SlideShare a Scribd company logo
1 of 10
The PCNet Project (B)
Dynamically Managing Residual
Risk
04/2005
This case was written by Christoph H. Loch, Professor of
Technology and Operations Management
It is based on real events, but the names of all companies and
participants have been disguised.
Any similarity with existing companies is accidental. The case
is intended to be used as a basis for class discussion rather than
to illustrate the effective or ineffective handling of an
administrative situation.
The unexpected events that worried Jack Muller represented
“residual risk”. In a project of
such complexity, no amount of planning can ever anticipate all
events, no matter how
thorough; there will always be some events that are not planned
for. Therefore, it is key to
build the capability of dealing with residual risk as it comes
along.
The direct outcome of the 18 September meeting was a
strengthening of the aggregate
oversight body (for the entire merger), not in the sense of it
exerting more pressure, but in
terms of adding experience and enhancing its problem-solving
and advice-giving capacity.
First, the Integration Management Committee Meeting became
the Performance Monitoring
Meeting, with a dedicated manager (who followed up issues),
expanded membership to add
relevant areas of expertise, and a more systematic synergy
follow up.
The Risk Management Office
At the level of the IT integration, Max Schmeling had already
begun to build a structure for
managing residual, unforeseen contingencies during execution.
The Risk Management
Office (RMO) was put in place as a complement to the Project
Management Office (PMO).
Whereas the PMO followed up on actions and on reporting, the
RMO focused on responding
to deviations. It was a central control point to which all teams
were required to call in at least
once a day to report on progress and problems that arose.
The RMO achieved two things. First, it represented a problem-
solving resource – Metal
Resources Co. had its own technical experts present in this
center, plus experts on call from
all technical areas at the main systems vendors (such as HP and
IBM for PCs, Cisco for
routers, Microsoft for operating systems, SAP for R3, EDS for
the network operation, etc),
and experts in culture and change management were also on
call. Thus, when an unforeseen
problem occurred, the center diagnosed it with the team in
question and then helped to
mobilize the expertise to bring about, or plan, a solution as
quickly as possible. Second, the
rapid information exchange helped to set off alarm bells (early
warnings) as well as solution
approaches, across the many parallel teams. As they were
working on very similar issues at
multiple sites, a problem occurring at one site might well
subsequently occur at one of the
others, and thus the transfer of solutions was efficient. The
rapid communication of relevant
warnings from one team to another was dubbed “the hotwire”.
Thus, at each local deployment, a representative of the next
local deployment team (in another
state or country) was present so that they could become familiar
with the logistical as well as
technical issues. The Latin American deployment went very
smoothly as a result of this
approach. Similarly, problems that arose in the application
migration to the new platform in
Singapore were subsequently avoided throughout the Southeast
Asian region.
Both the PMO and the RMO also attempted to prevent certain
risks by enforcing strict
standards (thus reducing the complexity and number of things
that could go wrong), such as
all of North America having to move to a single SAP system
configuration (there was a
separate central control center for that project alone, which
worked with all the organizational
units to produce a common standard that satisfied most of the
needs). Many technical and
business software applications were standardized (such as
statistical analysis packages,
geological expert systems etc.), which, in turn, reduced the
number of different problems that
could occur and facilitated the sharing of solutions across
teams.
The activities of the RMO enabled the organization to work
with budget and schedule
variances (deviations) in a more sophisticated way, for example,
by performing variance
analysis. There was significant overspending in Phase 3,
because some work originally
foreseen for Phase 4 was in fact carried out at this point due to
small “design changes” or
improvements in protocols and processes as the organization
learned during the project. The
activities of the RMO involved providing explanations and
documentation for residual risk
and the respective actions required. Thus the organization had a
‘trace’ that offered a
thorough explanation of deviations and an institutionalized
effort to learn from such changes.
The following example illustrates the effect of such learning:
the early PC deployments took
several man days per person as the migration team was learning
and stabilizing the
components of the network, whereas later deployments required
only a few hours (a reduction
of 75%) and were much more stable. Overall, the project
remained slightly under budget,
although it took 6 months longer than originally planned.
Dealing With Individual Residual Risks
The problem of lost e-mails and corrupted e-mail capabilities
had to be attacked at two levels.
The first level was technical: when the lost file incidents were
examined, the root problem
turned out to be that Microsoft XP did not have a translator to
automatically modify files. In
response, the Microsoft developers made their own in-house
translator software available
which systematically eliminated the problems and improved the
overall robustness of the
network. Several similar fixes contributed to overall network
stabilization. The second
solution level concerned change management processes: over
time, the merger team put such
processes in place (“who can change what system features, after
discussing it with whom”),
and convinced employees to comply with them, which
eliminated incompatibilities introduced
by local changes.
The Sri Lankan government partner eventually came on board,
although at its own pace. This
contributed to a six-month delay but did not “stop the show”.
The refining manager who refused the deployment was won over
with a combination of carrot
and stick. On the one hand, the IT organization conducted a
security audit at his site, which
exposed serious vulnerability to external attacks and other
breakdowns. This allowed the
team to show him how badly it might get for him locally
(carrot) and make it clear that he
could not be permitted to pose a risk for the rest of the
organization (stick).
The cajoling and convincing of the refining plant manager was
then generalized to a
standardized, prepared, compelling argument that was used with
operating managers who
thought they had no time for off-line activities like IT migration
(Exhibit 1). The argument
again combined carrot and stick – on the one hand it explained
the benefits to the operating
