1. Compendium of Infrastructure Projects in Uganda
COMPENDIUM OF INFRASTRUCTURE PROJECTS
IN
TRANSPORT & ENERGY INVESTMENTS
Willy Mutenza
Head Office: 12 Eric Wilkins House, Avondale Square Estate, Old Kent Road, London SE1 5ES
Tel: +207 237 7317 Mob: +447790 647 089 - Email: info@mm2capital.com
Website: www.mm2capital.com
Skype: willymutenza
---------------------------------------------------Services: MM2 Capital, the convergence focal point for Investors and Business Entrepreneurs.
1
2. Compendium of Infrastructure Projects in Uganda
TABLE OF CONTENTS
Transport projects……………………………………………………….….. 4
Roads Transport …………………………………….……………….….
5
Alternative Route to Entebbe…………………………………………………….…… 6
Flyover between Jinja Road and Kibuye……………………………………….…… 7
Construction Equipment for Districts Roads…………………………………..…… .8
Kibuye - Busega - Mpigi Road……………………………………………………….. 9
Kampala Northern Bypass ………………………………………………………… 10
Kampala - Jinja ………………………………………………………………………11
Kampala (Zana) – Entebbe………………………………………………………… 12
Air Transport …………………………………………………….…. ….... 13
Commercial Free Zone…………………………………………………………… ….14
Cargo Center………………………………………………………...................... .....15
Rail Transport …………………………………………………..… ….... 16
Extension of Gulu Line to Juba………………………………………………………17
Reactivation of kampala – Kasese line and future extension of Rwanda and the
Democratic Republic of Congo……………………………………………………….18
Water Transport ……………………………………………….………..... 19
Redevelopment of Portbell Port……………………………………………….…..…20
Energy projects………………………………………………….………. ….21
Karuma large hydro power site (200mw)………………………………………..….22
Isimba large hydro power project (87 mw)…………………………………….……23
Ayago north large hydro power project (304mw)…………………………….…….24
Ayago south large hydro power project…………………………………….……….25
Murchision large hydropower project (642mw)………………………….…………26
Bugumira large hydro power project (109mw)…………………………….……….27
Kakaka small hydro power project (7.2 mw)…………………………….…………28
Muyembe/sirimityo small hydro power project (9.0 mw)……………….…………29
Nyamabuye small hydro power project (2.2mw)……………………….………….30
Yerya, Mahoma confluence hydro power project (3.0 mw)………….…………..31
Siti small hydro power project (2.5 mw)…………………………………………….32
Sipi/chebonet small hydro power project (2.5mw)…………………………… … ..33
2
3. Compendium of Infrastructure Projects in Uganda
Mvepi small hydro power project (2.4mw)………………………………………… .34
Sogahi small hydro power project (2.0 mw)……………………………………….. 35
Ela small hydro power project (1.5 mw)……….…………………………………….36
Ririma small hydro power project (1.5mw)………………………………………….37
Haisesero small hydro power project (1.0 mw)……………………………… …..38
Nyahuka small hydro power project (0.65mw)…………………………………......39
Nkusi small hydro power project (0.6mw)…………………………………………..40
Rwizi small hydro power project (0.5mw)……………………………………… …41
Sezibwa small hydro power project (0.5mw)……………………………………….42
Rwigo small hydro power project (0.48mw)……………………………… ………..43
Narwodo small hydro power project (0.4mw)……………………………… ………44
Agoi small hydro power project (0.35mw)…………………………………………..45
Kitumba small hydro power project (0.2 mw)……………………………………….46
Tokwe small hydro power project (0.4mw)………………………… ……………..47
Amua small hydro power project (0.18mw)…………………………………………48
Ngiti small hydro power project (0.15mw)…………………………..………………49
Leya small hydro power project (0.12mw)…………………………………………..50
Nyakibale hydro power project (0.1mw)……………………………………… …..51
Miria adua small hydro power project (0.1mw)……………………………………..52
Nkusi small hydro power project (11mw)……………………………………………53
Esia hydro power project (1.0 mw)…………………………………………… ……54
Manafwa small hydro power project (0.15mw)………………………………… …55
3
4. Compendium of Infrastructure Projects in Uganda
TRANSPORT PROJECTS
A. ROADS
B. AIR
C. RAIL
D. WATER
TOTAL NUMBER OF PROJECTS: 12
