SlideShare a Scribd company logo
1 of 4
Download to read offline
Works Programme

1.   PREAMBLE:
     The system of getting the works sanctioned through Works Programme each year is a well-known
     and established procedure.

      Investment decisions relating to the creation, acquisition and replacement of assets on the Railways
     are processed through the annual “Works, Machinery and Rolling Stock Programme”.

2. CO-ORDI ATIO :
    Chief Engineer is to co-ordinate with other departments and ensure that the proposals prepared by
    various departments are compiled in the form of Works Programme booklets. The over-all priorities
    of works within the ceiling given by the Board will be fixed by the General Manager in consultation
    with Heads of the Departments.

     However, while in respect of Plan Head 41 – Plant and Machinery, CME is the Nodal Officer and
     CPO is the Nodal Officer for staff quarters. In respect of Plan Head - 29 Road Safety Works - Level
     Crossings, interlocking works are dealt with by CSTE and works relating to manning of unmanned
     level crossings, provision of lifting barriers etc. are dealt with by CE.

3. PREPARATIO OF PRELIMI ARY WORKS PROGRAMME:
    In or about June/July each year, the Railway Board convey to each Railway, the total outlay in
    respect of each Plan Head, within which the Works Programme should be framed by the Railway.
    On receipt of this financial ceiling, Railway Administration is required to take stock of the schemes
    already framed and those under consideration and select for inclusion in the Works Programme
    within the financial ceiling such works as are expected to yield the maximum benefit to the Railway
    and its users.

4. ADVA CE PLA I G:
    Works Programme proposals are submitted for the approval of the Board in 3 stages as under:-

     i)     Advance list of proposals costing Rs.5 crores and above each is normally required to be
            submitted to the Board during June/July for their prior approval for inclusion in PWP.
     ii)    PWP consisting of works costing below Rs.5 crore each and lumpsum cost of works falling
            under GM’s power for sanction are normally due in Board’s Office during August.
     iii)   FWP : Such of those works included in PWP and approved by Board are submitted after
            Works Programme meeting with Board, which are normally due during
            November/December.


5. TARGET DATE FOR SUBMISSIO OF PROPOSALS:
    The target dates for receipt of proposals from the Divisions, sponsoring PHODs and processing the
    same for Works Programme are circulated to all concerned in such a manner that the Preliminary
    Works Programme of the following year is submitted to the Railway Board by first week of
    September or such earlier date as may be laid down by the Board.

     Proper financial appraisal of each of the work is required to be given in the Preliminary Works
     Programme together with the comments of the FA & CAO.




                                               Page 1 of 4
6. SPO SORI G OF PROPOSALS:
     The proposals from the Divisions for inclusion in the Works Programme should emanate from the
     sponsoring departments, which depending on the nature of proposal, inter-alia, will
     (a) arrange to obtain the estimated cost from Sr.DEN, Sr.DSTE, Sr.DME, Sr.DEE concerned,
     (b) have the proposals concurred in by Sr.DAO and obtain approval of DRM for inclusion in the
         PWP.

7. SELECTIO OF THE PROPOSAL FOR WORKS PROGRAMME :

    While selecting proposals, it should be kept in view that these proposals are financially viable,
    provide adequate returns, remove operational bottlenecks and/or are essentially required for
    providing/upgrading rail users' amenities and provide staff satisfaction.

    For prioritising various proposals, requests from people's representatives ( MPs and MLAs), various
    Rail Users' Committees such as ZRUCC, DRUCC etc. and Rail Users' Associations, Central and
    State Governments, Local Administrative Bodies, Gram Panchayats etc. should be considered.

    Instructions issued vide various Inspection Notes of Board's Officials, GM, PHODs and other
    Railway Officers should be given adequate attention.

9. THE MA      ER I WHICH THE PROPOSALS ARE TO BE SUBMITTED:

    With a view to avoiding above mentioned short-comings/deficiencies and for the purpose of framing
    a self-contained proposal in a proper manner, it is advised that the following aspects be kept in view
    while formulating the proposals:-

    i) The proposals for works costing above Rs.5 crores each which require Board’s prior approval for
       its inclusion in the PWP, should be framed and submitted to the Head Quarter's office with
       associated account’s concurrence/observations well in advance as per the schedule laid down by
       CE's office each year. Generally the vetted proposals mooted by the Division should reach the
       respective PHODs by the middle of May each year.

       These proposals, after examination and approval by the respective PHODs and vetting by FA &
       CAO should reach CE’s office by first week of June. This time schedule has been framed to
       make adequate room for getting Board’s prior approval for inclusion of the proposals of this
                                                                                                          st
       category in the Works Programme which is required to be submitted to the Board’s office by 1
       week of September each year.

    ii) As regards to proposals costing below Rs.5 crores each, which require Board’s acceptance for
        inclusion in the Works Programme, the time schedule for receipt of the same in the CE’s office,
        duly concurred in by Head Quarters finance, is middle of August. The time schedule needs to be
        followed truthfully at all levels.

    iii) While framing the proposals, it is very necessary that the field verification is carried out by the
        proposal framing authority and that the proposals are well thought of. It is very important that the
        plans are prepared and the estimated cost is worked out based on detailed field assessment,
        technical plans, proper layout, realistic assessment of quantity of works etc. and only then the
        proposals are processed for inclusion in Works Programme.

    iv) While the abstract estimate forms a part of the proposal, it is of utmost importance to ensure that
       the scope of works and the cost aspects are given due consideration so that there is no large
       variation in the cost in the detailed estimate vis-Ă -vis the abstract estimate. The Board have
       expressed their serious concern in some cases where there had been wide variation in the


                                               Page 2 of 4
anticipated cost shown at the time of sanctioning the proposals and that at the time of execution
       of works.

