SlideShare a Scribd company logo
1 of 31
Download to read offline
ILP Professional Lighting Summit
14th June 2017 Glasgow
Louis Fourie MIET AMILP
Director
Clayton Fourie Consultancy
Erskine Bridge Electrical &
Lighting Refurbishment
1. Introduction
1. Introduction
Open 2nd June 1971 by Princess Anne
1. Existing Supply
Admin Building Dalnottar Substation
1. Previous Lighting
• The original street lighting consisted of:
• 5No high mast units at Admin Building & 15No Twin bracket columns
in centre reserve on south approach.
• 40No twin brackets in centre reserve across the bridge deck.
• 16No high masts north of the bridge.
• Two aircraft navigation lights on each tower.
1. Previous Electrical Network
• Electrical & Lighting network was 45 years old and reached the end of
there design life.
• The electrical network at the south end started in the switch room inside
admin building and ran out to the road through a service tunnel.
• At the north end, the supply came from a sub station at Dalnottar
Interchange
• Cables then ran up the central reserve into bridge and through the bridge
via 6No steel ducts
• Termination into 16No DB. 8No from north and 8No from south
• Admin building in south to mid-span.
• Dalnottar in North to mid-span
1. Previous Electrical Network
Steel duct running threw bridge
Steel duct where they are open.
1. Original Electrical Network
Original Distribution Board Original Distribution Board
1. Original Electrical Network
Cable entering bridge deck at north abutment T-joint forms mains to DB & Conduit to street lighting
1. Original Electrical Network
Cable entering bridge deck at north abutment T-joint form mains to DB & Conduit to street lighting
1. Original Electrical Network
The man rider taking you up to the top of the
tower.
Great view from the top of the tower
2. Design
1. The original high mast units at the admin building were no longer required due to
removal of the tolls and were replace with standard road lighting on the verge.
2. The number of lanterns were reduced from 40No to 26No.
3. The twin bracket columns in the center reserve were replaced with opposite
columns in the verge.
4. This removed the need for replacing the central reserve barriers comply with latest
standards and don’t need double fast lane closers for maintenance.
5. All the new columns were aluminum, passively safe type, fitted with LED lanterns
and central management system.
2. Design
1. The columns on the bridge deck were replaced with Aluminium columns and
required bespoke base plates.
2. Using CIE 115 and BS 5489 & BSEN 13201 we designed the scheme to M3 class
1. Minimum 1.0cd/m2 , Uo>40%
3. The electrical network no longer complied with safety standards
4. The high masts had exceeded their design service life and had to be replaced
5. The columns in the central reserve did not have sufficient clearance to allow the
barrier to deflect and operate in the correct manner, thus the new columns were
moved to the edge of carriageway
6. We looked at 8no lantern manufactures lantern and found a number of options
which would be acceptable. The final choice was proposed by the contractor
7. As per Transport Scotland standards all lanterns would be LED and controlled by
CMS.
2. Design
1. We decided to split the north and south network into 2No. separate supplies each.
One unmetered for street lighting and one metered for everything else.
2. The cable calcs showed that 95mm2 4core + earth cables would be required for new
main supply cables.
3. Each circuit is about 1300m in length.
4. After undertaking a Risk Assessment and consultation with the client, the decision
was made to install a ATEX Zone 2 equipment inside the bridge deck. This minimises
the risk of explosion if there is a build up of vapour inside the bridge following fuel or
chemical spill on the bridge.
5. As outside the bridge, all lanterns were LED and furthermore had to be vibration
resistant and incorporate emergency back up.
6. The light levels inside the bridge deck are 100Lux average over the central walkway.
2. Design
95mm ² 4 Core
XLPE/SWA/XLPE
+ 95mm2 XLPE/SWA/XLPE
earth
V = 400 volts
ELI = 0.35 Ω
2
1
4
TP+N
MCCB
64A
80A
TP+N
MCCB
40A
95mm ²4 Core
XLPE/SWA/XLPE+
95mm
XLPE/SWA
/XLPE EARTH
GS05 SOUTH SIDE BRIDGE
TERMINATION PILLAR
NEW PILLAR
STREET LIGHTING SUPPLY DBL1
95mm ²4 Core
LSZH/GSWB/EPR+ 95mm²
LSZH/GSWB/EPR EARTH
Vd = 4.74 volts
ELI = 0.62 Ω
METERED SUPPLY TO DB1
GS01 TOLL ADMIN
BUILDING
UNMETERED LIVE SUPPLY
GS05U
DBL1 TO DBL8 WITHIN BRIDGE, REFER TO DRG NOS
1/SW/1203/016/ELEC/004
METERED SUPPLY
FROM GS02
95mm ²4 Core
XLPE/SWA/XLPE+
95mm²
XLPE/SWA /XLPE
EARTH
METEREDUNMETERED
GS02 TOLL ADMIN
BUILDING
METERED LIVE SUPPLY
TP+N
MCCB
40A
2
35mm ² 4 Core
XLPE/SWA/XLPE +
35mm² XLPE/SWA/XLPE
earth
AB01
GS03
GS04
TP+N
MCCB
40A
3
TEDP
DB1 TO DB8 WITHIN BRIDGE, REFER TO DRG NOS
1/SW/1203/016/ELEC/003
95mm ² 4 Core
XLPE/SWA/XLPE
+ 95mm2 XLPE/SWA/XLPE
earth
80A
1
HAZARDS AREA ZONE 2
UNMETERED SUPPLY
FROM GS02
95mm ²4 Core
XLPE/SWA/XLPE+
95mm²
XLPE/SWA /XLPE
EARTH
V = 0.87 volts
ELI = 0.39Ω
Vd = 1.72 volts
ELI = 0.6 Ω
Vd = 2.31volts
ELI = 0.69 Ω
Vd = 3.6 volts
ELI = 0.99 Ω
Vd = 1.56 volts
ELI = 0.62 Ω
V = 400 volts
ELI = 0.35 Ω
GS05M
35mm ² 4 Core
XLPE/SWA/XLPE +
35mm² XLPE/SWA/XLPE
earth
35mm ² 4 Core
XLPE/SWA/XLPE +
35mm² XLPE/SWA/XLPE
earth
35mm ² 4 Core
XLPE/SWA/XLPE +
35mm² XLPE/SWA/XLPE
earth
ELECTRICAL NETWORK SOUTH OF BRIDGE
Schematic diagram for
Main network from admin
building
2. Design
16mm²3 core
XLPE/SWA/XLPE
16mm² 3core
XLPE/SWA/XLPE
Vd = 7.58V
ELI = 1.63 Ω
16mm²3 core
XLPE/SWA/XLPE
Vd = 7.58V
ELI = 1.63 Ω
Vd = 7.52V
ELI = 1.61 Ω
Vd = 7.58V
ELI = 1.61 Ω
Vd = 3.29V
ELI = 0.89 Ω
Vd = 3.29V
ELI = 1.1Ω
16mm² 3core
XLPE/SWA/XLPE
16mm²3core
XLPE/SWA/XLPE
16mm²3 core
XLPE/SWA/XLPE
16A Sockets
32A Sockets
16A Sockets
32A Sockets
64A Sockets
NAV
RAD
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
03
05
04
02
06
07
09
11
10
08
12
1314
01
02
03
04
01
02
03
04
01
02
03
04
01
02
03
04
01
02
03
04
01
02
03
04
01
02
03
04
15
1718
16 1516 1516
15
17
19
18
16
20
21
2324
22
15
17
19
18
16
20
21
23
25
24
22
26
15
1718
16
15
17
19
18
16
20
2122
15
17
19
18
16
20
2122
15
17
19
18
16
20
15
17
19
18
16
20
21
2324
22
15
17
19
18
16
20
2122
15
17
19
18
16
20
2122
S01
S02
S03
S04S05
S06S07
S08S09
S10
S11
S12S13
S14S15
S16
S01
S02
S03
S04
S05
S06S07
S08S09
S10
S11
S12S13
S14S15
S16
S01
S02
S03
S04S05
S06S07
S08S09
S10
S11
S12S13
S14S15
S16
S01
S02
S03
S04
S05
S06S07
S08S09
S10
S11
S12S13
S14S15
