SlideShare a Scribd company logo
1 of 12
+
Zylar Industries
Case
Group-4 SIMATUPANG
Denny Ardhia Mangara
Sebastian Muhammad
Hanif Sabaruddin
Irvan Jauhari
+
The Business
 Zylar Industries is a manufacturer of standard and custom-designed
bottling equipment.
 Lyan Company asked Zylar to quote a price for a custom-designed
bottling machine to be delivered in April. Lyan intends to make a
decision on the purchase of such a machine by January 1, so Zylar
would have the entire first quarter of 20x1 to build the equipment.
 Zylar's pricing policy for custom-designed equipment is 50 percent
markup on absorption manufacturing cost
Estimate Direct Material & Direct Labor
Direct Material $ 256,000
Direct Labor (11,000 hrs at $15) $ 165,000
Review result
+
The Business – Cont’d
 Manufacturing overhead is applied on the basis of direct-labor
hours.
 Zylar normally plans to run its plant at a level of 15,000 DLH
per month and assigns OH on the basis of 180,000 DLH per
year.
 The overhead application rate for 20x1 of $9.00 per hour is
based on the following budgeted manufacturing overhead costs
for 20x1.
Budgeted Manufacturing Overhead Costs For 20x1.
Variable Manufacturing OH $ 972,000
Fix Manufacturing OH $ 648,000
Total Manufacturing OH (a) $ 1,620,000
DL Hours per Year (b) 180,000
OH / Hours (a / b) $ 9.00
+
Issues
 Zylar’s has limited production capacity if Zylar is awarded
the job, one of the standard product production would be
reduced.
 For current Zylar’s production requires 12,000 DLH per month
during 1st quarter.
 To fulfill the Lyan’s query, Zylar need to increase 15,000 DLH
each month on short notice.
 Sales for standard product would be lost for $12,000 and yet
there will be no future loss.
+
The Demand
 Lyan needs the custom-designed equipment to increase its bottle-
making capacity so that it will not have to buy bottles from an outside
supplier.
 Lyan Company requires 5,000,000 bottles annually.
 Its present equipment has a maximum capacity of 4,500,000 bottles
with a directly traceable cash outlay cost of 15 cents per bottle.
 Thus, Lyan has had to purchase 500,000 bottles from a supplier at 40
cents each. The new equipment would allow Lyan to manufacture its
entire Annual demand for bottles at a direct-material cost savings of 1
cent per bottle. Zylar estimates that Lyan's annual bottle demand will
continue to be 5,000,000 bottles over the next five years, the
estimated life of the special-purpose equipment
+
Question#1
 Calculate the bid Zylar would submit if it follows its standard pricing
policy for special-purpose equipment.
BID BASED ON STANDARD PRICING
Direct material $256,000
Direct labor (11,000 DLH @ $15) $165,000
Manufacturing overhead (11,000 DLH @ $9) $99,000
Total manufacturing costs $520,000
Pricing Policy, Markup (50% of full cost) $260,000
Standard pricing policy bid $780,000
Answer #1
+
Question#2
 Calculate the minimum bid Zylar would be willing to submit on
the Lyan equipment that would result in the same total
contribution margin as planned for the first quarter of 20x1.
MINIMUM BID
Direct material $256,000
Direct labor (11,000 DLH @ $15) $165,000
Variable manufacturing overhead (11,000 DLH@$5.4) $59,400
Opportunity lost of sales (*) $35,200
Minimum bid $515,600
Answer #2
+
* OPPORTUNITY LOSS OF SALES
Selling price per unit of standard product $ 12,000
Variable costs per unit
Direct material $ 2,500
Direct labor (250 DLH @ $15) $ 3,750
Variable overhead (250 DLH @ $5.40) $ 1,350 $ 7,600
Contribution Margin PerUnit $ 4,400
Standard product requirements (12,000 DLH x 3) 36,000 DLH
Special order requirements 11,000 DLH
Total hours required 47,000 DLH
Plant capacity per quarter (15,000 DLH x 3) 45,000 DLH
Shortage in hours 2,000 DLH
Lost unit sales (2,000 DLH ÷ 250 DLH) 8
Lost contribution $ 35,200
+
Question#3
 Suppose Zylar Industries has submitted a bid slightly above the
minimum calculated in requirement (2). Upon receiving Zylar's
bid, Lyan's assistant purchasing manager telephoned his friend
at Tygar Corporation: “Hey Joe, we just got a bid from Zylar
Industries on some customized equipment. I think Tygar would
stand a good chance of beating it. Stop by the house this
evening, and I'll show you the details of Zylar's bid and the
specifications on the machine.”
 Is Lyan Company's assistant purchasing manager acting
ethically?
+
Answer #3
 It is definitely against the code of conduct. Should company
would like to gain the competitive price, company shall notify to
all bidders at the same time with regard to the specification and
its term and condition.
 Bidders’ proposal must be treated as confidential document
and the document will only be disclosed on the bid opening
date.
+
Recommendation
 Zylar has to consider the term and condition of the contract
particularly the penalty due to delay delivery because Zylar has
limited production capacity and knowing that their employee’s
unwilling to work overtime
+
Thank you