units themselves and emphasized that they could get help; on
the other it threatened them that
their network would no longer be supported if they did not
migrate. This standard argument
was, of course, complemented by personal visits and face-to-
face explanations.
Overall Project Success
“You guys will have to learn how to walk, whistle and chew
gum, all at the same
time.”
Martin Folz, CEO
The ITC organization did learn to “walk, whistle and chew gum
at the same time”, as the
CEO demanded. They took the metaphor seriously enough to
define it: walking meant to not
disrupt ongoing operations, whistling to lead the project with
state-of-the-art methods, and
chewing gum stood for status reviews and dealing with residual
risks. At the end, no
unexpected event was serious enough to break the project. The
thorough planning, combined
with the flexibility of the RMO and the hotwire, was so
powerful that the huge IT merger
became a convincing success. The total IT merger project beat
its target by $20 million,
producing $230 million of synergies in the first year, and the
PCNet project made a
significant contribution to this overfulfillment (partially driven
by an extra $10 million in PC
discounts that came out of the proactive negotiations).
Critical to this success was the support and constancy of
purpose of top management: the
CEO listened to the business case and stayed the course. No IT
migration budgets were cut,
in spite of the lean economic times, and the project was able to
maintain priority and focus.
Exhibit 1
Communication Document for Operating Company Compliance
The PCNet Deployment Consultant team presents……..
The Top Ten List of “Reasons why you should quickly and
carefully
decommission your legacy IT environment”
10. Dual environments will make it more difficult to maintain
IP compliance, particularly once Microsoft
ceases support of NT 4.0.
9. Dual environments are impacting our networks due to
unnecessary traffic from the legacy
infrastructures such as file replication, Exchange Global
Catalog replication, SMS inventory and
package traffic, as well as WINS and DNS traffic.
8. Increased vulnerability to security attacks and viruses as
vendors start dropping maintenance
support for Win9x, NT4 and W2K, and our internal centralized
efforts are no longer funded for
these environments.
7. Increased cost for support as troubleshooting by support staff
becomes a lot more complex due to
having to follow separate processes and using different tools in
order to support two environments.
Cost also increases due to reduced reliability and increased
break/fix calls as hardware has lived
long past its planned life-cycle.
6. Legacy Master Account NT4 and AD domains will be
decommissioned, leaving resource domains
with no trusts. The old PC and workstation environments will
lose connectivity. There will also be
performance issues as Master Account domain controllers are
removed one by one.
5. The decommissioning effort is part of Metal Resources and
RBD synergy cost-savings and the
realization of these savings now becomes our responsibility.
4. The business case for the synergies will be compromised by
having to support dual
infrastructures.
3. Manpower can be redirected towards strategic projects once
deployment and decommissioning
efforts are completed (and we can take our vacations now!).
2. Old computing standards monthly costs will be increased by
x2, x4 and x6 the longer you keep
your old hardware. Costs to maintain old infrastructure will be
divided by the number of remaining
old standard users.
And the #1 Reason is …
1. The old desktop has been declared “non-standard”. Yes, it is
true. The sun has set on the old
standard, with the IT design team only providing Anti-Virus
updates and major security patches.
Having old standard machines at your site makes your site
“Non-Standard”.
---------------------------------------------------------------------------
-------------------------------------------------------------
Here are three documents to help you in your efforts to
decommission:
Decommission Legacy Systems Guide
Decommissioning Server Assets
Decommissioning Workstation Assets
*** If the thought of pulling the plug on your favorite Compaq
Proliant server is giving you nightmares
and sleepless nights, then please email me back about getting
the PCNet Deployment Consultant
team to offer decommissioning consulting services at your site.
31
"The PCNet Project (B) Dynamically Managing Residual Risk."
Loch, Christoph. Case No.
5272b. Published 04/2005, INSEAD, (6 pages).
Answer all questions completely
No Plagiarism
Cite all resources used and use in-text citations
Assignment 3: Risk Workshop and Risk Register
Note: The assignments are a series of papers that are based on
the same case. The assignments are dependent upon one
another.
Write an eight to ten (8-10) Risk Workshop and Risk Register
Component paper in which you:
1. Identify the required pre-workshop activities.
2. Prepare a risk workshop agenda based on Figure B-8 (shown
below), Sample Agenda for a First Risk Assessment / Two –
Day Risk Workshop (Appendix B of the Hillson and Simon
text). Include suggested time intervals for each activity and
justify why each agenda item is relevant for this case.
3. Determine the top five (5) threats in a risk register following
Figure B-11 (shown below), Sample Simplified Risk Register
Format (Appendix B of the Hillson and Simon text). Include
information from the case for each threat.
4. Justify the assignment of probability and impacts for each
threat identified in criterion number 3 of this assignment.
5. Document the top three (3) opportunities in a risk register
following Figure B-11 (shown below), Sample Simplified Risk
Register Format (Appendix B of the Hillson and Simon text).
Include information from the case for each opportunity.
6. Justify the assignment of probability and impacts for each
opportunity identified in criterion number 5 of this assignment.
7. Use at least two (2) quality resources in this assignment.
Note: Wikipedia and similar Websites do not qualify as quality
resources.
Your assignment must follow these formatting requirements:
· Be typed, double spaced, using Times New Roman font (size
12), with one-inch margins on all sides.
· Include a cover page containing the title of the assignment, the
students name, the professors name, the course title, and the
date. The cover page and the reference page are not included in
the required assignment page length.
The specific course learning outcomes associated with this
assignment are:
· Assess and prioritize risks to the project through an analysis
of the active threats and opportunities presented.
· Apply the Active Threats and Opportunities Management
(ATOM) process to ensure a consistent, measurable result of
this analysis.
· Use technology and information resources to research issues in
project risk management
· Write clearly and concisely about project risk management
using proper writing mechanics.
Figure B-8
Figure B-11
(Description section is first, then pre-response impact, then
post-response impact)