S16
S01
S02
S03
S04
S05
S06S07
S08S09
S10
S11
S12S13
S14S15
S16
S01
S02
S03
S04S05
S06S07
S08S09
S10
S11
S12S13
S14S15
S16
S01
S02
S03
S04
S05
S06S07
S08S09
S10
S11
S12S13
S14S15
S16
S18
S20
S22
S17
S19
S21
S18
S20
S22
S17
S19
S21
S18
S20
S22
S17
S19
S21S18
S20
S22
S17
S19
S21
S18
S20
S22
S17
S19
S21
S24
S26
S23
S25
S24
S26
S23
S25
DB1 (in box 79) DB2 (in box 75) DB3 (in box 71) DB4 ( in box 67) DB5 (in box 61)
DB6 ( in box 55)
GS
02
GS
05M
01
02
03
04
01
03
05
04
02
06
01
03
05
04
02
06
07
09
11
10
08
12
1314
S01
S02
S03
S04
S05
S06S07
S08S09
S10
01
03
05
04
02
06
07
09
11
10
08
12
1314
DB8 (in box 43)
Ancilliary apparatus located in box 69 to be re
connected to electrical supply. Refer to notes
Ancilliary apparatus located in box
58 to be re connected to electrical
supply. Refer to notes
Ancilliary apparatus located in box
49 to be re connected to electrical
supply. Refer to notes
DB7 (in box 49)
Vd=6.42V
ELI=0.83Ω Vd=5.78V
ELI=0.75Ω
Vd=5.78V
ELI=0.9Ω
Vd=7.13V
ELI=0.74Ω
Vd=6.69V
ELI=0.85Ω
Vd=6.69V
ELI=1Ω
Vd=8.28V
ELI=0.8Ω
Vd=6.69V
ELI=0.9Ω
Vd=6.97V
ELI=0.87Ω
Vd=8.56V
ELI=0.8Ω
Vd=6.97V
ELI=0.89Ω
Vd=6.97V
ELI=0.96Ω
Vd=7.23V
ELI=0.9Ω
Vd=7.23V
ELI=1Ω
Vd=10.6V
ELI=0.94Ω
Vd=7.23V
ELI=1.13Ω
Vd=7.58V
ELI=0.9Ω
Vd=7.58V
ELI=1.24Ω
Vd=10.95V
ELI=0.97Ω
Vd=7.58V
ELI=1.1Ω
Vd=7.92V
ELI=0.97Ω
Vd=7.92V
ELI=1.2Ω
Vd=9.82V
ELI=0.94Ω
Vd=7.92V
ELI=1.2Ω
Vd=8.65V
ELI=1Ω
Vd=8.65V
ELI=1.27Ω
Vd=10.55V
ELI=1Ω
Vd=8.65V
ELI=1.12Ω
Vd=8.28V
ELI=1Ω
Vd=8.28V
ELI=1.2Ω
Vd=8.28V
ELI=1.27Ω
Vd=9.65V
ELI=0.95Ω
25mm² 4Core LSZH/GSWB/EPR Cable
+25mm² earth Cable
95mm² 4Core LSZH/GSWB/EPR Cable
+95mm² single Core LSZH/GSWB/EPR
earth Cable
ACFT NAV
RAD
WIND
CPCCTV
25mm4c25mm4c25mm4c
25mm4c25mm4c25mm4c
95mm² 4Core XPLE/SWA/XPLE
Cable +95mm² single Core
XPLE/SWA/XPLE earth Cable
HAZARDOUS AREA
ZONE 2
1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 9
25mm4c25mm4c25mm4c
1 2 3 4 5 6 7 8 9
25mm4c25mm4c25mm4c
1 2 3 4 5 6 7 8 9
25mm4c25mm4c25mm4c
1 2 3 4 5 6 7 8 9
25mm4c25mm4c
1 2 3 4 5 6 7 8 9
25mm4c25mm4c
1 2 3 4 5 6 7 8 91 2 3 4 5 6 7 8 9
25mm4c25mm4c
CPCCTV
CTRL
Schematic diagram for network inside bridge
deck
Schematic diagram for street lighting
south of the bridge
2. Design
Vd = 6 volts
ELI = 0.64 Ω
95mm ² 4 Core
XLPE/SWA/XLPE
+ 95mm2 XLPE/SWA/XLPE
V = 400 volts
ELI = 0.35 Ω
7
TP+N
MCCB
32A
95mm² 4 Core
XLPE/SWA/XLPE +
95mm²
XLPE/SWA /XLPE
EARTH
GS07 NORTH SIDE BRIDGE
TERMINATION PILLAR
NEW PILLAR
95mm ²4 Core
LSZH/GSWB/EPR+ 95mm²
LSZH/GSWB/EPR EARTH
V = 5.5 volts
ELI = 0.72 Ω
GS08 DALNOTTOR
UNMETERED LIVE SUPPLY
METERED SUPPLY FROM
GS08 95mm ²4 Core
XLPE/SWA/XLPE+ 95mm²
XLPE/SWA /XLPE EARTH
GS08H16
METEREDUNMETERED
Vd =4.75 volts
ELI = 0.6 Ω
TP+N
MCCB
32A
GS08H13 GS08H14 GS08H15
Vd = 5.95 volts
ELI = 0.66 Ω
GS08H10 GS08H05 GS08H07
Vd = 8.2 volts
ELI = 0.78 ΩTP+N
MCCB
32A
GS08H11 GS08H12
VMSS2
Vd =6 volts
ELI = 0.66 Ω
TP+N
MCCB
32A
GS08H08 GS08H06
GS08H09 VMSS3
TP+N
MCCB
32A
Vd =1.63 volts
ELI = 0.43 Ω
GS08H04
1
Vd = 4.52 volts
ELI =0.54 Ω
GS08H03 GS08H02 GS08H01
TP+N
MCCB
32A
VMSS4
2
3
4
5
6
Vd = 8.66 volts
ELI = 0.8 Ω
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
STREET LIGHTING SUPPLY DBL17
METERED SUPPLY TO DB17
DBL17 TO DBL9 WITHIN BRIDGE, REFER TO DRG NOS
13/SW/1203/016/ELEC/006
DB17 TO DB9 WITHIN BRIDGE, REFER TO DRG NOS
13/SW/1203/016/ELEC/007
HAZARDS AREA ZONE 2
80A
TP+N
MCCB
80A
TP+N
MCCB
V = 400 volts
ELI = 0.35 Ω
Vd =6 volts
ELI = 0.66 Ω
GS07U
GS07M
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
35mm ² 4 Core
XLPE/SWA/XLPE + 35mm ²
XLPE/SWA/XLPE earth
1
ELECTRICAL NETWORK NORTH OF BRIDGE
Schematic diagram for network north of the bridge
2. Design
Tool capable of cutting through steel duct with out damaging cables inside
2. Design
Step 1
New BT Fibre
in duct
New Virgin
Fibre in duct
Traffic Scotland
Fibre
Electrical Mains
Electrical Mains
Redundant BT
Copper
Street Lighting Cable
New Traffic Scotland CCTV
Traffic Scotland Duct
Live Electrical Cable
Live Electrical Cable
Step 2
Step 4
Step 5
New BT Fibre in ducts
New Virgin Fibre in duct
Traffic Scotland Fibre
New Street Lighting Cable
New Traffic Scotland CCTV
New Auxiliary Cables
Electrical Mains
Electrical Mains
Redundant BT
Copper
Street Lighting Cable
New Traffic Scotland CCTV
Traffic Scotland Duct
Live Electrical Cable
Live Electrical Cable
New Electrical Mains
Metered
New Electrical Mains
Unmetered New Street Lighting
Cable
New Auxiliary Cables
Proposed Steps for removal of steel ducts.
New BT Fibre
in duct
New Virgin
Fibre in duct
New BT Fibre in ducts
New Virgin Fibre in duct
Traffic Scotland
Fibre
Auxiliary Cables
Move required
cable out of
harms way
Cut steel duct into small
pieces and remove
redundent ducts and cables
from bridge
Install cable ladder in
place of the first 3no
steel ducts
Cut remaining steel ducts
and redundent cables into
small pieces and remove
from bridge structure.
Install new cable ladder
into space of steel ducts.
Move all cables and ducts
to first cable ladder
Auxiliary Cables
New Traffic Scotland CCTV
New Electrical Mains
Metered
New Electrical Mains
Unmetered
2. Design
Specimen design for the new bracket for the LED replacement aircraft navigation lanterns
2. Construction
For the 95mm2 cable we had to use 200mm⌀ ducts. Purple street lighting duct is
100mm⌀.
2. Construction
High mast lowered and cut into 4 pieces to be taken from site to licensed recycling plant
2. Construction
All the bolts in the bridge deck were pull tested and after the new column was fitted
sealed with grout to water proof the column base.
2. Construction
New LED Lantern fitted with CMS nodes , show the uniformity achieved on the
approach road and in the compound.
2. Construction
The uniformity achieved on the approach road north of the bridge using high mast units.
2. Construction
New LED Zone 2 lighting inside the bridge deck
2. Construction
The new Zone 2 DB and new cable ladders with electrical cable and coms cable
separated.
3. What was achieved.
1. Environmental impact.
1. The new lighting installation has reduced the energy by 70% energy (£50K
per year)
2. Over £3K reduction in carbon tax per year.
3. 20% material was recycled dusring the course of the project.
2. The contract was completed on budget and on time.
4. Thanks to
1. Transport Scotland Bridges section
2. Scotland Transerv for managing the contract.
3. Lightways Contracting
5. Questions
Finished!Finished!Finished!Finished!
Louis Fourie CEng MIET MILP
Clayton Fourie Consultancy Ltd
Tel: 07906664770
Email: louis@claytonfourie.com

