SlideShare a Scribd company logo
VIETNAM - Power Development Planning VIII (“PDP8”) - Vietnam
Government’s plan to De-carbonize the Country - what you must know:
Question#1. What impact is PDP8 likely to have on the country’s efforts to decarbonize the
economy?
Answer#1:
The draft Power Development Planning VIII (“PDP8”) reinforces the Vietnam Government’s current
view on prioritizing renewable energy sources to minimize negative impacts caused by electricity
production on the environment. Importation of fuels (coal, LNG) are encouraged as a way to diversify
the country’s primary energy sources, and the same goes for the establishment of transmission and
distribution grid links with China, Laos and Cambodia in order to maximize each country’s energy
potential. Imported electricity sources from neighboring countries are to be considered as prioritized
projects because imported electricity will reduce environmental impact compared to domestic
production.
As of 2020, the country’s total generation capacity is about 69.3 gigawatt (GW), including 16.5 GW of
solar power (approx. 24% of the total capacity) and 0.6 GW of wind power. More than 50% Vietnam’s
electricity generation came from coal in 2020. Vietnam’s reliance on coal-fired power remains heavily
to meet rapidly increasing electricity demand. Hydroelectric generation is also significant as the country
is home to a number of large rivers. Non-hydro renewable sources such as wind and solar made up 5%
of Vietnam’s electricity generation in 2020. Under the draft PDP 8, Vietnam plans to increase solar
capacity to 18.6 GW and wind capacity to 18 GW by 2030.
Question#2. Does PDP8 target specific regions of the country? Are these regions that are more
likely to be impacted by the transition to a low carbon economy?
Answer#2:
Yes, one of the most notable differences between the Draft PDP 8 and Revised PDP 7 (the latest official
national power development planning) is the level of power demand between the North and the South.
According to PDP8, the proportion of commercial electricity in the North will gradually increase from
42.4% in 2020 to 45.8% in 2045, while the South will decrease its proportion from 47.4% in 2020 to
43.6% by 2045. By 2040, the North’s commercial electricity demand will start to exceed that of the
South. As a result, this will significantly affect the strategy in PDP8 to develop the transmission grid
and generation sources (including RE sources) to meet the demand.
The draft PDP 8 is oriented to focus on the development of transmission grid of at least 220KV to solve
overcapacity issues that has been occurring in recent years. As to grid development, in the period of
2021-2030, MOIT sees the need to build 86 GVA with a capacity of 500kV per station and nearly
13,000 km of DLZ. From 2031-2045, an additional construction of 103 GVA with capacity of 500kV
and nearly 6000 stations is required. The 220kV power grid needs construction of 95 GVA, nearly
21,000 km DMZ and 108 GVA, more than 4000 km NE. Total investment capital for electricity
development in the period 2021-2030 is roughly USD 128.3 billion USD, of which: USD 95.4 billion
for the power sources, USD 32.9 billion for the grids. The average structure of capital investment shall
be 74% / 26%.
The draft PDP8 appears to concern a surging oversupply of solar power in 2030 in many regions, such
as the Central Highlands (estimated 1,500 MW but registered 5,500 MW), the South Central (estimated
5,200 MW but registered 11,600 MW), or the Southern (estimated 9,200 MW but registered 14,800
MW). The wind power shares the same situation as the registered capacity exceeds normal estimated
capacity in Central Highlands (estimated 4,000 MW but registered 10,000 MW) and Southern
(estimated 6800 MW but registered 17,000 MW). Accordingly, the draft PDP8 must solve this
unbalance to ensure the sustainable development of the renewable energy sources in Vietnam. It is
expected that future policy on renewable energy will base on auction rather than FIT.
For example, below is the draft policy for solar power projects. In late January 2021, the Ministry of
Industry and Trade (“MOIT”) issued the draft Decision of the Prime Minister guiding the selection of
investors implementing solar power projects under the bidding mechanism (“the Draft”). According to
the Draft, the Decision would be applicable to projects with grids connected directly to the national
power network. The Ministry of Industry and Trade shall coordinate with the Electricity of Vietnam
and the People’s Committees of localities to organize the formulation and approval of the renewable
energy power source development plan for a period of 5 years and every 2 years to serve as a basis for
the bidding system. In addition, every 02 years, the Ministry of Industry and Trade shall issue a Price
Framework for electricity generation in order to determine the ceiling price for bidding to select
investors of solar power projects with COD in the next 02 years. The plan for development of renewable
energy power sources for a period of 5 years shall include the total capacity scale for each renewable
energy power source in the 5-year period, the total capacity scale for each renewable energy power
source for each load region (8 regions) and a list of transmission lines and substations (220 kV at least)
to be put into operation for a period of 5 years. The 02-year plan shall have similar content but for a 2-
year period only and shall be more provincial specific.
Question#3. Were issues of economic, racial, and gender equity considered in the development
of PDP8?
Answer#3:
Yes, any policy of the Government must consider these issues but it is very challenging to identify
whether they are well reflected into the policy including PDP8. This is a very broad and difficult
question.
Question#4. Was there a debate amongst political leaders about the costs and benefits of
PDP8?
Answer#4: Yes, of course. It appears that the new Government now has different views and priorities
than the former and as a result the PDP8 must be revised to reflect such priorities.
As you may know, in late March 2021, the very first draft of PDP8 PM Decision (“Draft Decision”)
has been published through unofficial sources (i.e. not through the Ministry of Industry and Trade
(MOIT)’s website). Such PM Draft Decision was planned to be signed off at the end of March during
the last days of Prime Minister Nguyen Xuan Phuc’s administration, but it was delayed as the hand-
over to new administration was already under way. It appeared that the investors and LNG-to-power
projects in this first PM Draft Decision were scaled down comparing to those in the PDP8 proposal
published by Ministry of Industry and Trade (MOIT) earlier.
On 23 April 2021, the Deputy Prime Minister (DPM) Le Van Thanh directed a Government’s meeting
on the PDP8 and concluded that, among others, PDP8 must be (i) updated with qualifications for
prioritized projects, and (ii) revised to reasonably review and allocate development of power sources,
especially LNG-to-power projects in PDP8 in order to ensure the competition, optimization on
development of power system. DPM asked the MOIT to careful review and digest opinion from EVN
in its official letter No. 1645/EVN-KH dated 2 April 2021. Finally, the DPM required the MOIT to
submit the updated PDP8 proposal prior to 15 June 2021.
Unfortunately, due to Covid-19 situation and heavy workload on updating the PDP8 proposal, MOIT
failed to submit a revised proposal to the Government for consideration. On 17 June 2021, the MOIT
Minister arranged a press meeting to update the PDP8 progress and planned to submit the revised PDP8
proposal to the Government within June 2021. So far, based on our intel, the MOIT is still reworking
its draft and PDP8 is expected to be approved COB this year ideally.
Question#5. What role did various stakeholders (e.g., business, not-for-profits) take in
advocating for or against PDP8 or trying to influence its development?
Answer#5:
Yes, there are many stakeholders here, e.g., EVN, local developers, business communities (such as
Chambers and VBF) and state authorities. However, please kindly note that the draft PDP8 is mainly
drafted by the Energy Institution (NB: an institution under EVN until it was taken over by MOIT since
2010). The MOIT was collecting opinion from all stakeholders for the draft PDP8 made by the Energy
Institution. It is worth noting that the opinion from EVN is always critically important as it (including
its affiliates and subsidiaries) still remains the position of a monopoly wholesaler in the market. The
new Government requested the MOIT to revisit EVN’s opinion for revising the current draft PDP8.
Question#6. Which key stakeholders were in favour of PDP8? How did they organize and
influence decision making?
Answer#6:
Yes, it is very challenging to answer black or white on this question. PDP8 is the prioritized policy of
the Government for the energy sector. Thus, there is always a favorable trend for this policy to come
out soon. We however do note that there are different views on the contents of the PDP8, but not an
issue of support or opposition.
Question#7. Which key stakeholders were against PDP8? How did they organize and influence
decision making? Were there specific measures to address their concerns?
Answer#7:
Yes, it is very challenging to answer a black or white question. PDP8 is the prioritized policy of the
Government for the energy sector. Thus, there is always a favorable trend for this policy to come out
soon. We however do note that there are different views on the contents of the PDP8, but not an issue
of support or opposition.
Question#8. Has PDP8 been well-received by the public?
Answer#8:
Yes, it has been well received by the public. However, the foreign invested business communities still
have some concerns, among others, over the current PDP8:
• No clear plan for variable renewable energy in the technology mix. PDP8 must ensure
Vietnam planning remains cutting-edge to include full representation of variability and assessing power
system reliability.
• No plan for nuclear power.
• Need to construct a regulatory and permitting environment that attracts private sector
investment in clean energy generation and energy efficiency.
• Need a clear policy to ensure EVN to share the market risks: e.g., a bankable (take or pay)
power purchase agreement with generators.
• Need to halt further development of coal based projects: it is recommended to suspend the
approval of any new coal thermal power plants and conducting a strategic review of those that are
already approved but which do not have financing or power purchase agreements.
• Need to develop a flexible transmission network in view of the market orientation and
increased variable renewable energy.
• Need to build schemes to address the uncertainties: from fuel prices to demand growth and
oversupply and curtailment.
***
For more information on the above, please do not hesitate to contact the author Dr. Oliver Massmann
under omassmann@duanemorris.com. Dr. Oliver Massmann is the General Director of Duane Morris
Vietnam LLC, Member to the Supervisory Board of PetroVietnam Insurance JSC and the only foreign
lawyer presenting in Vietnamese language to members of the NATIONAL ASSEMBLY OF
VIETNAM.
 VIETNAM - Power Development Planning VIII (“PDP8”)  - Vietnam Government’s plan to De-carbonize the Country - what you must know:

