SlideShare a Scribd company logo
Site 6 - Prototype 3




                 KAP 2 – King Abdullah Project




Technical Proposal – Revision 2.03



                  Section: IP Telephony Network
                                       Solution
                                     Document author: Wael Ghazzawi

                                     Revision date: December 01, 2011




                                                                        1
Site 6 - Prototype 3

Table of Contents


    Introduction ............................................................................................................................................ 3
    Single Line Diagram ................................................................................................................................ 4
    Quantitative Analysis ............................................................................................................................. 5
    Bill of Quantities ..................................................................................................................................... 6
    Component Specifications ..................................................................................................................... 9
    Phone Sets Power Load ........................................................................................................................ 11
    Power Load & Heat Dissipation ........................................................................................................... 12
    Appendix............................................................................................................................................... 13
       A. Specification Sheet – 8488-SO-06-03-039-FD-T-300-00.dwg;
       B. Specification Sheet – 8488-SO-06-03-039-FD-T-310-00.dwg;
       C. Specification Sheet – 8488-SO-06-03-039-FD-T-320-00.dwg;
       D. Data Sheet – HP DL360G7SRVR
       E. Data Sheet – Avaya 450G
       F. Data Sheet – Avaya 1608-I BLK
       G. Data Sheet – Avaya 9621G




                                                                                                                                                                  2
Site 6 - Prototype 3

Introduction


  This Technical Submittal details the proposed HP Data Network Solution designed to be
  deployed in PROTOTYPE 3 (Site 6), “Soldiers Institute in King Fahad Security College” subject to
  the initial riser diagram(s) with:

  Reference number:

  8488-SO-06-03-039-FD-T-300-00.dwg;
  8488-SO-06-03-039-FD-T-310-00.dwg;
  8488-SO-06-03-039-FD-T-320-00.dwg;

  Titled: “King Fahad Security College in Riyadh Educational Building”
  Consultant: “Not Specified”
  File Description: The riser diagram(s) reflect the cabinet layout for the Low Current Rooms that
  are distributed over (Ground, 1st, 2nd floors). This allows the generation of a quantitative
  analysis table that reflects the number of IP Nods allowing the determination of the required
  system solution capacity.




                                                                                                     3
Site 6 - Prototype 3

Single Line Diagram


  The Following Diagram provides a high detail equivalent Riser diagram for the IP Telephony
  Solution required equivalent to the information provided in the passive riser diagram (subject
  to the project riser drawing: “8488-SO-06-03-039-FD-T-3X0-00.dwg”) with special emphases on
  showing the exact models constituting each stage of the design.




                                                                                                   4
Site 6 - Prototype 3

Quantitative Analysis

  The table below uses quantitative analysis based on the drawing(s) “Structured cabling network
  – Master Plan” projecting the exact number and type of Nods connected to each Low Current
  room in addition to projecting the number of switches and patch panels required to service
  them.

                                            Educational Building
                                               Ground Floor

                                                         Copper        Switch                        Security
                            Cabinet        UPC                                   T/D       IPTV
 N#         Cabinet                                    Patch Panel       - 24                         Outlets
                              Size       Capacity                               outlets   Outlets
                                                           24U          Ports                       (DC- CCTV)

  1    LC Cabinet GR32A    42 U        4 KW - 3 U                  2        2       20         4               9
  2    LC Cabinet GR44     42 U        4 KW - 3 U                  2        2       28         7               6
  3    LC Cabinet GR55A    42 U        4 KW - 3 U                  2        2       25         8               6
  4    LC Cabinet GR72     42U         4 KW - 3 U                  2        2       24         8               6
  5    LC Cabinet GR83A    42 U        4 KW - 3 U                  2        2       16         5               7
                                                 First Floor

                                                         Copper        Switch                        Security
                            Cabinet        UPC                                   T/D       IPTV
            Cabinet                                    Patch Panel       - 24                         Outlets
                              Size       Capacity                               outlets   Outlets
                                                           24U          Ports                       (DC- CCTV)

   6   LC Cabinet 029      42 U        4 KW - 3 U                  4        4       58         2              10
   7   LC Cabinet 048      42U         4 KW - 3 U                  3        3       41        12               4
   8   LC Cabinet 065      42 U        4 KW - 3 U                  9        9      164        12               7
   9   LC Cabinet 082      42 U        4 KW - 3 U                  4        4       67        12               6
  10   LC Cabinet 100A     42 U        4 KW - 3 U                  2        2       30         7               7
                                                 2nd Floor

                                                         Copper        Switch                        Security
                            Cabinet        UPC                                   T/D       IPTV
            Cabinet                                    Patch Panel       - 24                         Outlets
                              Size       Capacity                               outlets   Outlets
                                                           24U          Ports                       (DC- CCTV)

  11   LC Cabinet 052      42 U        4 KW - 3 U                  3        3       31         8               7
  12   LC Cabinet 081      42 U        4 KW - 3 U                  4        4       51        12               8
  13   LC Cabinet 106A     42 U        4 KW - 3 U                  8        8      138         9              13
  14   LC Cabinet 134      42 U        4 KW - 3 U                  4        4       57        12               6
  15   LC Cabinet 158A     42 U        4 KW - 3 U                  3        3       32         8               6




                                                                                                          5
Site 6 - Prototype 3

 Bill of Quantities

    The tables below provide a quantitative list of the required components/Sub-components, to
    achieve the required performance criteria as set forth in the project specifications and in
    alignment with the notes provided by the consultant on the approved drawings.