More Related Content

Similar to The PCNet Project (B)Dynamically Managing ResidualRisk042.docx

Rsc 2009 Process Management Yesterday Today Tomorrow
Rsc 2009   Process Management Yesterday Today TomorrowRsc 2009   Process Management Yesterday Today Tomorrow
Rsc 2009 Process Management Yesterday Today Tomorrowdjtrent
 
Automated Issue Assignment Results And Insights From An Industrial Case
Automated Issue Assignment  Results And Insights From An Industrial CaseAutomated Issue Assignment  Results And Insights From An Industrial Case
Automated Issue Assignment Results And Insights From An Industrial CaseJim Webb
 
3784_Streamlining_the_development_process_with_feature_flighting_and_Azure_cl...
3784_Streamlining_the_development_process_with_feature_flighting_and_Azure_cl...3784_Streamlining_the_development_process_with_feature_flighting_and_Azure_cl...
3784_Streamlining_the_development_process_with_feature_flighting_and_Azure_cl...Crystal Thomas
 
Novell Teaming Use Cases
Novell Teaming Use CasesNovell Teaming Use Cases
Novell Teaming Use CasesNovell
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementJoe Osborn
 
Operations management practical problem ii flow charting a proces
Operations management practical problem ii flow charting a procesOperations management practical problem ii flow charting a proces
Operations management practical problem ii flow charting a procesPOLY33
 
London Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyLondon Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyMonzer Osama Alchikh WARAK
 
ERP - Implementation is The Challenge
ERP - Implementation is The ChallengeERP - Implementation is The Challenge
ERP - Implementation is The Challengevinaya.hs
 
How To Build Mature SM - final
How To Build Mature SM - finalHow To Build Mature SM - final
How To Build Mature SM - finalDanijel Božić
 
Marius_2016_resume
Marius_2016_resumeMarius_2016_resume
Marius_2016_resumeMarius Mihel
 
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdfSteven Callahan
 
REGULARIZED FUZZY NEURAL NETWORKS TO AID EFFORT FORECASTING IN THE CONSTRUCTI...
REGULARIZED FUZZY NEURAL NETWORKS TO AID EFFORT FORECASTING IN THE CONSTRUCTI...REGULARIZED FUZZY NEURAL NETWORKS TO AID EFFORT FORECASTING IN THE CONSTRUCTI...
REGULARIZED FUZZY NEURAL NETWORKS TO AID EFFORT FORECASTING IN THE CONSTRUCTI...ijaia
 
Uncovering Key Challenges in Offshore Software Development.pdf
Uncovering Key Challenges in Offshore Software Development.pdfUncovering Key Challenges in Offshore Software Development.pdf
Uncovering Key Challenges in Offshore Software Development.pdfSiya Carla
 
JeffDavisProjectPortfolio
JeffDavisProjectPortfolioJeffDavisProjectPortfolio
JeffDavisProjectPortfolioJeff Davis
 
Sad considerations for-candidate_system
Sad considerations for-candidate_systemSad considerations for-candidate_system
Sad considerations for-candidate_systemSwapnil Walde
 

Similar to The PCNet Project (B)Dynamically Managing ResidualRisk042.docx (20)