TOTAL ESTIMATED COST USD: 1,620,900,000
4
5. Compendium of Infrastructure Projects in Uganda
A)
ROADS TRANSPORT
NUMBER OF PROJECTS: 07
PROJECT NAMES:
1) Alternative Route to Entebbe
2) Flyover between Jinja Road and Kibuye
3) Construction Equipment for Districts Roads
4) Kibuye – Busega – Mpigi Road
5) Kampala Northern By pass
6) Kampala – Jinja Road
7) Kampala (zana) - Entebbe
TOTAL ESTIMATED COST USD: 782.4 MILLION
5
6. Compendium of Infrastructure Projects in Uganda
1) ALTERNATIVE ROUTE TO ENTEBBE (40KM)
Project Description/Scope
Feasibility Study
Detailed Engineering Design
Construction
Estimated Costs (US $)
50 Million
Project Status
Feasibility Study and Detailed Engineering Design in
progress
Responsible Institution
Ministry of Works and Transport
6
7. Compendium of Infrastructure Projects in Uganda
2)
FLYOVER BETWEEN
KIBUYE (4.7KM)
JINJA
ROAD
AND
Project Description/Scope
Feasibility Study
Detailed Engineering Design
Construction
Estimated Costs (US $)
75 Million
Project Status
To be in place by year 2018
Responsible Institution
Ministry of Works and Transport
7
8. Compendium of Infrastructure Projects in Uganda
3) SUPPLY OF CONSTRUCTION EQUIPMENT
FOR DISTRICT ROADS
Project Description/Scope
Supply of Equipment
After sales Service
Managing Workshops
Training Managers and operators
Estimated Costs (US $)
80 Million
Project Status/Remarks
Government will meet the cost of constructing the
mechanical workshops
Responsible Institution
Ministry of Works and Transport
8
9. Compendium of Infrastructure Projects in Uganda
4) KIBUYE – BUSEGA – MPIGI (32 KMS)
Project Description/Scope
Review of detailed studies
Construction works for dualling the road
construction consultancy supervision services
and
Estimated Costs (US $)
128 Million
Project Status
Procurement of consultancy services for the feasibility
study, detailed engineering designs and other tender
assistance is on course
Responsible Institution
Ministry of Works and Transport
9
10. Compendium of Infrastructure Projects in Uganda
5) KAMPALA NORTHERN BY PASS (18.6 KMS)
Project Description/Scope
Review of detailed studies
Construction works for dualling the road
construction consultancy supervision services
and
Estimated Costs (US $)
74.4 Million
Project Status
Procurement of consultancy services for the feasibility
study, detailed engineering designs and other tender
assistance is on course
Responsible Institution
Ministry of Works and Transport
10
11. Compendium of Infrastructure Projects in Uganda
6) KAMPALA – JINJA (72 KMS)
Project Description/Scope
Review of detailed studies
Construction works for dualling the road
construction consultancy supervision services
and
Estimated Costs (US $)
288 Million
Project Status
Procurement of consultancy services for the feasibility
study, detailed engineering designs and other tender
assistance is on course
Responsible Institution
Ministry of Works and Transport
11
12. Compendium of Infrastructure Projects in Uganda
7) KAMPALA – (ZANA) ENTEBBE (32 KMS)
Project Description/Scope
Review of detailed studies
Construction works for dualling the road
construction consultancy supervision services
and
Estimated Costs (US $)
87 Million
Project Status
Procurement of consultancy services for the feasibility
study, detailed engineering designs and other tender
assistance is on course
Responsible Institution
Ministry of Works and Transport
12
13. Compendium of Infrastructure Projects in Uganda
B)
AIR TRANSPORT
NUMBER OF PROJECTS: 02
PROJECT NAMES:
1) Commercial Free Zone
2) Cargo Center
TOTAL ESTIMATED COST USD:
55 MILLION
13
14. Compendium of Infrastructure Projects in Uganda
1) COMMERCIAL FREE ZONE
Project Description/Scope
Feasibility Study
Detailed Engineering Design
Construction
Estimated Costs (US $)
30 Million
Project Status/Remarks
