SlideShare a Scribd company logo
1 of 80
Chapter 5
Construction Project
Management body of
knowledge
Construction Project Management body of
knowledge
Project process management
Project scope management
Project quality management
Project stake holder management
Project communication management
Risk and Uncertainty management
2
• Project management is the application of knowledge, skills,
tools, and techniques to project activities to meet the project
requirements.
• This application of knowledge requires the effective
management of the project processes.
• A process is a set of interrelated actions and activities
performed to create a pre-specified product, service, or
result.
•Each process is characterized by its inputs, the tools and
techniques that can be applied, and the resulting outputs.
3
5.1 Project Process Management
•Project Life Cycle
• A project life cycle is the series of phases that a project passes
through from its initiation to its closure.
• The phases are generally sequential, and their names and numbers
are determined by the management, the nature of the project itself,
and its area of application.
• Phases are generally time bounded, with a start and ending or
control point.
4
5.1 Project Process Management
•Project Life Cycle…
•The project life cycle can be determined or shaped by the
unique aspects of the organization, industry, or technology
employed.
•The life cycle provides the basic framework for managing
the project, regardless of the specific work involved.
5
5.1 Project Process Management
•Project Life Cycle…
6
5.1 Project Process Management
Generic Project
Life Cycle
Structure
• Some literatures presented project life cycle into four to five
phases with nearly similar functions under their classification.
Project Mgmt Organized by: Belachew Asteray (PhD) 7
5.1 Project Process Management…
Items Project Management Processes Authors
1 Identify a need, Develop a proposed Solution, Perform the Project, and
Terminate the project
Gido & Clements, 1999
2 Initiating, Planning, Executing, Controlling, and Closing PMIBoK, 2000
3 Feasibility or Conceptual, Definition, Execution and Close out Laufer, 1995
4 Conceptualization, Planning, Execution and Termination Meredith & Mantel, 2000
5 Early or Front - End Assessment, Implementation Knut Samset, 2001
6 Concept (Conceive), Planning (Design, Plan and Allocate), Execute,
Termination (Deliver, Review and Support).
Chapman & Ward, 1997:
Eight stages
7 Planning, Appraisal and Design; Selection, Approval & Activation;
Operation, Control and Hand over; and Evaluation and Refinement.
Goodman, 1984: 11 stages
• Construction Management Process System
• The construction process is defined as all processes which guides
towards the planned construction works.
• This means that the construction process as a concept covers sub
processes having different characteristics.
• These sub processes can be grouped under three major
classifications: Core processes, Administrative processes and Public
regulatory processes. These processes are termed Project
Processes.
8
5.1 Project Process Management…
Project Management Process Vs Life Cycle
9
Core
Processes
Concept
Definition
Concept
Development
Design of buildings,
Roads, etc & Physical
construction works
Maintenance
Period and
Defect Remedies
Administrative
Processes
Concept Evaluation
Project Approval
Budget Allocation
Monitoring,
Procurement and Other
Processes
Acceptance /
Hand Over
Public
Regulatory
Processes
Right-of-way (if necessary)
and
Regulatory Permits
Tender award
and
Changes and Variation
Final Approval
and
User Permit
Project
Closing
Project
Implementation
Project
Definition
Project
Development
Project cycle
Project cycle
Project process
5.1 Project Process Management…
10
5.1 Project Process Management…
Modified Project Management Process (Source: Wubishet, 2004)
Project Completion
Project Implementation
Project Definition
Project Formulation
& Basic Planning
Project
Design
Project
Construction
Project-Product
Transfer
Administrative Monitoring & Planning
Contract Administration
C
O
R
E
S
U
P
P
O
R
T
•The Project management process includes two separate
elements.
11
5.1 Project Process Management…
• The first includes two processes which
were meant for one of the elements that
PMBoK used to define a project.
• A project is temporary and hence has a
definite beginning and a definite end.
(Initiating and closing)
• The second one is built upon the bases of
the three well known traditional
management functions.
• Planning,
• Executing and
• Controlling.
• At the same time these processes are
made cyclic depending on the degree of
uniqueness.
 Scope: thesumoftheproducts,services,andresultstobe providedbyaproject
E.g.buildingforresidential,school,factory,forservice lifeof‘x’years
 Scope management–theprocess of identifying anddoing onlytheworksthatarenecessary
tocompleteaproject successfully. Avoidsdoing unapproved extrawork(scope creep)and
unnecessaryworks including“gold plating”,i.e., doingextra seeking for good name and/or
hiddenagenda
 Forcontractors scopehas to consider the whole activities: thedeliverables and the enablers
14
ConstructionProjectScope
5.2 Project Scope Management
 Approach inplanning Scope
 Creating(WorkBreakdownStructure(WBS):break the worksinto desired lowerlevels.
It isdividing thegeneral scope into type and hierarchy of 3 to 5 levels
 The hierarchical breaking down of the works may be done based on size,complexity,
proximity or/and phase of completion required by the specific contract
 WBS mayincludedividing the project work into areas, sectors or tasks, groups or a
combination of these whichmayfurther be divided into sub-project,functions (tasks),
work packages,activities and operations or processes
15
Planning ConstructionProjectScope
🞑 Source are Documents and Site investigation
 Document Study
 Using project’s plans (drawings), BoQs, specifications, contract conditions; relevant codes,
legal & regulatory documents;social, businessand natural environments; material sources.
 Site Investigation
 Identifying local inputs , utility lines, safety and health issues; site office location, social
(culture) and environmental factors; statusof work site (right-of-way)
 Competency required: Knowledge of the work, prior practice on similar work, experience in
decomposing works with respect to resource allocation, quality and cost control and discipline/desire
 The project manager (project lead team) needs to knowthe full picture of the worksincluding the
environment where it is to be implemented
16
 WBS preparation benefits
🞑 WBS helps not to miss work items of the scope and to:
Identify risks and address themproperly
Keep stakeholders informed and hence get their cooperation
Get commitment and focus of teams involved
Ensure better control
Control the impact of desired changes (control for scope creep and gold
plating)
RulesinperformingWBS
T
eam participation and systematic approach to splitting
Only the work required to make the project deliverable are the focus
Function or TASK group
1
EW
EXCAVN
LAYOUT EXCAVATION LEVE
LING
FILL CARTAWAY
MASONRY CONCR
E
TE
FWK R
E
-BAR CONCR
E
T
E
FINISHES E
L
E
C & SANT
Level -1
Level -2
L-3
Sample outcome of WBS
• In the project context, the term scope can refer to:
• Product scope: The features and functions that characterize a
product, service, or result
• Project scope: The work performed to deliver a product, service,
or result with the specified features and functions.
• Project Scope Management includes the processes required to
ensure that the project includes all the work required to complete
the project successfully.
• Managing the project scope is primarily concerned with defining
and controlling what is and is not included in the project.
17
Project Scope Management from PMBOK
• Project Scope Management processes include the following:
1. Plan Scope Management: The process of creating a scope