Rsc 2009 Process Management Yesterday Today Tomorrow
Rsc 2009   Process Management Yesterday Today TomorrowRsc 2009   Process Management Yesterday Today Tomorrow
Rsc 2009 Process Management Yesterday Today Tomorrow
 
Automated Issue Assignment Results And Insights From An Industrial Case
Automated Issue Assignment  Results And Insights From An Industrial CaseAutomated Issue Assignment  Results And Insights From An Industrial Case
Automated Issue Assignment Results And Insights From An Industrial Case
 
3784_Streamlining_the_development_process_with_feature_flighting_and_Azure_cl...
3784_Streamlining_the_development_process_with_feature_flighting_and_Azure_cl...3784_Streamlining_the_development_process_with_feature_flighting_and_Azure_cl...
3784_Streamlining_the_development_process_with_feature_flighting_and_Azure_cl...
 
h6358-ictsi-cporellano
h6358-ictsi-cporellanoh6358-ictsi-cporellano
h6358-ictsi-cporellano
 
Case study v7.2
Case study v7.2Case study v7.2
Case study v7.2
 
Novell Teaming Use Cases
Novell Teaming Use CasesNovell Teaming Use Cases
Novell Teaming Use Cases
 
Resume_Tushar_Bhilare
Resume_Tushar_BhilareResume_Tushar_Bhilare
Resume_Tushar_Bhilare
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project Management
 
Effective Virtual Projects
Effective Virtual ProjectsEffective Virtual Projects
Effective Virtual Projects
 
Operations management practical problem ii flow charting a proces
Operations management practical problem ii flow charting a procesOperations management practical problem ii flow charting a proces
Operations management practical problem ii flow charting a proces
 
London Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyLondon Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of Emergency
 
ERP - Implementation is The Challenge
ERP - Implementation is The ChallengeERP - Implementation is The Challenge
ERP - Implementation is The Challenge
 
DRP.ppt
DRP.pptDRP.ppt
DRP.ppt
 
How To Build Mature SM - final
How To Build Mature SM - finalHow To Build Mature SM - final
How To Build Mature SM - final
 
Marius_2016_resume
Marius_2016_resumeMarius_2016_resume
Marius_2016_resume
 
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf
 
REGULARIZED FUZZY NEURAL NETWORKS TO AID EFFORT FORECASTING IN THE CONSTRUCTI...
REGULARIZED FUZZY NEURAL NETWORKS TO AID EFFORT FORECASTING IN THE CONSTRUCTI...REGULARIZED FUZZY NEURAL NETWORKS TO AID EFFORT FORECASTING IN THE CONSTRUCTI...
REGULARIZED FUZZY NEURAL NETWORKS TO AID EFFORT FORECASTING IN THE CONSTRUCTI...
 
Uncovering Key Challenges in Offshore Software Development.pdf
Uncovering Key Challenges in Offshore Software Development.pdfUncovering Key Challenges in Offshore Software Development.pdf
Uncovering Key Challenges in Offshore Software Development.pdf
 
JeffDavisProjectPortfolio
JeffDavisProjectPortfolioJeffDavisProjectPortfolio
JeffDavisProjectPortfolio
 
Sad considerations for-candidate_system
Sad considerations for-candidate_systemSad considerations for-candidate_system
Sad considerations for-candidate_system
 

More from oreo10

All scientific theories must be able to make testable predictions. S.docx
All scientific theories must be able to make testable predictions. S.docxAll scientific theories must be able to make testable predictions. S.docx
All scientific theories must be able to make testable predictions. S.docxoreo10
 
All I wnat is to write a reflection paper on my project which is hac.docx
All I wnat is to write a reflection paper on my project which is hac.docxAll I wnat is to write a reflection paper on my project which is hac.docx
All I wnat is to write a reflection paper on my project which is hac.docxoreo10
 
Alice,Betty, and Carol are playing a game with 48 marbles in a circl.docx
Alice,Betty, and Carol are playing a game with 48 marbles in a circl.docxAlice,Betty, and Carol are playing a game with 48 marbles in a circl.docx
Alice,Betty, and Carol are playing a game with 48 marbles in a circl.docxoreo10
 
All healthcare organizations must convert to an Electronic Health Re.docx
All healthcare organizations must convert to an Electronic Health Re.docxAll healthcare organizations must convert to an Electronic Health Re.docx
All healthcare organizations must convert to an Electronic Health Re.docxoreo10
 
All round writer onlyThis is an individual Mediation assignment..docx
All round writer onlyThis is an individual Mediation assignment..docxAll round writer onlyThis is an individual Mediation assignment..docx
All round writer onlyThis is an individual Mediation assignment..docxoreo10
 
Alice was wondering whether it was a good idea to invest her money i.docx
Alice was wondering whether it was a good idea to invest her money i.docxAlice was wondering whether it was a good idea to invest her money i.docx
Alice was wondering whether it was a good idea to invest her money i.docxoreo10
 