Line #   General D.        Vendor         P#      Material ID   Description                        ∑ Qty
                                          1.1      183443       CM S87XX MODEL                       1
                                                                MGMT R6 SITE ADMIN - STD/ENT ED      1
                                                    216893
                                          1.2                   LIC
                                                                AVAYA AURATM STDED R6               293
                                                    225150
                                          1.3                   101-1000NEWLIC
                                                                SAL STDALN GATEWAY LIC R1.5          1
                                          1.4       227272
                                                                DWNLD
                                          1.5       227273      SAL POLICY SRVR LIC R1.5 DWNLD       1
                                          1.6       259401      MEDIA ENCRYPTION R6+/MBT             1
                                          1.7       260054      AES 6.X BSC TSAPI FOR BNDL          293
                                                                DL360G7SRVR CM5.2.1+                 2
                                                    263764
                                          1.8                   S/D/MBT/SBC
                                                                R6 LARGE ENT DUPLX SOLUTION          1
                                                    266522
                                          1.9                   TRACKING
                                          1.10    405362641     PWR CORD USA                         2
                                          1.11    700500751     ADMIN TOOLS R6.0 CD                  1
                                                                PROGNOSIS VOIP MONITORING R3         1
                                                  700500754
         Communication                    1.12                  CD
 1.1                           Avaya              405362641     PWR CORD USA                         2
         Manager                          1.13
                                          1.14    700381254     COMPACT FLASH 128MB RHS              1
                                                                G450 MP80 W/POWER SUPPLY             2
                                                  700459456
                                          1.15                  NON-GSA
                                                                MM711 ANLG MEDIA MODULE - NON        4
                                                  700466626
                                          1.16                  GSA
                                                                MM710B E1/T1 MEDIA MODULE -          2
                                                  700466634
                                          1.17                  NON GSA
                                                                AVAYA AURATM SYSTEM PLTFRM           2
                                                  700500929
                                          1.18                  6.0.3 DVD
                                          1.19    700500961     AVAYA AURATM R6.0.1 MEDIA DVD        2
                                          1.20    700383326     96XX RPLCMNT LINE CORD              283
                                          1.21    700395445     120A CSU CABLE 50FT RHS              2
                                          1.22      232253      SA CM MODEL                          1
                                                                SA PREF AURATM R6 SE 101-1000 N1    293
                                                    238921
                                          1.23                  1YPP
                                          1.24      240505      SA PREF AES R6 BSC TSAPI 1YPP       293
                                          1.25      185146      INTRG MGMT NEW MODEL                 1




                                                                                                     6
Site 6 - Prototype 3

 Bill of Quantities (Continued)

    The tables below provide a quantitative list of the required components/Sub-components, to
    achieve the required performance criteria as set forth


Line #   General D.      Vendor           P#     Material ID   Description                       ∑ Qty
                                                               MGMT R6 SITE ADMIN LIC -                  1
                                                   216891
                                          1.26                 ASA/VAM

                                                   216894      MGMT R6 NTWK MGMT LIC - NM                1
                                          1.27
                                                               MGMT R6 PERF-ADMIN 50 VOICE SYS           1
                                                   216897
                                          1.28                 LIC

                                                               SAL STDALN GATEWAY LIC R1.5               1
                                                   227272
                                          1.29                 DWNLD

                                                   232255      SA INTGR MGMT MODEL                       1
                                          1.30
                                                               SA PREF IMR6 SITE ADM ASA/VAM             1
                                                   241716
                                          1.31                 1YPP

                                                   241726      SA PREF IM R6 NTWK MGMT 1YPP              1
                                          1.32
                                                               SA PREF IM R6 PERF-ADM 50 VCE             1
                                                   241736
                                          1.33                 1YPP
         Communication
 1.2                          Avaya
         Manager                                   184048      MM MODEL                                  1
                                          1.34
                                                               MM SIP ITG 48 CHNL N/ENCRPT               1
                                                   190930
                                          1.35                 N/CARDS

                                                               MM R5.X SPEECH TRACKING 1 SEAT          293
                                                   223959
                                          1.36                 NEW

                                                   224261      MM R5.X AV STORE SEAT TRACKING            1
                                          1.37
                                                               SAL STDALN GATEWAY LIC R1.5               1
                                                   227272
                                          1.38                 DWNLD

                                                   227273      SAL POLICY SRVR LIC R1.5 DWNLD            1
                                          1.39
                                                               MMR5.2 MAS AP LIC AVSTORE NEW             1
                                                   228140
                                          1.40                 AVSRVR

                                                               MM R5.2 MSS APP LIC NEW AVAYA             1
                                                   228141
                                          1.41                 SRVR




                                                                                                   7
Site 6 - Prototype 3

 Bill of Quantities (Continued)

       The tables below provide a quantitative list of the required components/Sub-components, to
       achieve the required performance criteria as set forth