More Related Content

What's hot

LED street lighting: What it is and how it has worked for us
LED street lighting: What it is and how it has worked for usLED street lighting: What it is and how it has worked for us
LED street lighting: What it is and how it has worked for usUniversity of Minnesota
 
NZEB Office Building including renewable energy ratio calculation orla coyle
NZEB Office Building including renewable energy ratio calculation  orla coyleNZEB Office Building including renewable energy ratio calculation  orla coyle
NZEB Office Building including renewable energy ratio calculation orla coyleSustainableEnergyAut
 
Energy Efficient Lighting | Infineon Technologies
Energy Efficient Lighting  | Infineon TechnologiesEnergy Efficient Lighting  | Infineon Technologies
Energy Efficient Lighting | Infineon TechnologiesInfineon Technologies AG
 
Exorg Group Solar Division
Exorg Group Solar DivisionExorg Group Solar Division
Exorg Group Solar DivisionBiju Soman
 
Fahad & Tahalia Roads Underpass LED Lighting
Fahad & Tahalia Roads Underpass LED LightingFahad & Tahalia Roads Underpass LED Lighting
Fahad & Tahalia Roads Underpass LED LightingMichael Santiago
 
Energy efficient lighting technologies
Energy efficient lighting technologiesEnergy efficient lighting technologies
Energy efficient lighting technologiesVishwajeet Rajwaday
 
Keynote - Joseph Simonelli
Keynote - Joseph SimonelliKeynote - Joseph Simonelli
Keynote - Joseph SimonelliReenergize
 
Nice Technologies' Solar Products
Nice Technologies' Solar Products Nice Technologies' Solar Products
Nice Technologies' Solar Products kunalljain
 
Advances in Molten Salt Thermal Storage [CSTP 2010]
Advances in Molten Salt Thermal Storage [CSTP 2010]Advances in Molten Salt Thermal Storage [CSTP 2010]
Advances in Molten Salt Thermal Storage [CSTP 2010]Smithers Apex
 
LED Lighting for Energy Efficiency By, Er. Swapnil V. Kaware
LED Lighting for Energy Efficiency By, Er. Swapnil V. KawareLED Lighting for Energy Efficiency By, Er. Swapnil V. Kaware
LED Lighting for Energy Efficiency By, Er. Swapnil V. KawareProf. Swapnil V. Kaware
 
DTLe Panel Revie presentation-2018-03-28 NAVY Caderock
DTLe Panel Revie presentation-2018-03-28 NAVY CaderockDTLe Panel Revie presentation-2018-03-28 NAVY Caderock
DTLe Panel Revie presentation-2018-03-28 NAVY Caderocknino marcantonio
 