    v) Apart from this, planning with involvement of all concerned departments will obviate frequent
       change of scope of work and avoid introduction of large number of material modifications, which
       are undesirable features and need to be controlled.

    vi) Justification: All proposals should have proper justification supported by necessary drawings.

    vii) Costing: While working out the cost, in addition to giving the overall Department-wise break
       up, details of cost should also be furnished. Provision made towards Departmental and General
                                                                                                 st
       charges should not exceed the limits prescribed. Cost as likely to prevail on 1 April of
       Programme year may be assessed to avoid any revision of cost while sanctioning detailed
       estimates.

    viii) Efforts should be made to complete the on going works as expeditiously as possible so as to
       reduce their throw forward liability. New works that are essentially required need only be
       proposed. Divisions should indicate their priority in respect of works emanating from them.

    ix) Departmental Heads at HQ’s are required to critically scrutinise the proposals received from the
       Divisions with regard to its need, competing demands from other Divisions and limited
       availability of funds and priorities of the works and forward such of these proposals with
       modifications as found necessary to FA & CAO for concurrence endorsing a copy to CPDE.
       Prior to this, the various costs of sub-estimates of other Departments are to be got certified
       through them.

       They are also required to indicate priorities for works in respective Plan Heads. Cost of proposals
       sponsored at Head Quarter’s level should be obtained from CE/CAO/CEE/ CSTE/CME, as
       concerned, by the sponsoring PHODs and the same forwarded to FA & CAO for concurrence.

    x) The controlling PHOD at HQ should also arrange to reply any query raised by FA &CAO as
       expeditiously as possible in consultation with other Departments, where necessary, and obtain
       Finance concurrence. Final proposal as concurred in by FA & CAO may be sent to CPDE in
       time.

    xi) Details of costs (latest sanctioned/updated cost) , expenditure etc. of all works which are likely to
       appear as a Work in Progress in the Programme Year shall be furnished in the proforma as may
       be prescribed. In addition, progress of works in descriptive/quantitative terms should also be
       furnished. Any bottleneck /problem faced in progressing the works should also be brought out.


10. DELEGATIO OF POWERS :
    The Board have delegated powers to GM for sanctioning works costing not more than Rs.100 lakhs
    each under PH-4200 and M&P items costing not more than Rs. 10 lakhs each, provided that the total
    lump sum provision made in the budget for such works is not exceeded. Latest delegation of powers
    can be seen from the latest delegations issued from time to time.

11. OUT-OF-TUR PROPOSAL:
     After the Pink Book is circulated and Budget Grant is communicated to the Railways by the Board,
     sometimes, during the year, occasion arises when a very urgent work is required to be taken up for
     execution which cannot pend for the regular Works Programme for the next year. In such cases, the
     proposals are mooted on out-of-turn basis with the finance concurrence and GM's sanction or with
     the sanction of the Board, as the case may be, depending on the anticipated cost of the work. In
     terms of the extant rules, as obtaining now, out-of-turn proposals costing upto Rs. 100 lakhs each in
     respect of line capacity works can be sanctioned by GM. As regards works falling under different
                                               Page 3 of 4
Plan Heads, GM's power is limited upto Rs.100 to 200 lakhs each for sanction on out-of-turn basis.
     However, GM is empowered to sanction out of turn works subject to the provision that the funds
     required for such works as provided in the sanctioned budget for works in these categories are not
     exceeded.
11.1 Such out-of-turn sanctions by GM are subject to budgetary ceiling limit of Rs.6 crores in a financial
     year provided that the sanctioned budget (other than lump sum ) for works in these categories is not
     exceeded and also provided norms fixed for completion of works under different Plan Heads are
     followed. The out-of-turn proposals are also required to be formulated in the same manner as
     mentioned earlier.
11.2 Board's sanction is required in respect of works costing more than the above limits for our-of-turn
     sanction.
12. GE ERAL:
      An important requirement for effective investment planing is the realistic estimation of the project
      cost. Full details of the scheme must be worked out and detailed plans and estimate duly prepared.
      In the case of yard remodelling, line capacity works, goods shed facilities and important buildings,
      the estimate should be based on plans approved and signed by the concerned department who
      should scrutinise the plan to avoid the need for making any substantial modification in the required
      facility at a subsequent stage (Para 604 E).
12.1 All proposals costing Rs.100 Lakhs and above each should be worked out comprehensively and sent
      to the Board along with other details of (i.) the technical features, (ii.) cost break up, (iii.) benefit
      expected to accrue, (iv.) financial implication.). A sketch map of each proposal should also be sent.
      The Railway should clearly bring out the purpose of each scheme and confirm that the proposal
      meets the objective fully and that the scope and cost of the project have been arrived at after the
      fullest possible investigation including assessment of the financial implications. After the schemes
      have been scrutinized by the Board, the Railway is advised of the acceptance, with or without any
      modifications for inclusion in the Works Programme. ( Para 607 E)
12.2 While the sanctioned works costing more than Rs.50 lakhs each find places in the Pink Book, those
      costing above Rs.30 Lakhs and below Rs. 50 Lakhs each are included in the Railway's LAW Book
      after sanction by the Board.
12.3 Works once introduced, through Works Programme (including Track Renewal Programme) and
      taken up after the estimates have been sanctioned by the competent authority, should continue to be
      included every year till they are finally completed, except in cases where the works have reached
      the completion stage and where funds required, if meagre, could be found by re-appropriation.