Line #    General D.          Vendor         P#     Material ID   Description                        ∑ Qty
                                                     228159       MM R5.2 1 SEAT NEW                    293
                                             1.42
                                                      259724      MM R5.X NEW SYSTEM TRACKING                1
                                             1.43
                                                      264184      DL360 MAS SRVR MM AVSTR                    1
                                             1.44
                                                      264186      DL360 MSS SRVR MM                          1
                                             1.45
                                                     405362641    PWR CORD USA                               3
                                             1.46
          Communication
 1.3                              Avaya                           AM KEYBOARD US TYPE WITH                   1
          Manager
                                                     700403520
                                             1.47                 MOUSE RHS

                                                                  AM KVM SWITCH 2-PORT /W CABLES             1
                                                     700403785
                                             1.48                 RHS

                                                      232258      SA MSGING MODEL                            1
                                             1.49
                                                      231929      SA PREF MOD MSG R5 SEAT 1YPP             293
                                             1.50
                                                     700458532    IP PHONE 1608-I BLK                      268
                                             1.51
  2.      Phone Sets              Avaya
                                                     700480601    IP PHONE 9621G                           15
                                             1.52




                                                                                                       8
Site 6 - Prototype 3

Component Specifications

  Based on the previous section we will now start discussing our solution components and
  present a general overview on their performance details.

     (1) Communication Manager: This represents the main singular point of data aggregation
         for the IP Phone Calls, where IP and external outgoing and incoming call requests are
         processed and redirected to establish either an internal connection (Extension to
         extension call), internal to external or Extension to internal calls. Within this particular
         solution the communication manager acts as well as the Voice Mail Server with
         auto-reply and redirect capabilities that is developed in a software environment
         allowing for integration of 3rd party productivity and analysis software solutions to
         enhance the productivity. The main item that makes up the Communication Manager is:

             a. “DL360G7SRVR CM5.2.1” HP Server running Avaya software solution

         Where item (a) holds and integrates most of the software packages listed in the BoQ
         above having the server hardware developed by HP running the priority software of
         Avaya and is especially designed for deployment in medium to large scale enterprise
         solutions for highly critical applications with high performance levels and redundancy
         requirements.

         Refer to Appendix 1: Data Sheet- HP DL360G7 Server


     (2) Voice Gateway: This represents the Edge interface between STC hardware and the
         Communication Manager is meant to handle the connection of SIP, E1 and even analogue
         phone lines to the system allowing for external phone calls. What is important to note is
         that the Voice Gateway represented in our solution by the G450 as well is expandable by
         special modules that allows connecting analogue phone sets and analogue fax lines to
         the IP based solution. The main item that makes up the Voice Gateway is:

             a. “G450” Avaya Analogue Voice Gateway

         Where item (a) is meant in this designed solution to act as a modular voice gateway that
         allows the connection of external lines to the Communication Manager, as well as
         expanding the support of the IP Based solution to analogue lines given that the proper
         modules are installed in their designated locations.

         Refer to Appendix 2: Data Sheet – Avaya G450


     (3) Telephone Sets: The Phone Sets and based on the requirements and the specifications
         both quantitative and technical resulted in selecting the following two models:

             a. “1608-I BLK” Avaya Phone Set
             b. “9621G” Avaya Advanced Phone Set

         Where item (a) and (b) are directly connected to the designated ports in each room and
         programed with the generally defined extension as will be requested by the client.

         Refer to Appendix 3: Data Sheet – Avaya 1608-I BLK




                                                                                                        9
Site 6 - Prototype 3

Component Specifications (continued)

        Refer to Appendix 3: Data Sheet – Avaya 9621G




                                                                      10
Site 6 - Prototype 3

Phone Sets Power Load

     The following section will present the Power Load ratting of the components making up the
     above presented IP Telephony Solution for the purpose of facilitating the PoE requirements of
     the data switches to be used.

N#      Vendor - Model/Device                Maximum Power Load      Data-rate                   Model Number
        9621G



1.                                                 4.19 Watt         10/100/1000                       700480601




        1608I-BLK



2.                                                 3.82 Watt         10/100                            700480601




     Note: We would recommend the use of HP switches since they support Class 1 PoE devices on
     all ports of their switches allowing indiscriminant connection without worrying for overloading
     the PoE maximum capacity.




                                                                                                             11
Site 6 - Prototype 3

Power Load and Heat Dissipation

     The following section will present the Power Load ratting of the components making up the
     above presented Data Solution for the purpose of facilitating electric-design power calculation
     concerning the power-cable amp-load ratting and UPS ratting required for this section of the
     MTR. In addition the BTU head dissipation of each component and operational temperature is
     listed to help determine the best suited HVAC cooling system ratting.

                                                                                                        Operational
N#       Vendor - Model/Device               Maximum Power Load       Maximum Heat Dissipation
                                                                                                       Temperature
         G450
         Avaya Voice Gateway
                                                                                                       0 – 45 degree
1.                                                  400 Watt          1780 BTU/hr (1878 kJ/hr)
                                                                                                           Celsius


         HP Proliant DL360 G7
                                                                                                       0 – 45 degree
2.                                                  920 Watt          2968.6 BTU/hr (3132.04 kJ/hr)
                                                                                                           Celsius



     Note: To achieve the highest performance the room temperature must be kept at a maximum of
         , As well note that the BTU ratting specified above is per unit quantity, the HVAC must in
     addition take into consideration the dissipation of any additional active or radiant passive
     device placed within the same area.