Copper alloy conductors for overhead lines - Nordic Conference on Electricity...
Copper alloy conductors for overhead lines - Nordic Conference on Electricity...Copper alloy conductors for overhead lines - Nordic Conference on Electricity...
Copper alloy conductors for overhead lines - Nordic Conference on Electricity...Leonardo ENERGY
 
GE LED Plug-in 2Pin - Product Presentation
GE LED Plug-in 2Pin - Product Presentation GE LED Plug-in 2Pin - Product Presentation
GE LED Plug-in 2Pin - Product Presentation GE Lighting Europe
 
CLFR with Biomass 250 kW, Thailand
CLFR with Biomass 250 kW, ThailandCLFR with Biomass 250 kW, Thailand
CLFR with Biomass 250 kW, ThailandJack Wong
 
Lou presentation led lighting - opfma conference 2013 final
Lou presentation   led lighting - opfma conference 2013 finalLou presentation   led lighting - opfma conference 2013 final
Lou presentation led lighting - opfma conference 2013 finalWikLOU
 
Examples of NZEB in the Public Sector by John Furlong
Examples of NZEB in the Public Sector by John FurlongExamples of NZEB in the Public Sector by John Furlong
Examples of NZEB in the Public Sector by John FurlongSustainableEnergyAut
 
NZEB Office Building by David Walshe
NZEB Office Building by  David WalsheNZEB Office Building by  David Walshe
NZEB Office Building by David WalsheSustainableEnergyAut
 

What's hot (20)

LED street lighting: What it is and how it has worked for us
LED street lighting: What it is and how it has worked for usLED street lighting: What it is and how it has worked for us
LED street lighting: What it is and how it has worked for us
 
NZEB Office Building including renewable energy ratio calculation orla coyle
NZEB Office Building including renewable energy ratio calculation  orla coyleNZEB Office Building including renewable energy ratio calculation  orla coyle
NZEB Office Building including renewable energy ratio calculation orla coyle
 
Energy Efficient Lighting | Infineon Technologies
Energy Efficient Lighting  | Infineon TechnologiesEnergy Efficient Lighting  | Infineon Technologies
Energy Efficient Lighting | Infineon Technologies
 
Exorg Group Solar Division
Exorg Group Solar DivisionExorg Group Solar Division
Exorg Group Solar Division
 
Fahad & Tahalia Roads Underpass LED Lighting
Fahad & Tahalia Roads Underpass LED LightingFahad & Tahalia Roads Underpass LED Lighting
Fahad & Tahalia Roads Underpass LED Lighting
 
Energy efficient lighting technologies
Energy efficient lighting technologiesEnergy efficient lighting technologies
Energy efficient lighting technologies
 
Keynote - Joseph Simonelli
Keynote - Joseph SimonelliKeynote - Joseph Simonelli
Keynote - Joseph Simonelli
 
5 lighting
5 lighting5 lighting
5 lighting
 
Nice Technologies' Solar Products
Nice Technologies' Solar Products Nice Technologies' Solar Products
Nice Technologies' Solar Products
 
Advances in Molten Salt Thermal Storage [CSTP 2010]
Advances in Molten Salt Thermal Storage [CSTP 2010]Advances in Molten Salt Thermal Storage [CSTP 2010]
Advances in Molten Salt Thermal Storage [CSTP 2010]
 
PLS 2016: The business case for LED street lighting
PLS 2016: The business case for LED street lightingPLS 2016: The business case for LED street lighting
PLS 2016: The business case for LED street lighting
 
LED Lighting for Energy Efficiency By, Er. Swapnil V. Kaware
LED Lighting for Energy Efficiency By, Er. Swapnil V. KawareLED Lighting for Energy Efficiency By, Er. Swapnil V. Kaware
LED Lighting for Energy Efficiency By, Er. Swapnil V. Kaware
 
RENEWABLE ENERGY SOLUTIONS
RENEWABLE ENERGY SOLUTIONSRENEWABLE ENERGY SOLUTIONS
RENEWABLE ENERGY SOLUTIONS
 
DTLe Panel Revie presentation-2018-03-28 NAVY Caderock
DTLe Panel Revie presentation-2018-03-28 NAVY CaderockDTLe Panel Revie presentation-2018-03-28 NAVY Caderock
DTLe Panel Revie presentation-2018-03-28 NAVY Caderock
 
Copper alloy conductors for overhead lines - Nordic Conference on Electricity...
Copper alloy conductors for overhead lines - Nordic Conference on Electricity...Copper alloy conductors for overhead lines - Nordic Conference on Electricity...
Copper alloy conductors for overhead lines - Nordic Conference on Electricity...
 
GE LED Plug-in 2Pin - Product Presentation
GE LED Plug-in 2Pin - Product Presentation GE LED Plug-in 2Pin - Product Presentation
GE LED Plug-in 2Pin - Product Presentation
 
CLFR with Biomass 250 kW, Thailand
CLFR with Biomass 250 kW, ThailandCLFR with Biomass 250 kW, Thailand
CLFR with Biomass 250 kW, Thailand
 
Lou presentation led lighting - opfma conference 2013 final
Lou presentation   led lighting - opfma conference 2013 finalLou presentation   led lighting - opfma conference 2013 final
Lou presentation led lighting - opfma conference 2013 final
 
Examples of NZEB in the Public Sector by John Furlong
Examples of NZEB in the Public Sector by John FurlongExamples of NZEB in the Public Sector by John Furlong
Examples of NZEB in the Public Sector by John Furlong
 
NZEB Office Building by David Walshe
NZEB Office Building by  David WalsheNZEB Office Building by  David Walshe
NZEB Office Building by David Walshe
 

Similar to PLS 2017: Erskine Bridge Electrical and Lighting Refurbishment

Solar Power Plant At Dindigul
Solar Power Plant At DindigulSolar Power Plant At Dindigul
Solar Power Plant At Dindigulwajidsharieff
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976Southern Railway
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses reportkamal soni
 
Cathodic prevention of steel rebars in concrete the international outlook
Cathodic prevention of steel rebars in concrete the international outlookCathodic prevention of steel rebars in concrete the international outlook
Cathodic prevention of steel rebars in concrete the international outlookSimone Tremolada
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects ceaMahesh Chandra Manav
 
Performances of distribution transformer installed in metallic enclosures
Performances of  distribution transformer installed in metallic enclosuresPerformances of  distribution transformer installed in metallic enclosures
Performances of distribution transformer installed in metallic enclosuresnehakardam
 
Traction distribution
Traction distribution Traction distribution
Traction distribution Amit Kumar
 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notesmichaeljmack
 
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-OnNexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-OnThorne & Derrick International
 
xxxQxxx Quotation Estimate for Electrical Work of Poultry Processing Plant
xxxQxxx Quotation Estimate for Electrical Work of Poultry Processing PlantxxxQxxx Quotation Estimate for Electrical Work of Poultry Processing Plant
xxxQxxx Quotation Estimate for Electrical Work of Poultry Processing PlantMuhammad Sarfraz
 
