We specialize in Auto Insertion machine and SMT equipments, provide spare parts, sub-assembly, retrofit kit, repair kit, upgrading, training, overhaul service. www.smthelp.com
2. http://www.smthelp.com
• Reduce the operator labor intensity
• Reduce the equipment efficiency loss caused by operator sabotage
• Save operators, one person can operate several machines.
• Can the attachment (In - line) SMT production line.
• A more secure protection operation.
• Automatic production mode.
Manual loader
and unloader
Automatic loader and unloader
(material box model)
Automatic loader and
unloade(attachment
model)
3. http://www.smthelp.com
Technical renovation project mainly includes four modules setup and training:
1.Bridge type automatic institution adapted for changing plate
2.Container loader and material box unloader
3.Electric control circuit
4.Software Settings.
The content of the technical
5.Training
• Training operation for operator
• Maintenance engineer training
4. http://www.smthelp.com
The implementation steps
• Technical renovation engineering installation and debugging need about 1.5 days
• Operation training and maintenance training need 0.5 days
Component installation project include:
1.Installation of bridge type automatic agency for changing board
2.Rotary worktable PCB fixture from stationary orbit type
Lift bridge components
Fixed clamp Rail clamp