                                                                                                               12
Site 6 - Prototype 3

Appendix




                         13

More Related Content

What's hot

Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...Gary Hayes
 
Power Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage CablesPower Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage Cables
Thorne & Derrick International
 
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
Thorne & Derrick International
 
VLAN and its implementation
VLAN  and its implementation VLAN  and its implementation
VLAN and its implementation
Mohit Kumar
 
Manual consul _____1773529
Manual consul _____1773529Manual consul _____1773529
Manual consul _____1773529jhonkjkj
 
Data Center Checklist for Infrastructure Best Practices (SlideShare)
Data Center Checklist for Infrastructure Best Practices (SlideShare)Data Center Checklist for Infrastructure Best Practices (SlideShare)
Data Center Checklist for Infrastructure Best Practices (SlideShare)
SP Home Run Inc.
 
Key Policy Considerations When Implementing Next-Generation Firewalls
Key Policy Considerations When Implementing Next-Generation FirewallsKey Policy Considerations When Implementing Next-Generation Firewalls
Key Policy Considerations When Implementing Next-Generation Firewalls
AlgoSec
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
Power System Operation
 
Hipot cable-testing
Hipot cable-testingHipot cable-testing
Hipot cable-testing
KEP Power Testing Ltd.
 
AUTO-RECLOSING & LOCAL SYSTEM RESTORATION
AUTO-RECLOSING & LOCAL SYSTEM RESTORATIONAUTO-RECLOSING & LOCAL SYSTEM RESTORATION
AUTO-RECLOSING & LOCAL SYSTEM RESTORATION
Power System Operation
 
High-Density Wireless Networks for Auditoriums
High-Density Wireless Networks for AuditoriumsHigh-Density Wireless Networks for Auditoriums
High-Density Wireless Networks for Auditoriums
Aruba, a Hewlett Packard Enterprise company
 
Examensarbete - Kungälv Energi
Examensarbete - Kungälv EnergiExamensarbete - Kungälv Energi
Examensarbete - Kungälv EnergiAndreas Lundell
 
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Thorne & Derrick International
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
14 palo alto quality of service(qos) concept
14 palo alto quality of service(qos) concept14 palo alto quality of service(qos) concept
14 palo alto quality of service(qos) concept
Mostafa El Lathy
 
Installation of Metering System at DTC
Installation of Metering System at DTCInstallation of Metering System at DTC
Installation of Metering System at DTCDheeraj Mehta
 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learned
michaeljmack
 
Resin Cable Joints, Multicore Power Cables XLPE PILC - Branch Joints - Cable ...
Resin Cable Joints, Multicore Power Cables XLPE PILC - Branch Joints - Cable ...Resin Cable Joints, Multicore Power Cables XLPE PILC - Branch Joints - Cable ...
Resin Cable Joints, Multicore Power Cables XLPE PILC - Branch Joints - Cable ...
Thorne & Derrick International
 
XLPE Land Cable System
XLPE Land Cable SystemXLPE Land Cable System
XLPE Land Cable System
Beny Indrawan S
 

What's hot (20)

Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
 
Power Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage CablesPower Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage Cables
 
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
 
VLAN and its implementation
VLAN  and its implementation VLAN  and its implementation
VLAN and its implementation
 
Manual consul _____1773529
Manual consul _____1773529Manual consul _____1773529
Manual consul _____1773529
 
Data Center Checklist for Infrastructure Best Practices (SlideShare)
Data Center Checklist for Infrastructure Best Practices (SlideShare)Data Center Checklist for Infrastructure Best Practices (SlideShare)
Data Center Checklist for Infrastructure Best Practices (SlideShare)
 
Key Policy Considerations When Implementing Next-Generation Firewalls
Key Policy Considerations When Implementing Next-Generation FirewallsKey Policy Considerations When Implementing Next-Generation Firewalls
Key Policy Considerations When Implementing Next-Generation Firewalls
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Hipot cable-testing
Hipot cable-testingHipot cable-testing
Hipot cable-testing
 
AUTO-RECLOSING & LOCAL SYSTEM RESTORATION
AUTO-RECLOSING & LOCAL SYSTEM RESTORATIONAUTO-RECLOSING & LOCAL SYSTEM RESTORATION
AUTO-RECLOSING & LOCAL SYSTEM RESTORATION
 
High-Density Wireless Networks for Auditoriums
High-Density Wireless Networks for AuditoriumsHigh-Density Wireless Networks for Auditoriums
High-Density Wireless Networks for Auditoriums
 
Examensarbete - Kungälv Energi
Examensarbete - Kungälv EnergiExamensarbete - Kungälv Energi
Examensarbete - Kungälv Energi
 
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
14 palo alto quality of service(qos) concept
14 palo alto quality of service(qos) concept14 palo alto quality of service(qos) concept
14 palo alto quality of service(qos) concept
 
Installation of Metering System at DTC
Installation of Metering System at DTCInstallation of Metering System at DTC
Installation of Metering System at DTC
 
Datacenter overview
Datacenter overviewDatacenter overview
Datacenter overview
 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learned
 
Resin Cable Joints, Multicore Power Cables XLPE PILC - Branch Joints - Cable ...
Resin Cable Joints, Multicore Power Cables XLPE PILC - Branch Joints - Cable ...Resin Cable Joints, Multicore Power Cables XLPE PILC - Branch Joints - Cable ...
Resin Cable Joints, Multicore Power Cables XLPE PILC - Branch Joints - Cable ...
 