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...
Electrical safety presentation by jmv railway and invitation ireee2019 at ...Mahesh Chandra Manav
 
Presentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsPresentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsMahesh Chandra Manav
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Mahesh Chandra Manav
 
UNDERGROUND HIGH POWER TRANSMISSION LINES
UNDERGROUND HIGH POWER TRANSMISSION LINESUNDERGROUND HIGH POWER TRANSMISSION LINES
UNDERGROUND HIGH POWER TRANSMISSION LINESVISHNU ARAVIND
 

Similar to PLS 2017: Erskine Bridge Electrical and Lighting Refurbishment (20)

Harish aggarwal
Harish aggarwalHarish aggarwal
Harish aggarwal
 
Solar Power Plant At Dindigul
Solar Power Plant At DindigulSolar Power Plant At Dindigul
Solar Power Plant At Dindigul
 
Mike's presentation
Mike's presentationMike's presentation
Mike's presentation
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses report
 
Cathodic prevention of steel rebars in concrete the international outlook
Cathodic prevention of steel rebars in concrete the international outlookCathodic prevention of steel rebars in concrete the international outlook
Cathodic prevention of steel rebars in concrete the international outlook
 
PEC (1).pptx
PEC (1).pptxPEC (1).pptx
PEC (1).pptx
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects cea
 
Performances of distribution transformer installed in metallic enclosures
Performances of  distribution transformer installed in metallic enclosuresPerformances of  distribution transformer installed in metallic enclosures
Performances of distribution transformer installed in metallic enclosures
 
Traction distribution
Traction distribution Traction distribution
Traction distribution
 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
 
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-OnNexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
 
xxxQxxx Quotation Estimate for Electrical Work of Poultry Processing Plant
xxxQxxx Quotation Estimate for Electrical Work of Poultry Processing PlantxxxQxxx Quotation Estimate for Electrical Work of Poultry Processing Plant
xxxQxxx Quotation Estimate for Electrical Work of Poultry Processing Plant
 
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
 
Presentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsPresentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lps
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)
 
UNDERGROUND HIGH POWER TRANSMISSION LINES
UNDERGROUND HIGH POWER TRANSMISSION LINESUNDERGROUND HIGH POWER TRANSMISSION LINES
UNDERGROUND HIGH POWER TRANSMISSION LINES
 
c4interc
c4intercc4interc
c4interc
 

More from Institution of Lighting Professionals

ILP Ireland webinar: Dark Skies or Safer Streets – are we taking a holistic a...
ILP Ireland webinar: Dark Skies or Safer Streets – are we taking a holistic a...ILP Ireland webinar: Dark Skies or Safer Streets – are we taking a holistic a...
ILP Ireland webinar: Dark Skies or Safer Streets – are we taking a holistic a...Institution of Lighting Professionals
 
ILP Bristol webinar: Supporting the roll-out of Electric Vehicle charging inf...
ILP Bristol webinar: Supporting the roll-out of Electric Vehicle charging inf...ILP Bristol webinar: Supporting the roll-out of Electric Vehicle charging inf...
ILP Bristol webinar: Supporting the roll-out of Electric Vehicle charging inf...Institution of Lighting Professionals
 
ILP Sustainability CPD Afternoon: Creating a Circular Economy in the Lighting...
ILP Sustainability CPD Afternoon: Creating a Circular Economy in the Lighting...ILP Sustainability CPD Afternoon: Creating a Circular Economy in the Lighting...
ILP Sustainability CPD Afternoon: Creating a Circular Economy in the Lighting...Institution of Lighting Professionals
 
ILP Sustainability CPD Afternoon: Local Council Roads Innovation Group: en ro...
ILP Sustainability CPD Afternoon: Local Council Roads Innovation Group: en ro...ILP Sustainability CPD Afternoon: Local Council Roads Innovation Group: en ro...
ILP Sustainability CPD Afternoon: Local Council Roads Innovation Group: en ro...Institution of Lighting Professionals
 
CPD from the ILP: The Role of Public Lighting in Designing Safer Places
CPD from the ILP: The Role of Public Lighting in Designing Safer PlacesCPD from the ILP: The Role of Public Lighting in Designing Safer Places
CPD from the ILP: The Role of Public Lighting in Designing Safer PlacesInstitution of Lighting Professionals
 
YLP CPD Webinar: Two expert planners talk about lighting and dark skies
YLP CPD Webinar: Two expert planners talk about lighting and dark skiesYLP CPD Webinar: Two expert planners talk about lighting and dark skies
YLP CPD Webinar: Two expert planners talk about lighting and dark skiesInstitution of Lighting Professionals
 
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice -...
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice -...ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice -...
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice -...Institution of Lighting Professionals
 
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice p...
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice p...ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice p...
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice p...Institution of Lighting Professionals
 
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...Institution of Lighting Professionals
 
ILP Ireland CPD Webinar: Road Lighting Standards for Europe and beyond
ILP Ireland CPD Webinar: Road Lighting Standards for Europe and beyondILP Ireland CPD Webinar: Road Lighting Standards for Europe and beyond
ILP Ireland CPD Webinar: Road Lighting Standards for Europe and beyondInstitution of Lighting Professionals
 

More from Institution of Lighting Professionals (20)

YLP CPD webinar: We share the night
YLP CPD webinar: We share the nightYLP CPD webinar: We share the night
YLP CPD webinar: We share the night
 
ILP Durham CPD: COP26
ILP Durham CPD: COP26ILP Durham CPD: COP26
ILP Durham CPD: COP26
 
ILP Durham CPD: Lighting for Ecology
ILP Durham CPD: Lighting for EcologyILP Durham CPD: Lighting for Ecology
ILP Durham CPD: Lighting for Ecology
 
ILP Durham CPD: Why a site visit is important on a traffic route
ILP Durham CPD: Why a site visit is important on a traffic routeILP Durham CPD: Why a site visit is important on a traffic route
ILP Durham CPD: Why a site visit is important on a traffic route
 
ILP Ireland webinar: Dark Skies or Safer Streets – are we taking a holistic a...
ILP Ireland webinar: Dark Skies or Safer Streets – are we taking a holistic a...ILP Ireland webinar: Dark Skies or Safer Streets – are we taking a holistic a...
ILP Ireland webinar: Dark Skies or Safer Streets – are we taking a holistic a...
 
ILP Bristol webinar: Supporting the roll-out of Electric Vehicle charging inf...
ILP Bristol webinar: Supporting the roll-out of Electric Vehicle charging inf...ILP Bristol webinar: Supporting the roll-out of Electric Vehicle charging inf...
ILP Bristol webinar: Supporting the roll-out of Electric Vehicle charging inf...
 
