The following schedule is for a project where the key resource is tractors. This schedule is contingent on having four tractors. Unfortunately, half of the tractors broke just before the start of the project, which you need to complete in 11 months. 1) Develop a resource schedule in the hereunder loading chart reflecting that you now have only half of the tractors available 2) Can you still complete the project in 11 months?.