SlideShare a Scribd company logo
1 of 4
Download to read offline
Nuffield Health, Bournemouth Hospital
In a challenging live environment, SWH Build undertook extensive refurbishment
and internal alterations to the Purbeck Ward at Nuffield Hospital, Bournemouth. In
addition to the main ward, the project also included minor enabling and phasing
works throughout the hospital.
This 12 week contract period was non-negotiable in terms of deadline due to other
operational aspects of the hospital. To achieve completion on programme, SWH
Build managers formed excellent working relationships with key hospital personnel
to ensure efficient communication.
Despite the complexities of the building and challenges of working around live
operating theatres, the SWH Build team achieved what at times seemed the
impossible, and ultimately completed the project on programme.
The Purbeck Ward was handed back to the hospital early January 2015 amongst
high praise from hospital management, and will go on to reinforce the excellent and
growing reputation of SWH Build working in healthcare environments.
The right people for the job
Poole High School
This project commenced early May and ran through until late
August 2014 with SWH Build working to a non-negotiable
deadline to coincide with the start of a new school year.
The programme of work involved a high specification re-roof
and re-clad of existing modular buildings in addition to an
extensive internal refurbishment.
The SWH Build team were up against the clock from the offset.
Other issues such as restricted access and adapting to a live
environment were also challenges met by the team, led by
Area Manager and former pupil of the school, Luke Trussler.
Design issues presented by the age of the existing building
were successfully overcome through the course of the job.
Despite these complications, this project achieved completed
on time and the SWH Build team had a very positive impact
on the staff at Poole High School, with the Site Manager being
invited to join the Board of Governors as a Consultant for Build
and Maintenance.
As a result of the successful works, mid-way into the project
SWH Build were also asked to complete a second project
within the timescale; converting and refurbishing the existing
caretaker’s house into an inclusion unit for the children at the
school. This additional work, led by Andrew Knowler Contracts
Supervisor, ran alongside the original project smoothly and
was completed in line with the main works and the start of the
new school year.
Preston Academy ASD Unit
This design and build project consisted of the construction of a single storey stand-
alone building in the grounds of Preston Academy School in Yeovil. Working closely
with our chosen architects, Reed Holland, the new build Autism Unit was completed
January 2014 and opened to pupils April 2014. The facility provides a specific
learning environment for the pupils, who have Autism and Asperger’s Syndrome.
The high performance design was constructed from traditional block work with a
mixture of finish render and cedar timber cladding. Internally, the building created
a calming atmosphere and was decorated in light colours while specific carpets
were selected for their particular material. Sound scoops were inserted into the walls
of all teaching areas to reduce the amount of noise passing through. Underfloor
heating runs throughout the build. SWH undertook all mechanical and electrical
works including the installation of IT systems and a security system.
We do more than you think
Musbury Care Home
The works at Musbury Care Home, Axminister, consisted of the
conversion of a large ground floor garage space in a new supported
living space comprising of 3, high specification, self-contained ensuite
rooms with communal facilities.
In addition, SWH Build also converted first floor office space into
comfortable living quarters for the onsite care team.
A live project from January 2014 until April 2014, the new living
spaces were handed over on programme with hugely positive reaction
from residents and staff alike.
Head Office
Rockbeare Hill
Rockbeare
Exeter
Devon
EX5 2HB
01404 821 500
Poole
Arena Business Centre
Holyrood Close
Poole
Dorset
BH17 7FJ
01202 607 446
Plymouth
First Floor, Building 1
Brooklands Office Campus
Budshead Road
Crownhill
Plymouth
PL6 5XR
01752 967 867
ContainsOrdnanceSurveydata©Crowncopyrightanddatabaserights2015
1
3
2
1
2
3
swhltd.co.uk

More Related Content

Similar to SWH Build Poole Brochure

Australian Catholic University Package A
Australian Catholic University Package AAustralian Catholic University Package A
Australian Catholic University Package AOd Solutions
 
John Flynn Private Hospital
John Flynn Private Hospital John Flynn Private Hospital
John Flynn Private Hospital Od Solutions
 
University of Queensland Steele Building
University of Queensland Steele Building University of Queensland Steele Building
University of Queensland Steele Building Od Solutions
 