management plan documents how the project scope will be defined,
validated, and controlled.
2. Collect Requirements: The process of determining, documenting, and
managing stakeholder needs and requirements to meet project
objectives.
3. Define Scope: The process of developing a detailed description of the
project and product.
4. Create work breakdown structure (WBS): The process of
subdividing project deliverables and project work into smaller, more
manageable components.
5. Validate Scope: The process of formalizing acceptance of the
completed project deliverables.
6. Control Scope: The process of monitoring the status of the project and
product scope and managing changes to the scope baseline.
18
1. Plan Scope Management
• The key benefit of this process is that it provides guidance and
direction on how scope will be managed throughout the project.
19
2. Collect Requirements
• The key benefit of this process is that it provides the basis
for defining and managing the project scope including
product scope.
20
3. Define Scope
• The key benefit of this process is that it describes the product,
service, or result boundaries by defining which of the requirements
collected will be included in and excluded from the project scope.
21
4. Create Work Breakdown Structure (WBS)
• The key benefit of this process is that it provides a structured vision
of what has to be delivered.
• The WBS is a hierarchical decomposition of the total scope of work
to be carried out by the project team to accomplish the project
objectives and create the required deliverables.
22
5. Validate Scope
• The key benefit of this process is that it brings objectivity to the
acceptance process and increases the chance of final product,
service, or result acceptance by validating each deliverable.
23
6. Control Scope
• The key benefit of this process is that it allows the scope baseline to
be maintained throughout the project.
24
 Quality: isdefined asfitness for purpose specified by a designer/customer.
 May include desires for safety, functionality, aesthetics, reliability,
durability/service life, maintainability of a product .
 Quality system refers to established organized routines and procedures which
comprise elements set as standard.
 Quality System Pillars: quality assurance (used to verify) &/or which may be
set by the management, customer regulatory body; and quality control used to
identify and eliminate non-conformance
21
5.3 Project Quality Management
 Quality Assurance: is the application of planned, systematic, quality activities to
ensurethat theproject will employall processesneededto meetrequirement
 It is part of quality management focused on providing confidence that quality
requirementswill be fulfilled’ ISO9000
 The aim is to prevent defects focus on the process used to make the product.
It is a proactive quality process
 Improve development and test processes so that defect do not arise
 Preventive process
22
 Quality Control
 Control is concerned with comparing the work results with the
requirement to ensure that the result is acceptable
 Partofqualitymanagementfocusedonfulfillingquality requirements’ISO
 Performing QC involves monitoring specific project resultsto determine
the cause of unsatisfactory results
 QCObjective:to ascertain thestandard of a product that can meet the
requirement of the customer are produced
 Identifydefectsafteraproductisdevelopedandbeforeitisreleased
 Itisreactivequalityprocess,finds/detectdefectsaftertesting
 Correctiveprocess
23
 Inspection:
 Determining the acceptability of an output/product of a process at a
givenstage.
 It includes measuring, examining or testing and comparing whether the
resultsconformtotherelevant requirements.
 PlanningInspectionincludes:wheretoinspect,what resourcestouseand
extentofinspectionaredetermined.
 Hence,itisapplyingtoolsandtechniquesfortheworks andmanagement
objectivestoidentifylevelofconformity
24
29
Construction Quality Control
Who
Quality
Control
(QC)
Usually the contractor (or a third party) is responsible for
performing Quality Control (QC) making sure that the standards are
meet for production
Quality
Assurance
(QA)
 Usually the government or outside third party is responsible for performing
Quality Assurance (QA).
 QA is spot checking of contract compliance, test results, and ultimately
making sure that the quality control process is working
 A government organizations/clients or any executing agencies will have very
clear guidance on what is required per contract as far as the QA/QC is
concerned.
 Policy and Guidelines
 Standards and Specifications
 Rules and Regulations
 Terms and conditions of the contract
•Quality Management is an important project management
function.
•It is one of the critical attributes of project success, with
the others being cost, time and safety.
•Quality Management involves :
• Setting Quality Standards to achieve both technical and
managerial competence,
• Scheduling inspections,
• Managing any required rework,
• Documentation.
30
Construction Quality management from PMBOK
The basic approach to project quality management is intended to
be compatible with International Organization for Standardization
(ISO) quality standards.
In the context of achieving ISO compatibility, modern quality
management approaches seek to minimize variation and to
deliver results that meet defined requirements.
Project Quality Management processes include:
1. Plan Quality Management
2. Perform Quality Assurance
3. Control Quality
31
1. Plan Quality Management
• Plan Quality Management is the process of
•identifying quality requirements and/or standards for
the project and its deliverables, and
•documenting how the project will demonstrate
compliance with relevant quality requirements and/or
standards.
• The key benefit of this process is that it provides guidance
and direction on how quality will be managed and
validated throughout the project.
32
1. Plan Quality Management…
33
2. Perform Quality Assurance
• It is the process of auditing the quality requirements and the
results from quality control measurements to ensure that
appropriate quality standards and operational definitions are used.
• The key benefit of this process is that it facilitates the
improvement of quality processes.
Project Mgmt Organized by: Belachew Asteray (PhD) 34
3. Control Quality
•Control Quality is the process of monitoring and
recording results of executing the quality activities to
assess performance and recommend necessary changes.
•The key benefits of this process include:
(1) identifying the causes of poor process or product quality
and recommending and/or taking action to eliminate them; and
(2) validating that project deliverables and work meet the
requirements specified by key stakeholders necessary for
final acceptance.
35
3. Control Quality…
36
•Stakeholders can be defined as either individuals or units
or organization itself for which they claim a stake in the
project such that they get benefit from or affected by the
whole processes of the project and its deliverables.
37
5.4 Project Stakeholder Management
Who are stakeholders of CI?
Project stakeholders or participants or parties:
• Are individuals and organizations who are actively involved in
project execution or successful project completion.
• Are those who have stakes or vested interest in construction
project
• Are those who has a telling effect on a project
38
5.4 Project Stakeholder Management…
The practice of planning, designing, constructing, and operating a facility is a collective
effort of different groups of professionals.
Depending on the size, complexity, and purpose of a particular construction project, the
project team may include:
• A Client or an Owner or Employer: Individuals, government, real estate developers etc.
• Financial institutions or other investors that provide the funding
• Local planning and code authorities
39