13 FI AL WORKS PROGRAMME:
    After having examined the individual Railway’s programme and discussions with the General
    Managers, the Railway Board decide the works which should be undertaken during the following
    year and which should be included in the final Works Programme. The Zonal Railway then modify
    their Preliminary Works Programme, if any, as a result of the Board’s decision and send their Final
    Works Programme to the Railway Board by the stipulated date. ( Para 623 E)

14 CO CLUSIO :
    In view of the what has been brought out in the foregoing paragraphs, it is advised that utmost care
    be taken in framing the Works Programme proposals, taking into consideration of all aspects and
    judicious decision in prioritising the works Plan Headwise. The proposals need to be self-contained,
    well though of, supported by adequate justification defining the scope of work fully and based on
    detailed field assessment, technical plans, proper layout, realistic assessment of quantity of works
    and estimated cost for the best investment planning. Works in progress also need a very careful
    consideration in respect of projection of requirement of fund based on actual progress and its
    priority. It is also equally necessary to ensure that the planning of proposals is started well in
    advance so that the really essential and important proposals are not missed. For this purpose the time
    schedule laid down need to be truthfully followed.


                                                 Page 4 of 4

More Related Content

What's hot

Manpower planning on Indian Railways
Manpower planning on Indian RailwaysManpower planning on Indian Railways
Manpower planning on Indian RailwaysMohandas Poonthiyil
 
Workshop accounts (indian railways)
Workshop accounts (indian railways)Workshop accounts (indian railways)
Workshop accounts (indian railways)Nageswara Rao M
 
Railways control over expenditure and classification of revenue expenditure
Railways control over expenditure and classification of revenue expenditureRailways control over expenditure and classification of revenue expenditure
Railways control over expenditure and classification of revenue expenditureNageswara Rao M
 
Control over expenditure in Indian Railways
Control over expenditure in Indian RailwaysControl over expenditure in Indian Railways
Control over expenditure in Indian RailwaysNageswara Rao M
 
Pass presentation 2017 ppt
Pass presentation  2017 pptPass presentation  2017 ppt
Pass presentation 2017 pptMohandas Poonthiyil
 
Indian railways financial accounts, audit inspection & cash imprest
Indian railways financial accounts, audit inspection & cash imprestIndian railways financial accounts, audit inspection & cash imprest
Indian railways financial accounts, audit inspection & cash imprestNageswara Rao M
 
project report on water supply works under supervision of indian railways
project report on water supply works under supervision of indian railwaysproject report on water supply works under supervision of indian railways
project report on water supply works under supervision of indian railwaysDevesh Chaurasia
 
Audit objections draft para & audit para in Indian Railways
Audit objections draft para & audit para in Indian RailwaysAudit objections draft para & audit para in Indian Railways
Audit objections draft para & audit para in Indian RailwaysNageswara Rao M
 
Summer training report coach care new Delhi rkgit
Summer training report coach care new Delhi rkgitSummer training report coach care new Delhi rkgit
Summer training report coach care new Delhi rkgitItnesh Kumar
 
railway_plant_layout
railway_plant_layoutrailway_plant_layout
railway_plant_layoutRajshree Tiwari
 
Classification of expenditure recent changes 07.01.2021
Classification of expenditure   recent changes 07.01.2021Classification of expenditure   recent changes 07.01.2021
Classification of expenditure recent changes 07.01.2021Nageswara Rao M
 
Railway zones of India
Railway zones of IndiaRailway zones of India
Railway zones of IndiaHarminder Singh
 
Indian railways workshop accounts
Indian railways workshop accountsIndian railways workshop accounts
Indian railways workshop accountsNageswara Rao M
 
Various types of gates, their important components
Various types of gates, their important componentsVarious types of gates, their important components
Various types of gates, their important componentsIEI GSC
 
inspection of gates of Dam
inspection of gates of Daminspection of gates of Dam
inspection of gates of DamTushar Dholakia
 
RAILWAY CLASSIFICATION OF EXPENDITURE RULES
RAILWAY CLASSIFICATION OF EXPENDITURE RULESRAILWAY CLASSIFICATION OF EXPENDITURE RULES
RAILWAY CLASSIFICATION OF EXPENDITURE RULESNageswara Rao M
 
Railway Training Report
Railway Training ReportRailway Training Report
Railway Training ReportVishal Singh
 
Project Report on railway workshop Jhansi
Project Report on railway workshop JhansiProject Report on railway workshop Jhansi
Project Report on railway workshop JhansiVirendra Kumar Gautam
 

What's hot (20)

Manpower planning on Indian Railways
Manpower planning on Indian RailwaysManpower planning on Indian Railways
Manpower planning on Indian Railways
 
Workshop accounts (indian railways)
Workshop accounts (indian railways)Workshop accounts (indian railways)
Workshop accounts (indian railways)
 
Railways control over expenditure and classification of revenue expenditure
Railways control over expenditure and classification of revenue expenditureRailways control over expenditure and classification of revenue expenditure
Railways control over expenditure and classification of revenue expenditure
 
Control over expenditure in Indian Railways
Control over expenditure in Indian RailwaysControl over expenditure in Indian Railways
Control over expenditure in Indian Railways
 
Pass presentation 2017 ppt
Pass presentation  2017 pptPass presentation  2017 ppt
Pass presentation 2017 ppt
 
Railway Siding
Railway SidingRailway Siding
Railway Siding
 
Indian railways financial accounts, audit inspection & cash imprest
Indian railways financial accounts, audit inspection & cash imprestIndian railways financial accounts, audit inspection & cash imprest
Indian railways financial accounts, audit inspection & cash imprest
 
Railway Audit.ppt
Railway Audit.pptRailway Audit.ppt
Railway Audit.ppt
 
project report on water supply works under supervision of indian railways
project report on water supply works under supervision of indian railwaysproject report on water supply works under supervision of indian railways
project report on water supply works under supervision of indian railways
 
Audit objections draft para & audit para in Indian Railways
Audit objections draft para & audit para in Indian RailwaysAudit objections draft para & audit para in Indian Railways
Audit objections draft para & audit para in Indian Railways
 