ILP Scotland webinar: Luminaire Design for the Circular Economy
ILP Scotland webinar: Luminaire Design for the Circular EconomyILP Scotland webinar: Luminaire Design for the Circular Economy
ILP Scotland webinar: Luminaire Design for the Circular Economy
 
ILP Sustainability CPD Afternoon: Creating a Circular Economy in the Lighting...
ILP Sustainability CPD Afternoon: Creating a Circular Economy in the Lighting...ILP Sustainability CPD Afternoon: Creating a Circular Economy in the Lighting...
ILP Sustainability CPD Afternoon: Creating a Circular Economy in the Lighting...
 
ILP Sustainability CPD Afternoon: Local Council Roads Innovation Group: en ro...
ILP Sustainability CPD Afternoon: Local Council Roads Innovation Group: en ro...ILP Sustainability CPD Afternoon: Local Council Roads Innovation Group: en ro...
ILP Sustainability CPD Afternoon: Local Council Roads Innovation Group: en ro...
 
How To Be Brilliant At Being Different
How To Be Brilliant At Being DifferentHow To Be Brilliant At Being Different
How To Be Brilliant At Being Different
 
ILP Durham CPD: The Intrigue of Colour
ILP Durham CPD: The Intrigue of ColourILP Durham CPD: The Intrigue of Colour
ILP Durham CPD: The Intrigue of Colour
 
ILP Durham CPD: The Fascination of Colour
ILP Durham CPD: The Fascination of ColourILP Durham CPD: The Fascination of Colour
ILP Durham CPD: The Fascination of Colour
 
ILP Birmingham CPD: Relighting spaces in the built environment
ILP Birmingham CPD: Relighting spaces in the built environment ILP Birmingham CPD: Relighting spaces in the built environment
ILP Birmingham CPD: Relighting spaces in the built environment
 
ILP Bristol CPD: Technological Challenges in Smart Public Lighting
ILP Bristol CPD: Technological Challenges in Smart Public LightingILP Bristol CPD: Technological Challenges in Smart Public Lighting
ILP Bristol CPD: Technological Challenges in Smart Public Lighting
 
CPD from the ILP: The Role of Public Lighting in Designing Safer Places
CPD from the ILP: The Role of Public Lighting in Designing Safer PlacesCPD from the ILP: The Role of Public Lighting in Designing Safer Places
CPD from the ILP: The Role of Public Lighting in Designing Safer Places
 
YLP CPD Webinar: Two expert planners talk about lighting and dark skies
YLP CPD Webinar: Two expert planners talk about lighting and dark skiesYLP CPD Webinar: Two expert planners talk about lighting and dark skies
YLP CPD Webinar: Two expert planners talk about lighting and dark skies
 
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice -...
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice -...ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice -...
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice -...
 
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice p...
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice p...ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice p...
ILP Durham CPD Webinar: Northern England Dark Skies – sharing good practice p...
 
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
 
ILP Ireland CPD Webinar: Road Lighting Standards for Europe and beyond
ILP Ireland CPD Webinar: Road Lighting Standards for Europe and beyondILP Ireland CPD Webinar: Road Lighting Standards for Europe and beyond
ILP Ireland CPD Webinar: Road Lighting Standards for Europe and beyond
 

Recently uploaded

Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfakankshagupta7348026
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Hasting Chen
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Delhi Call girls
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptssuser319dad
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrsaastr
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptxBasil Achie
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 

Recently uploaded (20)

Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdf
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.ppt
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 

