Neo4j and Technip Energies Italy executed an Innovation Lab Sprint. The goal of the laboratory has been to frame, design and prototype the use case identified by their colleagues of Planning, Equipment and Construction disciplines, by applying Knowledge Graph technology, as the way to connect the data to gain information and insights as an immediate value, that is:
– capturing engineering deliverable milestone chain by gaining insights into a schedule
– performing reasoning on information, evidence and data
– extracting insights from data
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
Technip Energies Italy: Planning is a graph matter
1. This document and all information are confidential and may not be used, reproduced or distributed without prior authorization of TECHNIP ENERGIES
Planning is a graph matter
June 2023
Innovation Lab Sprint: a week @Technip Energies Italy
Neo4j Rome Graph Summit
2. “It’s easier to edit than to author.
Before we iterate, please thank the
authors”
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
2
4. €12.8B
Backlog at end 2022
€6.4B
Full year 2022 adjusted revenue
25+
Leading proprietary
technologies
A leading Engineering &
Technology company for
the Energy Transition
4
Technip Energies at a glance
Listed on
Euronext Paris
Stock Exchange
Headquartered in
Paris
60+
Years of operations
~14,000
Employees in 30 countries
450 projects
Under execution
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
5. A global footprint close to our clients
5
Aberdeen
A Coruna
Aktau
Al Khobar
Atyrau
Baku
Bangkok
Barcelona
Bogota
Boston, MA
Cairo
Caracas
Chennai
Claremont, CA
Compiegne
Dahej
Dakar
Doha
Frankfurt
Gothenburg
Ho Chi Minh
Jakarta
Kuwait City
Lyon
Madrid
Maputo
Marseille
Martigues
Mexico City
Milan
Milton Keynes
Moscow
Noida
Oman
Oslo
Perth
Rio de Janeiro
Rotterdam
Rouen
Sens
Seoul
Shanghai
Singapore
St Petersburg
Stavanger
Szczecin
Tarragona
Tripoli
Warsaw
Weymouth, MA
Zoetermeer
Technip Energies Headquarters Key regional operating centers Other permanent offices (see city list above)
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
6. An organization supporting our strategy and ambition
4 Business Lines and One T.EN delivery global organization
T.EN X
Consulting &
Products
Sustainable Fuels,
Chemicals &
Circularity
Carbon Free
Solutions
• Liquefied Natural
Gas (LNG)
• Floating Liquefied
Natural Gas (FLNG)
• Grey and Blue H2
• Blue ammonia
• Gas-to-liquids (GTL)
• Gas Processing &
Monetization
• Advisory & digital
services
• Project
management
consulting (PMC)
• Loading Systems
• Biofuels & Fuels
• Biochemicals &
Petrochemicals
• Sustainable
chemistry
• Ethylene
• Fertilizers
• Circular economy
• Offshore wind
• Green H2 value
chain
• CO2 management
• Nuclear
• Life sciences
• Mining & metals
CROSS MARKET
MARKET
Gas & Low Carbon
Energies
6
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
One T.EN Delivery
• A global network of
Operating Centers to
address all markets
and segments
• Collaboration with
Business Lines in
Tendering and
project execution
• Optimized methods
and tools to warrant
excellence in
execution
GLOBAL
7. Innovation Lab sprint
02 • Service by and perfomed with Neo4J in December
2022
• 5 days shot
• Interesting to those of you that have not Neo4j
solution in place yet
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
9
8. Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
10
Our execution process
Process Engineering design Procurement Construction
9. And here it is…
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
11
10. Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
12
Planning outstanding complexity
Stack | Numbers
L1- work
process
L2 - major
activity
L3 - tasks
L4 - deliverable
L5 - data
Innovation Lab
scope
Future
enhancement
8000activity
6,5link/activity on avg
60000link among activities
300pdf pages
4project phases
12construction disciplines
10engineering discplines
6procurement disciplines
Conceptualized data model Planning figures
11. Nowdays and the possible
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
13
Primavera P6 database converted into graph db:
planning is a graph matter
Primavera P6 : 22 db tables, 30+ columns used on lab
12. Neo4j Innovation Lab Sprint
Neo4j, Inc. All rights reserved 2022
14
Executive
Feedback
Presentation
Source data
to populate
model
Storyboardin
g/
Mockups
Identify Stakeholders / Synopsis
Functional – Emotional – Social
Needs
Build
Query
Import
Data
Areas of
Significanc
e
Related
“Graph
Questions”
Generate
Data
Model
Define
Target
Use Case
Challenges
&
Opportunitie
s
Build
Prototype/Wireframes
Finalize & Present
Day 5
Day 4
Build Prototype
Craft
Scenario
Day 2-3
Materialize Model
Day 1
Use Case Model &
Generation
Business
Design
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
13. Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
15
UC1: Accelerate discussions during progress review meeting
UC2: Baseline Schedule review by Engineering discipline
UC3: Ad-hoc analysis of critical activity chains
Discipline coordinator
Planning manager
Project Director Other
Simulation
Search for
info
Search for
info
Need live
decision-
making
Primavera
Power BI
Excel/PDF
Risk Analysis
…
Excel/PDF
Unstructured data
…
Value stream map
18. Day 4. Build prototype
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
20
19. Day 4. Build prototype
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
21
20. A “google” for the plant
A possible Digital Twin
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
22
21. Key takeaways
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
23
• Representing tasks as a graph makes dependencies are more visible
• Critical path analysis techniques gather more information about scheduling
and risk
• Decision making is boosted
• Workflow detected, learning curve accelerated
• Planning review is more accessible
22. About Innovation Lab by Neo4j
Voglia di competere,
animati dal
confrontarsi su
necessità
apparentemente
distanti, portando
creatività e specificità
nel generare nuove
idee.
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
24
Experience | accelerate digital trasformation | voice of the customers
OUTCOME
23. Thank you
Planning is a graph matter - Innovation Lab Sprint
A week @Technip Energies Italy – June 2023
WATCH THE VIDEO TO KNOW MORE
Editor's Notes
So three business lines are really focused on specific markets and one is cross market.
So let's start with Gas and Low Carbon Energies where you will find LNG, Floating LNG and anything around actual gas. You will find grey and blue Hydroge, blue ammonia. You will find gas to liquids, gas processing and monetization. Basically everything that is related to gas. Also everything that emanates from natural gas will fall into these business line.
Second business line covers fuels, chemicals and circularity, it is about biofuels, traditional and clean fuels, biochemicals, sustainable chemistry, ethylene, fertilizers and circular economy.
The third one is carbon free solutions, offshore wind, which is floating wind in our case; Green H2 value chain; CO2 management; nuclear life sciences; mining & metals. So basically, everything that he's absolutely carbon free.
And finally, T.EN X Consulting and Products. It is about advisory and digital services; PMC; Cybernetix; Loading System for products; Genesis being an advisory and consulting business falls into these cross market business.
The icons at the bottom of the chart are a reminder of the four pillars.
And how basically the business lines are consistent with the four pillars that we saw earlier.