Summer training report coach care new Delhi rkgit
Summer training report coach care new Delhi rkgitSummer training report coach care new Delhi rkgit
Summer training report coach care new Delhi rkgit
 
railway_plant_layout
railway_plant_layoutrailway_plant_layout
railway_plant_layout
 
Classification of expenditure recent changes 07.01.2021
Classification of expenditure   recent changes 07.01.2021Classification of expenditure   recent changes 07.01.2021
Classification of expenditure recent changes 07.01.2021
 
Railway zones of India
Railway zones of IndiaRailway zones of India
Railway zones of India
 
Indian railways workshop accounts
Indian railways workshop accountsIndian railways workshop accounts
Indian railways workshop accounts
 
Various types of gates, their important components
Various types of gates, their important componentsVarious types of gates, their important components
Various types of gates, their important components
 
inspection of gates of Dam
inspection of gates of Daminspection of gates of Dam
inspection of gates of Dam
 
RAILWAY CLASSIFICATION OF EXPENDITURE RULES
RAILWAY CLASSIFICATION OF EXPENDITURE RULESRAILWAY CLASSIFICATION OF EXPENDITURE RULES
RAILWAY CLASSIFICATION OF EXPENDITURE RULES
 
Railway Training Report
Railway Training ReportRailway Training Report
Railway Training Report
 
Project Report on railway workshop Jhansi
Project Report on railway workshop JhansiProject Report on railway workshop Jhansi
Project Report on railway workshop Jhansi
 

Similar to Works programme

Rolling Stock Programme for locomotives-SK.pdf
Rolling Stock Programme for locomotives-SK.pdfRolling Stock Programme for locomotives-SK.pdf
Rolling Stock Programme for locomotives-SK.pdfHARENDRASINGH159221
 
Formulation and Approval of Various Infrastructure Projects
Formulation and Approval of Various Infrastructure ProjectsFormulation and Approval of Various Infrastructure Projects
Formulation and Approval of Various Infrastructure ProjectsGAURAV. H .TANDON
 
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission ProjectsTariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission ProjectsAmitava Nag
 
Navi mumbai metro new
Navi mumbai metro newNavi mumbai metro new
Navi mumbai metro newRashid Kaskar
 
Methodology for DPR & PMC Road works.pdf
Methodology  for DPR & PMC Road works.pdfMethodology  for DPR & PMC Road works.pdf
Methodology for DPR & PMC Road works.pdfWapcosLimited3
 
Csr 2014-khyber-pakhtunkhwa
Csr 2014-khyber-pakhtunkhwaCsr 2014-khyber-pakhtunkhwa
Csr 2014-khyber-pakhtunkhwaIftikhar Mahmood
 
012741
012741012741
012741Majed Com
 
Maaden Exp.
Maaden Exp.Maaden Exp.
Maaden Exp.Zafar Iqbal
 
1217 loc tenders
1217 loc tenders1217 loc tenders
1217 loc tendersAntonio Bove
 
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENTMANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENTTaiwo Okuselu
 
Tariff based competitive bidding for intra state trans. projects
Tariff based competitive bidding for intra state trans. projectsTariff based competitive bidding for intra state trans. projects
Tariff based competitive bidding for intra state trans. projectsAmitava Nag
 
Plastic park scheme Ministry Of Chemical and Fertilizers
Plastic park scheme Ministry Of Chemical and FertilizersPlastic park scheme Ministry Of Chemical and Fertilizers
Plastic park scheme Ministry Of Chemical and FertilizersBakul Haria
 
professional services and value engeneering
professional services and value engeneeringprofessional services and value engeneering
professional services and value engeneeringAbdo Jamous El Jamous
 
Neda contractor performance evaluation system
Neda contractor performance evaluation system Neda contractor performance evaluation system
Neda contractor performance evaluation system Mabelle Gaytano
 
Guidelines for the monitoring officers
Guidelines for the monitoring officersGuidelines for the monitoring officers
Guidelines for the monitoring officershayat alishah
 
CATOs-Opportunities-for-Onshore-Tranmission-final[1]
CATOs-Opportunities-for-Onshore-Tranmission-final[1]CATOs-Opportunities-for-Onshore-Tranmission-final[1]
CATOs-Opportunities-for-Onshore-Tranmission-final[1]Aditi Tulpule
 
Bid Writing Beginners Guide
Bid Writing   Beginners GuideBid Writing   Beginners Guide
Bid Writing Beginners GuideJerry Allen
 

Similar to Works programme (20)

Rolling Stock Programme for locomotives-SK.pdf
Rolling Stock Programme for locomotives-SK.pdfRolling Stock Programme for locomotives-SK.pdf
Rolling Stock Programme for locomotives-SK.pdf
 
Formulation and Approval of Various Infrastructure Projects
Formulation and Approval of Various Infrastructure ProjectsFormulation and Approval of Various Infrastructure Projects
Formulation and Approval of Various Infrastructure Projects
 
workshop
workshopworkshop
workshop
 
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission ProjectsTariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
 
Navi mumbai metro new
Navi mumbai metro newNavi mumbai metro new
Navi mumbai metro new
 
Methodology for DPR & PMC Road works.pdf
Methodology  for DPR & PMC Road works.pdfMethodology  for DPR & PMC Road works.pdf
Methodology for DPR & PMC Road works.pdf
 
Csr 2014-khyber-pakhtunkhwa
Csr 2014-khyber-pakhtunkhwaCsr 2014-khyber-pakhtunkhwa
Csr 2014-khyber-pakhtunkhwa
 
4
44
4
 
Q130302108111
Q130302108111Q130302108111
Q130302108111
 
012741
012741012741
012741
 
Maaden Exp.
Maaden Exp.Maaden Exp.
Maaden Exp.
 