More Related Content

What's hot

Case study on Cost Accounting
Case study on Cost AccountingCase study on Cost Accounting
Case study on Cost AccountingAditya Purohit
 
Sistema de Costeo ABC en la Industria Textil
Sistema de Costeo ABC en la Industria TextilSistema de Costeo ABC en la Industria Textil
Sistema de Costeo ABC en la Industria TextilGeovanny Moreno P
 
Los costos y gastos por Lucía Lasso
Los costos y gastos por Lucía LassoLos costos y gastos por Lucía Lasso
Los costos y gastos por Lucía Lassoanalucialasso
 
Job costing Tutorial
Job costing TutorialJob costing Tutorial
Job costing TutorialSvtuition
 
As 2 inventories valuation
As   2 inventories valuationAs   2 inventories valuation
As 2 inventories valuationNitesh Kumar
 
Absorption and marginal costing
Absorption and marginal costingAbsorption and marginal costing
Absorption and marginal costingTrisha Dookhony
 
Cost allocation joint cost [compatibility mode]
Cost allocation   joint cost [compatibility mode]Cost allocation   joint cost [compatibility mode]
Cost allocation joint cost [compatibility mode]RESHMI RAVEENDRAN
 
Analisis de-costos-y-punto-de-equilibrio
Analisis de-costos-y-punto-de-equilibrioAnalisis de-costos-y-punto-de-equilibrio
Analisis de-costos-y-punto-de-equilibrioPatricia Alayo Paytan
 
Managerial Accounting Garrison Noreen Brewer Chapter 07
Managerial Accounting Garrison Noreen Brewer Chapter 07Managerial Accounting Garrison Noreen Brewer Chapter 07
Managerial Accounting Garrison Noreen Brewer Chapter 07Asif Hasan
 
Fundamentals of accounting - manufacturing
Fundamentals of accounting - manufacturingFundamentals of accounting - manufacturing
Fundamentals of accounting - manufacturingJohn Paul Espino
 

What's hot (20)

Case study on Cost Accounting
Case study on Cost AccountingCase study on Cost Accounting
Case study on Cost Accounting
 
Financial Assets
Financial AssetsFinancial Assets
Financial Assets
 
Sistema de Costeo ABC en la Industria Textil
Sistema de Costeo ABC en la Industria TextilSistema de Costeo ABC en la Industria Textil
Sistema de Costeo ABC en la Industria Textil
 
Los costos y gastos por Lucía Lasso
Los costos y gastos por Lucía LassoLos costos y gastos por Lucía Lasso
Los costos y gastos por Lucía Lasso
 
Costsheet final
Costsheet finalCostsheet final
Costsheet final
 
Costos
Costos Costos
Costos
 
Job costing Tutorial
Job costing TutorialJob costing Tutorial
Job costing Tutorial
 
