College Station City Council Workshop September 24, 2020
TxDOT Projects
Doug Marino, P.E.
Texas Dept. of Transportation – Bryan District
College Station City Council Workshop September 24, 2020
Projects In Construction
2
 South College Ave. – Shared Use Path – From Hensel Park to University
Dr.
– $710,000
– Construction Underway and continues to Early 2021
 George Bush Dr. – Raised Medians – From Wellborn Rd. to Texas Ave.
– $2.4 MM
– Construction Begins this Fall and continues through Summer 2021
 Wellborn Rd./Holleman Dr. – Intersection Improvements
– $3.2 MM
– Construction Begins in January 2021 and continues through August 2021
 FM 2818 – Super Street – From University Dr. to Wellborn Rd.
– $43.7 MM
– Construction Begins this Fall and continues through Fall 2023
College Station City Council Workshop September 24, 2020
Projects Under Development
3
 SH 6 – Expansion – From SH 21 to SH 40
– Estimated $216 MM
– Phase 1 – Fall 2022 to 2025 Phase 2 – Fall 2024 to 2026
 George Bush Dr./Wellborn Rd. Underpass
– Estimated $69 MM
– Target Construction Begin 2023 to End option of 2025 or 2026
 Wellborn Rd. – Widening – From SH 40 to Greens Prairie Rd.
– Estimated $29 MM
– Target Construction Begin 2026
 SH 30 (Harvey Rd.) – Shared Use Path – From Texas Ave. to SH 6
– Estimated $5 MM
– Target Construction Begin 2026
 FM 60 – Pedestrian Concept – Northgate Area
College Station City Council Workshop September 24, 2020
Thank you!
4
Doug Marino, P.E.
Director TP&D
TxDOT – Bryan District
doug.marino@txdot.gov
(979) 778-9635

TxDOT Projects in College Station

  • 1.
    College Station CityCouncil Workshop September 24, 2020 TxDOT Projects Doug Marino, P.E. Texas Dept. of Transportation – Bryan District
  • 2.
    College Station CityCouncil Workshop September 24, 2020 Projects In Construction 2  South College Ave. – Shared Use Path – From Hensel Park to University Dr. – $710,000 – Construction Underway and continues to Early 2021  George Bush Dr. – Raised Medians – From Wellborn Rd. to Texas Ave. – $2.4 MM – Construction Begins this Fall and continues through Summer 2021  Wellborn Rd./Holleman Dr. – Intersection Improvements – $3.2 MM – Construction Begins in January 2021 and continues through August 2021  FM 2818 – Super Street – From University Dr. to Wellborn Rd. – $43.7 MM – Construction Begins this Fall and continues through Fall 2023
  • 3.
    College Station CityCouncil Workshop September 24, 2020 Projects Under Development 3  SH 6 – Expansion – From SH 21 to SH 40 – Estimated $216 MM – Phase 1 – Fall 2022 to 2025 Phase 2 – Fall 2024 to 2026  George Bush Dr./Wellborn Rd. Underpass – Estimated $69 MM – Target Construction Begin 2023 to End option of 2025 or 2026  Wellborn Rd. – Widening – From SH 40 to Greens Prairie Rd. – Estimated $29 MM – Target Construction Begin 2026  SH 30 (Harvey Rd.) – Shared Use Path – From Texas Ave. to SH 6 – Estimated $5 MM – Target Construction Begin 2026  FM 60 – Pedestrian Concept – Northgate Area
  • 4.
    College Station CityCouncil Workshop September 24, 2020 Thank you! 4 Doug Marino, P.E. Director TP&D TxDOT – Bryan District doug.marino@txdot.gov (979) 778-9635