5.4 Project Stakeholder Management…
• Consultants or Licensed architects and engineers who provide design work and prepare
construction documents
• Contractors who provide construction services and install systems
• Marketing or leasing agents
• Facility managers who are responsible for operating the facility.
40
5.4 Project Stakeholder Management…
41
Stakeholder Ecosystem
5.4 Project Stakeholder Management…
42
Employer(s)
Financier(s)
Contractor(s)
Consultant(s)
Regulatory Bodies
Stakeholders'
in Public
Construction
Projects
The Construction
Industry
Project Organization(s)
Government(s)
Supplier(s)
Sub-contractor(s)
Sub-Consultant(s)
The Public
Financial Institutions
Other Interest Groups
Beneficiary(s)
Other sectors
Internal Stakeholders External Stakeholders
Stakeholders in Public Construction Projects
5.4 Project Stakeholder Management…
A. Client
• The client is the initiator and owner of the project.
• It is the most important party who is active from inception to completion
and event to post-occupancy maintenance.
43
Idea
Land
client
Capital
5.4 Project Stakeholder Management…
• Clients may be classified as Public sector clients and private sector clients.
• Public sector clients
 Central Government Offices (Ministries)
 Local Authorities (Regional or Town)
 Public Corporations
• Private sector clients
 These are private individuals & private companies
44
5.4 Project Stakeholder Management…
B. Consultant
• The consultant transfers the wish of the owner into realizable form and
makes the study, design and possibly the supervision.
• The main role of the consultant is to interpret the client’s project
requirement into a specific design.
C. Contractor
• The contractor is the one who performs the work
• These are groups established mainly as commercial companies, that contract
to construct development projects.
45
5.4 Project Stakeholder Management…
D. Public Sector Agencies
• Statutory Authorities
• _These bodies offer technical advice during design and construction in their respective
areas.
• E.g. ERA, EWWC, Fire Authority - requires meeting their specific requirements. Thus
early information to these authorities is required.
• Municipalities and Government Authorities
• These bodies offer the basic Land permit and building permit.
46
5.4 Project Stakeholder Management…
E. Insurance Companies: Contractors are required to provide bid bonds as a
condition of being allowed to bid, and then they must provide insurance too.
F. Banks: Banks provide the working capital contractors need to build the
project.
G. Suppliers: The quality of a construction project is very dependent on the
quality of the suppliers used by individual contractors.
H. Trade (labor) unions: are unions of the working class that look after unfair
treatment of workers (like payment issues, firing issues) as well as issues
related to occupational health and safety.
47
5.4 Project Stakeholder Management…
• The activities and roles of each player varies from project to project and
ownership.
• But, in general, the following figure shows the roles of each participant at
different stages of construction.
48
General Activity relationships among the Client, Consultant &
the contractor
5.4 Project Stakeholder Management…
49
5.4 Project Stakeholder Management…
• Project Stakeholder Management includes the processes required
• to identify the people, groups, or organizations that could impact or
be impacted by the project,
• to analyze stakeholder expectations and their impact on the project,
and
• to develop appropriate management strategies for effectively
engaging stakeholders in project decisions and execution.
• Stakeholder management focuses on continuous communication
with stakeholders to understand their needs and expectations,
addressing issues as they occur, managing conflicting interests and
fostering appropriate stakeholder engagement in project decisions
and activities.
50
5.4 Project Stakeholder Management…
•Stakeholder satisfaction should be managed as a key project
objective.
•Every project will have stakeholders who are impacted by
or can impact the project in a positive or negative way.
•The ability of the project manager to correctly identify and
manage these stakeholders in an appropriate manner can
mean the difference between success and failure.
51
5.4 Project Stakeholder Management…
•While some stakeholders may have a limited ability
to influence the project, others may have
significant influence on the project and its expected
outcomes.
•Project Stakeholder Management processes include :
1. Identify Stakeholder
2. Plan Stakeholder
3. Manage Stakeholder
4. Control Stakeholder
52
5.4 Project Stakeholder Management…
1. Identify Stakeholders
• Identify Stakeholders is the process of identifying the people, groups, or
organizations that could impact or be impacted by a decision, activity, or
outcome of the project, analyzing and documenting relevant information
regarding their interests, involvement, interdependencies, influence, and
potential impact on project success.
• The key benefit of this process is that it allows the project manager to
identify the appropriate focus for each stakeholder or group of stakeholders.
53
2. Plan Stakeholder Management
• Plan Stakeholder Management is the process of developing
appropriate management strategies to effectively engage
stakeholders throughout the project life cycle, based on the analysis
of their needs, interests, and potential impact on project success.
• The key benefit of this process is that it provides a clear, actionable plan to
interact with project stakeholders to support the project’s interests.
54
3. Manage Stakeholder Engagement
• It is the process of communicating and working with
stakeholders
•to meet their needs/expectations,
•address issues as they occur, and
•foster appropriate stakeholder engagement in project
activities throughout the project life cycle.
• The key benefit of this process is that it allows the project
manager to increase support and minimize resistance
from stakeholders, significantly increasing the chances to
achieve project success
55
56
Managing Project Stakeholders
4. Control Stakeholder Engagement
• It is the process of monitoring overall project stakeholder relationships and
adjusting strategies and plans for engaging stakeholders.
• The key benefit of this process is that it will maintain or increase the
efficiency and effectiveness of stakeholder engagement activities as the
project evolves and its environment changes.
57
• Project Communications Management includes the processes
that are required to ensure timely and appropriate
planning, collection, creation, distribution, storage, retrieval,
management, control, monitoring, and the ultimate
disposition of project information.
• Project managers spend most of their time communicating
with team members and other project stakeholders,
whether they are internal (at all organizational levels) or
external to the organization.
58
5.5 Project Communications Management
•The communication activities involved in these processes
may often have many potential dimensions that need to be
considered, including, but not limited to:
• Internal (within the project) and external (customer, vendors,
other projects, organizations, the public);
• Formal (reports, minutes, briefings) and informal (emails,
memos, discussions);
• Vertical (up and down the organization) and horizontal (with
peers);
• Official (newsletters, annual report) and unofficial (off the
record communications); and
• Written and oral, and verbal (voice inflections) and nonverbal
(body language).
59
5.5 Project Communications Management…
• Most communication skills are common for both general
management and project management, such as, but not limited to:
• Listening actively and effectively;
• Questioning and probing ideas and situations to ensure better understanding;