More Related Content

What's hot

Lo hoi 2
Lo hoi 2Lo hoi 2
THE EU ENERGY POLICY WHAT IS MAIN PURPOSE OF EU ENERGY STRATEGY?
THE EU ENERGY POLICY WHAT IS MAIN PURPOSE OF EU ENERGY STRATEGY?THE EU ENERGY POLICY WHAT IS MAIN PURPOSE OF EU ENERGY STRATEGY?
THE EU ENERGY POLICY WHAT IS MAIN PURPOSE OF EU ENERGY STRATEGY?
İzmir University of Economics
 
Vietnam M&A Research Report 2019
Vietnam M&A Research Report 2019Vietnam M&A Research Report 2019
Vietnam M&A Research Report 2019
FiinGroup JSC
 
OP Brexit (Edited 1).pptx
OP Brexit (Edited 1).pptxOP Brexit (Edited 1).pptx
OP Brexit (Edited 1).pptx
PiyushSingh973960
 
Trắc nghiệm môn nguyên lý kế toán (có đa)
Trắc nghiệm môn nguyên lý kế toán (có đa)Trắc nghiệm môn nguyên lý kế toán (có đa)
Trắc nghiệm môn nguyên lý kế toán (có đa)Học Huỳnh Bá
 
Câu hỏi định tính vật lý
Câu hỏi định tính vật lýCâu hỏi định tính vật lý
Câu hỏi định tính vật lý
huuchinhld
 
GIAI TICH HE THONG DIEN NANG CAO - PHẦN MỞ ĐẦU CÁC VẤN ĐỀ CƠ BẢN
GIAI TICH HE THONG DIEN NANG CAO - PHẦN MỞ ĐẦU CÁC VẤN ĐỀ CƠ BẢNGIAI TICH HE THONG DIEN NANG CAO - PHẦN MỞ ĐẦU CÁC VẤN ĐỀ CƠ BẢN
GIAI TICH HE THONG DIEN NANG CAO - PHẦN MỞ ĐẦU CÁC VẤN ĐỀ CƠ BẢN
Đinh Công Thiện Taydo University
 
Bài giảng Năng lượng tái tạo-Đại học SPKT TP.HCM
Bài giảng Năng lượng tái tạo-Đại học SPKT TP.HCMBài giảng Năng lượng tái tạo-Đại học SPKT TP.HCM
Bài giảng Năng lượng tái tạo-Đại học SPKT TP.HCM
Tuong Do
 
EV CHARGING WITH IOT
EV CHARGING WITH IOTEV CHARGING WITH IOT
EV CHARGING WITH IOT
Sumant Kumar
 
Battery Circular Economy approaches for redesign, reuse and regulation
Battery Circular Economy approaches for redesign, reuse and regulationBattery Circular Economy approaches for redesign, reuse and regulation
Battery Circular Economy approaches for redesign, reuse and regulation
OlgaRodrguezLargo
 
Bai giang may dien
Bai giang may dienBai giang may dien
Bai giang may dien
Lợi Tấn
 
Jean-Marc Jancovici, un décroissant pronucléaire en campagne 18/03/2022
Jean-Marc Jancovici, un décroissant pronucléaire en campagne 18/03/2022Jean-Marc Jancovici, un décroissant pronucléaire en campagne 18/03/2022
Jean-Marc Jancovici, un décroissant pronucléaire en campagne 18/03/2022
Joëlle Leconte
 
