- 4. 1 8 11 16 20 A B C D E 0 5 10 15 20 Sequence of Tasks Slide Title Days
- 5. 1 9 12 17 21 A B C D E 0 5 10 15 20 Delay on Task B Project Delayed Slide Title Days
- 6. 1 5 8 11 16 20 A B C D E 0 5 10 15 20 Days F Float Time (15 days) Slide Title
- 7. 1 5 8 11 16 20 A B C D E 0 5 10 15 20 Days F Float Time (3 days) Slide Title
- 8. 1 8 9 12 17 21 A B C D E 0 5 10 15 20 Days Project Delayed F Slide Title
- 9. A F E D C B Slide Title
- 10. 1 5 8 11 16 20 Slide Title A B C D E 0 5 10 15 20 F Total 4 6 6 6 6 3 3 3 2 2 2 2 2 2 2 3 3 3 3 3 1 3 3 3 3 3 3 3 2 2 2 2 2 2 2 Days Allocation
- 11. 1 5 8 11 16 20 Slide Title A B C D E 0 5 10 15 20 F Allocation Total 4 6 6 6 6 3 3 3 2 2 2 2 2 2 2 Exceeds Supply! 3 3 3 3 3 1 3 3 3 3 3 3 3 2 2 2 2 2 2 2 Days
- 12. 1 8 11 13 16 20 Slide Title A B C D E 0 5 10 15 20 F 1 3 3 3 3 3 3 3 5 5 5 3 3 2 2 2 2 3 3 3 3 3 1 3 3 3 3 3 3 3 2 2 2 2 2 2 2 Task F delayed to avoid conflict with Task B Days
- 13. 1 8 11 16 20 Slide Title A B C D E 0 5 10 15 20 F 3 5 5 5 5 5 5 5 2 2 2 2 2 2 2 1 3 3 3 3 3 3 3 2 2 2 2 2 2 2 Allocation reduced – duration increased 2 2 2 2 2 2 2 2 Days