- 33. Investigate why this area was prone to water deficits and how this affected the locals
- 53. Plan… how we can help resolve the problem
- 68. Project Budget Donor Contribution Items Quantities Unit Price/ Cost Total RMB Cement 30 tons 1 Ton = RMB 320 (Guide) 9600 Pipe (75 mm) 1500 m 1m = 1.52kg 1Kg = RMB14.5 (Lanzhou ) 33,060
- 69. Pipe (32 mm) 700m 1m = 0.32kg 1Kg = RMB14.5 (Lanzhou ) 3,248 Pipe (25mm) 900m 1m= 0.21kg 1Kg = RMB14.5 (Lanzhou ) 2,740.5 Iron Bar 1 ton RMB 3500 (Xining) 3,500 Water Design Expert 1 RMB 2000 2,000 Skilled Cement Workers 4 1 = RMB 50 per day for 30 days 6,000
- 70. Connections Unknown App. RMB 2,200 2,200 Transportation Fee Unknown App. RMB 4,000 4,000 Administrative Fee Unknown App. RMB 1500 1,500 Labor Machine Fee Unknown App. RMB 2000 2,000 Total (Donor Contribution) 69,848.5