Manufacturing accounts
Manufacturing accountsManufacturing accounts
Manufacturing accounts
 
As 2 inventories valuation
As   2 inventories valuationAs   2 inventories valuation
As 2 inventories valuation
 
estado fiancieros consolidados
estado fiancieros consolidados estado fiancieros consolidados
estado fiancieros consolidados
 
Absorption and marginal costing
Absorption and marginal costingAbsorption and marginal costing
Absorption and marginal costing
 
Cost allocation joint cost [compatibility mode]
Cost allocation   joint cost [compatibility mode]Cost allocation   joint cost [compatibility mode]
Cost allocation joint cost [compatibility mode]
 
Job order costing
Job order costingJob order costing
Job order costing
 
Analisis de-costos-y-punto-de-equilibrio
Analisis de-costos-y-punto-de-equilibrioAnalisis de-costos-y-punto-de-equilibrio
Analisis de-costos-y-punto-de-equilibrio
 
chap003.ppt
chap003.pptchap003.ppt
chap003.ppt
 
Seccion 13 inventarios
Seccion 13  inventariosSeccion 13  inventarios
Seccion 13 inventarios
 
Propiedad planta-y-equipo(1)
Propiedad planta-y-equipo(1)Propiedad planta-y-equipo(1)
Propiedad planta-y-equipo(1)
 
Operating costing
Operating costingOperating costing
Operating costing
 
Managerial Accounting Garrison Noreen Brewer Chapter 07
Managerial Accounting Garrison Noreen Brewer Chapter 07Managerial Accounting Garrison Noreen Brewer Chapter 07
Managerial Accounting Garrison Noreen Brewer Chapter 07
 
Fundamentals of accounting - manufacturing
Fundamentals of accounting - manufacturingFundamentals of accounting - manufacturing
Fundamentals of accounting - manufacturing
 

Viewers also liked

Development pack
Development packDevelopment pack
Development packctkmedia
 
Shooting schedule
Shooting scheduleShooting schedule
Shooting schedulectkmedia
 
Preproductionworksheet
PreproductionworksheetPreproductionworksheet
Preproductionworksheetctkmedia
 
Road transport india safety bill dunu roy itp jan 2016
Road transport india safety bill dunu roy itp jan 2016Road transport india safety bill dunu roy itp jan 2016
Road transport india safety bill dunu roy itp jan 2016Arnaud Renard
 
Tugas matematika 1 (semester 2) - Mencari Turunan
Tugas matematika 1 (semester 2) - Mencari TurunanTugas matematika 1 (semester 2) - Mencari Turunan
Tugas matematika 1 (semester 2) - Mencari Turunanmizapisari
 
Reactive compatibilization of natural rubber (nr) vs Xnbr
Reactive compatibilization of natural rubber (nr) vs XnbrReactive compatibilization of natural rubber (nr) vs Xnbr
Reactive compatibilization of natural rubber (nr) vs Xnbrlukkumanul
 
Estimation of the Rolling Resistance of Tires
Estimation of the Rolling Resistance of TiresEstimation of the Rolling Resistance of Tires
Estimation of the Rolling Resistance of TiresBrian Wiegand
 
Rolling Resistance Thresholds
Rolling Resistance ThresholdsRolling Resistance Thresholds
Rolling Resistance ThresholdsArnaud Renard
 
Air Transport India
Air Transport IndiaAir Transport India
Air Transport IndiaAmit Anand
 
My Tableau Journey
My Tableau JourneyMy Tableau Journey
My Tableau JourneyAndy Kriebel
 
Exemplarpreprodreport
ExemplarpreprodreportExemplarpreprodreport
Exemplarpreprodreportctkmedia
 
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...Unmetric
 
Public transport problems in mumbai
Public transport problems in mumbaiPublic transport problems in mumbai
Public transport problems in mumbaiaziz khan
 

Viewers also liked (20)