PLS 2017: Erskine Bridge Electrical and Lighting Refurbishment

  • 1. ILP Professional Lighting Summit 14th June 2017 Glasgow Louis Fourie MIET AMILP Director Clayton Fourie Consultancy Erskine Bridge Electrical & Lighting Refurbishment
  • 3. 1. Introduction Open 2nd June 1971 by Princess Anne
  • 4. 1. Existing Supply Admin Building Dalnottar Substation
  • 5. 1. Previous Lighting • The original street lighting consisted of: • 5No high mast units at Admin Building & 15No Twin bracket columns in centre reserve on south approach. • 40No twin brackets in centre reserve across the bridge deck. • 16No high masts north of the bridge. • Two aircraft navigation lights on each tower.
  • 6. 1. Previous Electrical Network • Electrical & Lighting network was 45 years old and reached the end of there design life. • The electrical network at the south end started in the switch room inside admin building and ran out to the road through a service tunnel. • At the north end, the supply came from a sub station at Dalnottar Interchange • Cables then ran up the central reserve into bridge and through the bridge via 6No steel ducts • Termination into 16No DB. 8No from north and 8No from south • Admin building in south to mid-span. • Dalnottar in North to mid-span
  • 7. 1. Previous Electrical Network Steel duct running threw bridge Steel duct where they are open.
  • 8. 1. Original Electrical Network Original Distribution Board Original Distribution Board
  • 9. 1. Original Electrical Network Cable entering bridge deck at north abutment T-joint forms mains to DB & Conduit to street lighting
  • 10. 1. Original Electrical Network Cable entering bridge deck at north abutment T-joint form mains to DB & Conduit to street lighting
  • 11. 1. Original Electrical Network The man rider taking you up to the top of the tower. Great view from the top of the tower
  • 12. 2. Design 1. The original high mast units at the admin building were no longer required due to removal of the tolls and were replace with standard road lighting on the verge. 2. The number of lanterns were reduced from 40No to 26No. 3. The twin bracket columns in the center reserve were replaced with opposite columns in the verge. 4. This removed the need for replacing the central reserve barriers comply with latest standards and don’t need double fast lane closers for maintenance. 5. All the new columns were aluminum, passively safe type, fitted with LED lanterns and central management system.
  • 13. 2. Design 1. The columns on the bridge deck were replaced with Aluminium columns and required bespoke base plates. 2. Using CIE 115 and BS 5489 & BSEN 13201 we designed the scheme to M3 class 1. Minimum 1.0cd/m2 , Uo>40% 3. The electrical network no longer complied with safety standards 4. The high masts had exceeded their design service life and had to be replaced 5. The columns in the central reserve did not have sufficient clearance to allow the barrier to deflect and operate in the correct manner, thus the new columns were moved to the edge of carriageway 6. We looked at 8no lantern manufactures lantern and found a number of options which would be acceptable. The final choice was proposed by the contractor 7. As per Transport Scotland standards all lanterns would be LED and controlled by CMS.
  • 14. 2. Design 1. We decided to split the north and south network into 2No. separate supplies each. One unmetered for street lighting and one metered for everything else. 2. The cable calcs showed that 95mm2 4core + earth cables would be required for new main supply cables. 3. Each circuit is about 1300m in length. 4. After undertaking a Risk Assessment and consultation with the client, the decision was made to install a ATEX Zone 2 equipment inside the bridge deck. This minimises the risk of explosion if there is a build up of vapour inside the bridge following fuel or chemical spill on the bridge. 5. As outside the bridge, all lanterns were LED and furthermore had to be vibration resistant and incorporate emergency back up. 6. The light levels inside the bridge deck are 100Lux average over the central walkway.
  • 15. 2. Design 95mm ² 4 Core XLPE/SWA/XLPE + 95mm2 XLPE/SWA/XLPE earth V = 400 volts ELI = 0.35 Ω 2 1 4 TP+N MCCB 64A 80A TP+N MCCB 40A 95mm ²4 Core XLPE/SWA/XLPE+ 95mm XLPE/SWA /XLPE EARTH GS05 SOUTH SIDE BRIDGE TERMINATION PILLAR NEW PILLAR STREET LIGHTING SUPPLY DBL1 95mm ²4 Core LSZH/GSWB/EPR+ 95mm² LSZH/GSWB/EPR EARTH Vd = 4.74 volts ELI = 0.62 Ω METERED SUPPLY TO DB1 GS01 TOLL ADMIN BUILDING UNMETERED LIVE SUPPLY GS05U DBL1 TO DBL8 WITHIN BRIDGE, REFER TO DRG NOS 1/SW/1203/016/ELEC/004 METERED SUPPLY FROM GS02 95mm ²4 Core XLPE/SWA/XLPE+ 95mm² XLPE/SWA /XLPE EARTH METEREDUNMETERED GS02 TOLL ADMIN BUILDING METERED LIVE SUPPLY TP+N MCCB 40A 2 35mm ² 4 Core XLPE/SWA/XLPE + 35mm² XLPE/SWA/XLPE earth AB01 GS03 GS04 TP+N MCCB 40A 3 TEDP DB1 TO DB8 WITHIN BRIDGE, REFER TO DRG NOS 1/SW/1203/016/ELEC/003 95mm ² 4 Core XLPE/SWA/XLPE + 95mm2 XLPE/SWA/XLPE earth 80A 1 HAZARDS AREA ZONE 2 UNMETERED SUPPLY FROM GS02 95mm ²4 Core XLPE/SWA/XLPE+ 95mm² XLPE/SWA /XLPE EARTH V = 0.87 volts ELI = 0.39Ω Vd = 1.72 volts ELI = 0.6 Ω Vd = 2.31volts ELI = 0.69 Ω Vd = 3.6 volts ELI = 0.99 Ω Vd = 1.56 volts ELI = 0.62 Ω V = 400 volts ELI = 0.35 Ω GS05M 35mm ² 4 Core XLPE/SWA/XLPE + 35mm² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm² XLPE/SWA/XLPE earth ELECTRICAL NETWORK SOUTH OF BRIDGE Schematic diagram for Main network from admin building
  • 16. 2. Design 16mm²3 core XLPE/SWA/XLPE 16mm² 3core XLPE/SWA/XLPE Vd = 7.58V ELI = 1.63 Ω 16mm²3 core XLPE/SWA/XLPE Vd = 7.58V ELI = 1.63 Ω Vd = 7.52V ELI = 1.61 Ω Vd = 7.58V ELI = 1.61 Ω Vd = 3.29V ELI = 0.89 Ω Vd = 3.29V ELI = 1.1Ω 16mm² 3core XLPE/SWA/XLPE 16mm²3core XLPE/SWA/XLPE 16mm²3 core XLPE/SWA/XLPE 16A Sockets 32A Sockets 16A Sockets 32A Sockets 64A Sockets NAV RAD 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 03 05 04 02 06 07 09 11 10 08 12 1314 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 15 1718 16 1516 1516 15 17 19 18 16 20 21 2324 22 15 17 19 18 16 20 21 23 25 24 22 26 15 1718 16 15 17 19 18 16 20 2122 15 17 19 18 16 20 2122 15 17 19 18 16 20 15 17 19 18 16 20 21 2324 22 15 17 19 18 16 20 2122 15 17 19 18 16 20 2122 S01 S02 S03 S04S05 S06S07 S08S09 S10 S11 S12S13 S14S15 S16 S01 S02 S03 S04 S05 S06S07 S08S09 S10 S11 S12S13 S14S15 S16 S01 S02 S03 S04S05 S06S07 S08S09 S10 S11 S12S13 S14S15 S16 S01 S02 S03 S04 S05 S06S07 S08S09 S10 S11 S12S13 S14S15 S16 S01 S02 S03 S04 S05 S06S07 S08S09 S10 S11 