Rostrevor College
Rostrevor College Rostrevor College
Rostrevor College Od Solutions
 
Whitescape State Education Case Study
Whitescape State Education Case StudyWhitescape State Education Case Study
Whitescape State Education Case StudyAndrew White
 
Lewis & Hickey - Education
Lewis & Hickey - EducationLewis & Hickey - Education
Lewis & Hickey - EducationTim Hall
 
Case Study - Bethnal Green Community College
Case Study - Bethnal Green Community CollegeCase Study - Bethnal Green Community College
Case Study - Bethnal Green Community CollegeFlexiDry Global Ltd
 
Kingston City School District Superintendent Goals Summary Report
Kingston City School District Superintendent Goals Summary Report Kingston City School District Superintendent Goals Summary Report
Kingston City School District Superintendent Goals Summary Report Preview Freeman
 
Broadstock Highfield BSF Casestudy
Broadstock Highfield BSF CasestudyBroadstock Highfield BSF Casestudy
Broadstock Highfield BSF Casestudyjonstoney
 
2016_project sheets
2016_project sheets2016_project sheets
2016_project sheetscathy kubany
 
Braithwaite Case Study Fit Out
Braithwaite Case Study Fit OutBraithwaite Case Study Fit Out
Braithwaite Case Study Fit Outlukebraithwaite
 
Creating excellent-primary-schools 2
Creating excellent-primary-schools 2Creating excellent-primary-schools 2
Creating excellent-primary-schools 2HugoCopire1
 
Woodbar Education Brochure
Woodbar Education BrochureWoodbar Education Brochure
Woodbar Education BrochureBarry Robinson
 
O.H. Platt HS additions & renovations
O.H. Platt HS additions & renovationsO.H. Platt HS additions & renovations
O.H. Platt HS additions & renovationsSteve Baranello
 
Newsletter oct dec 2013
Newsletter oct   dec 2013Newsletter oct   dec 2013
Newsletter oct dec 2013Lauren Poston
 

Similar to SWH Build Poole Brochure (20)

Australian Catholic University Package A
Australian Catholic University Package AAustralian Catholic University Package A
Australian Catholic University Package A
 
John Flynn Private Hospital
John Flynn Private Hospital John Flynn Private Hospital
John Flynn Private Hospital
 
University of Queensland Steele Building
University of Queensland Steele Building University of Queensland Steele Building
University of Queensland Steele Building
 
Rostrevor College
Rostrevor College Rostrevor College
Rostrevor College
 
Glenn Hutchison # Project Portfolio # V9
Glenn Hutchison # Project Portfolio # V9Glenn Hutchison # Project Portfolio # V9
Glenn Hutchison # Project Portfolio # V9
 
Whitescape State Education Case Study
Whitescape State Education Case StudyWhitescape State Education Case Study
Whitescape State Education Case Study
 
Lewis & Hickey - Education
Lewis & Hickey - EducationLewis & Hickey - Education
Lewis & Hickey - Education
 
Case Study - Bethnal Green Community College
Case Study - Bethnal Green Community CollegeCase Study - Bethnal Green Community College
Case Study - Bethnal Green Community College
 
Kingston City School District Superintendent Goals Summary Report
Kingston City School District Superintendent Goals Summary Report Kingston City School District Superintendent Goals Summary Report
Kingston City School District Superintendent Goals Summary Report
 
Reference S V Smyth - Prof Atkin
Reference S V Smyth - Prof AtkinReference S V Smyth - Prof Atkin
Reference S V Smyth - Prof Atkin
 
St Mark's Center for Innovation
St Mark's Center for InnovationSt Mark's Center for Innovation
St Mark's Center for Innovation
 
Broadstock Highfield BSF Casestudy
Broadstock Highfield BSF CasestudyBroadstock Highfield BSF Casestudy
Broadstock Highfield BSF Casestudy
 
2016_project sheets
2016_project sheets2016_project sheets
2016_project sheets
 
JG Molloy Brochure - Building On Our Reputation
JG Molloy Brochure - Building On Our ReputationJG Molloy Brochure - Building On Our Reputation
JG Molloy Brochure - Building On Our Reputation
 
Braithwaite Case Study Fit Out
Braithwaite Case Study Fit OutBraithwaite Case Study Fit Out
Braithwaite Case Study Fit Out
 