XLPE Land Cable System
XLPE Land Cable SystemXLPE Land Cable System
XLPE Land Cable System
 

Similar to Technical Proposal - IP Telephony

Technical Proposal - Structured Cabling
Technical Proposal - Structured CablingTechnical Proposal - Structured Cabling
Technical Proposal - Structured Cabling
wolfthrone
 
Distributech 2015 taking interoperability to the next level
Distributech 2015   taking interoperability to the next levelDistributech 2015   taking interoperability to the next level
Distributech 2015 taking interoperability to the next level
Schneider Electric
 
Technical Proposal - IPTV - Solution Design
Technical Proposal - IPTV - Solution DesignTechnical Proposal - IPTV - Solution Design
Technical Proposal - IPTV - Solution Design
wolfthrone
 
Advanced view of atmega microcontroller projects list (1632) at mega32 avr
Advanced view of atmega microcontroller projects list (1632)   at mega32 avrAdvanced view of atmega microcontroller projects list (1632)   at mega32 avr
Advanced view of atmega microcontroller projects list (1632) at mega32 avr
WiseNaeem
 
PLC-updated.pptx
PLC-updated.pptxPLC-updated.pptx
PLC-updated.pptx
Sachiv3
 
Cost Efficient Design of Reversible Adder Circuits for Low Power Applications
Cost Efficient Design of Reversible Adder Circuits for Low Power ApplicationsCost Efficient Design of Reversible Adder Circuits for Low Power Applications
Cost Efficient Design of Reversible Adder Circuits for Low Power Applications
VIT-AP University
 
Functional Test Systems - Testing Days Bajío
Functional Test Systems - Testing Days BajíoFunctional Test Systems - Testing Days Bajío
Functional Test Systems - Testing Days Bajío
Interlatin
 
Technical Proposal - IPTV - Channel Management
Technical Proposal - IPTV - Channel ManagementTechnical Proposal - IPTV - Channel Management
Technical Proposal - IPTV - Channel Management
wolfthrone
 
Datasheet bq33200
Datasheet bq33200Datasheet bq33200
Datasheet bq33200
Đức Hữu
 
Allenbradley Control Logix PLC Network Architecture
Allenbradley Control Logix PLC Network  ArchitectureAllenbradley Control Logix PLC Network  Architecture
Allenbradley Control Logix PLC Network Architecture
DEEPAK GORAI
 
pec_en-A1.ppt
pec_en-A1.pptpec_en-A1.ppt
pec_en-A1.ppt
PoiuytPoiuyt2
 
Cisco catalyst 6500 architecture white paper
Cisco catalyst 6500 architecture white paperCisco catalyst 6500 architecture white paper
Cisco catalyst 6500 architecture white paper
IT Tech
 
L13 ic based triggering circuit
L13 ic based triggering circuitL13 ic based triggering circuit
L13 ic based triggering circuit
Mohammad Umar Rehman
 
Cisco catalyst 3650-24ts-s datasheet
Cisco catalyst 3650-24ts-s datasheetCisco catalyst 3650-24ts-s datasheet
Cisco catalyst 3650-24ts-s datasheet
Mark Tsui
 
Frdm k64 f-sch
Frdm k64 f-schFrdm k64 f-sch
Frdm k64 f-sch
Fernando
 
74ALVT162245DGG:11- Componentschip.com
74ALVT162245DGG:11- Componentschip.com74ALVT162245DGG:11- Componentschip.com
74ALVT162245DGG:11- Componentschip.com
Kenny Choi
 
Rockwell Automation (Alleb-Bradley Products )
Rockwell Automation (Alleb-Bradley Products )Rockwell Automation (Alleb-Bradley Products )
Rockwell Automation (Alleb-Bradley Products )VIVEK YADAV
 

Similar to Technical Proposal - IP Telephony (20)

Technical Proposal - Structured Cabling
Technical Proposal - Structured CablingTechnical Proposal - Structured Cabling
Technical Proposal - Structured Cabling
 
Distributech 2015 taking interoperability to the next level
Distributech 2015   taking interoperability to the next levelDistributech 2015   taking interoperability to the next level
Distributech 2015 taking interoperability to the next level
 
Technical Proposal - IPTV - Solution Design
Technical Proposal - IPTV - Solution DesignTechnical Proposal - IPTV - Solution Design
Technical Proposal - IPTV - Solution Design
 
Advanced view of atmega microcontroller projects list (1632) at mega32 avr
Advanced view of atmega microcontroller projects list (1632)   at mega32 avrAdvanced view of atmega microcontroller projects list (1632)   at mega32 avr
Advanced view of atmega microcontroller projects list (1632) at mega32 avr
 
SynergieCAD-V93K-CTH-Configuration_MAR16
SynergieCAD-V93K-CTH-Configuration_MAR16SynergieCAD-V93K-CTH-Configuration_MAR16
SynergieCAD-V93K-CTH-Configuration_MAR16
 
PLC-updated.pptx
PLC-updated.pptxPLC-updated.pptx
PLC-updated.pptx
 
Cost Efficient Design of Reversible Adder Circuits for Low Power Applications
Cost Efficient Design of Reversible Adder Circuits for Low Power ApplicationsCost Efficient Design of Reversible Adder Circuits for Low Power Applications
Cost Efficient Design of Reversible Adder Circuits for Low Power Applications
 