All organisms have DNA, which differs only in the number and order o.docx
All organisms have DNA, which differs only in the number and order o.docxAll organisms have DNA, which differs only in the number and order o.docx
All organisms have DNA, which differs only in the number and order o.docxoreo10
 
All literature involves some kind of performance which is intended f.docx
All literature involves some kind of performance which is intended f.docxAll literature involves some kind of performance which is intended f.docx
All literature involves some kind of performance which is intended f.docxoreo10
 
All key elements of the assignment are covered in a substantiv.docx
All key elements of the assignment are covered in a substantiv.docxAll key elements of the assignment are covered in a substantiv.docx
All key elements of the assignment are covered in a substantiv.docxoreo10
 
Alice, Betty and Carol are playing a game with 48 marbles in a circl.docx
Alice, Betty and Carol are playing a game with 48 marbles in a circl.docxAlice, Betty and Carol are playing a game with 48 marbles in a circl.docx
Alice, Betty and Carol are playing a game with 48 marbles in a circl.docxoreo10
 
Alice Jones was employed as a clerk-typist by a company. She request.docx
Alice Jones was employed as a clerk-typist by a company. She request.docxAlice Jones was employed as a clerk-typist by a company. She request.docx
Alice Jones was employed as a clerk-typist by a company. She request.docxoreo10
 
Air and Water Pollution PaperAir and water pollutants exist in m.docx
Air and Water Pollution PaperAir and water pollutants exist in m.docxAir and Water Pollution PaperAir and water pollutants exist in m.docx
Air and Water Pollution PaperAir and water pollutants exist in m.docxoreo10
 
Air pollution is an environmental health problem in many cities thro.docx
Air pollution is an environmental health problem in many cities thro.docxAir pollution is an environmental health problem in many cities thro.docx
Air pollution is an environmental health problem in many cities thro.docxoreo10
 
After your topic has been approved, the next step is to research.docx
After your topic has been approved, the next step is to research.docxAfter your topic has been approved, the next step is to research.docx
After your topic has been approved, the next step is to research.docxoreo10
 
After watching three of the five movie clips listed in the Multime.docx
After watching three of the five movie clips listed in the Multime.docxAfter watching three of the five movie clips listed in the Multime.docx
After watching three of the five movie clips listed in the Multime.docxoreo10
 
Aging and Disability WorksheetPart IIdentify 2 or .docx
Aging and Disability WorksheetPart IIdentify 2 or .docxAging and Disability WorksheetPart IIdentify 2 or .docx
Aging and Disability WorksheetPart IIdentify 2 or .docxoreo10
 
After watching the video and reading the Web Resource, CDC Autism .docx
After watching the video and reading the Web Resource, CDC Autism .docxAfter watching the video and reading the Web Resource, CDC Autism .docx
After watching the video and reading the Web Resource, CDC Autism .docxoreo10
 
AI Artificial Intelligence1Reading responsePeter .docx
AI Artificial Intelligence1Reading responsePeter .docxAI Artificial Intelligence1Reading responsePeter .docx
AI Artificial Intelligence1Reading responsePeter .docxoreo10
 
Agree or disagree with, and discuss the following statement Corp.docx
Agree or disagree with, and discuss the following statement Corp.docxAgree or disagree with, and discuss the following statement Corp.docx
Agree or disagree with, and discuss the following statement Corp.docxoreo10
 
After watching Reactions to an Impending Death Sentence and Ti.docx
After watching Reactions to an Impending Death Sentence and Ti.docxAfter watching Reactions to an Impending Death Sentence and Ti.docx
After watching Reactions to an Impending Death Sentence and Ti.docxoreo10
 

More from oreo10 (20)

All scientific theories must be able to make testable predictions. S.docx
All scientific theories must be able to make testable predictions. S.docxAll scientific theories must be able to make testable predictions. S.docx
All scientific theories must be able to make testable predictions. S.docx
 
All I wnat is to write a reflection paper on my project which is hac.docx
All I wnat is to write a reflection paper on my project which is hac.docxAll I wnat is to write a reflection paper on my project which is hac.docx
All I wnat is to write a reflection paper on my project which is hac.docx
 
Alice,Betty, and Carol are playing a game with 48 marbles in a circl.docx
Alice,Betty, and Carol are playing a game with 48 marbles in a circl.docxAlice,Betty, and Carol are playing a game with 48 marbles in a circl.docx
Alice,Betty, and Carol are playing a game with 48 marbles in a circl.docx
 
All healthcare organizations must convert to an Electronic Health Re.docx
All healthcare organizations must convert to an Electronic Health Re.docxAll healthcare organizations must convert to an Electronic Health Re.docx
All healthcare organizations must convert to an Electronic Health Re.docx
 
All round writer onlyThis is an individual Mediation assignment..docx
All round writer onlyThis is an individual Mediation assignment..docxAll round writer onlyThis is an individual Mediation assignment..docx
All round writer onlyThis is an individual Mediation assignment..docx
 