Public secondary schools email list
Public secondary schools email listPublic secondary schools email list
Public secondary schools email list
lmartin01
 
KINH TẾ HỌC VĨ MÔ - Chương 5 CHÍNH SÁCH TÀI CHÍNH VÀ NGOẠI THƯƠNG
KINH TẾ HỌC VĨ MÔ - Chương 5 CHÍNH SÁCH TÀI CHÍNH VÀ NGOẠI THƯƠNGKINH TẾ HỌC VĨ MÔ - Chương 5 CHÍNH SÁCH TÀI CHÍNH VÀ NGOẠI THƯƠNG
KINH TẾ HỌC VĨ MÔ - Chương 5 CHÍNH SÁCH TÀI CHÍNH VÀ NGOẠI THƯƠNG
Digiword Ha Noi
 
Dầu mỏ khí thiên nhiên
Dầu mỏ khí thiên nhiênDầu mỏ khí thiên nhiên
Dầu mỏ khí thiên nhiên
Nguyễn Nhân
 
EEC โอกาสทางเศรษฐกิจของประเทศไทย
EEC โอกาสทางเศรษฐกิจของประเทศไทยEEC โอกาสทางเศรษฐกิจของประเทศไทย
EEC โอกาสทางเศรษฐกิจของประเทศไทย
Klangpanya
 
Hệ thống máy nghiền than trong nhà máy nhiệt điện Uông Bí, HAY
Hệ thống máy nghiền than trong nhà máy nhiệt điện Uông Bí, HAYHệ thống máy nghiền than trong nhà máy nhiệt điện Uông Bí, HAY
Hệ thống máy nghiền than trong nhà máy nhiệt điện Uông Bí, HAY
Dịch Vụ Viết Bài Trọn Gói ZALO 0917193864
 
Luận văn: Hệ thống bài tập phần Cơ sở lý thuyết cấu tạo chất, 9đ
Luận văn: Hệ thống bài tập phần Cơ sở lý thuyết cấu tạo chất, 9đLuận văn: Hệ thống bài tập phần Cơ sở lý thuyết cấu tạo chất, 9đ
Luận văn: Hệ thống bài tập phần Cơ sở lý thuyết cấu tạo chất, 9đ
Dịch vụ viết bài trọn gói ZALO: 0909232620
 
Tổ chức opec
Tổ chức opecTổ chức opec
Tổ chức opec
Nguyên Phạm
 
VIETNAM – WIND AND SOLAR PROJECTS: HOW TO GET DEALS DONE
VIETNAM – WIND AND SOLAR PROJECTS:  HOW TO GET DEALS DONEVIETNAM – WIND AND SOLAR PROJECTS:  HOW TO GET DEALS DONE
VIETNAM – WIND AND SOLAR PROJECTS: HOW TO GET DEALS DONE
Dr. Oliver Massmann
 

What's hot (20)

Lo hoi 2
Lo hoi 2Lo hoi 2
Lo hoi 2
 
THE EU ENERGY POLICY WHAT IS MAIN PURPOSE OF EU ENERGY STRATEGY?
THE EU ENERGY POLICY WHAT IS MAIN PURPOSE OF EU ENERGY STRATEGY?THE EU ENERGY POLICY WHAT IS MAIN PURPOSE OF EU ENERGY STRATEGY?
THE EU ENERGY POLICY WHAT IS MAIN PURPOSE OF EU ENERGY STRATEGY?
 
Vietnam M&A Research Report 2019
Vietnam M&A Research Report 2019Vietnam M&A Research Report 2019
Vietnam M&A Research Report 2019
 
OP Brexit (Edited 1).pptx
OP Brexit (Edited 1).pptxOP Brexit (Edited 1).pptx
OP Brexit (Edited 1).pptx
 
Trắc nghiệm môn nguyên lý kế toán (có đa)
Trắc nghiệm môn nguyên lý kế toán (có đa)Trắc nghiệm môn nguyên lý kế toán (có đa)
Trắc nghiệm môn nguyên lý kế toán (có đa)
 
Câu hỏi định tính vật lý
Câu hỏi định tính vật lýCâu hỏi định tính vật lý
Câu hỏi định tính vật lý
 
GIAI TICH HE THONG DIEN NANG CAO - PHẦN MỞ ĐẦU CÁC VẤN ĐỀ CƠ BẢN
GIAI TICH HE THONG DIEN NANG CAO - PHẦN MỞ ĐẦU CÁC VẤN ĐỀ CƠ BẢNGIAI TICH HE THONG DIEN NANG CAO - PHẦN MỞ ĐẦU CÁC VẤN ĐỀ CƠ BẢN
GIAI TICH HE THONG DIEN NANG CAO - PHẦN MỞ ĐẦU CÁC VẤN ĐỀ CƠ BẢN
 
Bài giảng Năng lượng tái tạo-Đại học SPKT TP.HCM
Bài giảng Năng lượng tái tạo-Đại học SPKT TP.HCMBài giảng Năng lượng tái tạo-Đại học SPKT TP.HCM
Bài giảng Năng lượng tái tạo-Đại học SPKT TP.HCM
 
EV CHARGING WITH IOT
EV CHARGING WITH IOTEV CHARGING WITH IOT
EV CHARGING WITH IOT
 
Battery Circular Economy approaches for redesign, reuse and regulation
Battery Circular Economy approaches for redesign, reuse and regulationBattery Circular Economy approaches for redesign, reuse and regulation
Battery Circular Economy approaches for redesign, reuse and regulation
 
Bai giang may dien
Bai giang may dienBai giang may dien
Bai giang may dien
 
Jean-Marc Jancovici, un décroissant pronucléaire en campagne 18/03/2022
Jean-Marc Jancovici, un décroissant pronucléaire en campagne 18/03/2022Jean-Marc Jancovici, un décroissant pronucléaire en campagne 18/03/2022
Jean-Marc Jancovici, un décroissant pronucléaire en campagne 18/03/2022
 
Public secondary schools email list
Public secondary schools email listPublic secondary schools email list
Public secondary schools email list
 