Functional Test Systems - Testing Days Bajío
Functional Test Systems - Testing Days BajíoFunctional Test Systems - Testing Days Bajío
Functional Test Systems - Testing Days Bajío
 
Technical Proposal - IPTV - Channel Management
Technical Proposal - IPTV - Channel ManagementTechnical Proposal - IPTV - Channel Management
Technical Proposal - IPTV - Channel Management
 
broadband
broadbandbroadband
broadband
 
Datasheet bq33200
Datasheet bq33200Datasheet bq33200
Datasheet bq33200
 
Allenbradley Control Logix PLC Network Architecture
Allenbradley Control Logix PLC Network  ArchitectureAllenbradley Control Logix PLC Network  Architecture
Allenbradley Control Logix PLC Network Architecture
 
pec_en-A1.ppt
pec_en-A1.pptpec_en-A1.ppt
pec_en-A1.ppt
 
Cisco catalyst 6500 architecture white paper
Cisco catalyst 6500 architecture white paperCisco catalyst 6500 architecture white paper
Cisco catalyst 6500 architecture white paper
 
L13 ic based triggering circuit
L13 ic based triggering circuitL13 ic based triggering circuit
L13 ic based triggering circuit
 
Cisco catalyst 3650-24ts-s datasheet
Cisco catalyst 3650-24ts-s datasheetCisco catalyst 3650-24ts-s datasheet
Cisco catalyst 3650-24ts-s datasheet
 
Frdm k64 f-sch
Frdm k64 f-schFrdm k64 f-sch
Frdm k64 f-sch
 
project 3 full report
project 3 full reportproject 3 full report
project 3 full report
 
74ALVT162245DGG:11- Componentschip.com
74ALVT162245DGG:11- Componentschip.com74ALVT162245DGG:11- Componentschip.com
74ALVT162245DGG:11- Componentschip.com
 
Rockwell Automation (Alleb-Bradley Products )
Rockwell Automation (Alleb-Bradley Products )Rockwell Automation (Alleb-Bradley Products )
Rockwell Automation (Alleb-Bradley Products )
 

Recently uploaded

To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Paul Groth
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
g2nightmarescribd
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
Dorra BARTAGUIZ
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 

Recently uploaded (20)