Alice was wondering whether it was a good idea to invest her money i.docx
Alice was wondering whether it was a good idea to invest her money i.docxAlice was wondering whether it was a good idea to invest her money i.docx
Alice was wondering whether it was a good idea to invest her money i.docx
 
All organisms have DNA, which differs only in the number and order o.docx
All organisms have DNA, which differs only in the number and order o.docxAll organisms have DNA, which differs only in the number and order o.docx
All organisms have DNA, which differs only in the number and order o.docx
 
All literature involves some kind of performance which is intended f.docx
All literature involves some kind of performance which is intended f.docxAll literature involves some kind of performance which is intended f.docx
All literature involves some kind of performance which is intended f.docx
 
All key elements of the assignment are covered in a substantiv.docx
All key elements of the assignment are covered in a substantiv.docxAll key elements of the assignment are covered in a substantiv.docx
All key elements of the assignment are covered in a substantiv.docx
 
Alice, Betty and Carol are playing a game with 48 marbles in a circl.docx
Alice, Betty and Carol are playing a game with 48 marbles in a circl.docxAlice, Betty and Carol are playing a game with 48 marbles in a circl.docx
Alice, Betty and Carol are playing a game with 48 marbles in a circl.docx
 
Alice Jones was employed as a clerk-typist by a company. She request.docx
Alice Jones was employed as a clerk-typist by a company. She request.docxAlice Jones was employed as a clerk-typist by a company. She request.docx
Alice Jones was employed as a clerk-typist by a company. She request.docx
 
Air and Water Pollution PaperAir and water pollutants exist in m.docx
Air and Water Pollution PaperAir and water pollutants exist in m.docxAir and Water Pollution PaperAir and water pollutants exist in m.docx
Air and Water Pollution PaperAir and water pollutants exist in m.docx
 
Air pollution is an environmental health problem in many cities thro.docx
Air pollution is an environmental health problem in many cities thro.docxAir pollution is an environmental health problem in many cities thro.docx
Air pollution is an environmental health problem in many cities thro.docx
 
After your topic has been approved, the next step is to research.docx
After your topic has been approved, the next step is to research.docxAfter your topic has been approved, the next step is to research.docx
After your topic has been approved, the next step is to research.docx
 
After watching three of the five movie clips listed in the Multime.docx
After watching three of the five movie clips listed in the Multime.docxAfter watching three of the five movie clips listed in the Multime.docx
After watching three of the five movie clips listed in the Multime.docx
 
Aging and Disability WorksheetPart IIdentify 2 or .docx
Aging and Disability WorksheetPart IIdentify 2 or .docxAging and Disability WorksheetPart IIdentify 2 or .docx
Aging and Disability WorksheetPart IIdentify 2 or .docx
 
After watching the video and reading the Web Resource, CDC Autism .docx
After watching the video and reading the Web Resource, CDC Autism .docxAfter watching the video and reading the Web Resource, CDC Autism .docx
After watching the video and reading the Web Resource, CDC Autism .docx
 
AI Artificial Intelligence1Reading responsePeter .docx
AI Artificial Intelligence1Reading responsePeter .docxAI Artificial Intelligence1Reading responsePeter .docx
AI Artificial Intelligence1Reading responsePeter .docx
 
Agree or disagree with, and discuss the following statement Corp.docx
Agree or disagree with, and discuss the following statement Corp.docxAgree or disagree with, and discuss the following statement Corp.docx
Agree or disagree with, and discuss the following statement Corp.docx
 
After watching Reactions to an Impending Death Sentence and Ti.docx
After watching Reactions to an Impending Death Sentence and Ti.docxAfter watching Reactions to an Impending Death Sentence and Ti.docx
After watching Reactions to an Impending Death Sentence and Ti.docx
 

Recently uploaded

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 

Recently uploaded (20)

