- The Vietnamese government issued Notice No. 92/TB-VPCP finalizing the National Power Development Plan for 2021-2030 (PDP VIII). Deputy Prime Minister Le Van Thanh directed the Ministry of Industry and Trade to finalize PDP VIII.
- PDP VIII must contribute to Vietnam's commitment to reach net zero emissions by 2050 and follow a green, circular economy. For solar projects already in the previous plan but not implemented, MOIT must review purchase prices and efficiency.
- MOIT will review solar capacity already planned but not implemented due to inefficiency, and consider adjustments. Rooftop solar that follows regulations and does not exploit mechanisms will have its consumption balanced, excluding 7,755