1217 loc tenders
1217 loc tenders1217 loc tenders
1217 loc tenders
 
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENTMANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
 
Tariff based competitive bidding for intra state trans. projects
Tariff based competitive bidding for intra state trans. projectsTariff based competitive bidding for intra state trans. projects
Tariff based competitive bidding for intra state trans. projects
 
Plastic park scheme Ministry Of Chemical and Fertilizers
Plastic park scheme Ministry Of Chemical and FertilizersPlastic park scheme Ministry Of Chemical and Fertilizers
Plastic park scheme Ministry Of Chemical and Fertilizers
 
professional services and value engeneering
professional services and value engeneeringprofessional services and value engeneering
professional services and value engeneering
 
Neda contractor performance evaluation system
Neda contractor performance evaluation system Neda contractor performance evaluation system
Neda contractor performance evaluation system
 
Guidelines for the monitoring officers
Guidelines for the monitoring officersGuidelines for the monitoring officers
Guidelines for the monitoring officers
 
CATOs-Opportunities-for-Onshore-Tranmission-final[1]
CATOs-Opportunities-for-Onshore-Tranmission-final[1]CATOs-Opportunities-for-Onshore-Tranmission-final[1]
CATOs-Opportunities-for-Onshore-Tranmission-final[1]
 
Bid Writing Beginners Guide
Bid Writing   Beginners GuideBid Writing   Beginners Guide
Bid Writing Beginners Guide
 

More from SrinivasaRao Guduru

Basic training on Wabco load sensing device
Basic training on Wabco load sensing deviceBasic training on Wabco load sensing device
Basic training on Wabco load sensing deviceSrinivasaRao Guduru
 
Air springs rdso 2009-cg-cmi-01
Air springs rdso 2009-cg-cmi-01Air springs rdso 2009-cg-cmi-01
Air springs rdso 2009-cg-cmi-01SrinivasaRao Guduru
 
Identification and treatment of bed bugs
Identification and treatment of bed bugsIdentification and treatment of bed bugs
Identification and treatment of bed bugsSrinivasaRao Guduru
 
Introduction handbook on LHB coaches
Introduction handbook on LHB coachesIntroduction handbook on LHB coaches
Introduction handbook on LHB coachesSrinivasaRao Guduru
 
Handbook on works contract management
Handbook on works contract managementHandbook on works contract management
Handbook on works contract managementSrinivasaRao Guduru
 
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01SrinivasaRao Guduru
 
Pamphlet on air suspension system for fiat bogie
Pamphlet on air suspension system for fiat bogiePamphlet on air suspension system for fiat bogie
Pamphlet on air suspension system for fiat bogieSrinivasaRao Guduru
 
Pamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockPamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockSrinivasaRao Guduru
 
Handbook on maintenance of air brake system in lhb coaches (ftil type)
Handbook on maintenance of air brake system in lhb coaches (ftil type)Handbook on maintenance of air brake system in lhb coaches (ftil type)
Handbook on maintenance of air brake system in lhb coaches (ftil type)SrinivasaRao Guduru
 
Report on standardisation of enroute carriage watering system
Report on standardisation of enroute carriage watering systemReport on standardisation of enroute carriage watering system
Report on standardisation of enroute carriage watering systemSrinivasaRao Guduru
 
Draft handbook on linen management
Draft handbook on linen managementDraft handbook on linen management
Draft handbook on linen managementSrinivasaRao Guduru
 
Handbook on wheel slide protection device (wsp)
Handbook on wheel slide protection device (wsp)Handbook on wheel slide protection device (wsp)
Handbook on wheel slide protection device (wsp)SrinivasaRao Guduru
 
Pamphlet on air suspension system fitted on hybrid coaches
Pamphlet on air suspension system fitted on hybrid coachesPamphlet on air suspension system fitted on hybrid coaches
Pamphlet on air suspension system fitted on hybrid coachesSrinivasaRao Guduru
 
Standardisation of enroute carriage watering system
Standardisation of enroute carriage watering systemStandardisation of enroute carriage watering system
Standardisation of enroute carriage watering systemSrinivasaRao Guduru
 
Handbook on maintenance of digital axle counter
Handbook on maintenance of digital axle counterHandbook on maintenance of digital axle counter
Handbook on maintenance of digital axle counterSrinivasaRao Guduru
 
Report on running room facilities
Report on running room facilitiesReport on running room facilities
Report on running room facilitiesSrinivasaRao Guduru
 
GM weight loss diet management plan
GM weight loss diet management plan GM weight loss diet management plan
GM weight loss diet management plan SrinivasaRao Guduru
 
Maintenace manual for wagons
Maintenace manual for wagonsMaintenace manual for wagons
Maintenace manual for wagonsSrinivasaRao Guduru
 
Maintenace of passenger emergency alarm system of coaching stock
Maintenace of passenger emergency alarm system of coaching stockMaintenace of passenger emergency alarm system of coaching stock
Maintenace of passenger emergency alarm system of coaching stockSrinivasaRao Guduru
 

More from SrinivasaRao Guduru (20)

Basic training on Wabco load sensing device
Basic training on Wabco load sensing deviceBasic training on Wabco load sensing device
Basic training on Wabco load sensing device
 
Air springs rdso 2009-cg-cmi-01
Air springs rdso 2009-cg-cmi-01Air springs rdso 2009-cg-cmi-01
Air springs rdso 2009-cg-cmi-01
 
Identification and treatment of bed bugs
Identification and treatment of bed bugsIdentification and treatment of bed bugs
Identification and treatment of bed bugs
 
Introduction handbook on LHB coaches
Introduction handbook on LHB coachesIntroduction handbook on LHB coaches
Introduction handbook on LHB coaches
 