KINH TẾ HỌC VĨ MÔ - Chương 5 CHÍNH SÁCH TÀI CHÍNH VÀ NGOẠI THƯƠNG
KINH TẾ HỌC VĨ MÔ - Chương 5 CHÍNH SÁCH TÀI CHÍNH VÀ NGOẠI THƯƠNGKINH TẾ HỌC VĨ MÔ - Chương 5 CHÍNH SÁCH TÀI CHÍNH VÀ NGOẠI THƯƠNG
KINH TẾ HỌC VĨ MÔ - Chương 5 CHÍNH SÁCH TÀI CHÍNH VÀ NGOẠI THƯƠNG
 
Dầu mỏ khí thiên nhiên
Dầu mỏ khí thiên nhiênDầu mỏ khí thiên nhiên
Dầu mỏ khí thiên nhiên
 
EEC โอกาสทางเศรษฐกิจของประเทศไทย
EEC โอกาสทางเศรษฐกิจของประเทศไทยEEC โอกาสทางเศรษฐกิจของประเทศไทย
EEC โอกาสทางเศรษฐกิจของประเทศไทย
 
Hệ thống máy nghiền than trong nhà máy nhiệt điện Uông Bí, HAY
Hệ thống máy nghiền than trong nhà máy nhiệt điện Uông Bí, HAYHệ thống máy nghiền than trong nhà máy nhiệt điện Uông Bí, HAY
Hệ thống máy nghiền than trong nhà máy nhiệt điện Uông Bí, HAY
 
Luận văn: Hệ thống bài tập phần Cơ sở lý thuyết cấu tạo chất, 9đ
Luận văn: Hệ thống bài tập phần Cơ sở lý thuyết cấu tạo chất, 9đLuận văn: Hệ thống bài tập phần Cơ sở lý thuyết cấu tạo chất, 9đ
Luận văn: Hệ thống bài tập phần Cơ sở lý thuyết cấu tạo chất, 9đ
 
Tổ chức opec
Tổ chức opecTổ chức opec
Tổ chức opec
 
VIETNAM – WIND AND SOLAR PROJECTS: HOW TO GET DEALS DONE
VIETNAM – WIND AND SOLAR PROJECTS:  HOW TO GET DEALS DONEVIETNAM – WIND AND SOLAR PROJECTS:  HOW TO GET DEALS DONE
VIETNAM – WIND AND SOLAR PROJECTS: HOW TO GET DEALS DONE
 

Similar to VIETNAM - Power Development Planning VIII (“PDP8”) - Vietnam Government’s plan to De-carbonize the Country - what you must know:

OECD-ENV Vietnam questionnaire key points
OECD-ENV Vietnam questionnaire key pointsOECD-ENV Vietnam questionnaire key points
OECD-ENV Vietnam questionnaire key points
OECD Environment
 
VIETNAM – POWER ENERGY – TRANSITION AND PDP8 – HOW THE EVFTA AND THE EVIPA AN...
VIETNAM – POWER ENERGY – TRANSITION AND PDP8 – HOW THE EVFTA AND THE EVIPA AN...VIETNAM – POWER ENERGY – TRANSITION AND PDP8 – HOW THE EVFTA AND THE EVIPA AN...
VIETNAM – POWER ENERGY – TRANSITION AND PDP8 – HOW THE EVFTA AND THE EVIPA AN...
Dr. Oliver Massmann
 
INVESTING IN LIQUEFIED NATURAL GAS (LNG) IN VIETNAM
INVESTING IN LIQUEFIED NATURAL GAS (LNG) IN VIETNAM INVESTING IN LIQUEFIED NATURAL GAS (LNG) IN VIETNAM
INVESTING IN LIQUEFIED NATURAL GAS (LNG) IN VIETNAM
Dr. Oliver Massmann
 
Vietnam – Power Development Plan 8 – Estimated Issuance Date
Vietnam – Power Development Plan 8 – Estimated Issuance DateVietnam – Power Development Plan 8 – Estimated Issuance Date
Vietnam – Power Development Plan 8 – Estimated Issuance Date
Dr. Oliver Massmann
 
VIETNAM – LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
VIETNAM –  LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8VIETNAM –  LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
VIETNAM – LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
Dr. Oliver Massmann
 
VIETNAM – POWER SECTOR REFORM COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
VIETNAM – POWER SECTOR REFORM  COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...VIETNAM – POWER SECTOR REFORM  COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
VIETNAM – POWER SECTOR REFORM COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
Dr. Oliver Massmann
 
VIETNAM – RENEWABLE ENERGIES - Identifying the Amazing Development - what you...
VIETNAM – RENEWABLE ENERGIES - Identifying the Amazing Development - what you...VIETNAM – RENEWABLE ENERGIES - Identifying the Amazing Development - what you...
VIETNAM – RENEWABLE ENERGIES - Identifying the Amazing Development - what you...
Dr. Oliver Massmann
 
VIETNAM – ENERGY – LNG AND POWER DEVELOPMENT PLAN 8 - PDP 8 – LATEST UPDATES
VIETNAM – ENERGY – LNG AND POWER DEVELOPMENT PLAN 8 - PDP 8 – LATEST UPDATESVIETNAM – ENERGY – LNG AND POWER DEVELOPMENT PLAN 8 - PDP 8 – LATEST UPDATES
VIETNAM – ENERGY – LNG AND POWER DEVELOPMENT PLAN 8 - PDP 8 – LATEST UPDATES
Dr. Oliver Massmann
 
VIETNAM – APPRAISAL OF WIND POWER PROJECTS SUSPENDED
VIETNAM – APPRAISAL OF WIND POWER PROJECTS SUSPENDEDVIETNAM – APPRAISAL OF WIND POWER PROJECTS SUSPENDED
VIETNAM – APPRAISAL OF WIND POWER PROJECTS SUSPENDED
Dr. Oliver Massmann
 
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
Dr. Oliver Massmann
 
Vietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key HighlightsVietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key Highlights
Dr. Oliver Massmann
 
JAPAN (6)
JAPAN (6)JAPAN (6)
JAPAN (6)
Nitin Maurya
 
Future Watch: Taiwan energy policy shift and its future aspects
Future Watch: Taiwan energy policy shift and its future aspectsFuture Watch: Taiwan energy policy shift and its future aspects
Future Watch: Taiwan energy policy shift and its future aspects
Team Finland Future Watch
 
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Power Development Plan 8 - ...
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Power Development Plan 8 - ...Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Power Development Plan 8 - ...
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Power Development Plan 8 - ...
Dr. Oliver Massmann
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Dr. Oliver Massmann
 
VIETNAM - ENERGY - Power Development Master Plan 8 - Latest Update
VIETNAM - ENERGY - Power Development Master Plan 8 - Latest UpdateVIETNAM - ENERGY - Power Development Master Plan 8 - Latest Update
VIETNAM - ENERGY - Power Development Master Plan 8 - Latest Update
Dr. Oliver Massmann
 