Dr. Neeraj Israni
Dr. Neeraj IsraniDr. Neeraj Israni
Dr. Neeraj Israni
 
Development pack
Development packDevelopment pack
Development pack
 
Print Portfolio
Print PortfolioPrint Portfolio
Print Portfolio
 
Shooting schedule
Shooting scheduleShooting schedule
Shooting schedule
 
Preproductionworksheet
PreproductionworksheetPreproductionworksheet
Preproductionworksheet
 
Woman of Promise Program
Woman of Promise ProgramWoman of Promise Program
Woman of Promise Program
 
Road transport india safety bill dunu roy itp jan 2016
Road transport india safety bill dunu roy itp jan 2016Road transport india safety bill dunu roy itp jan 2016
Road transport india safety bill dunu roy itp jan 2016
 
Nice ventures
Nice venturesNice ventures
Nice ventures
 
Tugas matematika 1 (semester 2) - Mencari Turunan
Tugas matematika 1 (semester 2) - Mencari TurunanTugas matematika 1 (semester 2) - Mencari Turunan
Tugas matematika 1 (semester 2) - Mencari Turunan
 
Missing Piece
Missing PieceMissing Piece
Missing Piece
 
redesign knowledge work
redesign knowledge workredesign knowledge work
redesign knowledge work
 
Reactive compatibilization of natural rubber (nr) vs Xnbr
Reactive compatibilization of natural rubber (nr) vs XnbrReactive compatibilization of natural rubber (nr) vs Xnbr
Reactive compatibilization of natural rubber (nr) vs Xnbr
 
Estimation of the Rolling Resistance of Tires
Estimation of the Rolling Resistance of TiresEstimation of the Rolling Resistance of Tires
Estimation of the Rolling Resistance of Tires
 
Rolling Resistance Thresholds
Rolling Resistance ThresholdsRolling Resistance Thresholds
Rolling Resistance Thresholds
 
Air Transport India
Air Transport IndiaAir Transport India
Air Transport India
 
My Tableau Journey
My Tableau JourneyMy Tableau Journey
My Tableau Journey
 
Exemplarpreprodreport
ExemplarpreprodreportExemplarpreprodreport
Exemplarpreprodreport
 
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
Comparison of Michelin, Goodyear, Continental, Firestone and Other Top Tire B...
 
Fire kills 1
Fire kills 1Fire kills 1
Fire kills 1
 
Public transport problems in mumbai
Public transport problems in mumbaiPublic transport problems in mumbai
Public transport problems in mumbai
 

Similar to zyler

Discuss at least two ways that you can help to control what inform.docx
Discuss at least two ways that you can help to control what inform.docxDiscuss at least two ways that you can help to control what inform.docx
Discuss at least two ways that you can help to control what inform.docxduketjoy27252
 
MA - CH10 HW2 1.value12.50 pointsDue to evaporation d.docx
MA - CH10 HW2 1.value12.50 pointsDue to evaporation d.docxMA - CH10 HW2 1.value12.50 pointsDue to evaporation d.docx
MA - CH10 HW2 1.value12.50 pointsDue to evaporation d.docxinfantsuk
 
ch07 full chapter.pptx
ch07 full chapter.pptxch07 full chapter.pptx
ch07 full chapter.pptxahalalami
 
Question 1(2.5 points)Kinsi Corporation manufactures three.docx
Question 1(2.5 points)Kinsi Corporation manufactures three.docxQuestion 1(2.5 points)Kinsi Corporation manufactures three.docx
Question 1(2.5 points)Kinsi Corporation manufactures three.docxhildredzr1di
 
A ll questions according to topics
A ll questions according to topicsA ll questions according to topics
A ll questions according to topicsZiyad Zaidi
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11shyaminfo06
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11pavucloud08
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11eyavagal
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11olivergeorg
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11olivergeorg
 
Basic Global Business Presentation1
Basic Global Business Presentation1Basic Global Business Presentation1
Basic Global Business Presentation1uconyejiaka
 