• Educating to increase team’s knowledge so that they can be more effective;
• Fact-finding to identify or confirm information;
• Setting and managing expectations;
• Persuading a person, a team, or an organization to perform an action;
• Motivating to provide encouragement or reassurance;
• Coaching to improve performance and achieve desired results;
• Negotiating to achieve mutually acceptable agreements between parties;
• Resolving conflict to prevent disruptive impacts; and
• Summarizing, recapping, and identifying the next steps.
60
5.5 Project Communications Management…
•Effective communication creates a bridge between diverse
stakeholders who may have different cultural and
organizational backgrounds, different levels of expertise,
and different perspectives and interests, which impact or
have an influence upon the project execution or outcome.
•Project Communications Management processes include:
1. Plan Communications
2. Manage Communications
3. Control Communications
61
5.5 Project Communications Management…
1. Plan Communications Management
• It is the process of developing an appropriate approach and plan for
project communications based on stakeholder’s information needs and
requirements, and available organizational assets.
• The key benefit of this process is that it identifies and documents the
approach to communicate most effectively and efficiently with
stakeholders.
62
5.5 Project Communications Management…
2. Manage Communications
• It is the process of creating, collecting, distributing, storing,
retrieving, and the ultimate disposition of project information
in accordance to the communications management plan.
• The key benefit of this process is that it enables an efficient and
effective communications flow between project stakeholders.
63
5.5 Project Communications Management…
3. Control Communications
• Control Communications is the process of monitoring and controlling
communications throughout the entire project life cycle to ensure the
information needs of the project stakeholders are met.
• The key benefit of this process is that it ensures an optimal information
flow among all communication participants, at any moment in time.
64
5.5 Project Communications Management…
 Risk: possibility of meeting danger or suffering, harm, loss
 Uncertainty inherent in plans and the possibility of something
happening that can affect the prospects of achieving project goals
 Unlike the usual dictionary definition of “risk” which refers only to
undesirable events interpretation of risk include both downside and
upside variations in the values involved
2
5.6 Risk and Uncertainty Management
 Planning for Project Risk Management
🞑Planning risk involves paying attention when we don’t want project fail. Aside “acts of
God” most projects fail due to:
 Actually impossible—lies outside of technical capability available at the time
 Over constrained— possible but unrealistic time and resource
 Not competently managed –have the time and resourcesbut poorly managed . This
can succeed through giving adequate attention to project and risk planning
4
Planning Risk Management
Planning for Project Risk Management
🞑 Overall project planning process is essential since without this it is not possible to
know what may go right or wrong and manage proactively.
 Planninghelpsto discoverpossiblefailure areas and modes.
 At project level other activities may take priority than planning for risk; but without
planning there can be little risk management
5
7
Hazard
Should not be ignored
Risk management Too
high to be covered
with contingency
Not serious
Trivial
Not serious
Expect
Impact
Probability
Low High
Low
High
Realisticand honest estimate results from the parties’ trust and cooperation
Planning Risk Management
8
Planning Risk Management
Step1: Analyze the project to identify sourcesof
risks
Step 2: RiskAssessment(qualitative & Quantitative)
•Probability
•Severity
•controllability
Step 4: R
esponse Control
•Risk R
esponse Control
•Implement strategy
•Monitor and Adjust
•Apply change management
Step 3: R
esponse development
•Develop strategy
•Develop contingency plan manage
Response
developm
ent plan
Known
risks
RiskAssess
ment
Response
control
9
 Performing Quantitative Analysis of the Risks
🞑ProbabilityAnalysis: take the highranking risksfrom the qualitative analysis and
quantify their probabilities using
 Past data analysis using statistical distribution methods(objective)
 Delphi method: gathering opinions of individuals secretly till their subjective
estimations approaches to single figure
 Expert group discussion (this is also subjective)
 Require continuous probability distribution suchasnormal or triangular
Planning Risk Management
10
🞑Prepare Response Plan to the Risks
The options of managing risks are to treat the Cause or Effect of a risk event
 Avoid
 Sharing
 Transferring to subcontractor, supplier, insurance
 Retain : risks that can’t be shared or transferred has to be owned. Better ability of
control isprevention, lesser cost, ability to manage external risks
 Mitigation (minimizing impact or occurrence)
•Uncertainties and Changes in undertaking a public
construction project come from many sources and often
involve many participants and resources.
•The perceptions and attitude of practitioners towards
uncertainties and changes matters a lot in effective
performance determinations.
72
Uncertainty and Risk Management from PMBOK
•Project Risk Management processes include:
1. Plan Risk Management
2. Identify Risks
3. Perform Qualitative Risk Analysis
4. Perform Quantitative Risk Analysis
5. Plan Risk Responses
6. Control Risks
73
1. Plan Risk Management
•Plan Risk Management is the process of defining how to
conduct risk management activities for a project.
•The key benefit of this process is it ensures that the
degree, type, and visibility of risk management are
commensurate with both the risks and the importance
of the project to the organization.
•The risk management plan is vital to communicate with
and obtain agreement and support from all stakeholders
to ensure the risk management process is supported and
performed effectively over the project life cycle.
74
2. Identify Risks
• Identify Risks is the process of determining which risks may
affect the project and documenting their characteristics.
• The key benefit of this process is the documentation of existing risks and the
knowledge and ability it provides to the project team to anticipate events.
75
3. Perform Qualitative Risk Analysis
• Perform Qualitative Risk Analysis is the process of prioritizing risks for
further analysis or action by assessing and combining their probability
of occurrence and impact.
• The key benefit of this process is that it enables project managers to reduce
the level of uncertainty and to focus on high-priority risks.
76
4. Perform Quantitative Risk Analysis
• Perform Quantitative Risk Analysis is the process of numerically analyzing
the effect of identified risks on overall project objectives.
• The key benefit of this process is that it produces quantitative risk
information to support decision making in order to reduce project
uncertainty.
77
5. Plan Risk Responses
• Plan Risk Responses is the process of developing options and actions to
enhance opportunities and to reduce threats to project objectives.
• The key benefit of this process is that it addresses the risks by their
priority, inserting resources and activities into the budget, schedule and
project management plan as needed.
78
6. Control Risks
• Control Risks is the process of implementing risk response plans,
tracking identified risks, monitoring residual risks, identifying new
risks, and evaluating risk process effectiveness throughout the project.
• The key benefit of this process is that it improves efficiency of the risk
approach throughout the project life cycle to continuously optimize risk
responses.
79
Thank you!
80

