Exepron Cri$cal	Chain	Project	Management 

adopts the scientific approach of elegant simplicity. 

Keep it simple.
Finish-to-Start Task dependency
Start-to-finish, partial finish-to-start, finish-to-finish, start-to-start or any other 

combination looks sophisticated but this is a recipe for chaos and confusion.
Occam’s Razor: William of Occam
The principle states that one should not make more assumptions than the minimum needed
Occam's razor helps us to "shave off" those concepts, variables or constructs that are not really needed to explain the
phenomenon. By doing so, developing a model will become much easier, and there is less chance of introducing
inconsistencies, ambiguities and redundancies.
Tasks durations consisting of hands-on touch-time estimates.
Task Duration
Hands-on Touch-Time
Interference
Variation & Uncertainty
1287 – 1347
Start-to-finish, partial finish-to-start, finish-to-finish, start-to-start or any combination
looks sophisticated but it is a recipe for chaos and confusion.
Task Durations:

Finish-to-Start & Touch-Time
Combined with variation absorbing, tactical BUFFERS located within the project network.
Elements working together: making Uncertainty and Variability visible and predictable.
Simplicity avoids the chaos of over sophistication.
“Precision cannot be created where it cannot exist”
	
Project Management is the ability to manage Uncertainty and Variability.
Task durations are not precise, discrete or absolute, they are non-discreet numbers, continuous and measured. 

Task durations are essentially a best guess at a future point in time of what might occur when executed.


Planning is a point in time, which could be 6 month or more ahead of the Tasks actual execution.
Sophistication does not mean
precision.
It probably means chaos and
confusion.
The more opportunity for permutations
means permutations will explode and
significantly reduce system
controllability.
Future conditions are unknown and non-discrete
The conditions at a future date, when the task duration will be subject to many influences:
Resource availably, Resource skill, Material delivery performance, Administrative capability, Weather, Vendor
availability, Customer approval, Government regulation, out come of Inspections, Material conditions, etc. etc. the
list is endless.
Again “Precision cannot be created where it cannot exist”.
Change is here to Stay
www.Exepron.com
Immunize your projects from
Uncertainty and Variability:
email: CustomerSupport@Exepron.com

Why every task needs a successor.

  • 1.
    SIMPLICITY
 CARRIED TO ANEXTREME BECOMES 
 ELEGANCE Jon Franklin
  • 2.
    EVERYTHING SHOULD BEMADE AS SIMPLE AS POSSIBLE, BUT NOT SIMPLER Albert Einstein Exepron Cri$cal Chain Project Management 
 adopts the scientific approach of elegant simplicity. 
 Keep it simple. Finish-to-Start Task dependency Start-to-finish, partial finish-to-start, finish-to-finish, start-to-start or any other 
 combination looks sophisticated but this is a recipe for chaos and confusion.
  • 3.
    Occam’s Razor: Williamof Occam The principle states that one should not make more assumptions than the minimum needed Occam's razor helps us to "shave off" those concepts, variables or constructs that are not really needed to explain the phenomenon. By doing so, developing a model will become much easier, and there is less chance of introducing inconsistencies, ambiguities and redundancies. Tasks durations consisting of hands-on touch-time estimates. Task Duration Hands-on Touch-Time Interference Variation & Uncertainty 1287 – 1347 Start-to-finish, partial finish-to-start, finish-to-finish, start-to-start or any combination looks sophisticated but it is a recipe for chaos and confusion.
  • 4.
    Task Durations:
 Finish-to-Start &Touch-Time Combined with variation absorbing, tactical BUFFERS located within the project network. Elements working together: making Uncertainty and Variability visible and predictable. Simplicity avoids the chaos of over sophistication.
  • 5.
    “Precision cannot becreated where it cannot exist” Project Management is the ability to manage Uncertainty and Variability. Task durations are not precise, discrete or absolute, they are non-discreet numbers, continuous and measured. 
 Task durations are essentially a best guess at a future point in time of what might occur when executed. 
 Planning is a point in time, which could be 6 month or more ahead of the Tasks actual execution. Sophistication does not mean precision. It probably means chaos and confusion. The more opportunity for permutations means permutations will explode and significantly reduce system controllability.
  • 6.
    Future conditions areunknown and non-discrete The conditions at a future date, when the task duration will be subject to many influences: Resource availably, Resource skill, Material delivery performance, Administrative capability, Weather, Vendor availability, Customer approval, Government regulation, out come of Inspections, Material conditions, etc. etc. the list is endless. Again “Precision cannot be created where it cannot exist”. Change is here to Stay
  • 7.