The Energy Institute delivered a letter to the Ministry of Industry and Trade regarding the development of the Implementation Plan for Vietnam's Power Development Plan VIII (PDP 8). The letter notes that more time is needed to develop the Implementation Plan, as the PDP 8 only outlines targets for 2030 and 2050, while the Implementation Plan requires detailed goals and projections over the entire planning period. Developing these specific goals requires significant data collection and human resources. As a result, the Energy Institute concludes it is not possible to issue the Implementation Plan by June as requested, and recommends pushing the deadline back to August or October to allow sufficient time for proper development of the plan.