3. TEMPORARY CONSTRUCTION FACILITIES
(TCF) @ JAFURAH
Project Quality Index (%)
Month PROCUREMENT CONSTRUCTION OVERALL
January 2023 95.22 98.55 97.72
February 2023 100.00 78.14 82.78
March 2023 100.00 95.83 96.68
April 2023 100.00 95.38 96.70
May 2023 100.00 91.30 93.65
June 2023 100.00 91.30 93.65
July 2023 100.00 95.85 96.79
August 2023 100 93.49 94.71
September 2023 100 93.09 94.54
October 2023 100 94.75 95.58
November 2023 100 93.06 94.19
December 2023 100 90.77 92.33
4. TEMPORARY CONSTRUCTION FACILITIES
(TCF) @ JAFURAH
Company NCRs Status
This Week Cumulative
S. No. ITEMS
Total
Issued
Open Closed
Total
Issued
Open Closed
1 Minor 0 0 0 5 4 1
2 Moderate 0 0 0 0 0 0
3 Major 0 0 0 0 0 0
Total 0 0 0 5 4 1
5. TEMPORARY CONSTRUCTION FACILITIES
(TCF) @ JAFURAH
LBEs Status
This Week Cumulative
S. No. ITEMS
Total
Issued
Open Closed
Total
Issued
Open Closed
1 Standard Violation 0 0 0 89 06 83
2 Pro Active Notification 0 0 0 92 00 92
3 General Comments 0 0 0 01 00 01
Total 0 0 0 182 06 176