More Related Content

What's hot

Project integration management
Project  integration managementProject  integration management
Project integration managementdeep sharma
 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Jeffrey Cheah
 
Software Project Management (lecture 2)
Software Project Management (lecture 2)Software Project Management (lecture 2)
Software Project Management (lecture 2)Syed Muhammad Hammad
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE S. Sathishkumar
 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Jeffrey Cheah
 
Project Management Professional (PMI) Study Guide
Project Management Professional (PMI) Study GuideProject Management Professional (PMI) Study Guide
Project Management Professional (PMI) Study Guidemsrakesh
 
Project management professional
Project management professionalProject management professional
Project management professionalRaynaITSTEP
 
CMMI v 1.2 Basics
CMMI v 1.2 BasicsCMMI v 1.2 Basics
CMMI v 1.2 BasicsQAI
 
Project scope management and planning
Project scope management and planningProject scope management and planning
Project scope management and planningAbubeker mukemil
 
Project Management
Project ManagementProject Management
Project Managementguest4408ddc
 
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process GroupsVanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groupsvanessahartsfield
 

What's hot (19)

Managing & Supervising Projects, Consultants & Contractors
Managing & Supervising Projects, Consultants & ContractorsManaging & Supervising Projects, Consultants & Contractors
Managing & Supervising Projects, Consultants & Contractors
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
Project lifecycle in IT industry
Project lifecycle in IT industryProject lifecycle in IT industry
Project lifecycle in IT industry
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)
 
Software Project Management (lecture 2)
Software Project Management (lecture 2)Software Project Management (lecture 2)
Software Project Management (lecture 2)
 
Scope definition
Scope definitionScope definition
Scope definition
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
Project Management Professional (PMI) Study Guide
Project Management Professional (PMI) Study GuideProject Management Professional (PMI) Study Guide
Project Management Professional (PMI) Study Guide
 
Project management professional
Project management professionalProject management professional
Project management professional
 
CMMI v 1.2 Basics
CMMI v 1.2 BasicsCMMI v 1.2 Basics
CMMI v 1.2 Basics
 
Project scope management and planning
Project scope management and planningProject scope management and planning
Project scope management and planning
 
PMP PMBOK5 Ch4 integration management
PMP PMBOK5 Ch4 integration managementPMP PMBOK5 Ch4 integration management
PMP PMBOK5 Ch4 integration management
 
Project Management
Project ManagementProject Management
Project Management
 
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process GroupsVanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
 
1 project management framework
1  project management framework1  project management framework
1 project management framework
 

Similar to Chapter 5- Project mgt.pptx

3 scope Management
3 scope Management 3 scope Management
3 scope Management Qussay Karam
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training programParamjit Arora
 
03 project management processes for a project
03  project management processes for a project03  project management processes for a project
03 project management processes for a projectAla Ibrahim
 
Project scope management
Project scope managementProject scope management
Project scope managementANOOP S NAIR
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project ManagementReetesh Gupta
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxkiranroy6777
 
Scope management based on project management.
Scope management  based on project management.Scope management  based on project management.
Scope management based on project management.Niloy Biswas
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project managementprakashnachnani
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6Amit Gupta
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTSAJJAD KHUDHUR ABBAS
 
Project management.docx
Project management.docxProject management.docx
Project management.docxHumaRazi1
 
Topic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdfTopic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdfHuyNguyen657394
 
2. Project Scope Management.ppt
2. Project Scope Management.ppt2. Project Scope Management.ppt
2. Project Scope Management.pptMohamadAGhareb
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsJacobs Engineering
 
Project Management Process
Project Management ProcessProject Management Process
Project Management ProcessSaqib Raza
 
Atoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfAtoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfLe Duong
 

Similar to Chapter 5- Project mgt.pptx (20)

PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
 
03 project management processes for a project
03  project management processes for a project03  project management processes for a project
03 project management processes for a project
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
 
Scope management based on project management.
Scope management  based on project management.Scope management  based on project management.
Scope management based on project management.
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project management
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXT
 
Project management.docx
Project management.docxProject management.docx
Project management.docx
 
Topic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdfTopic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdf
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
2. Project Scope Management.ppt
2. Project Scope Management.ppt2. Project Scope Management.ppt
2. Project Scope Management.ppt
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
Project Management Process
Project Management ProcessProject Management Process
Project Management Process
 
Atoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfAtoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdf
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 