Handbook on works contract management
Handbook on works contract managementHandbook on works contract management
Handbook on works contract management
 
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
 
Pamphlet on air suspension system for fiat bogie
Pamphlet on air suspension system for fiat bogiePamphlet on air suspension system for fiat bogie
Pamphlet on air suspension system for fiat bogie
 
Pamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockPamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stock
 
Handbook on maintenance of air brake system in lhb coaches (ftil type)
Handbook on maintenance of air brake system in lhb coaches (ftil type)Handbook on maintenance of air brake system in lhb coaches (ftil type)
Handbook on maintenance of air brake system in lhb coaches (ftil type)
 
Report on standardisation of enroute carriage watering system
Report on standardisation of enroute carriage watering systemReport on standardisation of enroute carriage watering system
Report on standardisation of enroute carriage watering system
 
Bio toilets presentation
Bio toilets presentation Bio toilets presentation
Bio toilets presentation
 
Draft handbook on linen management
Draft handbook on linen managementDraft handbook on linen management
Draft handbook on linen management
 
Handbook on wheel slide protection device (wsp)
Handbook on wheel slide protection device (wsp)Handbook on wheel slide protection device (wsp)
Handbook on wheel slide protection device (wsp)
 
Pamphlet on air suspension system fitted on hybrid coaches
Pamphlet on air suspension system fitted on hybrid coachesPamphlet on air suspension system fitted on hybrid coaches
Pamphlet on air suspension system fitted on hybrid coaches
 
Standardisation of enroute carriage watering system
Standardisation of enroute carriage watering systemStandardisation of enroute carriage watering system
Standardisation of enroute carriage watering system
 
Handbook on maintenance of digital axle counter
Handbook on maintenance of digital axle counterHandbook on maintenance of digital axle counter
Handbook on maintenance of digital axle counter
 
Report on running room facilities
Report on running room facilitiesReport on running room facilities
Report on running room facilities
 
GM weight loss diet management plan
GM weight loss diet management plan GM weight loss diet management plan
GM weight loss diet management plan
 
Maintenace manual for wagons
Maintenace manual for wagonsMaintenace manual for wagons
Maintenace manual for wagons
 
Maintenace of passenger emergency alarm system of coaching stock
Maintenace of passenger emergency alarm system of coaching stockMaintenace of passenger emergency alarm system of coaching stock
Maintenace of passenger emergency alarm system of coaching stock
 

Recently uploaded

Call US đź“ž 9892124323 âś… Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US đź“ž 9892124323 âś… Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US đź“ž 9892124323 âś… Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US đź“ž 9892124323 âś… Kurla Call Girls In Kurla ( Mumbai ) secure servicePooja Nehwal
 
VIP Call Girls in Saharanpur Aarohi 8250192130 Independent Escort Service Sah...
VIP Call Girls in Saharanpur Aarohi 8250192130 Independent Escort Service Sah...VIP Call Girls in Saharanpur Aarohi 8250192130 Independent Escort Service Sah...
VIP Call Girls in Saharanpur Aarohi 8250192130 Independent Escort Service Sah...Suhani Kapoor
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfGale Pooley
 
Log your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignLog your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignHenry Tapper
 
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Roomdivyansh0kumar0
 
Chapter 2.ppt of macroeconomics by mankiw 9th edition
Chapter 2.ppt of macroeconomics by mankiw 9th editionChapter 2.ppt of macroeconomics by mankiw 9th edition
Chapter 2.ppt of macroeconomics by mankiw 9th editionMuhammadHusnain82237
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdfHenry Tapper
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...Call Girls in Nagpur High Profile
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...makika9823
 
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service AizawlVip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawlmakika9823
 
Stock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfStock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfMichael Silva
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...Henry Tapper
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Roomdivyansh0kumar0
 
How Automation is Driving Efficiency Through the Last Mile of Reporting
How Automation is Driving Efficiency Through the Last Mile of ReportingHow Automation is Driving Efficiency Through the Last Mile of Reporting
How Automation is Driving Efficiency Through the Last Mile of ReportingAggregage
 
20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdfAdnet Communications
 
Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Commonwealth
 
Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spiritegoetzinger
 
Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Sapana Sha
 

Recently uploaded (20)

Call US đź“ž 9892124323 âś… Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US đź“ž 9892124323 âś… Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US đź“ž 9892124323 âś… Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US đź“ž 9892124323 âś… Kurla Call Girls In Kurla ( Mumbai ) secure service
 
VIP Call Girls in Saharanpur Aarohi 8250192130 Independent Escort Service Sah...
VIP Call Girls in Saharanpur Aarohi 8250192130 Independent Escort Service Sah...VIP Call Girls in Saharanpur Aarohi 8250192130 Independent Escort Service Sah...
VIP Call Girls in Saharanpur Aarohi 8250192130 Independent Escort Service Sah...
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdf
 
Log your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignLog your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaign
 
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
 
Chapter 2.ppt of macroeconomics by mankiw 9th edition
Chapter 2.ppt of macroeconomics by mankiw 9th editionChapter 2.ppt of macroeconomics by mankiw 9th edition
Chapter 2.ppt of macroeconomics by mankiw 9th edition
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdf
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
 
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service AizawlVip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
 
Stock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfStock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdf
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
 
How Automation is Driving Efficiency Through the Last Mile of Reporting
How Automation is Driving Efficiency Through the Last Mile of ReportingHow Automation is Driving Efficiency Through the Last Mile of Reporting
How Automation is Driving Efficiency Through the Last Mile of Reporting
 
20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf
 
Commercial Bank Economic Capsule - April 2024
Commercial Bank Economic Capsule - April 2024Commercial Bank Economic Capsule - April 2024
Commercial Bank Economic Capsule - April 2024
 
Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]
 
Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spirit
 
Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111
 

Works programme

  • 1. Works Programme 1. PREAMBLE: The system of getting the works sanctioned through Works Programme each year is a well-known and established procedure. Investment decisions relating to the creation, acquisition and replacement of assets on the Railways are processed through the annual “Works, Machinery and Rolling Stock Programme”. 2. CO-ORDI ATIO : Chief Engineer is to co-ordinate with other departments and ensure that the proposals prepared by various departments are compiled in the form of Works Programme booklets. The over-all priorities of works within the ceiling given by the Board will be fixed by the General Manager in consultation with Heads of the Departments. However, while in respect of Plan Head 41 – Plant and Machinery, CME is the Nodal Officer and CPO is the Nodal Officer for staff quarters. In respect of Plan Head - 29 Road Safety Works - Level Crossings, interlocking works are dealt with by CSTE and works relating to manning of unmanned level crossings, provision of lifting barriers etc. are dealt with by CE. 3. PREPARATIO OF PRELIMI ARY WORKS PROGRAMME: In or about June/July each year, the Railway Board convey to each Railway, the total outlay in respect of each Plan Head, within which the Works Programme should be framed by the Railway. On receipt of this financial ceiling, Railway Administration is required to take stock of the schemes already framed and those under consideration and select for inclusion in the Works Programme within the financial ceiling such works as are expected to yield the maximum benefit to the Railway and its users. 4. ADVA CE PLA I G: Works Programme proposals are submitted for the approval of the Board in 3 stages as under:- i) Advance list of proposals costing Rs.5 crores and above each is normally required to be submitted to the Board during June/July for their prior approval for inclusion in PWP. ii) PWP consisting of works costing below Rs.5 crore each and lumpsum cost of works falling under GM’s power for sanction are normally due in Board’s Office during August. iii) FWP : Such of those works included in PWP and approved by Board are submitted after Works Programme meeting with Board, which are normally due during November/December. 5. TARGET DATE FOR SUBMISSIO OF PROPOSALS: The target dates for receipt of proposals from the Divisions, sponsoring PHODs and processing the same for Works Programme are circulated to all concerned in such a manner that the Preliminary Works Programme of the following year is submitted to the Railway Board by first week of September or such earlier date as may be laid down by the Board. Proper financial appraisal of each of the work is required to be given in the Preliminary Works Programme together with the comments of the FA & CAO. Page 1 of 4
  • 2. 6. SPO SORI G OF PROPOSALS: The proposals from the Divisions for inclusion in the Works Programme should emanate from the sponsoring departments, which depending on the nature of proposal, inter-alia, will (a) arrange to obtain the estimated cost from Sr.DEN, Sr.DSTE, Sr.DME, Sr.DEE concerned, (b) have the proposals concurred in by Sr.DAO and obtain approval of DRM for inclusion in the PWP. 7. SELECTIO OF THE PROPOSAL FOR WORKS PROGRAMME : While selecting proposals, it should be kept in view that these proposals are financially viable, provide adequate returns, remove operational bottlenecks and/or are essentially required for providing/upgrading rail users' amenities and provide staff satisfaction. For prioritising various proposals, requests from people's representatives ( MPs and MLAs), various Rail Users' Committees such as ZRUCC, DRUCC etc. and Rail Users' Associations, Central and State Governments, Local Administrative Bodies, Gram Panchayats etc. should be considered. Instructions issued vide various Inspection Notes of Board's Officials, GM, PHODs and other Railway Officers should be given adequate attention. 9. THE MA ER I WHICH THE PROPOSALS ARE TO BE SUBMITTED: With a view to avoiding above mentioned short-comings/deficiencies and for the purpose of framing a self-contained proposal in a proper manner, it is advised that the following aspects be kept in view while formulating the proposals:- i) The proposals for works costing above Rs.5 crores each which require Board’s prior approval for its inclusion in the PWP, should be framed and submitted to the Head Quarter's office with associated account’s concurrence/observations well in advance as per the schedule laid down by CE's office each year. Generally the vetted proposals mooted by the Division should reach the respective PHODs by the middle of May each year. These proposals, after examination and approval by the respective PHODs and vetting by FA & CAO should reach CE’s office by first week of June. This time schedule has been framed to make adequate room for getting Board’s prior approval for inclusion of the proposals of this st category in the Works Programme which is required to be submitted to the Board’s office by 1 week of September each year. ii) As regards to proposals costing below Rs.5 crores each, which require Board’s acceptance for inclusion in the Works Programme, the time schedule for receipt of the same in the CE’s office, duly concurred in by Head Quarters finance, is middle of August. The time schedule needs to be followed truthfully at all levels. iii) While framing the proposals, it is very necessary that the field verification is carried out by the proposal framing authority and that the proposals are well thought of. It is very important that the plans are prepared and the estimated cost is worked out based on detailed field assessment, technical plans, proper layout, realistic assessment of quantity of works etc. and only then the proposals are processed for inclusion in Works Programme. iv) While the abstract estimate forms a part of the proposal, it is of utmost importance to ensure that the scope of works and the cost aspects are given due consideration so that there is no large variation in the cost in the detailed estimate vis-Ă -vis the abstract estimate. The Board have expressed their serious concern in some cases where there had been wide variation in the Page 2 of 4
