The document outlines the workflow for pre-project sanctioning under the Pradhan Mantri Awas Yojana. It involves the following key steps: 1) ULB prepares the HFAPoA/AIP and identifies beneficiaries, uploading their details to the MIS system to check for duplicates. 2) ULB also prepares the DPR for projects and attaches beneficiaries. 3) The DPR is then sent to the state for approval/rejection/modifications and entry of survey data into the MIS. 4) If approved, the DPR moves to the PMU, mission directorate, and appraisal agency for further scrutiny before final approval by the CSMC and release