Chapter 5- Project mgt.pptx

  • 2. Construction Project Management body of knowledge Project process management Project scope management Project quality management Project stake holder management Project communication management Risk and Uncertainty management 2
  • 3. • Project management is the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements. • This application of knowledge requires the effective management of the project processes. • A process is a set of interrelated actions and activities performed to create a pre-specified product, service, or result. •Each process is characterized by its inputs, the tools and techniques that can be applied, and the resulting outputs. 3 5.1 Project Process Management
  • 4. •Project Life Cycle • A project life cycle is the series of phases that a project passes through from its initiation to its closure. • The phases are generally sequential, and their names and numbers are determined by the management, the nature of the project itself, and its area of application. • Phases are generally time bounded, with a start and ending or control point. 4 5.1 Project Process Management
  • 5. •Project Life Cycle… •The project life cycle can be determined or shaped by the unique aspects of the organization, industry, or technology employed. •The life cycle provides the basic framework for managing the project, regardless of the specific work involved. 5 5.1 Project Process Management
  • 6. •Project Life Cycle… 6 5.1 Project Process Management Generic Project Life Cycle Structure
  • 7. • Some literatures presented project life cycle into four to five phases with nearly similar functions under their classification. Project Mgmt Organized by: Belachew Asteray (PhD) 7 5.1 Project Process Management… Items Project Management Processes Authors 1 Identify a need, Develop a proposed Solution, Perform the Project, and Terminate the project Gido & Clements, 1999 2 Initiating, Planning, Executing, Controlling, and Closing PMIBoK, 2000 3 Feasibility or Conceptual, Definition, Execution and Close out Laufer, 1995 4 Conceptualization, Planning, Execution and Termination Meredith & Mantel, 2000 5 Early or Front - End Assessment, Implementation Knut Samset, 2001 6 Concept (Conceive), Planning (Design, Plan and Allocate), Execute, Termination (Deliver, Review and Support). Chapman & Ward, 1997: Eight stages 7 Planning, Appraisal and Design; Selection, Approval & Activation; Operation, Control and Hand over; and Evaluation and Refinement. Goodman, 1984: 11 stages
  • 8. • Construction Management Process System • The construction process is defined as all processes which guides towards the planned construction works. • This means that the construction process as a concept covers sub processes having different characteristics. • These sub processes can be grouped under three major classifications: Core processes, Administrative processes and Public regulatory processes. These processes are termed Project Processes. 8 5.1 Project Process Management…
  • 9. Project Management Process Vs Life Cycle 9 Core Processes Concept Definition Concept Development Design of buildings, Roads, etc & Physical construction works Maintenance Period and Defect Remedies Administrative Processes Concept Evaluation Project Approval Budget Allocation Monitoring, Procurement and Other Processes Acceptance / Hand Over Public Regulatory Processes Right-of-way (if necessary) and Regulatory Permits Tender award and Changes and Variation Final Approval and User Permit Project Closing Project Implementation Project Definition Project Development Project cycle Project cycle Project process 5.1 Project Process Management…
  • 10. 10 5.1 Project Process Management… Modified Project Management Process (Source: Wubishet, 2004) Project Completion Project Implementation Project Definition Project Formulation & Basic Planning Project Design Project Construction Project-Product Transfer Administrative Monitoring & Planning Contract Administration C O R E S U P P O R T
  • 11. •The Project management process includes two separate elements. 11 5.1 Project Process Management… • The first includes two processes which were meant for one of the elements that PMBoK used to define a project. • A project is temporary and hence has a definite beginning and a definite end. (Initiating and closing) • The second one is built upon the bases of the three well known traditional management functions. • Planning, • Executing and • Controlling. • At the same time these processes are made cyclic depending on the degree of uniqueness.
  • 12.  Scope: thesumoftheproducts,services,andresultstobe providedbyaproject E.g.buildingforresidential,school,factory,forservice lifeof‘x’years  Scope management–theprocess of identifying anddoing onlytheworksthatarenecessary tocompleteaproject successfully. Avoidsdoing unapproved extrawork(scope creep)and unnecessaryworks including“gold plating”,i.e., doingextra seeking for good name and/or hiddenagenda  Forcontractors scopehas to consider the whole activities: thedeliverables and the enablers 14 ConstructionProjectScope 5.2 Project Scope Management
  • 13.  Approach inplanning Scope  Creating(WorkBreakdownStructure(WBS):break the worksinto desired lowerlevels. It isdividing thegeneral scope into type and hierarchy of 3 to 5 levels  The hierarchical breaking down of the works may be done based on size,complexity, proximity or/and phase of completion required by the specific contract  WBS mayincludedividing the project work into areas, sectors or tasks, groups or a combination of these whichmayfurther be divided into sub-project,functions (tasks), work packages,activities and operations or processes 15 Planning ConstructionProjectScope
  • 14. 🞑 Source are Documents and Site investigation  Document Study  Using project’s plans (drawings), BoQs, specifications, contract conditions; relevant codes, legal & regulatory documents;social, businessand natural environments; material sources.  Site Investigation  Identifying local inputs , utility lines, safety and health issues; site office location, social (culture) and environmental factors; statusof work site (right-of-way)  Competency required: Knowledge of the work, prior practice on similar work, experience in decomposing works with respect to resource allocation, quality and cost control and discipline/desire  The project manager (project lead team) needs to knowthe full picture of the worksincluding the environment where it is to be implemented 16
  • 15.  WBS preparation benefits 🞑 WBS helps not to miss work items of the scope and to: Identify risks and address themproperly Keep stakeholders informed and hence get their cooperation Get commitment and focus of teams involved Ensure better control Control the impact of desired changes (control for scope creep and gold plating)
  • 16. RulesinperformingWBS T eam participation and systematic approach to splitting Only the work required to make the project deliverable are the focus Function or TASK group 1 EW EXCAVN LAYOUT EXCAVATION LEVE LING FILL CARTAWAY MASONRY CONCR E TE FWK R E -BAR CONCR E T E FINISHES E L E C & SANT Level -1 Level -2 L-3 Sample outcome of WBS
  • 17. • In the project context, the term scope can refer to: • Product scope: The features and functions that characterize a product, service, or result • Project scope: The work performed to deliver a product, service, or result with the specified features and functions. • Project Scope Management includes the processes required to ensure that the project includes all the work required to complete the project successfully. • Managing the project scope is primarily concerned with defining and controlling what is and is not included in the project. 17 Project Scope Management from PMBOK
  • 18. • Project Scope Management processes include the following: 1. Plan Scope Management: The process of creating a scope management plan documents how the project scope will be defined, validated, and controlled. 2. Collect Requirements: The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. 3. Define Scope: The process of developing a detailed description of the project and product. 4. Create work breakdown structure (WBS): The process of subdividing project deliverables and project work into smaller, more manageable components. 5. Validate Scope: The process of formalizing acceptance of the completed project deliverables. 6. Control Scope: The process of monitoring the status of the project and product scope and managing changes to the scope baseline. 18
  • 19. 1. Plan Scope Management • The key benefit of this process is that it provides guidance and direction on how scope will be managed throughout the project. 19
  • 20. 2. Collect Requirements • The key benefit of this process is that it provides the basis for defining and managing the project scope including product scope. 20
  • 21. 3. Define Scope • The key benefit of this process is that it describes the product, service, or result boundaries by defining which of the requirements collected will be included in and excluded from the project scope. 21
  • 22. 4. Create Work Breakdown Structure (WBS) • The key benefit of this process is that it provides a structured vision of what has to be delivered. • The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. 22
  • 23. 5. Validate Scope • The key benefit of this process is that it brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable. 23
  • 24. 6. Control Scope • The key benefit of this process is that it allows the scope baseline to be maintained throughout the project. 24
  • 25.  Quality: isdefined asfitness for purpose specified by a designer/customer.  May include desires for safety, functionality, aesthetics, reliability, durability/service life, maintainability of a product .  Quality system refers to established organized routines and procedures which comprise elements set as standard.  Quality System Pillars: quality assurance (used to verify) &/or which may be set by the management, customer regulatory body; and quality control used to identify and eliminate non-conformance 21 5.3 Project Quality Management