W8 Assignment Final Exam Question 1 1. An activity-based c.docx
W8 Assignment Final Exam Question 1 1. An activity-based c.docxW8 Assignment Final Exam Question 1 1. An activity-based c.docx
W8 Assignment Final Exam Question 1 1. An activity-based c.docxcelenarouzie
 
Acc 561-final-exam-guide-new-2018-score-100
Acc 561-final-exam-guide-new-2018-score-100Acc 561-final-exam-guide-new-2018-score-100
Acc 561-final-exam-guide-new-2018-score-100individual484
 
Proposal for Procurement Officer at Daleel Field
Proposal for Procurement Officer at Daleel FieldProposal for Procurement Officer at Daleel Field
Proposal for Procurement Officer at Daleel FieldMahmood Said Al Amri
 
Costi decisionali - 4. I Costi Opportunità
Costi decisionali - 4. I Costi OpportunitàCosti decisionali - 4. I Costi Opportunità
Costi decisionali - 4. I Costi OpportunitàManager.it
 
Exam 061683RR - PLANNING, PERFORMANCE Questions 1 to 20 Sele.docx
Exam 061683RR - PLANNING, PERFORMANCE Questions 1 to 20 Sele.docxExam 061683RR - PLANNING, PERFORMANCE Questions 1 to 20 Sele.docx
Exam 061683RR - PLANNING, PERFORMANCE Questions 1 to 20 Sele.docxgitagrimston
 

Similar to zyler (18)

Discuss at least two ways that you can help to control what inform.docx
Discuss at least two ways that you can help to control what inform.docxDiscuss at least two ways that you can help to control what inform.docx
Discuss at least two ways that you can help to control what inform.docx
 
MA - CH10 HW2 1.value12.50 pointsDue to evaporation d.docx
MA - CH10 HW2 1.value12.50 pointsDue to evaporation d.docxMA - CH10 HW2 1.value12.50 pointsDue to evaporation d.docx
MA - CH10 HW2 1.value12.50 pointsDue to evaporation d.docx
 
Mbaptmciijuly2009
Mbaptmciijuly2009Mbaptmciijuly2009
Mbaptmciijuly2009
 
Acct 505 final exam
Acct 505 final examAcct 505 final exam
Acct 505 final exam
 
ch07 full chapter.pptx
ch07 full chapter.pptxch07 full chapter.pptx
ch07 full chapter.pptx
 
Question 1(2.5 points)Kinsi Corporation manufactures three.docx
Question 1(2.5 points)Kinsi Corporation manufactures three.docxQuestion 1(2.5 points)Kinsi Corporation manufactures three.docx
Question 1(2.5 points)Kinsi Corporation manufactures three.docx
 
A ll questions according to topics
A ll questions according to topicsA ll questions according to topics
A ll questions according to topics
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11
 
Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11Stayer acc 560 week 7 homework chapter 11
Stayer acc 560 week 7 homework chapter 11
 
Basic Global Business Presentation1
Basic Global Business Presentation1Basic Global Business Presentation1
Basic Global Business Presentation1
 
W8 Assignment Final Exam Question 1 1. An activity-based c.docx
W8 Assignment Final Exam Question 1 1. An activity-based c.docxW8 Assignment Final Exam Question 1 1. An activity-based c.docx
W8 Assignment Final Exam Question 1 1. An activity-based c.docx
 
Acc 561-final-exam-guide-new-2018-score-100
Acc 561-final-exam-guide-new-2018-score-100Acc 561-final-exam-guide-new-2018-score-100
Acc 561-final-exam-guide-new-2018-score-100
 
Proposal for Procurement Officer at Daleel Field
Proposal for Procurement Officer at Daleel FieldProposal for Procurement Officer at Daleel Field
Proposal for Procurement Officer at Daleel Field
 
Costi decisionali - 4. I Costi Opportunità
Costi decisionali - 4. I Costi OpportunitàCosti decisionali - 4. I Costi Opportunità
Costi decisionali - 4. I Costi Opportunità
 