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 

The PCNet Project (B)Dynamically Managing ResidualRisk042.docx

  • 1. The PCNet Project (B) Dynamically Managing Residual Risk 04/2005 This case was written by Christoph H. Loch, Professor of Technology and Operations Management It is based on real events, but the names of all companies and participants have been disguised. Any similarity with existing companies is accidental. The case is intended to be used as a basis for class discussion rather than to illustrate the effective or ineffective handling of an administrative situation. The unexpected events that worried Jack Muller represented “residual risk”. In a project of such complexity, no amount of planning can ever anticipate all events, no matter how thorough; there will always be some events that are not planned for. Therefore, it is key to build the capability of dealing with residual risk as it comes along. The direct outcome of the 18 September meeting was a strengthening of the aggregate oversight body (for the entire merger), not in the sense of it exerting more pressure, but in terms of adding experience and enhancing its problem-solving and advice-giving capacity. First, the Integration Management Committee Meeting became the Performance Monitoring Meeting, with a dedicated manager (who followed up issues), expanded membership to add
  • 2. relevant areas of expertise, and a more systematic synergy follow up. The Risk Management Office At the level of the IT integration, Max Schmeling had already begun to build a structure for managing residual, unforeseen contingencies during execution. The Risk Management Office (RMO) was put in place as a complement to the Project Management Office (PMO). Whereas the PMO followed up on actions and on reporting, the RMO focused on responding to deviations. It was a central control point to which all teams were required to call in at least once a day to report on progress and problems that arose. The RMO achieved two things. First, it represented a problem- solving resource – Metal Resources Co. had its own technical experts present in this center, plus experts on call from all technical areas at the main systems vendors (such as HP and IBM for PCs, Cisco for routers, Microsoft for operating systems, SAP for R3, EDS for the network operation, etc), and experts in culture and change management were also on call. Thus, when an unforeseen problem occurred, the center diagnosed it with the team in question and then helped to mobilize the expertise to bring about, or plan, a solution as quickly as possible. Second, the rapid information exchange helped to set off alarm bells (early warnings) as well as solution approaches, across the many parallel teams. As they were working on very similar issues at multiple sites, a problem occurring at one site might well subsequently occur at one of the
  • 3. others, and thus the transfer of solutions was efficient. The rapid communication of relevant warnings from one team to another was dubbed “the hotwire”. Thus, at each local deployment, a representative of the next local deployment team (in another state or country) was present so that they could become familiar with the logistical as well as technical issues. The Latin American deployment went very smoothly as a result of this approach. Similarly, problems that arose in the application migration to the new platform in Singapore were subsequently avoided throughout the Southeast Asian region. Both the PMO and the RMO also attempted to prevent certain risks by enforcing strict standards (thus reducing the complexity and number of things that could go wrong), such as all of North America having to move to a single SAP system configuration (there was a separate central control center for that project alone, which worked with all the organizational units to produce a common standard that satisfied most of the needs). Many technical and business software applications were standardized (such as statistical analysis packages, geological expert systems etc.), which, in turn, reduced the number of different problems that could occur and facilitated the sharing of solutions across teams. The activities of the RMO enabled the organization to work with budget and schedule variances (deviations) in a more sophisticated way, for example, by performing variance analysis. There was significant overspending in Phase 3, because some work originally foreseen for Phase 4 was in fact carried out at this point due to
  • 4. small “design changes” or improvements in protocols and processes as the organization learned during the project. The activities of the RMO involved providing explanations and documentation for residual risk and the respective actions required. Thus the organization had a ‘trace’ that offered a thorough explanation of deviations and an institutionalized effort to learn from such changes. The following example illustrates the effect of such learning: the early PC deployments took several man days per person as the migration team was learning and stabilizing the components of the network, whereas later deployments required only a few hours (a reduction of 75%) and were much more stable. Overall, the project remained slightly under budget, although it took 6 months longer than originally planned. Dealing With Individual Residual Risks The problem of lost e-mails and corrupted e-mail capabilities had to be attacked at two levels. The first level was technical: when the lost file incidents were examined, the root problem turned out to be that Microsoft XP did not have a translator to automatically modify files. In response, the Microsoft developers made their own in-house translator software available which systematically eliminated the problems and improved the overall robustness of the network. Several similar fixes contributed to overall network stabilization. The second solution level concerned change management processes: over time, the merger team put such processes in place (“who can change what system features, after
  • 5. discussing it with whom”), and convinced employees to comply with them, which eliminated incompatibilities introduced by local changes. The Sri Lankan government partner eventually came on board, although at its own pace. This contributed to a six-month delay but did not “stop the show”. The refining manager who refused the deployment was won over with a combination of carrot and stick. On the one hand, the IT organization conducted a security audit at his site, which exposed serious vulnerability to external attacks and other breakdowns. This allowed the team to show him how badly it might get for him locally (carrot) and make it clear that he could not be permitted to pose a risk for the rest of the organization (stick). The cajoling and convincing of the refining plant manager was then generalized to a standardized, prepared, compelling argument that was used with operating managers who thought they had no time for off-line activities like IT migration (Exhibit 1). The argument again combined carrot and stick – on the one hand it explained the benefits to the operating units themselves and emphasized that they could get help; on the other it threatened them that their network would no longer be supported if they did not migrate. This standard argument was, of course, complemented by personal visits and face-to- face explanations. Overall Project Success “You guys will have to learn how to walk, whistle and chew gum, all at the same