S12S13 S14S15 S16 S01 S02 S03 S04S05 S06S07 S08S09 S10 S11 S12S13 S14S15 S16 S01 S02 S03 S04 S05 S06S07 S08S09 S10 S11 S12S13 S14S15 S16 S18 S20 S22 S17 S19 S21 S18 S20 S22 S17 S19 S21 S18 S20 S22 S17 S19 S21S18 S20 S22 S17 S19 S21 S18 S20 S22 S17 S19 S21 S24 S26 S23 S25 S24 S26 S23 S25 DB1 (in box 79) DB2 (in box 75) DB3 (in box 71) DB4 ( in box 67) DB5 (in box 61) DB6 ( in box 55) GS 02 GS 05M 01 02 03 04 01 03 05 04 02 06 01 03 05 04 02 06 07 09 11 10 08 12 1314 S01 S02 S03 S04 S05 S06S07 S08S09 S10 01 03 05 04 02 06 07 09 11 10 08 12 1314 DB8 (in box 43) Ancilliary apparatus located in box 69 to be re connected to electrical supply. Refer to notes Ancilliary apparatus located in box 58 to be re connected to electrical supply. Refer to notes Ancilliary apparatus located in box 49 to be re connected to electrical supply. Refer to notes DB7 (in box 49) Vd=6.42V ELI=0.83Ω Vd=5.78V ELI=0.75Ω Vd=5.78V ELI=0.9Ω Vd=7.13V ELI=0.74Ω Vd=6.69V ELI=0.85Ω Vd=6.69V ELI=1Ω Vd=8.28V ELI=0.8Ω Vd=6.69V ELI=0.9Ω Vd=6.97V ELI=0.87Ω Vd=8.56V ELI=0.8Ω Vd=6.97V ELI=0.89Ω Vd=6.97V ELI=0.96Ω Vd=7.23V ELI=0.9Ω Vd=7.23V ELI=1Ω Vd=10.6V ELI=0.94Ω Vd=7.23V ELI=1.13Ω Vd=7.58V ELI=0.9Ω Vd=7.58V ELI=1.24Ω Vd=10.95V ELI=0.97Ω Vd=7.58V ELI=1.1Ω Vd=7.92V ELI=0.97Ω Vd=7.92V ELI=1.2Ω Vd=9.82V ELI=0.94Ω Vd=7.92V ELI=1.2Ω Vd=8.65V ELI=1Ω Vd=8.65V ELI=1.27Ω Vd=10.55V ELI=1Ω Vd=8.65V ELI=1.12Ω Vd=8.28V ELI=1Ω Vd=8.28V ELI=1.2Ω Vd=8.28V ELI=1.27Ω Vd=9.65V ELI=0.95Ω 25mm² 4Core LSZH/GSWB/EPR Cable +25mm² earth Cable 95mm² 4Core LSZH/GSWB/EPR Cable +95mm² single Core LSZH/GSWB/EPR earth Cable ACFT NAV RAD WIND CPCCTV 25mm4c25mm4c25mm4c 25mm4c25mm4c25mm4c 95mm² 4Core XPLE/SWA/XPLE Cable +95mm² single Core XPLE/SWA/XPLE earth Cable HAZARDOUS AREA ZONE 2 1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 9 25mm4c25mm4c25mm4c 1 2 3 4 5 6 7 8 9 25mm4c25mm4c25mm4c 1 2 3 4 5 6 7 8 9 25mm4c25mm4c25mm4c 1 2 3 4 5 6 7 8 9 25mm4c25mm4c 1 2 3 4 5 6 7 8 9 25mm4c25mm4c 1 2 3 4 5 6 7 8 91 2 3 4 5 6 7 8 9 25mm4c25mm4c CPCCTV CTRL Schematic diagram for network inside bridge deck Schematic diagram for street lighting south of the bridge
  • 17. 2. Design Vd = 6 volts ELI = 0.64 Ω 95mm ² 4 Core XLPE/SWA/XLPE + 95mm2 XLPE/SWA/XLPE V = 400 volts ELI = 0.35 Ω 7 TP+N MCCB 32A 95mm² 4 Core XLPE/SWA/XLPE + 95mm² XLPE/SWA /XLPE EARTH GS07 NORTH SIDE BRIDGE TERMINATION PILLAR NEW PILLAR 95mm ²4 Core LSZH/GSWB/EPR+ 95mm² LSZH/GSWB/EPR EARTH V = 5.5 volts ELI = 0.72 Ω GS08 DALNOTTOR UNMETERED LIVE SUPPLY METERED SUPPLY FROM GS08 95mm ²4 Core XLPE/SWA/XLPE+ 95mm² XLPE/SWA /XLPE EARTH GS08H16 METEREDUNMETERED Vd =4.75 volts ELI = 0.6 Ω TP+N MCCB 32A GS08H13 GS08H14 GS08H15 Vd = 5.95 volts ELI = 0.66 Ω GS08H10 GS08H05 GS08H07 Vd = 8.2 volts ELI = 0.78 ΩTP+N MCCB 32A GS08H11 GS08H12 VMSS2 Vd =6 volts ELI = 0.66 Ω TP+N MCCB 32A GS08H08 GS08H06 GS08H09 VMSS3 TP+N MCCB 32A Vd =1.63 volts ELI = 0.43 Ω GS08H04 1 Vd = 4.52 volts ELI =0.54 Ω GS08H03 GS08H02 GS08H01 TP+N MCCB 32A VMSS4 2 3 4 5 6 Vd = 8.66 volts ELI = 0.8 Ω 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth STREET LIGHTING SUPPLY DBL17 METERED SUPPLY TO DB17 DBL17 TO DBL9 WITHIN BRIDGE, REFER TO DRG NOS 13/SW/1203/016/ELEC/006 DB17 TO DB9 WITHIN BRIDGE, REFER TO DRG NOS 13/SW/1203/016/ELEC/007 HAZARDS AREA ZONE 2 80A TP+N MCCB 80A TP+N MCCB V = 400 volts ELI = 0.35 Ω Vd =6 volts ELI = 0.66 Ω GS07U GS07M 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 35mm ² 4 Core XLPE/SWA/XLPE + 35mm ² XLPE/SWA/XLPE earth 1 ELECTRICAL NETWORK NORTH OF BRIDGE Schematic diagram for network north of the bridge
  • 18. 2. Design Tool capable of cutting through steel duct with out damaging cables inside
  • 19. 2. Design Step 1 New BT Fibre in duct New Virgin Fibre in duct Traffic Scotland Fibre Electrical Mains Electrical Mains Redundant BT Copper Street Lighting Cable New Traffic Scotland CCTV Traffic Scotland Duct Live Electrical Cable Live Electrical Cable Step 2 Step 4 Step 5 New BT Fibre in ducts New Virgin Fibre in duct Traffic Scotland Fibre New Street Lighting Cable New Traffic Scotland CCTV New Auxiliary Cables Electrical Mains Electrical Mains Redundant BT Copper Street Lighting Cable New Traffic Scotland CCTV Traffic Scotland Duct Live Electrical Cable Live Electrical Cable New Electrical Mains Metered New Electrical Mains Unmetered New Street Lighting Cable New Auxiliary Cables Proposed Steps for removal of steel ducts. New BT Fibre in duct New Virgin Fibre in duct New BT Fibre in ducts New Virgin Fibre in duct Traffic Scotland Fibre Auxiliary Cables Move required cable out of harms way Cut steel duct into small pieces and remove redundent ducts and cables from bridge Install cable ladder in place of the first 3no steel ducts Cut remaining steel ducts and redundent cables into small pieces and remove from bridge structure. Install new cable ladder into space of steel ducts. Move all cables and ducts to first cable ladder Auxiliary Cables New Traffic Scotland CCTV New Electrical Mains Metered New Electrical Mains Unmetered
  • 20. 2. Design Specimen design for the new bracket for the LED replacement aircraft navigation lanterns
  • 21. 2. Construction For the 95mm2 cable we had to use 200mm⌀ ducts. Purple street lighting duct is 100mm⌀.
  • 22. 2. Construction High mast lowered and cut into 4 pieces to be taken from site to licensed recycling plant
  • 23. 2. Construction All the bolts in the bridge deck were pull tested and after the new column was fitted sealed with grout to water proof the column base.
  • 24. 2. Construction New LED Lantern fitted with CMS nodes , show the uniformity achieved on the approach road and in the compound.
  • 25. 2. Construction The uniformity achieved on the approach road north of the bridge using high mast units.
  • 26. 2. Construction New LED Zone 2 lighting inside the bridge deck
  • 27. 2. Construction The new Zone 2 DB and new cable ladders with electrical cable and coms cable separated.
  • 28. 3. What was achieved. 1. Environmental impact. 1. The new lighting installation has reduced the energy by 70% energy (£50K per year) 2. Over £3K reduction in carbon tax per year. 3. 20% material was recycled dusring the course of the project. 2. The contract was completed on budget and on time.
  • 29. 4. Thanks to 1. Transport Scotland Bridges section 2. Scotland Transerv for managing the contract. 3. Lightways Contracting
  • 31. Finished!Finished!Finished!Finished! Louis Fourie CEng MIET MILP Clayton Fourie Consultancy Ltd Tel: 07906664770 Email: louis@claytonfourie.com