To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 

Technical Proposal - IP Telephony

  • 1. Site 6 - Prototype 3 KAP 2 – King Abdullah Project Technical Proposal – Revision 2.03 Section: IP Telephony Network Solution Document author: Wael Ghazzawi Revision date: December 01, 2011 1
  • 2. Site 6 - Prototype 3 Table of Contents Introduction ............................................................................................................................................ 3 Single Line Diagram ................................................................................................................................ 4 Quantitative Analysis ............................................................................................................................. 5 Bill of Quantities ..................................................................................................................................... 6 Component Specifications ..................................................................................................................... 9 Phone Sets Power Load ........................................................................................................................ 11 Power Load & Heat Dissipation ........................................................................................................... 12 Appendix............................................................................................................................................... 13 A. Specification Sheet – 8488-SO-06-03-039-FD-T-300-00.dwg; B. Specification Sheet – 8488-SO-06-03-039-FD-T-310-00.dwg; C. Specification Sheet – 8488-SO-06-03-039-FD-T-320-00.dwg; D. Data Sheet – HP DL360G7SRVR E. Data Sheet – Avaya 450G F. Data Sheet – Avaya 1608-I BLK G. Data Sheet – Avaya 9621G 2
  • 3. Site 6 - Prototype 3 Introduction This Technical Submittal details the proposed HP Data Network Solution designed to be deployed in PROTOTYPE 3 (Site 6), “Soldiers Institute in King Fahad Security College” subject to the initial riser diagram(s) with: Reference number: 8488-SO-06-03-039-FD-T-300-00.dwg; 8488-SO-06-03-039-FD-T-310-00.dwg; 8488-SO-06-03-039-FD-T-320-00.dwg; Titled: “King Fahad Security College in Riyadh Educational Building” Consultant: “Not Specified” File Description: The riser diagram(s) reflect the cabinet layout for the Low Current Rooms that are distributed over (Ground, 1st, 2nd floors). This allows the generation of a quantitative analysis table that reflects the number of IP Nods allowing the determination of the required system solution capacity. 3
  • 4. Site 6 - Prototype 3 Single Line Diagram The Following Diagram provides a high detail equivalent Riser diagram for the IP Telephony Solution required equivalent to the information provided in the passive riser diagram (subject to the project riser drawing: “8488-SO-06-03-039-FD-T-3X0-00.dwg”) with special emphases on showing the exact models constituting each stage of the design. 4
  • 5. Site 6 - Prototype 3 Quantitative Analysis The table below uses quantitative analysis based on the drawing(s) “Structured cabling network – Master Plan” projecting the exact number and type of Nods connected to each Low Current room in addition to projecting the number of switches and patch panels required to service them. Educational Building Ground Floor Copper Switch Security Cabinet UPC T/D IPTV N# Cabinet Patch Panel - 24 Outlets Size Capacity outlets Outlets 24U Ports (DC- CCTV) 1 LC Cabinet GR32A 42 U 4 KW - 3 U 2 2 20 4 9 2 LC Cabinet GR44 42 U 4 KW - 3 U 2 2 28 7 6 3 LC Cabinet GR55A 42 U 4 KW - 3 U 2 2 25 8 6 4 LC Cabinet GR72 42U 4 KW - 3 U 2 2 24 8 6 5 LC Cabinet GR83A 42 U 4 KW - 3 U 2 2 16 5 7 First Floor Copper Switch Security Cabinet UPC T/D IPTV Cabinet Patch Panel - 24 Outlets Size Capacity outlets Outlets 24U Ports (DC- CCTV) 6 LC Cabinet 029 42 U 4 KW - 3 U 4 4 58 2 10 7 LC Cabinet 048 42U 4 KW - 3 U 3 3 41 12 4 8 LC Cabinet 065 42 U 4 KW - 3 U 9 9 164 12 7 9 LC Cabinet 082 42 U 4 KW - 3 U 4 4 67 12 6 10 LC Cabinet 100A 42 U 4 KW - 3 U 2 2 30 7 7 2nd Floor Copper Switch Security Cabinet UPC T/D IPTV Cabinet Patch Panel - 24 Outlets Size Capacity outlets Outlets 24U Ports (DC- CCTV) 11 LC Cabinet 052 42 U 4 KW - 3 U 3 3 31 8 7 12 LC Cabinet 081 42 U 4 KW - 3 U 4 4 51 12 8 13 LC Cabinet 106A 42 U 4 KW - 3 U 8 8 138 9 13 14 LC Cabinet 134 42 U 4 KW - 3 U 4 4 57 12 6 15 LC Cabinet 158A 42 U 4 KW - 3 U 3 3 32 8 6 5
  • 6. Site 6 - Prototype 3 Bill of Quantities The tables below provide a quantitative list of the required components/Sub-components, to achieve the required performance criteria as set forth in the project specifications and in alignment with the notes provided by the consultant on the approved drawings. Line # General D. Vendor P# Material ID Description ∑ Qty 1.1 183443 CM S87XX MODEL 1 MGMT R6 SITE ADMIN - STD/ENT ED 1 216893 1.2 LIC AVAYA AURATM STDED R6 293 225150 1.3 101-1000NEWLIC SAL STDALN GATEWAY LIC R1.5 1 1.4 227272 DWNLD 1.5 227273 SAL POLICY SRVR LIC R1.5 DWNLD 1 1.6 259401 MEDIA ENCRYPTION R6+/MBT 1 1.7 260054 AES 6.X BSC TSAPI FOR BNDL 293 DL360G7SRVR CM5.2.1+ 2 263764 1.8 S/D/MBT/SBC R6 LARGE ENT DUPLX SOLUTION 1 266522 1.9 TRACKING 1.10 405362641 PWR CORD USA 2 1.11 700500751 ADMIN TOOLS R6.0 CD 1 PROGNOSIS VOIP MONITORING R3 1 700500754 Communication 1.12 CD 1.1 Avaya 405362641 PWR CORD USA 2 Manager 1.13 1.14 700381254 COMPACT FLASH 128MB RHS 1 G450 MP80 W/POWER SUPPLY 2 700459456 1.15 NON-GSA MM711 ANLG MEDIA MODULE - NON 4 700466626 1.16 GSA MM710B E1/T1 MEDIA MODULE - 2 700466634 1.17 NON GSA AVAYA AURATM SYSTEM PLTFRM 2 700500929 1.18 6.0.3 DVD 1.19 700500961 AVAYA AURATM R6.0.1 MEDIA DVD 2 1.20 700383326 96XX RPLCMNT LINE CORD 283 1.21 700395445 120A CSU CABLE 50FT RHS 2 1.22 232253 SA CM MODEL 1 SA PREF AURATM R6 SE 101-1000 N1 293 238921 1.23 1YPP 1.24 240505 SA PREF AES R6 BSC TSAPI 1YPP 293 1.25 185146 INTRG MGMT NEW MODEL 1 6