Exam 061683RR - PLANNING, PERFORMANCE Questions 1 to 20 Sele.docx
Exam 061683RR - PLANNING, PERFORMANCE Questions 1 to 20 Sele.docxExam 061683RR - PLANNING, PERFORMANCE Questions 1 to 20 Sele.docx
Exam 061683RR - PLANNING, PERFORMANCE Questions 1 to 20 Sele.docx
 

More from Maninerror Hanif

More from Maninerror Hanif (8)

making performance reviews
making performance reviewsmaking performance reviews
making performance reviews
 
Engstorm case
Engstorm caseEngstorm case
Engstorm case
 
Ricardo Semler
Ricardo SemlerRicardo Semler
Ricardo Semler
 
medi sys corp the intenscare
medi sys corp the intenscaremedi sys corp the intenscare
medi sys corp the intenscare
 
Landau Media
Landau MediaLandau Media
Landau Media
 
ikea marketing case
ikea marketing caseikea marketing case
ikea marketing case
 
Redesign knowledge work
Redesign knowledge workRedesign knowledge work
Redesign knowledge work
 
integrating innovation style and knowledge into strategy
integrating innovation style and knowledge into strategyintegrating innovation style and knowledge into strategy
integrating innovation style and knowledge into strategy
 

Recently uploaded

The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfGale Pooley
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...ssifa0344
 
Dividend Policy and Dividend Decision Theories.pptx
Dividend Policy and Dividend Decision Theories.pptxDividend Policy and Dividend Decision Theories.pptx
Dividend Policy and Dividend Decision Theories.pptxanshikagoel52
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxhiddenlevers
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...shivangimorya083
 
Quarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingQuarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingMaristelaRamos12
 
The Economic History of the U.S. Lecture 22.pdf
The Economic History of the U.S. Lecture 22.pdfThe Economic History of the U.S. Lecture 22.pdf
The Economic History of the U.S. Lecture 22.pdfGale Pooley
 
The Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdfThe Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdfGale Pooley
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfGale Pooley
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...Suhani Kapoor
 
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spiritegoetzinger
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Pooja Nehwal
 
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Roomdivyansh0kumar0
 
The Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfThe Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfGale Pooley
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130Suhani Kapoor
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfGale Pooley
 

Recently uploaded (20)

The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdf
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
 
Dividend Policy and Dividend Decision Theories.pptx
Dividend Policy and Dividend Decision Theories.pptxDividend Policy and Dividend Decision Theories.pptx
Dividend Policy and Dividend Decision Theories.pptx
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
 
Quarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingQuarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of Marketing
 
The Economic History of the U.S. Lecture 22.pdf
The Economic History of the U.S. Lecture 22.pdfThe Economic History of the U.S. Lecture 22.pdf
The Economic History of the U.S. Lecture 22.pdf
 
The Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdfThe Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdf
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdf
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
 
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spirit
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
 
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
 
The Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfThe Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdf
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
 