  • 3. anticipated cost shown at the time of sanctioning the proposals and that at the time of execution of works. v) Apart from this, planning with involvement of all concerned departments will obviate frequent change of scope of work and avoid introduction of large number of material modifications, which are undesirable features and need to be controlled. vi) Justification: All proposals should have proper justification supported by necessary drawings. vii) Costing: While working out the cost, in addition to giving the overall Department-wise break up, details of cost should also be furnished. Provision made towards Departmental and General st charges should not exceed the limits prescribed. Cost as likely to prevail on 1 April of Programme year may be assessed to avoid any revision of cost while sanctioning detailed estimates. viii) Efforts should be made to complete the on going works as expeditiously as possible so as to reduce their throw forward liability. New works that are essentially required need only be proposed. Divisions should indicate their priority in respect of works emanating from them. ix) Departmental Heads at HQ’s are required to critically scrutinise the proposals received from the Divisions with regard to its need, competing demands from other Divisions and limited availability of funds and priorities of the works and forward such of these proposals with modifications as found necessary to FA & CAO for concurrence endorsing a copy to CPDE. Prior to this, the various costs of sub-estimates of other Departments are to be got certified through them. They are also required to indicate priorities for works in respective Plan Heads. Cost of proposals sponsored at Head Quarter’s level should be obtained from CE/CAO/CEE/ CSTE/CME, as concerned, by the sponsoring PHODs and the same forwarded to FA & CAO for concurrence. x) The controlling PHOD at HQ should also arrange to reply any query raised by FA &CAO as expeditiously as possible in consultation with other Departments, where necessary, and obtain Finance concurrence. Final proposal as concurred in by FA & CAO may be sent to CPDE in time. xi) Details of costs (latest sanctioned/updated cost) , expenditure etc. of all works which are likely to appear as a Work in Progress in the Programme Year shall be furnished in the proforma as may be prescribed. In addition, progress of works in descriptive/quantitative terms should also be furnished. Any bottleneck /problem faced in progressing the works should also be brought out. 10. DELEGATIO OF POWERS : The Board have delegated powers to GM for sanctioning works costing not more than Rs.100 lakhs each under PH-4200 and M&P items costing not more than Rs. 10 lakhs each, provided that the total lump sum provision made in the budget for such works is not exceeded. Latest delegation of powers can be seen from the latest delegations issued from time to time. 11. OUT-OF-TUR PROPOSAL: After the Pink Book is circulated and Budget Grant is communicated to the Railways by the Board, sometimes, during the year, occasion arises when a very urgent work is required to be taken up for execution which cannot pend for the regular Works Programme for the next year. In such cases, the proposals are mooted on out-of-turn basis with the finance concurrence and GM's sanction or with the sanction of the Board, as the case may be, depending on the anticipated cost of the work. In terms of the extant rules, as obtaining now, out-of-turn proposals costing upto Rs. 100 lakhs each in respect of line capacity works can be sanctioned by GM. As regards works falling under different Page 3 of 4
  • 4. Plan Heads, GM's power is limited upto Rs.100 to 200 lakhs each for sanction on out-of-turn basis. However, GM is empowered to sanction out of turn works subject to the provision that the funds required for such works as provided in the sanctioned budget for works in these categories are not exceeded. 11.1 Such out-of-turn sanctions by GM are subject to budgetary ceiling limit of Rs.6 crores in a financial year provided that the sanctioned budget (other than lump sum ) for works in these categories is not exceeded and also provided norms fixed for completion of works under different Plan Heads are followed. The out-of-turn proposals are also required to be formulated in the same manner as mentioned earlier. 11.2 Board's sanction is required in respect of works costing more than the above limits for our-of-turn sanction. 12. GE ERAL: An important requirement for effective investment planing is the realistic estimation of the project cost. Full details of the scheme must be worked out and detailed plans and estimate duly prepared. In the case of yard remodelling, line capacity works, goods shed facilities and important buildings, the estimate should be based on plans approved and signed by the concerned department who should scrutinise the plan to avoid the need for making any substantial modification in the required facility at a subsequent stage (Para 604 E). 12.1 All proposals costing Rs.100 Lakhs and above each should be worked out comprehensively and sent to the Board along with other details of (i.) the technical features, (ii.) cost break up, (iii.) benefit expected to accrue, (iv.) financial implication.). A sketch map of each proposal should also be sent. The Railway should clearly bring out the purpose of each scheme and confirm that the proposal meets the objective fully and that the scope and cost of the project have been arrived at after the fullest possible investigation including assessment of the financial implications. After the schemes have been scrutinized by the Board, the Railway is advised of the acceptance, with or without any modifications for inclusion in the Works Programme. ( Para 607 E) 12.2 While the sanctioned works costing more than Rs.50 lakhs each find places in the Pink Book, those costing above Rs.30 Lakhs and below Rs. 50 Lakhs each are included in the Railway's LAW Book after sanction by the Board. 12.3 Works once introduced, through Works Programme (including Track Renewal Programme) and taken up after the estimates have been sanctioned by the competent authority, should continue to be included every year till they are finally completed, except in cases where the works have reached the completion stage and where funds required, if meagre, could be found by re-appropriation. 13 FI AL WORKS PROGRAMME: After having examined the individual Railway’s programme and discussions with the General Managers, the Railway Board decide the works which should be undertaken during the following year and which should be included in the final Works Programme. The Zonal Railway then modify their Preliminary Works Programme, if any, as a result of the Board’s decision and send their Final Works Programme to the Railway Board by the stipulated date. ( Para 623 E) 14 CO CLUSIO : In view of the what has been brought out in the foregoing paragraphs, it is advised that utmost care be taken in framing the Works Programme proposals, taking into consideration of all aspects and judicious decision in prioritising the works Plan Headwise. The proposals need to be self-contained, well though of, supported by adequate justification defining the scope of work fully and based on detailed field assessment, technical plans, proper layout, realistic assessment of quantity of works and estimated cost for the best investment planning. Works in progress also need a very careful consideration in respect of projection of requirement of fund based on actual progress and its priority. It is also equally necessary to ensure that the planning of proposals is started well in advance so that the really essential and important proposals are not missed. For this purpose the time schedule laid down need to be truthfully followed. Page 4 of 4