STAGE 1 PRESENTATION
AT….M/S Larsen & Toubro
Vishal Kotiya (60012148002)
Mentor :- E Narayanan
INTRODUCTION TO L&T
• Larsen & Toubro Limited” is India’s premier technology – driven company
with leading edge capabilities in the fields related to Engineering,
Infrastructure & Basic Industries
• The main functioning L&T workshop is located at Hazira, which is spread
over an area of 73,600sq.mtrs.
• The powai campus of L&T is the oldest facility as well as the most diverse in
terms of employee strength and operations
• The campus is well equipped with facilites for fabrication, machining,
handling & quality control
ORGANISATIONAL STRUCTURE
PRESENT STATUS OF L&T
• L&T From the last 7 Decades Serving Vital Human needs have diversified
into its each and every range of products and projects.
• Ranging from nuclear, hydrocarbon, aerospace, shipbuilding, electrical &
electronics
• the company produces precision engineering components and have
mastered in the manufacturing of heat exchangers and pressure vessels.
• L&T now have 23 manufacturing units spread all over the country.
• IT aims to build on its traditional strengths and fulfils its vision of becoming a
world-class company dedicated to professionalism & excellence.
INTRODUCTION TO FLIGHT SYSTEM
BUISNESS UNIT (FSBU)
FLIGHT SYSTEM BUISNESS UNIT
• As the name implies, the department is concerned with the production of
testing equipment's for defence & space vehicles.
• This department manufactures the motor casing of the Polar Satellite
Launch Vehicle (PSLV) as well as the booster of the Geo-stationary Satellite
Launch Vehicle (GSLV).
• Current projects undergoing in the department are Reflector deployment
mechanism, Hpersonic wind tunnel system.
• manufacture of Rocket Motor Casings: S200 for GSLV Mk III and S139 for
PSLV & GSLV.
• The group is been divided into 4 sub groups such as Design group, project
management group, marketing & quality control.
INTRODUCTION TO PROJECT
MANGEMENT GROUP
• The group is involved in management and planning of all critical activity
which is required for the production of the job.
• The department is been subdivided into no of teams which deals with
planning of different components to be manufactured from the whole as a
project.
• For eg of a wind tunnel system different group deals with production of
different components individually.
•
OBJECTIVES
• To study the drawings and to decide the proper sequence for
manufacturing of job.
• To decide the estimated starting and completion date of the project
and to keep a track on project with the help of software’s like MS Project.
• To co-ordinate with the shop floor supervisor and workers and to solve
the problem if any.
• To decide the necessary templates, gauges, tools required for
production.
• To find out the vendor details if a particular material or component is
to be procured from vendor.
FUNCTIONS
• To prepare the detailed plate cutting layout (PCL) & plate cutting
requisition (PCR)
• To prepare the Detailed Process Plan (DPP) for fabrication and machining.
• To manage the necessary inventory with the help of software’s like ERP-LN
• Preparing design change requisition(DCR)
• Checking material requisition (MR).
INTRODUCTION TO WIND TUNNEL
SYSTEM
SUBSYSTEMS OF WIND TUNNEL
• PRESSURE REGULATING SYSTEM
• HEATING SYSTEM
• SETTLING CHAMBER
• NOZZLE
• TEST SECTION
• DIFFUSER
• CONNECTING DUCT
• VACCUM SPHERES
SETTLING CHAMBER
• Settling chamber is a large area low
velocity section connected to a pipeline
it is connevted to a nozzle
• It is needed to improve the uniformity of
flow entering the nozzle
• The settling chamber is used to reduce
this turbulence in the flow before it enters
the nozzle
NOZZLE
• Nozzle are required to accelerate the
flow from low speed to high speed
• The nozzle are assembled with the settling
chamber with the upstream end and with
the test section in the downsteam end
Diffuser
• The air leaving the test section of the High
speed test facility is at high temperatures
(high enough to disallow direct exhaust
into the atmosphere) and is at velocities
at this temperature
• Hence, slowing down and cooling the air
leaving the test section is an absolute
necessity for the safe day-to-day
operation of the tunnel.
CONNECTING DUCT
• Connecting duct is the interface
between the Diffuser & after cooler. It is
sloping downwards form inlet to outlet to
bridge the height difference between the
outlet of Diffuser & inlet of After cooler.
• . A manhole is provided on the
connecting duct near the after cooler
end to enable any inspection /
maintenance.
Project 1:- Comparing The Cost of The Weld
Through Value Engineering Process
• OBJECTIVE: Determining the total welding cost for each welding process for
Circumseam seam and Longseam weld for a 6500 x 2000 x 16 THICK plate
For flange to shell and total long seam weld.
Progress Achieved : cost calculation completed for
1. Shielded metal arc welding (Smaw)
2. Tungsten arc welding (TIG)
Project 2 :- Design And Load Calculation
For Trolley of Diffuser System
Progress achieved :-
1. Design calculations for screw jack completed
2. Selection of bearing for trolley completed
3. Drawing 3d models in Solidworks

More Related Content

Similar to STAGE 1 PRESENTATION.pptx

Shafeeque CV (1)
Shafeeque CV (1)Shafeeque CV (1)
Shafeeque CV (1)
Mohd Shafeeque
 
