- Environmental Review (PER) was held in the fall of 1997 ā€¢ Be careful with the promise of heritage. Heritage that is 20 years old and without the original people is not heritage ā€“ 20 year old designs really can not be reproduced. At a minimum, electronic parts are not available, processes have changed and the people who put it together are no longer around ā€“ Change in application of heritage designs were not completely reanalyzed ā€“ Since ETM/L6 was a commercial buy, a gap existed in NASAā€™s understanding of the heritage design ā€¢ Donā€™t comprise the test program when using hardware and software based on heritage designs 13
  • 14. Final Thoughts ā€¢ Get good people and let them do their jobs ā€¢ Build good chemistry between all contractor and government team members. This ensures that everyone is a stakeholder in the success of the mission ā€¢ Never forget who is ultimately accountable ā€¢ Attack your problems early and aggressively. Donā€™t put your head in the sand and hope things will get better. They donā€™t! ā€¢ Always tell the truth, but do it at the right moment. Give your problems a little time to age. Follow the 24-48 hour gestation rule ā€¢ Donā€™t constantly ask for direction or guidance. If you do, you will get it. Itā€™s your project, manage it ā€¢ Communicate communicate communicate. Canā€™t over communicate ā€¢ A test is worth a thousand analyses. Get operating time on the hardware and software. Test as you fly. Donā€™t forget to test with the ground system ā€¢ Take care of yourself. Nobody else will. This means eat well and exercise. Project management is more of a marathon than a sprint ā€¢ The reward for doing a good job (at least at GSFC) is the opportunity to do it again ā€¢ Above all else ā€œMission Successā€. Make the right technical decisions. This achieves mission safety 14