Pre-feasibility already done
Responsible Institution
Ministry of Works and Transport
14
15. Compendium of Infrastructure Projects in Uganda
2) CARGO CENTRE
Project Description/Scope
Feasibility Study
Detailed Engineering Design
Construction
Estimated Costs (US $)
25 Million
Project Status/Remarks
To be in Place by year 2012
Responsible Institution
Ministry of Works and Transport
15
16. Compendium of Infrastructure Projects in Uganda
C)
RAIL TRANSPORT
NUMBER OF PROJECTS: 02
PROJECT NAMES:
1. Extension of Gulu line to Juba (320km)
2. Reactivation of Kampala-Kasese line (333km) and
future extension to Rwanda and the Democratic
Republic of Congo
TOTAL ESTIMATED COST USD:
770 MILLION
16
17. Compendium of Infrastructure Projects in Uganda
1) EXTENSION OF GULU LINE TO JUBA (320KM)
Project Description/Scope
Feasibility Study
Detailed Engineering Design
Construction
Estimated Costs (US $)
420 Million
Project Status
The cost covers all the items listed in the project scope
Responsible Institution
Ministry of Works and Transport
17
18. Compendium of Infrastructure Projects in Uganda
2) REACTIVATION OF KAMPALA-KASES LINE
(333KM) AND FUTURE EXTENSION OF LINE
TO RWANDA AND THE DEMOCRATIC
REPUBLIC OF CONGO
Project Description/Scope
Feasibility Study
Detailed Engineering Design
Construction
Estimated Costs (US $)
350 Million
Project Status/Remarks
The cost only covers the rehabilitation of the existing line
up to Kasese
Responsible Institution
Ministry of Works and Transport
18
19. Compendium of Infrastructure Projects in Uganda
D)
WATER TRANSPORT
NUMBER OF PROJECTS: 01
PROJECT NAME:
1. Redevelopment of Port Bell Port
TOTAL ESTIMATED COST USD:
13.5 MILLION
19
20. Compendium of Infrastructure Projects in Uganda
1) REDEVELOPMENT OF PORT BELL PORT
Project Description/Scope
Feasibility Study
Detailed Engineering Design
Construction
Estimated Costs (US $)
420 Million
Project Status/Remarks
The cost includes rehabilitation of the Port and terminal
building facilities
Responsible Institution
Ministry of Works and Transport
20
21. Compendium of Infrastructure Projects in Uganda
ENERGY PROJECTS
A) LARGE HYDRO POWER PROJECTS
-
NUMBER OF PROJECTS
-
06
B) SMALL HYDRO POWER PROJECTS
-
NUMBER OF PROJECTS
-
TOTAL NUMBER OF ENERGY PROJECTS: -
28
34
21
22. Compendium of Infrastructure Projects in Uganda
1) DEVELOPMENT OF KARUMA LARGE HYDRO
POWER SITE (200MW)
Estimated Costs (US $)
300 - 700 Million1
Project Status/Remarks
To be developed as a Public Project
Responsible Institution
Ministry of Energy and Mineral Development
1
Note: Hydro power project development costs in Uganda range between US$ 1.5
Million and US$ 3.5 Million per MW (Electricity Regulatory Authority)
22
23. Compendium of Infrastructure Projects in Uganda
2) DEVELOPMENT OF ISIMBA LARGE HYDRO
POWER PROJECT (87 MW)
Estimated Costs (US $)
130 – 304.5 Million
Project Status/Remarks
Preliminary Studies are available
Responsible Institution
Ministry of Energy and Mineral Development
23
24. Compendium of Infrastructure Projects in Uganda
3) DEVELOPMENT OF AYAGO NORTH LARGE
HYDRO POWER PROJECT (304MW)
Estimated Costs (US $)
456 Million – 1.064 Billion
Project Status/Remarks
Preliminary studies have been done and are available
Responsible Institution
Ministry of Energy and Mineral Development
24
25. Compendium of Infrastructure Projects in Uganda
4) DEVELOPMENT OF AYAGO SOUTH LARGE
HYDRO POWER PROJECT
Estimated Costs (US $)
351- 819 Million
Project Status/Remarks
Preliminary studies done and are available
Responsible Institution
Ministry of Energy and Mineral Development
25
26. Compendium of Infrastructure Projects in Uganda
5) DEVELOPMENT OF MURCHISION LARGE
HYDROPOWER PROJECT (642MW)
Estimated Costs (US $)
963 Million – 2.247 Billion
Project Status/Remarks
Preliminary Studies have been done and are available.