  • 26.  Quality Assurance: is the application of planned, systematic, quality activities to ensurethat theproject will employall processesneededto meetrequirement  It is part of quality management focused on providing confidence that quality requirementswill be fulfilled’ ISO9000  The aim is to prevent defects focus on the process used to make the product. It is a proactive quality process  Improve development and test processes so that defect do not arise  Preventive process 22
  • 27.  Quality Control  Control is concerned with comparing the work results with the requirement to ensure that the result is acceptable  Partofqualitymanagementfocusedonfulfillingquality requirements’ISO  Performing QC involves monitoring specific project resultsto determine the cause of unsatisfactory results  QCObjective:to ascertain thestandard of a product that can meet the requirement of the customer are produced  Identifydefectsafteraproductisdevelopedandbeforeitisreleased  Itisreactivequalityprocess,finds/detectdefectsaftertesting  Correctiveprocess 23
  • 28.  Inspection:  Determining the acceptability of an output/product of a process at a givenstage.  It includes measuring, examining or testing and comparing whether the resultsconformtotherelevant requirements.  PlanningInspectionincludes:wheretoinspect,what resourcestouseand extentofinspectionaredetermined.  Hence,itisapplyingtoolsandtechniquesfortheworks andmanagement objectivestoidentifylevelofconformity 24
  • 29. 29 Construction Quality Control Who Quality Control (QC) Usually the contractor (or a third party) is responsible for performing Quality Control (QC) making sure that the standards are meet for production Quality Assurance (QA)  Usually the government or outside third party is responsible for performing Quality Assurance (QA).  QA is spot checking of contract compliance, test results, and ultimately making sure that the quality control process is working  A government organizations/clients or any executing agencies will have very clear guidance on what is required per contract as far as the QA/QC is concerned.  Policy and Guidelines  Standards and Specifications  Rules and Regulations  Terms and conditions of the contract
  • 30. •Quality Management is an important project management function. •It is one of the critical attributes of project success, with the others being cost, time and safety. •Quality Management involves : • Setting Quality Standards to achieve both technical and managerial competence, • Scheduling inspections, • Managing any required rework, • Documentation. 30 Construction Quality management from PMBOK
  • 31. The basic approach to project quality management is intended to be compatible with International Organization for Standardization (ISO) quality standards. In the context of achieving ISO compatibility, modern quality management approaches seek to minimize variation and to deliver results that meet defined requirements. Project Quality Management processes include: 1. Plan Quality Management 2. Perform Quality Assurance 3. Control Quality 31
  • 32. 1. Plan Quality Management • Plan Quality Management is the process of •identifying quality requirements and/or standards for the project and its deliverables, and •documenting how the project will demonstrate compliance with relevant quality requirements and/or standards. • The key benefit of this process is that it provides guidance and direction on how quality will be managed and validated throughout the project. 32
  • 33. 1. Plan Quality Management… 33
  • 34. 2. Perform Quality Assurance • It is the process of auditing the quality requirements and the results from quality control measurements to ensure that appropriate quality standards and operational definitions are used. • The key benefit of this process is that it facilitates the improvement of quality processes. Project Mgmt Organized by: Belachew Asteray (PhD) 34
  • 35. 3. Control Quality •Control Quality is the process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes. •The key benefits of this process include: (1) identifying the causes of poor process or product quality and recommending and/or taking action to eliminate them; and (2) validating that project deliverables and work meet the requirements specified by key stakeholders necessary for final acceptance. 35
  • 37. •Stakeholders can be defined as either individuals or units or organization itself for which they claim a stake in the project such that they get benefit from or affected by the whole processes of the project and its deliverables. 37 5.4 Project Stakeholder Management
  • 38. Who are stakeholders of CI? Project stakeholders or participants or parties: • Are individuals and organizations who are actively involved in project execution or successful project completion. • Are those who have stakes or vested interest in construction project • Are those who has a telling effect on a project 38 5.4 Project Stakeholder Management…
  • 39. The practice of planning, designing, constructing, and operating a facility is a collective effort of different groups of professionals. Depending on the size, complexity, and purpose of a particular construction project, the project team may include: • A Client or an Owner or Employer: Individuals, government, real estate developers etc. • Financial institutions or other investors that provide the funding • Local planning and code authorities 39 5.4 Project Stakeholder Management…
  • 40. • Consultants or Licensed architects and engineers who provide design work and prepare construction documents • Contractors who provide construction services and install systems • Marketing or leasing agents • Facility managers who are responsible for operating the facility. 40 5.4 Project Stakeholder Management…
  • 41. 41 Stakeholder Ecosystem 5.4 Project Stakeholder Management…
  • 42. 42 Employer(s) Financier(s) Contractor(s) Consultant(s) Regulatory Bodies Stakeholders' in Public Construction Projects The Construction Industry Project Organization(s) Government(s) Supplier(s) Sub-contractor(s) Sub-Consultant(s) The Public Financial Institutions Other Interest Groups Beneficiary(s) Other sectors Internal Stakeholders External Stakeholders Stakeholders in Public Construction Projects 5.4 Project Stakeholder Management…
  • 43. A. Client • The client is the initiator and owner of the project. • It is the most important party who is active from inception to completion and event to post-occupancy maintenance. 43 Idea Land client Capital 5.4 Project Stakeholder Management…
  • 44. • Clients may be classified as Public sector clients and private sector clients. • Public sector clients  Central Government Offices (Ministries)  Local Authorities (Regional or Town)  Public Corporations • Private sector clients  These are private individuals & private companies 44 5.4 Project Stakeholder Management…
  • 45. B. Consultant • The consultant transfers the wish of the owner into realizable form and makes the study, design and possibly the supervision. • The main role of the consultant is to interpret the client’s project requirement into a specific design. C. Contractor • The contractor is the one who performs the work • These are groups established mainly as commercial companies, that contract to construct development projects. 45 5.4 Project Stakeholder Management…
  • 46. D. Public Sector Agencies • Statutory Authorities • _These bodies offer technical advice during design and construction in their respective areas. • E.g. ERA, EWWC, Fire Authority - requires meeting their specific requirements. Thus early information to these authorities is required. • Municipalities and Government Authorities • These bodies offer the basic Land permit and building permit. 46 5.4 Project Stakeholder Management…
  • 47. E. Insurance Companies: Contractors are required to provide bid bonds as a condition of being allowed to bid, and then they must provide insurance too. F. Banks: Banks provide the working capital contractors need to build the project. G. Suppliers: The quality of a construction project is very dependent on the quality of the suppliers used by individual contractors. H. Trade (labor) unions: are unions of the working class that look after unfair treatment of workers (like payment issues, firing issues) as well as issues related to occupational health and safety. 47 5.4 Project Stakeholder Management…
  • 48. • The activities and roles of each player varies from project to project and ownership. • But, in general, the following figure shows the roles of each participant at different stages of construction. 48 General Activity relationships among the Client, Consultant & the contractor 5.4 Project Stakeholder Management…
  • 49. 49 5.4 Project Stakeholder Management…
  • 50. • Project Stakeholder Management includes the processes required • to identify the people, groups, or organizations that could impact or be impacted by the project, • to analyze stakeholder expectations and their impact on the project, and • to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution. • Stakeholder management focuses on continuous communication with stakeholders to understand their needs and expectations, addressing issues as they occur, managing conflicting interests and fostering appropriate stakeholder engagement in project decisions and activities. 50 5.4 Project Stakeholder Management…
  • 51. •Stakeholder satisfaction should be managed as a key project objective. •Every project will have stakeholders who are impacted by or can impact the project in a positive or negative way. •The ability of the project manager to correctly identify and manage these stakeholders in an appropriate manner can mean the difference between success and failure. 51 5.4 Project Stakeholder Management…
  • 52. •While some stakeholders may have a limited ability to influence the project, others may have significant influence on the project and its expected outcomes. •Project Stakeholder Management processes include : 1. Identify Stakeholder 2. Plan Stakeholder 3. Manage Stakeholder 4. Control Stakeholder 52 5.4 Project Stakeholder Management…
  • 53. 1. Identify Stakeholders • Identify Stakeholders is the process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project, analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success. • The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders. 53