  • 7. Site 6 - Prototype 3 Bill of Quantities (Continued) The tables below provide a quantitative list of the required components/Sub-components, to achieve the required performance criteria as set forth Line # General D. Vendor P# Material ID Description ∑ Qty MGMT R6 SITE ADMIN LIC - 1 216891 1.26 ASA/VAM 216894 MGMT R6 NTWK MGMT LIC - NM 1 1.27 MGMT R6 PERF-ADMIN 50 VOICE SYS 1 216897 1.28 LIC SAL STDALN GATEWAY LIC R1.5 1 227272 1.29 DWNLD 232255 SA INTGR MGMT MODEL 1 1.30 SA PREF IMR6 SITE ADM ASA/VAM 1 241716 1.31 1YPP 241726 SA PREF IM R6 NTWK MGMT 1YPP 1 1.32 SA PREF IM R6 PERF-ADM 50 VCE 1 241736 1.33 1YPP Communication 1.2 Avaya Manager 184048 MM MODEL 1 1.34 MM SIP ITG 48 CHNL N/ENCRPT 1 190930 1.35 N/CARDS MM R5.X SPEECH TRACKING 1 SEAT 293 223959 1.36 NEW 224261 MM R5.X AV STORE SEAT TRACKING 1 1.37 SAL STDALN GATEWAY LIC R1.5 1 227272 1.38 DWNLD 227273 SAL POLICY SRVR LIC R1.5 DWNLD 1 1.39 MMR5.2 MAS AP LIC AVSTORE NEW 1 228140 1.40 AVSRVR MM R5.2 MSS APP LIC NEW AVAYA 1 228141 1.41 SRVR 7
  • 8. Site 6 - Prototype 3 Bill of Quantities (Continued) The tables below provide a quantitative list of the required components/Sub-components, to achieve the required performance criteria as set forth Line # General D. Vendor P# Material ID Description ∑ Qty 228159 MM R5.2 1 SEAT NEW 293 1.42 259724 MM R5.X NEW SYSTEM TRACKING 1 1.43 264184 DL360 MAS SRVR MM AVSTR 1 1.44 264186 DL360 MSS SRVR MM 1 1.45 405362641 PWR CORD USA 3 1.46 Communication 1.3 Avaya AM KEYBOARD US TYPE WITH 1 Manager 700403520 1.47 MOUSE RHS AM KVM SWITCH 2-PORT /W CABLES 1 700403785 1.48 RHS 232258 SA MSGING MODEL 1 1.49 231929 SA PREF MOD MSG R5 SEAT 1YPP 293 1.50 700458532 IP PHONE 1608-I BLK 268 1.51 2. Phone Sets Avaya 700480601 IP PHONE 9621G 15 1.52 8
  • 9. Site 6 - Prototype 3 Component Specifications Based on the previous section we will now start discussing our solution components and present a general overview on their performance details. (1) Communication Manager: This represents the main singular point of data aggregation for the IP Phone Calls, where IP and external outgoing and incoming call requests are processed and redirected to establish either an internal connection (Extension to extension call), internal to external or Extension to internal calls. Within this particular solution the communication manager acts as well as the Voice Mail Server with auto-reply and redirect capabilities that is developed in a software environment allowing for integration of 3rd party productivity and analysis software solutions to enhance the productivity. The main item that makes up the Communication Manager is: a. “DL360G7SRVR CM5.2.1” HP Server running Avaya software solution Where item (a) holds and integrates most of the software packages listed in the BoQ above having the server hardware developed by HP running the priority software of Avaya and is especially designed for deployment in medium to large scale enterprise solutions for highly critical applications with high performance levels and redundancy requirements. Refer to Appendix 1: Data Sheet- HP DL360G7 Server (2) Voice Gateway: This represents the Edge interface between STC hardware and the Communication Manager is meant to handle the connection of SIP, E1 and even analogue phone lines to the system allowing for external phone calls. What is important to note is that the Voice Gateway represented in our solution by the G450 as well is expandable by special modules that allows connecting analogue phone sets and analogue fax lines to the IP based solution. The main item that makes up the Voice Gateway is: a. “G450” Avaya Analogue Voice Gateway Where item (a) is meant in this designed solution to act as a modular voice gateway that allows the connection of external lines to the Communication Manager, as well as expanding the support of the IP Based solution to analogue lines given that the proper modules are installed in their designated locations. Refer to Appendix 2: Data Sheet – Avaya G450 (3) Telephone Sets: The Phone Sets and based on the requirements and the specifications both quantitative and technical resulted in selecting the following two models: a. “1608-I BLK” Avaya Phone Set b. “9621G” Avaya Advanced Phone Set Where item (a) and (b) are directly connected to the designated ports in each room and programed with the generally defined extension as will be requested by the client. Refer to Appendix 3: Data Sheet – Avaya 1608-I BLK 9
  • 10. Site 6 - Prototype 3 Component Specifications (continued) Refer to Appendix 3: Data Sheet – Avaya 9621G 10
  • 11. Site 6 - Prototype 3 Phone Sets Power Load The following section will present the Power Load ratting of the components making up the above presented IP Telephony Solution for the purpose of facilitating the PoE requirements of the data switches to be used. N# Vendor - Model/Device Maximum Power Load Data-rate Model Number 9621G 1. 4.19 Watt 10/100/1000 700480601 1608I-BLK 2. 3.82 Watt 10/100 700480601 Note: We would recommend the use of HP switches since they support Class 1 PoE devices on all ports of their switches allowing indiscriminant connection without worrying for overloading the PoE maximum capacity. 11
  • 12. Site 6 - Prototype 3 Power Load and Heat Dissipation The following section will present the Power Load ratting of the components making up the above presented Data Solution for the purpose of facilitating electric-design power calculation concerning the power-cable amp-load ratting and UPS ratting required for this section of the MTR. In addition the BTU head dissipation of each component and operational temperature is listed to help determine the best suited HVAC cooling system ratting. Operational N# Vendor - Model/Device Maximum Power Load Maximum Heat Dissipation Temperature G450 Avaya Voice Gateway 0 – 45 degree 1. 400 Watt 1780 BTU/hr (1878 kJ/hr) Celsius HP Proliant DL360 G7 0 – 45 degree 2. 920 Watt 2968.6 BTU/hr (3132.04 kJ/hr) Celsius Note: To achieve the highest performance the room temperature must be kept at a maximum of , As well note that the BTU ratting specified above is per unit quantity, the HVAC must in addition take into consideration the dissipation of any additional active or radiant passive device placed within the same area. 12
  • 13. Site 6 - Prototype 3 Appendix 13