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdf
 

zyler

  • 1. + Zylar Industries Case Group-4 SIMATUPANG Denny Ardhia Mangara Sebastian Muhammad Hanif Sabaruddin Irvan Jauhari
  • 2. + The Business  Zylar Industries is a manufacturer of standard and custom-designed bottling equipment.  Lyan Company asked Zylar to quote a price for a custom-designed bottling machine to be delivered in April. Lyan intends to make a decision on the purchase of such a machine by January 1, so Zylar would have the entire first quarter of 20x1 to build the equipment.  Zylar's pricing policy for custom-designed equipment is 50 percent markup on absorption manufacturing cost Estimate Direct Material & Direct Labor Direct Material $ 256,000 Direct Labor (11,000 hrs at $15) $ 165,000 Review result
  • 3. + The Business – Cont’d  Manufacturing overhead is applied on the basis of direct-labor hours.  Zylar normally plans to run its plant at a level of 15,000 DLH per month and assigns OH on the basis of 180,000 DLH per year.  The overhead application rate for 20x1 of $9.00 per hour is based on the following budgeted manufacturing overhead costs for 20x1. Budgeted Manufacturing Overhead Costs For 20x1. Variable Manufacturing OH $ 972,000 Fix Manufacturing OH $ 648,000 Total Manufacturing OH (a) $ 1,620,000 DL Hours per Year (b) 180,000 OH / Hours (a / b) $ 9.00
  • 4. + Issues  Zylar’s has limited production capacity if Zylar is awarded the job, one of the standard product production would be reduced.  For current Zylar’s production requires 12,000 DLH per month during 1st quarter.  To fulfill the Lyan’s query, Zylar need to increase 15,000 DLH each month on short notice.  Sales for standard product would be lost for $12,000 and yet there will be no future loss.
  • 5. + The Demand  Lyan needs the custom-designed equipment to increase its bottle- making capacity so that it will not have to buy bottles from an outside supplier.  Lyan Company requires 5,000,000 bottles annually.  Its present equipment has a maximum capacity of 4,500,000 bottles with a directly traceable cash outlay cost of 15 cents per bottle.  Thus, Lyan has had to purchase 500,000 bottles from a supplier at 40 cents each. The new equipment would allow Lyan to manufacture its entire Annual demand for bottles at a direct-material cost savings of 1 cent per bottle. Zylar estimates that Lyan's annual bottle demand will continue to be 5,000,000 bottles over the next five years, the estimated life of the special-purpose equipment
  • 6. + Question#1  Calculate the bid Zylar would submit if it follows its standard pricing policy for special-purpose equipment. BID BASED ON STANDARD PRICING Direct material $256,000 Direct labor (11,000 DLH @ $15) $165,000 Manufacturing overhead (11,000 DLH @ $9) $99,000 Total manufacturing costs $520,000 Pricing Policy, Markup (50% of full cost) $260,000 Standard pricing policy bid $780,000 Answer #1
  • 7. + Question#2  Calculate the minimum bid Zylar would be willing to submit on the Lyan equipment that would result in the same total contribution margin as planned for the first quarter of 20x1. MINIMUM BID Direct material $256,000 Direct labor (11,000 DLH @ $15) $165,000 Variable manufacturing overhead (11,000 DLH@$5.4) $59,400 Opportunity lost of sales (*) $35,200 Minimum bid $515,600 Answer #2
  • 8. + * OPPORTUNITY LOSS OF SALES Selling price per unit of standard product $ 12,000 Variable costs per unit Direct material $ 2,500 Direct labor (250 DLH @ $15) $ 3,750 Variable overhead (250 DLH @ $5.40) $ 1,350 $ 7,600 Contribution Margin PerUnit $ 4,400 Standard product requirements (12,000 DLH x 3) 36,000 DLH Special order requirements 11,000 DLH Total hours required 47,000 DLH Plant capacity per quarter (15,000 DLH x 3) 45,000 DLH Shortage in hours 2,000 DLH Lost unit sales (2,000 DLH ÷ 250 DLH) 8 Lost contribution $ 35,200
  • 9. + Question#3  Suppose Zylar Industries has submitted a bid slightly above the minimum calculated in requirement (2). Upon receiving Zylar's bid, Lyan's assistant purchasing manager telephoned his friend at Tygar Corporation: “Hey Joe, we just got a bid from Zylar Industries on some customized equipment. I think Tygar would stand a good chance of beating it. Stop by the house this evening, and I'll show you the details of Zylar's bid and the specifications on the machine.”  Is Lyan Company's assistant purchasing manager acting ethically?
  • 10. + Answer #3  It is definitely against the code of conduct. Should company would like to gain the competitive price, company shall notify to all bidders at the same time with regard to the specification and its term and condition.  Bidders’ proposal must be treated as confidential document and the document will only be disclosed on the bid opening date.
  • 11. + Recommendation  Zylar has to consider the term and condition of the contract particularly the penalty due to delay delivery because Zylar has limited production capacity and knowing that their employee’s unwilling to work overtime