Data Centers Commissioning
Data Centers Commissioning Data Centers Commissioning
Data Centers Commissioning
ASHRAE Rajasthan Chapter
 
Vasco.ppt (1)
Vasco.ppt (1)Vasco.ppt (1)
Vasco.ppt (1)
NITIN PHADKE Singapore
 
Denholm Rees & O'Donnell + C E Edwards - Partnership for Performance
Denholm Rees & O'Donnell + C E Edwards - Partnership for PerformanceDenholm Rees & O'Donnell + C E Edwards - Partnership for Performance
Denholm Rees & O'Donnell + C E Edwards - Partnership for Performance
BSAMARKETING
 
Resume - Jason Lewis
Resume - Jason LewisResume - Jason Lewis
Resume - Jason Lewis
Jason Lewis
 
LinkedIn
LinkedInLinkedIn
LinkedIn
Bret Stauffer
 
Offshore Vacancies at Fluor Phils
Offshore Vacancies at Fluor PhilsOffshore Vacancies at Fluor Phils
Offshore Vacancies at Fluor Phils
Mannilen Parrone Marquez
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
Allwyn Stanley
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
Allwyn Stanley
 
Contribution to the Business Awards
Contribution to the Business AwardsContribution to the Business Awards
Contribution to the Business Awards
Azam Ghaffar
 
Resume
ResumeResume
Detail Design Review
Detail Design ReviewDetail Design Review
Detail Design Review
Michael Wanless
 
Mohd Hamid CV 10-12-2016
Mohd Hamid CV 10-12-2016Mohd Hamid CV 10-12-2016
Mohd Hamid CV 10-12-2016
mohd hamid
 
RESUME (11)
RESUME (11)RESUME (11)
RESUME (11)
muthusundar_14
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
Saminathan Ramadoss
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
Saminathan Ramadoss
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
Saminathan Ramadoss
 
RESUMEPIPINGDESIGN
RESUMEPIPINGDESIGNRESUMEPIPINGDESIGN
RESUMEPIPINGDESIGN
arun5561
 
Shruti_Pimpalkar
Shruti_PimpalkarShruti_Pimpalkar
Shruti_Pimpalkar
Shruti Pimpalkar
 
Wellington Shumba CV projects
Wellington Shumba CV projectsWellington Shumba CV projects
Wellington Shumba CV projects
weshumba
 

Similar to STAGE 1 PRESENTATION.pptx (20)

Shafeeque CV (1)
Shafeeque CV (1)Shafeeque CV (1)
Shafeeque CV (1)
 
Data Centers Commissioning
Data Centers Commissioning Data Centers Commissioning
Data Centers Commissioning
 
Vasco.ppt (1)
Vasco.ppt (1)Vasco.ppt (1)
Vasco.ppt (1)
 
Denholm Rees & O'Donnell + C E Edwards - Partnership for Performance
Denholm Rees & O'Donnell + C E Edwards - Partnership for PerformanceDenholm Rees & O'Donnell + C E Edwards - Partnership for Performance
Denholm Rees & O'Donnell + C E Edwards - Partnership for Performance
 
Resume - Jason Lewis
Resume - Jason LewisResume - Jason Lewis
Resume - Jason Lewis
 
LinkedIn
LinkedInLinkedIn
LinkedIn
 
Offshore Vacancies at Fluor Phils
Offshore Vacancies at Fluor PhilsOffshore Vacancies at Fluor Phils
Offshore Vacancies at Fluor Phils
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
 
Contribution to the Business Awards
Contribution to the Business AwardsContribution to the Business Awards
Contribution to the Business Awards
 
Resume
ResumeResume
Resume
 
Detail Design Review
Detail Design ReviewDetail Design Review
Detail Design Review
 
Mohd Hamid CV 10-12-2016
Mohd Hamid CV 10-12-2016Mohd Hamid CV 10-12-2016
Mohd Hamid CV 10-12-2016
 
RESUME (11)
RESUME (11)RESUME (11)
RESUME (11)
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
 
RESUMEPIPINGDESIGN
RESUMEPIPINGDESIGNRESUMEPIPINGDESIGN
RESUMEPIPINGDESIGN
 
Shruti_Pimpalkar
Shruti_PimpalkarShruti_Pimpalkar
Shruti_Pimpalkar
 
Wellington Shumba CV projects
Wellington Shumba CV projectsWellington Shumba CV projects
Wellington Shumba CV projects
 

Recently uploaded

Charging and Fueling Infrastructure Grant: Round 2 by Brandt Hertenstein
Charging and Fueling Infrastructure Grant: Round 2 by Brandt HertensteinCharging and Fueling Infrastructure Grant: Round 2 by Brandt Hertenstein
Charging and Fueling Infrastructure Grant: Round 2 by Brandt Hertenstein
Forth
 
MODULE ONE PRPC19 Design of Machine Elements- 1 .pdf
MODULE  ONE PRPC19 Design of Machine Elements- 1 .pdfMODULE  ONE PRPC19 Design of Machine Elements- 1 .pdf
MODULE ONE PRPC19 Design of Machine Elements- 1 .pdf
ShanthiniSellamuthu
 