Lawyer in Vietnam VIETNAM – THE DRAFT NATIONAL ELECTRICITY DEVELOPMENT PLANNI...
Lawyer in Vietnam VIETNAM – THE DRAFT NATIONAL ELECTRICITY DEVELOPMENT PLANNI...Lawyer in Vietnam VIETNAM – THE DRAFT NATIONAL ELECTRICITY DEVELOPMENT PLANNI...
Lawyer in Vietnam VIETNAM – THE DRAFT NATIONAL ELECTRICITY DEVELOPMENT PLANNI...
Dr. Oliver Massmann
 
OECD CEFIM Indonesia Questionnaire - Key points
OECD CEFIM Indonesia Questionnaire - Key pointsOECD CEFIM Indonesia Questionnaire - Key points
OECD CEFIM Indonesia Questionnaire - Key points
OECD Environment
 
Vietnam – Green Growth – 2015
Vietnam – Green Growth – 2015Vietnam – Green Growth – 2015
Vietnam – Green Growth – 2015
Dr. Oliver Massmann
 
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – WHY YOU SHOULD INVEST IN RE...
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – WHY YOU SHOULD INVEST IN RE...LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – WHY YOU SHOULD INVEST IN RE...
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – WHY YOU SHOULD INVEST IN RE...
Dr. Oliver Massmann
 

Similar to VIETNAM - Power Development Planning VIII (“PDP8”) - Vietnam Government’s plan to De-carbonize the Country - what you must know: (20)

OECD-ENV Vietnam questionnaire key points
OECD-ENV Vietnam questionnaire key pointsOECD-ENV Vietnam questionnaire key points
OECD-ENV Vietnam questionnaire key points
 
VIETNAM – POWER ENERGY – TRANSITION AND PDP8 – HOW THE EVFTA AND THE EVIPA AN...
VIETNAM – POWER ENERGY – TRANSITION AND PDP8 – HOW THE EVFTA AND THE EVIPA AN...VIETNAM – POWER ENERGY – TRANSITION AND PDP8 – HOW THE EVFTA AND THE EVIPA AN...
VIETNAM – POWER ENERGY – TRANSITION AND PDP8 – HOW THE EVFTA AND THE EVIPA AN...
 
INVESTING IN LIQUEFIED NATURAL GAS (LNG) IN VIETNAM
INVESTING IN LIQUEFIED NATURAL GAS (LNG) IN VIETNAM INVESTING IN LIQUEFIED NATURAL GAS (LNG) IN VIETNAM
INVESTING IN LIQUEFIED NATURAL GAS (LNG) IN VIETNAM
 
Vietnam – Power Development Plan 8 – Estimated Issuance Date
Vietnam – Power Development Plan 8 – Estimated Issuance DateVietnam – Power Development Plan 8 – Estimated Issuance Date
Vietnam – Power Development Plan 8 – Estimated Issuance Date
 
VIETNAM – LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
VIETNAM –  LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8VIETNAM –  LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
VIETNAM – LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
 
VIETNAM – POWER SECTOR REFORM COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
VIETNAM – POWER SECTOR REFORM  COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...VIETNAM – POWER SECTOR REFORM  COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
VIETNAM – POWER SECTOR REFORM COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
 
VIETNAM – RENEWABLE ENERGIES - Identifying the Amazing Development - what you...
VIETNAM – RENEWABLE ENERGIES - Identifying the Amazing Development - what you...VIETNAM – RENEWABLE ENERGIES - Identifying the Amazing Development - what you...
VIETNAM – RENEWABLE ENERGIES - Identifying the Amazing Development - what you...
 
VIETNAM – ENERGY – LNG AND POWER DEVELOPMENT PLAN 8 - PDP 8 – LATEST UPDATES
VIETNAM – ENERGY – LNG AND POWER DEVELOPMENT PLAN 8 - PDP 8 – LATEST UPDATESVIETNAM – ENERGY – LNG AND POWER DEVELOPMENT PLAN 8 - PDP 8 – LATEST UPDATES
VIETNAM – ENERGY – LNG AND POWER DEVELOPMENT PLAN 8 - PDP 8 – LATEST UPDATES
 
VIETNAM – APPRAISAL OF WIND POWER PROJECTS SUSPENDED
VIETNAM – APPRAISAL OF WIND POWER PROJECTS SUSPENDEDVIETNAM – APPRAISAL OF WIND POWER PROJECTS SUSPENDED
VIETNAM – APPRAISAL OF WIND POWER PROJECTS SUSPENDED
 
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
 
Vietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key HighlightsVietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key Highlights
 
JAPAN (6)
JAPAN (6)JAPAN (6)
JAPAN (6)
 
Future Watch: Taiwan energy policy shift and its future aspects
Future Watch: Taiwan energy policy shift and its future aspectsFuture Watch: Taiwan energy policy shift and its future aspects
Future Watch: Taiwan energy policy shift and its future aspects
 
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Power Development Plan 8 - ...
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Power Development Plan 8 - ...Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Power Development Plan 8 - ...
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Power Development Plan 8 - ...
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key Highlights
 
VIETNAM - ENERGY - Power Development Master Plan 8 - Latest Update
VIETNAM - ENERGY - Power Development Master Plan 8 - Latest UpdateVIETNAM - ENERGY - Power Development Master Plan 8 - Latest Update
VIETNAM - ENERGY - Power Development Master Plan 8 - Latest Update
 
Lawyer in Vietnam VIETNAM – THE DRAFT NATIONAL ELECTRICITY DEVELOPMENT PLANNI...
Lawyer in Vietnam VIETNAM – THE DRAFT NATIONAL ELECTRICITY DEVELOPMENT PLANNI...Lawyer in Vietnam VIETNAM – THE DRAFT NATIONAL ELECTRICITY DEVELOPMENT PLANNI...
Lawyer in Vietnam VIETNAM – THE DRAFT NATIONAL ELECTRICITY DEVELOPMENT PLANNI...
 
OECD CEFIM Indonesia Questionnaire - Key points
OECD CEFIM Indonesia Questionnaire - Key pointsOECD CEFIM Indonesia Questionnaire - Key points
OECD CEFIM Indonesia Questionnaire - Key points
 
Vietnam – Green Growth – 2015
Vietnam – Green Growth – 2015Vietnam – Green Growth – 2015
Vietnam – Green Growth – 2015
 
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – WHY YOU SHOULD INVEST IN RE...
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – WHY YOU SHOULD INVEST IN RE...LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – WHY YOU SHOULD INVEST IN RE...
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – WHY YOU SHOULD INVEST IN RE...
 