Project has adverse environment effects
Responsible Institution
Ministry of Energy and Mineral Development
26
27. Compendium of Infrastructure Projects in Uganda
6) DEVELOPMENT OF BUGUMIRA LARGE
HYDRO POWER PROJECT (109MW)
Estimated Costs (US $)
163.5 – 381.5 Million
Project Status/Remarks
Preliminary studies are available
Responsible Institution
Ministry of Energy and Mineral Development
27
28. Compendium of Infrastructure Projects in Uganda
7) DEVELOPMENT OF KAKAKA SMALL HYDRO
POWER PROJECT (7.2 MW)
Estimated Costs (US $)
10.8 – 25.2 Million
Project Status/Remarks
Preliminary technical studies carried out in 1999 and
2003
Responsible Institution
Ministry of Energy and Mineral Development
28
29. Compendium of Infrastructure Projects in Uganda
8) DEVELOPMENT OF MUYEMBE/SIRIMITYO
SMALL HYDRO POWER PROJECT (9.0 MW)
Estimated Costs (US $)
13.5 – 31.5 Million
Project Status/Remarks
Pre feasibility technical studies carried out
Responsible Institution
Ministry of Energy and Mineral Development
29
30. Compendium of Infrastructure Projects in Uganda
9) DEVELOPMENT OF NYAMABUYE SMALL
HYDRO POWER PROJECT (2.2MW)
Estimated Costs (US $)
3.3 – 7.7 Million
Project Status/Remarks
Preliminary technical studies carried out.
Responsible Institution
Ministry of Energy and Mineral Development
30
31. Compendium of Infrastructure Projects in Uganda
10) DEVELOPMENT OF YERYA, MAHOMA
CONFLUENCE HYDRO POWER PROJECT (3.0
MW)
Estimated Costs (US $)
4.5 – 10.5 Million
Project Status/Remarks
Preliminary technical studies are available
Responsible Institution
Ministry of Energy and Mineral Development
31
32. Compendium of Infrastructure Projects in Uganda
11) DEVELOPMENT OF SITI SMALL HYDRO
POWER PROJECT (2.5 MW)
Estimated Costs (US $)
3.75 – 8.75 Million
Project Status/Remarks
Preliminary technical studies are available
Responsible Institution
Ministry of Energy and Mineral Development
32
33. Compendium of Infrastructure Projects in Uganda
12) DEVELOPMENT OF SIPI/CHEBONET SMALL
HYDRO POWER PROJECT (2.5MW)
Estimated Costs (US $)
3.75 – 8.75 Million
Project Status/Remarks
Preliminary studies are available
Responsible Institution
Ministry of Energy and Mineral Development
33
34. Compendium of Infrastructure Projects in Uganda
13) DEVELOPMENT OF MVEPI SMALL HYDRO
POWER PROJECT (2.4MW)
Estimated Costs (US $)
3.6 – 8.4 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
34
35. Compendium of Infrastructure Projects in Uganda
14) DEVELOPMENT OF SOGAHI SMALL HYDRO
POWER PROJECT (2.0 MW)
Estimated Costs (US $)
3.75 – 7 Million
Project Status/Remarks
No studies.
Responsible Institution
Ministry of Energy and Mineral Development
35
36. Compendium of Infrastructure Projects in Uganda
15) DEVELOPMENT OF ELA SMALL HYDRO
POWER PROJECT (1.5 MW)
Estimated Costs (US $)
2.25 – 5.25 Million
Project Status/Remarks
Preliminary studies are available
Responsible Institution
Ministry of Energy and Mineral Development
36
37. Compendium of Infrastructure Projects in Uganda
16) DEVELOPMENT OF RIRIMA SMALL HYDRO
POWER PROJECT (1.5MW)
Estimated Costs (US $)
2.25 – 5.25 Million
Project Status/Remarks
Pre feasibility studies are available
Responsible Institution
Ministry of Energy and Mineral Development
37
38. Compendium of Infrastructure Projects in Uganda
17) DEVELOPMENT OF HAISESERO SMALL
HYDRO POWER PROJECT (1.0 MW)
Estimated Costs (US $)
1.5 – 3.5 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
38
39. Compendium of Infrastructure Projects in Uganda
18) DEVELOPMENT OF NYAHUKA SMALL
HYDRO POWER PROJECT (0.65MW)
Estimated Costs (US $)
0.975 – 2.275 Million
Project Status/Remarks
Preliminary technical studies are available
Responsible Institution
Ministry of Energy and Mineral Development
39
40. Compendium of Infrastructure Projects in Uganda
19) DEVELOPMENT OF NKUSI SMALL HYDRO
POWER PROJECT (0.6MW)
Estimated Costs (US $)
0.9 – 2.1 Million
Project Status/Remarks