  • 54. 2. Plan Stakeholder Management • Plan Stakeholder Management is the process of developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle, based on the analysis of their needs, interests, and potential impact on project success. • The key benefit of this process is that it provides a clear, actionable plan to interact with project stakeholders to support the project’s interests. 54
  • 55. 3. Manage Stakeholder Engagement • It is the process of communicating and working with stakeholders •to meet their needs/expectations, •address issues as they occur, and •foster appropriate stakeholder engagement in project activities throughout the project life cycle. • The key benefit of this process is that it allows the project manager to increase support and minimize resistance from stakeholders, significantly increasing the chances to achieve project success 55
  • 57. 4. Control Stakeholder Engagement • It is the process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders. • The key benefit of this process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes. 57
  • 58. • Project Communications Management includes the processes that are required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate disposition of project information. • Project managers spend most of their time communicating with team members and other project stakeholders, whether they are internal (at all organizational levels) or external to the organization. 58 5.5 Project Communications Management
  • 59. •The communication activities involved in these processes may often have many potential dimensions that need to be considered, including, but not limited to: • Internal (within the project) and external (customer, vendors, other projects, organizations, the public); • Formal (reports, minutes, briefings) and informal (emails, memos, discussions); • Vertical (up and down the organization) and horizontal (with peers); • Official (newsletters, annual report) and unofficial (off the record communications); and • Written and oral, and verbal (voice inflections) and nonverbal (body language). 59 5.5 Project Communications Management…
  • 60. • Most communication skills are common for both general management and project management, such as, but not limited to: • Listening actively and effectively; • Questioning and probing ideas and situations to ensure better understanding; • Educating to increase team’s knowledge so that they can be more effective; • Fact-finding to identify or confirm information; • Setting and managing expectations; • Persuading a person, a team, or an organization to perform an action; • Motivating to provide encouragement or reassurance; • Coaching to improve performance and achieve desired results; • Negotiating to achieve mutually acceptable agreements between parties; • Resolving conflict to prevent disruptive impacts; and • Summarizing, recapping, and identifying the next steps. 60 5.5 Project Communications Management…
  • 61. •Effective communication creates a bridge between diverse stakeholders who may have different cultural and organizational backgrounds, different levels of expertise, and different perspectives and interests, which impact or have an influence upon the project execution or outcome. •Project Communications Management processes include: 1. Plan Communications 2. Manage Communications 3. Control Communications 61 5.5 Project Communications Management…
  • 62. 1. Plan Communications Management • It is the process of developing an appropriate approach and plan for project communications based on stakeholder’s information needs and requirements, and available organizational assets. • The key benefit of this process is that it identifies and documents the approach to communicate most effectively and efficiently with stakeholders. 62 5.5 Project Communications Management…
  • 63. 2. Manage Communications • It is the process of creating, collecting, distributing, storing, retrieving, and the ultimate disposition of project information in accordance to the communications management plan. • The key benefit of this process is that it enables an efficient and effective communications flow between project stakeholders. 63 5.5 Project Communications Management…
  • 64. 3. Control Communications • Control Communications is the process of monitoring and controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met. • The key benefit of this process is that it ensures an optimal information flow among all communication participants, at any moment in time. 64 5.5 Project Communications Management…
  • 65.  Risk: possibility of meeting danger or suffering, harm, loss  Uncertainty inherent in plans and the possibility of something happening that can affect the prospects of achieving project goals  Unlike the usual dictionary definition of “risk” which refers only to undesirable events interpretation of risk include both downside and upside variations in the values involved 2 5.6 Risk and Uncertainty Management
  • 66.  Planning for Project Risk Management 🞑Planning risk involves paying attention when we don’t want project fail. Aside “acts of God” most projects fail due to:  Actually impossible—lies outside of technical capability available at the time  Over constrained— possible but unrealistic time and resource  Not competently managed –have the time and resourcesbut poorly managed . This can succeed through giving adequate attention to project and risk planning 4 Planning Risk Management
  • 67. Planning for Project Risk Management 🞑 Overall project planning process is essential since without this it is not possible to know what may go right or wrong and manage proactively.  Planninghelpsto discoverpossiblefailure areas and modes.  At project level other activities may take priority than planning for risk; but without planning there can be little risk management 5
  • 68. 7 Hazard Should not be ignored Risk management Too high to be covered with contingency Not serious Trivial Not serious Expect Impact Probability Low High Low High Realisticand honest estimate results from the parties’ trust and cooperation Planning Risk Management
  • 69. 8 Planning Risk Management Step1: Analyze the project to identify sourcesof risks Step 2: RiskAssessment(qualitative & Quantitative) •Probability •Severity •controllability Step 4: R esponse Control •Risk R esponse Control •Implement strategy •Monitor and Adjust •Apply change management Step 3: R esponse development •Develop strategy •Develop contingency plan manage Response developm ent plan Known risks RiskAssess ment Response control
  • 70. 9  Performing Quantitative Analysis of the Risks 🞑ProbabilityAnalysis: take the highranking risksfrom the qualitative analysis and quantify their probabilities using  Past data analysis using statistical distribution methods(objective)  Delphi method: gathering opinions of individuals secretly till their subjective estimations approaches to single figure  Expert group discussion (this is also subjective)  Require continuous probability distribution suchasnormal or triangular Planning Risk Management
  • 71. 10 🞑Prepare Response Plan to the Risks The options of managing risks are to treat the Cause or Effect of a risk event  Avoid  Sharing  Transferring to subcontractor, supplier, insurance  Retain : risks that can’t be shared or transferred has to be owned. Better ability of control isprevention, lesser cost, ability to manage external risks  Mitigation (minimizing impact or occurrence)
  • 72. •Uncertainties and Changes in undertaking a public construction project come from many sources and often involve many participants and resources. •The perceptions and attitude of practitioners towards uncertainties and changes matters a lot in effective performance determinations. 72 Uncertainty and Risk Management from PMBOK
  • 73. •Project Risk Management processes include: 1. Plan Risk Management 2. Identify Risks 3. Perform Qualitative Risk Analysis 4. Perform Quantitative Risk Analysis 5. Plan Risk Responses 6. Control Risks 73
  • 74. 1. Plan Risk Management •Plan Risk Management is the process of defining how to conduct risk management activities for a project. •The key benefit of this process is it ensures that the degree, type, and visibility of risk management are commensurate with both the risks and the importance of the project to the organization. •The risk management plan is vital to communicate with and obtain agreement and support from all stakeholders to ensure the risk management process is supported and performed effectively over the project life cycle. 74
  • 75. 2. Identify Risks • Identify Risks is the process of determining which risks may affect the project and documenting their characteristics. • The key benefit of this process is the documentation of existing risks and the knowledge and ability it provides to the project team to anticipate events. 75
  • 76. 3. Perform Qualitative Risk Analysis • Perform Qualitative Risk Analysis is the process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact. • The key benefit of this process is that it enables project managers to reduce the level of uncertainty and to focus on high-priority risks. 76
  • 77. 4. Perform Quantitative Risk Analysis • Perform Quantitative Risk Analysis is the process of numerically analyzing the effect of identified risks on overall project objectives. • The key benefit of this process is that it produces quantitative risk information to support decision making in order to reduce project uncertainty. 77
  • 78. 5. Plan Risk Responses • Plan Risk Responses is the process of developing options and actions to enhance opportunities and to reduce threats to project objectives. • The key benefit of this process is that it addresses the risks by their priority, inserting resources and activities into the budget, schedule and project management plan as needed. 78
  • 79. 6. Control Risks • Control Risks is the process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project. • The key benefit of this process is that it improves efficiency of the risk approach throughout the project life cycle to continuously optimize risk responses. 79