More from Dr. Oliver Massmann

Data Privacy Laws in Vietnam - The Basics & Guidance For Practical Handling
Data Privacy Laws in Vietnam - The Basics & Guidance For Practical HandlingData Privacy Laws in Vietnam - The Basics & Guidance For Practical Handling
Data Privacy Laws in Vietnam - The Basics & Guidance For Practical Handling
Dr. Oliver Massmann
 
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
Dr. Oliver Massmann
 
YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
Dr. Oliver Massmann
 
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
Dr. Oliver Massmann
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Dr. Oliver Massmann
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
Dr. Oliver Massmann
 
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Dr. Oliver Massmann
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Dr. Oliver Massmann
 
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Dr. Oliver Massmann
 
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
Dr. Oliver Massmann
 
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
Dr. Oliver Massmann
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Dr. Oliver Massmann
 
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
Dr. Oliver Massmann
 
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
Dr. Oliver Massmann
 
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Dr. Oliver Massmann
 
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
Dr. Oliver Massmann
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Dr. Oliver Massmann
 
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Dr. Oliver Massmann
 
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
Dr. Oliver Massmann
 
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
Dr. Oliver Massmann
 

More from Dr. Oliver Massmann (20)

Data Privacy Laws in Vietnam - The Basics & Guidance For Practical Handling
Data Privacy Laws in Vietnam - The Basics & Guidance For Practical HandlingData Privacy Laws in Vietnam - The Basics & Guidance For Practical Handling
Data Privacy Laws in Vietnam - The Basics & Guidance For Practical Handling
 
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
 
YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
 
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
 
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
 
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
 
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
 
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
 
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
 
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
 
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
 
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
 

Recently uploaded

原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
osenwakm
 
Patenting_Innovations_in_3D_Printing_Prosthetics.pptx
Patenting_Innovations_in_3D_Printing_Prosthetics.pptxPatenting_Innovations_in_3D_Printing_Prosthetics.pptx
Patenting_Innovations_in_3D_Printing_Prosthetics.pptx
ssuser559494
 
Search Warrants for NH Law Enforcement Officers
Search Warrants for NH Law Enforcement OfficersSearch Warrants for NH Law Enforcement Officers
Search Warrants for NH Law Enforcement Officers
RichardTheberge
 
V.-SENTHIL-BALAJI-SLP-C-8939-8940-2023-SC-Judgment-07-August-2023.pdf
V.-SENTHIL-BALAJI-SLP-C-8939-8940-2023-SC-Judgment-07-August-2023.pdfV.-SENTHIL-BALAJI-SLP-C-8939-8940-2023-SC-Judgment-07-August-2023.pdf
V.-SENTHIL-BALAJI-SLP-C-8939-8940-2023-SC-Judgment-07-August-2023.pdf
bhavenpr
 
What are the common challenges faced by women lawyers working in the legal pr...
What are the common challenges faced by women lawyers working in the legal pr...What are the common challenges faced by women lawyers working in the legal pr...
What are the common challenges faced by women lawyers working in the legal pr...
lawyersonia
 
Energizing Communities, Fostering Growth, Sustaining Futures
Energizing Communities, Fostering Growth, Sustaining FuturesEnergizing Communities, Fostering Growth, Sustaining Futures
Energizing Communities, Fostering Growth, Sustaining Futures
USDAReapgrants.com
 
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Syed Muhammad Humza Hussain
 
The Work Permit for Self-Employed Persons in Italy
The Work Permit for Self-Employed Persons in ItalyThe Work Permit for Self-Employed Persons in Italy
The Work Permit for Self-Employed Persons in Italy
BridgeWest.eu
 
Tax Law Notes on taxation law tax law for 10th sem
Tax Law Notes on taxation law tax law for 10th semTax Law Notes on taxation law tax law for 10th sem
Tax Law Notes on taxation law tax law for 10th sem
azizurrahaman17
 
From Promise to Practice. Implementing AI in Legal Environments
From Promise to Practice. Implementing AI in Legal EnvironmentsFrom Promise to Practice. Implementing AI in Legal Environments
From Promise to Practice. Implementing AI in Legal Environments
ssusera97a2f
 
Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976
PelayoGilbert
 
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
osenwakm
 
Sangyun Lee, 'Why Korea's Merger Control Occasionally Fails: A Public Choice ...
Sangyun Lee, 'Why Korea's Merger Control Occasionally Fails: A Public Choice ...Sangyun Lee, 'Why Korea's Merger Control Occasionally Fails: A Public Choice ...
Sangyun Lee, 'Why Korea's Merger Control Occasionally Fails: A Public Choice ...
Sangyun Lee
 
fnaf lore.pptx ...................................
fnaf lore.pptx ...................................fnaf lore.pptx ...................................
fnaf lore.pptx ...................................
20jcoello
 
Matthew Professional CV experienced Government Liaison
Matthew Professional CV experienced Government LiaisonMatthew Professional CV experienced Government Liaison
Matthew Professional CV experienced Government Liaison
MattGardner52
 
Genocide in International Criminal Law.pptx
Genocide in International Criminal Law.pptxGenocide in International Criminal Law.pptx
Genocide in International Criminal Law.pptx
MasoudZamani13
 
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Massimo Talia
 
Lifting the Corporate Veil. Power Point Presentation
Lifting the Corporate Veil. Power Point PresentationLifting the Corporate Veil. Power Point Presentation
Lifting the Corporate Veil. Power Point Presentation
seri bangash
 
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证如何办理
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证如何办理一比一原版(Lincoln毕业证)新西兰林肯大学毕业证如何办理
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证如何办理
gjsma0ep
 
Presentation (1).pptx Human rights of LGBTQ people in India, constitutional a...
Presentation (1).pptx Human rights of LGBTQ people in India, constitutional a...Presentation (1).pptx Human rights of LGBTQ people in India, constitutional a...
Presentation (1).pptx Human rights of LGBTQ people in India, constitutional a...
SKshi
 

Recently uploaded (20)

原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
 
Patenting_Innovations_in_3D_Printing_Prosthetics.pptx
Patenting_Innovations_in_3D_Printing_Prosthetics.pptxPatenting_Innovations_in_3D_Printing_Prosthetics.pptx
Patenting_Innovations_in_3D_Printing_Prosthetics.pptx
 
Search Warrants for NH Law Enforcement Officers
Search Warrants for NH Law Enforcement OfficersSearch Warrants for NH Law Enforcement Officers
Search Warrants for NH Law Enforcement Officers
 
V.-SENTHIL-BALAJI-SLP-C-8939-8940-2023-SC-Judgment-07-August-2023.pdf
V.-SENTHIL-BALAJI-SLP-C-8939-8940-2023-SC-Judgment-07-August-2023.pdfV.-SENTHIL-BALAJI-SLP-C-8939-8940-2023-SC-Judgment-07-August-2023.pdf
V.-SENTHIL-BALAJI-SLP-C-8939-8940-2023-SC-Judgment-07-August-2023.pdf
 
What are the common challenges faced by women lawyers working in the legal pr...
What are the common challenges faced by women lawyers working in the legal pr...What are the common challenges faced by women lawyers working in the legal pr...
What are the common challenges faced by women lawyers working in the legal pr...
 