Preliminary technical studies are available
Responsible Institution
Ministry of Energy and Mineral Development
40
41. Compendium of Infrastructure Projects in Uganda
20) DEVELOPMENT OF RWIZI SMALL HYDRO
POWER PROJECT (0.5MW)
Estimated Costs (US $)
0.75 – 1.75 Million
Project Status/Remarks
Preliminary studies are available
Responsible Institution
Ministry of Energy and Mineral Development
41
42. Compendium of Infrastructure Projects in Uganda
21) DEVELOPMENT OF SEZIBWA SMALL HYDRO
POWER PROJECT (0.5MW)
Estimated Costs (US $)
0.75 – 1.75 Million
Project Status/Remarks
Preliminary technical studies are available
Responsible Institution
Ministry of Energy and Mineral Development
42
43. Compendium of Infrastructure Projects in Uganda
22) DEVELOPMENT OF RWIGO SMALL HYDRO
POWER PROJECT (0.48MW)
Estimated Costs (US $)
0.72 – 1.68 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
43
44. Compendium of Infrastructure Projects in Uganda
23) DEVELOPMENT OF NARWODO SMALL
HYDRO POWER PROJECT (0.4MW)
Estimated Costs (US $)
0.6 – 1.4 Million
Project Status/Remarks
Preliminary studies are available
Responsible Institution
Ministry of Energy and Mineral Development
44
45. Compendium of Infrastructure Projects in Uganda
24) DEVELOPMENT OF AGOI SMALL HYDRO
POWER PROJECT (0.35MW)
Estimated Costs (US $)
0.525 –1.225 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
45
46. Compendium of Infrastructure Projects in Uganda
25) DEVELOPMENT OF KITUMBA SMALL
HYDRO POWER PROJECT (0.2 MW)
Estimated Costs (US $)
0.3 – 0.7 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
46
47. Compendium of Infrastructure Projects in Uganda
26) DEVELOPMENT OF TOKWE SMALL HYDRO
POWER PROJECT (0.4MW)
Estimated Costs (US $)
0.6 –1.4 Million
Project Status/Remarks
Preliminary technical studies
Responsible Institution
Ministry of Energy and Mineral Development
47
48. Compendium of Infrastructure Projects in Uganda
27) DEVELOPMENT OF AMUA SMALL HYDRO
POWER PROJECT (0.18MW)
Estimated Costs (US $)
0.27 – 0.63 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
48
49. Compendium of Infrastructure Projects in Uganda
28) DEVELOPMENT OF NGITI SMALL HYDRO
POWER PROJECT (0.15MW)
Estimated Costs (US $)
0.225 – 0.525 Million
Project Status/Remarks
Preliminary technical studies are available
Responsible Institution
Ministry of Energy and Mineral Development
49
50. Compendium of Infrastructure Projects in Uganda
29) DEVELOPMENT OF LEYA SMALL HYDRO
POWER PROJECT (0.12MW)
Estimated Costs (US $)
0.18 – 0.42 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
50
51. Compendium of Infrastructure Projects in Uganda
30) DEVELOPMENT OF NYAKIBALE HYDRO
POWER PROJECT (0.1MW)
Estimated Costs (US $)
0.15 – 0.35 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
51
52. Compendium of Infrastructure Projects in Uganda
31) DEVELOPMENT OF MIRIA ADUA SMALL
HYDRO POWER PROJECT (0.1MW)
Estimated Costs (US $)
0.15 – 0.35 Million
Project Status/Remarks
Preliminary studies are available
Responsible Institution
Ministry of Energy and Mineral Development
52
53. Compendium of Infrastructure Projects in Uganda
32) DEVELOPMENT OF NKUSI SMALL HYDRO
POWER PROJECT (11MW)
Estimated Costs (US $)
16.5 – 38.5 Million
Project Status/Remarks
No studies
Responsible Institution
Ministry of Energy and Mineral Development
53
54. Compendium of Infrastructure Projects in Uganda
33) DEVELOPMENT OF ESIA HYDRO POWER
PROJECT (1.0 MW)
Estimated Costs (US $)
1.5 – 3.5 Million
Project Status/Remarks
Preliminary studies are available
Responsible Institution
Ministry of Energy and Mineral Development
54
55. Compendium of Infrastructure Projects in Uganda
34) DEVELOPMENT OF MANAFWA SMALL
HYDRO POWER PROJECT (0.15MW)
Estimated Costs (US $)
0.225 – 0.525 Million
Project Status/Remarks
Preliminary technical studies carried out
Responsible Institution
Ministry of Energy and Mineral Development
55