Creating excellent-primary-schools 2
Creating excellent-primary-schools 2Creating excellent-primary-schools 2
Creating excellent-primary-schools 2
 
Woodbar Education Brochure
Woodbar Education BrochureWoodbar Education Brochure
Woodbar Education Brochure
 
O.H. Platt HS additions & renovations
O.H. Platt HS additions & renovationsO.H. Platt HS additions & renovations
O.H. Platt HS additions & renovations
 
Newsletter oct dec 2013
Newsletter oct   dec 2013Newsletter oct   dec 2013
Newsletter oct dec 2013
 
Get modern
Get modernGet modern
Get modern
 

SWH Build Poole Brochure

  • 1.
  • 2. Nuffield Health, Bournemouth Hospital In a challenging live environment, SWH Build undertook extensive refurbishment and internal alterations to the Purbeck Ward at Nuffield Hospital, Bournemouth. In addition to the main ward, the project also included minor enabling and phasing works throughout the hospital. This 12 week contract period was non-negotiable in terms of deadline due to other operational aspects of the hospital. To achieve completion on programme, SWH Build managers formed excellent working relationships with key hospital personnel to ensure efficient communication. Despite the complexities of the building and challenges of working around live operating theatres, the SWH Build team achieved what at times seemed the impossible, and ultimately completed the project on programme. The Purbeck Ward was handed back to the hospital early January 2015 amongst high praise from hospital management, and will go on to reinforce the excellent and growing reputation of SWH Build working in healthcare environments. The right people for the job Poole High School This project commenced early May and ran through until late August 2014 with SWH Build working to a non-negotiable deadline to coincide with the start of a new school year. The programme of work involved a high specification re-roof and re-clad of existing modular buildings in addition to an extensive internal refurbishment. The SWH Build team were up against the clock from the offset. Other issues such as restricted access and adapting to a live environment were also challenges met by the team, led by Area Manager and former pupil of the school, Luke Trussler. Design issues presented by the age of the existing building were successfully overcome through the course of the job. Despite these complications, this project achieved completed on time and the SWH Build team had a very positive impact on the staff at Poole High School, with the Site Manager being invited to join the Board of Governors as a Consultant for Build and Maintenance. As a result of the successful works, mid-way into the project SWH Build were also asked to complete a second project within the timescale; converting and refurbishing the existing caretaker’s house into an inclusion unit for the children at the school. This additional work, led by Andrew Knowler Contracts Supervisor, ran alongside the original project smoothly and was completed in line with the main works and the start of the new school year.
  • 3. Preston Academy ASD Unit This design and build project consisted of the construction of a single storey stand- alone building in the grounds of Preston Academy School in Yeovil. Working closely with our chosen architects, Reed Holland, the new build Autism Unit was completed January 2014 and opened to pupils April 2014. The facility provides a specific learning environment for the pupils, who have Autism and Asperger’s Syndrome. The high performance design was constructed from traditional block work with a mixture of finish render and cedar timber cladding. Internally, the building created a calming atmosphere and was decorated in light colours while specific carpets were selected for their particular material. Sound scoops were inserted into the walls of all teaching areas to reduce the amount of noise passing through. Underfloor heating runs throughout the build. SWH undertook all mechanical and electrical works including the installation of IT systems and a security system. We do more than you think Musbury Care Home The works at Musbury Care Home, Axminister, consisted of the conversion of a large ground floor garage space in a new supported living space comprising of 3, high specification, self-contained ensuite rooms with communal facilities. In addition, SWH Build also converted first floor office space into comfortable living quarters for the onsite care team. A live project from January 2014 until April 2014, the new living spaces were handed over on programme with hugely positive reaction from residents and staff alike.
  • 4. Head Office Rockbeare Hill Rockbeare Exeter Devon EX5 2HB 01404 821 500 Poole Arena Business Centre Holyrood Close Poole Dorset BH17 7FJ 01202 607 446 Plymouth First Floor, Building 1 Brooklands Office Campus Budshead Road Crownhill Plymouth PL6 5XR 01752 967 867 ContainsOrdnanceSurveydata©Crowncopyrightanddatabaserights2015 1 3 2 1 2 3 swhltd.co.uk