  • 6. time.” Martin Folz, CEO The ITC organization did learn to “walk, whistle and chew gum at the same time”, as the CEO demanded. They took the metaphor seriously enough to define it: walking meant to not disrupt ongoing operations, whistling to lead the project with state-of-the-art methods, and chewing gum stood for status reviews and dealing with residual risks. At the end, no unexpected event was serious enough to break the project. The thorough planning, combined with the flexibility of the RMO and the hotwire, was so powerful that the huge IT merger became a convincing success. The total IT merger project beat its target by $20 million, producing $230 million of synergies in the first year, and the PCNet project made a significant contribution to this overfulfillment (partially driven by an extra $10 million in PC discounts that came out of the proactive negotiations). Critical to this success was the support and constancy of purpose of top management: the CEO listened to the business case and stayed the course. No IT migration budgets were cut, in spite of the lean economic times, and the project was able to maintain priority and focus. Exhibit 1 Communication Document for Operating Company Compliance The PCNet Deployment Consultant team presents…….. The Top Ten List of “Reasons why you should quickly and carefully decommission your legacy IT environment” 10. Dual environments will make it more difficult to maintain
  • 7. IP compliance, particularly once Microsoft ceases support of NT 4.0. 9. Dual environments are impacting our networks due to unnecessary traffic from the legacy infrastructures such as file replication, Exchange Global Catalog replication, SMS inventory and package traffic, as well as WINS and DNS traffic. 8. Increased vulnerability to security attacks and viruses as vendors start dropping maintenance support for Win9x, NT4 and W2K, and our internal centralized efforts are no longer funded for these environments. 7. Increased cost for support as troubleshooting by support staff becomes a lot more complex due to having to follow separate processes and using different tools in order to support two environments. Cost also increases due to reduced reliability and increased break/fix calls as hardware has lived long past its planned life-cycle. 6. Legacy Master Account NT4 and AD domains will be decommissioned, leaving resource domains with no trusts. The old PC and workstation environments will lose connectivity. There will also be performance issues as Master Account domain controllers are removed one by one. 5. The decommissioning effort is part of Metal Resources and RBD synergy cost-savings and the realization of these savings now becomes our responsibility. 4. The business case for the synergies will be compromised by having to support dual
  • 8. infrastructures. 3. Manpower can be redirected towards strategic projects once deployment and decommissioning efforts are completed (and we can take our vacations now!). 2. Old computing standards monthly costs will be increased by x2, x4 and x6 the longer you keep your old hardware. Costs to maintain old infrastructure will be divided by the number of remaining old standard users. And the #1 Reason is … 1. The old desktop has been declared “non-standard”. Yes, it is true. The sun has set on the old standard, with the IT design team only providing Anti-Virus updates and major security patches. Having old standard machines at your site makes your site “Non-Standard”. --------------------------------------------------------------------------- ------------------------------------------------------------- Here are three documents to help you in your efforts to decommission: Decommission Legacy Systems Guide Decommissioning Server Assets Decommissioning Workstation Assets *** If the thought of pulling the plug on your favorite Compaq Proliant server is giving you nightmares and sleepless nights, then please email me back about getting the PCNet Deployment Consultant team to offer decommissioning consulting services at your site. 31 "The PCNet Project (B) Dynamically Managing Residual Risk." Loch, Christoph. Case No. 5272b. Published 04/2005, INSEAD, (6 pages).
  • 9. Answer all questions completely No Plagiarism Cite all resources used and use in-text citations Assignment 3: Risk Workshop and Risk Register Note: The assignments are a series of papers that are based on the same case. The assignments are dependent upon one another. Write an eight to ten (8-10) Risk Workshop and Risk Register Component paper in which you: 1. Identify the required pre-workshop activities. 2. Prepare a risk workshop agenda based on Figure B-8 (shown below), Sample Agenda for a First Risk Assessment / Two – Day Risk Workshop (Appendix B of the Hillson and Simon text). Include suggested time intervals for each activity and justify why each agenda item is relevant for this case. 3. Determine the top five (5) threats in a risk register following Figure B-11 (shown below), Sample Simplified Risk Register Format (Appendix B of the Hillson and Simon text). Include information from the case for each threat. 4. Justify the assignment of probability and impacts for each threat identified in criterion number 3 of this assignment. 5. Document the top three (3) opportunities in a risk register following Figure B-11 (shown below), Sample Simplified Risk Register Format (Appendix B of the Hillson and Simon text). Include information from the case for each opportunity. 6. Justify the assignment of probability and impacts for each opportunity identified in criterion number 5 of this assignment. 7. Use at least two (2) quality resources in this assignment. Note: Wikipedia and similar Websites do not qualify as quality resources. Your assignment must follow these formatting requirements:
  • 10. · Be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides. · Include a cover page containing the title of the assignment, the students name, the professors name, the course title, and the date. The cover page and the reference page are not included in the required assignment page length. The specific course learning outcomes associated with this assignment are: · Assess and prioritize risks to the project through an analysis of the active threats and opportunities presented. · Apply the Active Threats and Opportunities Management (ATOM) process to ensure a consistent, measurable result of this analysis. · Use technology and information resources to research issues in project risk management · Write clearly and concisely about project risk management using proper writing mechanics. Figure B-8 Figure B-11 (Description section is first, then pre-response impact, then post-response impact)