2. BACKGROUND
PHASE 1A
–Synthetics, parking and restrooms
completed June ’19
PHASE 1B
–Maintenance and accessibility elements
identified during design of 1A; Budgeted for
design and construction in FY ‘19 and ‘20
Capital Program
3. IMPROVEMENTS
• DRAINAGE – between fields 1-6 along Harvey
side of park
• ACCESSIBILITY – to fields currently non-
compliant, including heavy pedestrian areas
along roadway
• ROUNDABOUTS – installed early 2000s; asphalt
is failing due to high traffic volume, concrete
replacement
• RESTROOMS – along Harvey side of park
5. CONSTRUCTION CONTRACT
JACODY CONSTRUCTION | $1,934,233.26
–Funding Sources
• Parkland Dedication Community Zone
CD & Neighborhood Zone 4
• Field Redevelopment
• Certificates of Obligation
–Approval Needed
7. CHANGE ORDER
JACODY CONSTRUCTION | ($271,352.51)
–Resulting contract amount $1,662,880.49
–$78,125.00 reallocated to electrical issues –
VPAC softball (in progress)
–Approval Needed
8. SUMMATION & DISCUSSION
SEEKING APPROVAL ON TWO ITEMS
–Award of contract to JaCody Construction
$1,934,233.26
–Change order to JaCody Construction
($271,352.51); $1,662,880.49
SCHEDULE – mobilize first week of September,
completion early Spring 21