Energizing Communities, Fostering Growth, Sustaining Futures
Energizing Communities, Fostering Growth, Sustaining FuturesEnergizing Communities, Fostering Growth, Sustaining Futures
Energizing Communities, Fostering Growth, Sustaining Futures
 
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
 
The Work Permit for Self-Employed Persons in Italy
The Work Permit for Self-Employed Persons in ItalyThe Work Permit for Self-Employed Persons in Italy
The Work Permit for Self-Employed Persons in Italy
 
Tax Law Notes on taxation law tax law for 10th sem
Tax Law Notes on taxation law tax law for 10th semTax Law Notes on taxation law tax law for 10th sem
Tax Law Notes on taxation law tax law for 10th sem
 
From Promise to Practice. Implementing AI in Legal Environments
From Promise to Practice. Implementing AI in Legal EnvironmentsFrom Promise to Practice. Implementing AI in Legal Environments
From Promise to Practice. Implementing AI in Legal Environments
 
Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976
 
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
 
Sangyun Lee, 'Why Korea's Merger Control Occasionally Fails: A Public Choice ...
Sangyun Lee, 'Why Korea's Merger Control Occasionally Fails: A Public Choice ...Sangyun Lee, 'Why Korea's Merger Control Occasionally Fails: A Public Choice ...
Sangyun Lee, 'Why Korea's Merger Control Occasionally Fails: A Public Choice ...
 
fnaf lore.pptx ...................................
fnaf lore.pptx ...................................fnaf lore.pptx ...................................
fnaf lore.pptx ...................................
 
Matthew Professional CV experienced Government Liaison
Matthew Professional CV experienced Government LiaisonMatthew Professional CV experienced Government Liaison
Matthew Professional CV experienced Government Liaison
 
Genocide in International Criminal Law.pptx
Genocide in International Criminal Law.pptxGenocide in International Criminal Law.pptx
Genocide in International Criminal Law.pptx
 
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
 
Lifting the Corporate Veil. Power Point Presentation
Lifting the Corporate Veil. Power Point PresentationLifting the Corporate Veil. Power Point Presentation
Lifting the Corporate Veil. Power Point Presentation
 
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证如何办理
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证如何办理一比一原版(Lincoln毕业证)新西兰林肯大学毕业证如何办理
一比一原版(Lincoln毕业证)新西兰林肯大学毕业证如何办理
 
Presentation (1).pptx Human rights of LGBTQ people in India, constitutional a...
Presentation (1).pptx Human rights of LGBTQ people in India, constitutional a...Presentation (1).pptx Human rights of LGBTQ people in India, constitutional a...
Presentation (1).pptx Human rights of LGBTQ people in India, constitutional a...
 

VIETNAM - Power Development Planning VIII (“PDP8”) - Vietnam Government’s plan to De-carbonize the Country - what you must know:

  • 1. VIETNAM - Power Development Planning VIII (“PDP8”) - Vietnam Government’s plan to De-carbonize the Country - what you must know: Question#1. What impact is PDP8 likely to have on the country’s efforts to decarbonize the economy? Answer#1: The draft Power Development Planning VIII (“PDP8”) reinforces the Vietnam Government’s current view on prioritizing renewable energy sources to minimize negative impacts caused by electricity production on the environment. Importation of fuels (coal, LNG) are encouraged as a way to diversify the country’s primary energy sources, and the same goes for the establishment of transmission and distribution grid links with China, Laos and Cambodia in order to maximize each country’s energy potential. Imported electricity sources from neighboring countries are to be considered as prioritized projects because imported electricity will reduce environmental impact compared to domestic production. As of 2020, the country’s total generation capacity is about 69.3 gigawatt (GW), including 16.5 GW of solar power (approx. 24% of the total capacity) and 0.6 GW of wind power. More than 50% Vietnam’s electricity generation came from coal in 2020. Vietnam’s reliance on coal-fired power remains heavily to meet rapidly increasing electricity demand. Hydroelectric generation is also significant as the country is home to a number of large rivers. Non-hydro renewable sources such as wind and solar made up 5% of Vietnam’s electricity generation in 2020. Under the draft PDP 8, Vietnam plans to increase solar capacity to 18.6 GW and wind capacity to 18 GW by 2030. Question#2. Does PDP8 target specific regions of the country? Are these regions that are more likely to be impacted by the transition to a low carbon economy? Answer#2: Yes, one of the most notable differences between the Draft PDP 8 and Revised PDP 7 (the latest official national power development planning) is the level of power demand between the North and the South. According to PDP8, the proportion of commercial electricity in the North will gradually increase from 42.4% in 2020 to 45.8% in 2045, while the South will decrease its proportion from 47.4% in 2020 to 43.6% by 2045. By 2040, the North’s commercial electricity demand will start to exceed that of the South. As a result, this will significantly affect the strategy in PDP8 to develop the transmission grid and generation sources (including RE sources) to meet the demand. The draft PDP 8 is oriented to focus on the development of transmission grid of at least 220KV to solve overcapacity issues that has been occurring in recent years. As to grid development, in the period of 2021-2030, MOIT sees the need to build 86 GVA with a capacity of 500kV per station and nearly 13,000 km of DLZ. From 2031-2045, an additional construction of 103 GVA with capacity of 500kV and nearly 6000 stations is required. The 220kV power grid needs construction of 95 GVA, nearly 21,000 km DMZ and 108 GVA, more than 4000 km NE. Total investment capital for electricity
  • 2. development in the period 2021-2030 is roughly USD 128.3 billion USD, of which: USD 95.4 billion for the power sources, USD 32.9 billion for the grids. The average structure of capital investment shall be 74% / 26%. The draft PDP8 appears to concern a surging oversupply of solar power in 2030 in many regions, such as the Central Highlands (estimated 1,500 MW but registered 5,500 MW), the South Central (estimated 5,200 MW but registered 11,600 MW), or the Southern (estimated 9,200 MW but registered 14,800 MW). The wind power shares the same situation as the registered capacity exceeds normal estimated capacity in Central Highlands (estimated 4,000 MW but registered 10,000 MW) and Southern (estimated 6800 MW but registered 17,000 MW). Accordingly, the draft PDP8 must solve this unbalance to ensure the sustainable development of the renewable energy sources in Vietnam. It is expected that future policy on renewable energy will base on auction rather than FIT. For example, below is the draft policy for solar power projects. In late January 2021, the Ministry of Industry and Trade (“MOIT”) issued the draft Decision of the Prime Minister guiding the selection of investors implementing solar power projects under the bidding mechanism (“the Draft”). According to the Draft, the Decision would be applicable to projects with grids connected directly to the national power network. The Ministry of Industry and Trade shall coordinate with the Electricity of Vietnam and the People’s Committees of localities to organize the formulation and approval of the renewable energy power source development plan for a period of 5 years and every 2 years to serve as a basis for the bidding system. In addition, every 02 years, the Ministry of Industry and Trade shall issue a Price Framework for electricity generation in order to determine the ceiling price for bidding to select investors of solar power projects with COD in the next 02 years. The plan for development of renewable energy power sources for a period of 5 years shall include the total capacity scale for each renewable energy power source in the 5-year period, the total capacity scale for each renewable energy power source for each load region (8 regions) and a list of transmission lines and substations (220 kV at least) to be put into operation for a period of 5 years. The 02-year plan shall have similar content but for a 2- year period only and shall be more provincial specific. Question#3. Were issues of economic, racial, and gender equity considered in the development of PDP8? Answer#3: Yes, any policy of the Government must consider these issues but it is very challenging to identify whether they are well reflected into the policy including PDP8. This is a very broad and difficult question. Question#4. Was there a debate amongst political leaders about the costs and benefits of PDP8? Answer#4: Yes, of course. It appears that the new Government now has different views and priorities than the former and as a result the PDP8 must be revised to reflect such priorities.
  • 3. As you may know, in late March 2021, the very first draft of PDP8 PM Decision (“Draft Decision”) has been published through unofficial sources (i.e. not through the Ministry of Industry and Trade (MOIT)’s website). Such PM Draft Decision was planned to be signed off at the end of March during the last days of Prime Minister Nguyen Xuan Phuc’s administration, but it was delayed as the hand- over to new administration was already under way. It appeared that the investors and LNG-to-power projects in this first PM Draft Decision were scaled down comparing to those in the PDP8 proposal published by Ministry of Industry and Trade (MOIT) earlier. On 23 April 2021, the Deputy Prime Minister (DPM) Le Van Thanh directed a Government’s meeting on the PDP8 and concluded that, among others, PDP8 must be (i) updated with qualifications for prioritized projects, and (ii) revised to reasonably review and allocate development of power sources, especially LNG-to-power projects in PDP8 in order to ensure the competition, optimization on development of power system. DPM asked the MOIT to careful review and digest opinion from EVN in its official letter No. 1645/EVN-KH dated 2 April 2021. Finally, the DPM required the MOIT to submit the updated PDP8 proposal prior to 15 June 2021. Unfortunately, due to Covid-19 situation and heavy workload on updating the PDP8 proposal, MOIT failed to submit a revised proposal to the Government for consideration. On 17 June 2021, the MOIT Minister arranged a press meeting to update the PDP8 progress and planned to submit the revised PDP8 proposal to the Government within June 2021. So far, based on our intel, the MOIT is still reworking its draft and PDP8 is expected to be approved COB this year ideally. Question#5. What role did various stakeholders (e.g., business, not-for-profits) take in advocating for or against PDP8 or trying to influence its development? Answer#5: Yes, there are many stakeholders here, e.g., EVN, local developers, business communities (such as Chambers and VBF) and state authorities. However, please kindly note that the draft PDP8 is mainly drafted by the Energy Institution (NB: an institution under EVN until it was taken over by MOIT since 2010). The MOIT was collecting opinion from all stakeholders for the draft PDP8 made by the Energy Institution. It is worth noting that the opinion from EVN is always critically important as it (including its affiliates and subsidiaries) still remains the position of a monopoly wholesaler in the market. The new Government requested the MOIT to revisit EVN’s opinion for revising the current draft PDP8. Question#6. Which key stakeholders were in favour of PDP8? How did they organize and influence decision making? Answer#6: Yes, it is very challenging to answer black or white on this question. PDP8 is the prioritized policy of the Government for the energy sector. Thus, there is always a favorable trend for this policy to come out soon. We however do note that there are different views on the contents of the PDP8, but not an issue of support or opposition.
  • 4. Question#7. Which key stakeholders were against PDP8? How did they organize and influence decision making? Were there specific measures to address their concerns? Answer#7: Yes, it is very challenging to answer a black or white question. PDP8 is the prioritized policy of the Government for the energy sector. Thus, there is always a favorable trend for this policy to come out soon. We however do note that there are different views on the contents of the PDP8, but not an issue of support or opposition. Question#8. Has PDP8 been well-received by the public? Answer#8: Yes, it has been well received by the public. However, the foreign invested business communities still have some concerns, among others, over the current PDP8: • No clear plan for variable renewable energy in the technology mix. PDP8 must ensure Vietnam planning remains cutting-edge to include full representation of variability and assessing power system reliability. • No plan for nuclear power. • Need to construct a regulatory and permitting environment that attracts private sector investment in clean energy generation and energy efficiency. • Need a clear policy to ensure EVN to share the market risks: e.g., a bankable (take or pay) power purchase agreement with generators. • Need to halt further development of coal based projects: it is recommended to suspend the approval of any new coal thermal power plants and conducting a strategic review of those that are already approved but which do not have financing or power purchase agreements. • Need to develop a flexible transmission network in view of the market orientation and increased variable renewable energy. • Need to build schemes to address the uncertainties: from fuel prices to demand growth and oversupply and curtailment. *** For more information on the above, please do not hesitate to contact the author Dr. Oliver Massmann under omassmann@duanemorris.com. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC, Member to the Supervisory Board of PetroVietnam Insurance JSC and the only foreign lawyer presenting in Vietnamese language to members of the NATIONAL ASSEMBLY OF VIETNAM.