一比一原版(WashU文凭证书)圣路易斯华盛顿大学毕业证如何办理
一比一原版(WashU文凭证书)圣路易斯华盛顿大学毕业证如何办理一比一原版(WashU文凭证书)圣路易斯华盛顿大学毕业证如何办理
一比一原版(WashU文凭证书)圣路易斯华盛顿大学毕业证如何办理
afkxen
 
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
78tq3hi2
 
Charging Fueling & Infrastructure (CFI) Program Resources by Cat Plein
Charging Fueling & Infrastructure (CFI) Program Resources by Cat PleinCharging Fueling & Infrastructure (CFI) Program Resources by Cat Plein
Charging Fueling & Infrastructure (CFI) Program Resources by Cat Plein
Forth
 
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
78tq3hi2
 
Catalytic Converter theft prevention - NYC.pptx
Catalytic Converter theft prevention - NYC.pptxCatalytic Converter theft prevention - NYC.pptx
Catalytic Converter theft prevention - NYC.pptx
Blue Star Brothers
 
Charging Fueling & Infrastructure (CFI) Program by Kevin Miller
Charging Fueling & Infrastructure (CFI) Program  by Kevin MillerCharging Fueling & Infrastructure (CFI) Program  by Kevin Miller
Charging Fueling & Infrastructure (CFI) Program by Kevin Miller
Forth
 
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
afkxen
 
AadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects ( Asp Cranes ) RaipurAadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects
 
EV Charging at Multifamily Properties by Kevin Donnelly
EV Charging at Multifamily Properties by Kevin DonnellyEV Charging at Multifamily Properties by Kevin Donnelly
EV Charging at Multifamily Properties by Kevin Donnelly
Forth
 
Kaizen SMT_MI_PCBA for Quality Engineerspptx
Kaizen SMT_MI_PCBA for Quality EngineerspptxKaizen SMT_MI_PCBA for Quality Engineerspptx
Kaizen SMT_MI_PCBA for Quality Engineerspptx
vaibhavsrivastava482521
 
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
MarynaYurchenko2
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
g1inbfro
 
Here's Why Every Semi-Truck Should Have ELDs
Here's Why Every Semi-Truck Should Have ELDsHere's Why Every Semi-Truck Should Have ELDs
Here's Why Every Semi-Truck Should Have ELDs
jennifermiller8137
 
EN Artificial Intelligence by Slidesgo.pptx
EN Artificial Intelligence by Slidesgo.pptxEN Artificial Intelligence by Slidesgo.pptx
EN Artificial Intelligence by Slidesgo.pptx
aichamardi99
 
EV Charging at MFH Properties by Whitaker Jamieson
EV Charging at MFH Properties by Whitaker JamiesonEV Charging at MFH Properties by Whitaker Jamieson
EV Charging at MFH Properties by Whitaker Jamieson
Forth
 
Hand Gesture Control Robotic Arm using image processing.pptx
Hand Gesture Control Robotic Arm using image processing.pptxHand Gesture Control Robotic Arm using image processing.pptx
Hand Gesture Control Robotic Arm using image processing.pptx
wstatus456
 
Expanding Access to Affordable At-Home EV Charging by Vanessa Warheit
Expanding Access to Affordable At-Home EV Charging by Vanessa WarheitExpanding Access to Affordable At-Home EV Charging by Vanessa Warheit
Expanding Access to Affordable At-Home EV Charging by Vanessa Warheit
Forth
 
RACI Matrix Managed Services on Cloud 08-11-19_AS.pdf
RACI Matrix Managed Services on Cloud 08-11-19_AS.pdfRACI Matrix Managed Services on Cloud 08-11-19_AS.pdf
RACI Matrix Managed Services on Cloud 08-11-19_AS.pdf
xmasmen4u
 

Recently uploaded (20)

Charging and Fueling Infrastructure Grant: Round 2 by Brandt Hertenstein
Charging and Fueling Infrastructure Grant: Round 2 by Brandt HertensteinCharging and Fueling Infrastructure Grant: Round 2 by Brandt Hertenstein
Charging and Fueling Infrastructure Grant: Round 2 by Brandt Hertenstein
 
MODULE ONE PRPC19 Design of Machine Elements- 1 .pdf
MODULE  ONE PRPC19 Design of Machine Elements- 1 .pdfMODULE  ONE PRPC19 Design of Machine Elements- 1 .pdf
MODULE ONE PRPC19 Design of Machine Elements- 1 .pdf
 
一比一原版(WashU文凭证书)圣路易斯华盛顿大学毕业证如何办理
一比一原版(WashU文凭证书)圣路易斯华盛顿大学毕业证如何办理一比一原版(WashU文凭证书)圣路易斯华盛顿大学毕业证如何办理
一比一原版(WashU文凭证书)圣路易斯华盛顿大学毕业证如何办理
 
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
 
Charging Fueling & Infrastructure (CFI) Program Resources by Cat Plein
Charging Fueling & Infrastructure (CFI) Program Resources by Cat PleinCharging Fueling & Infrastructure (CFI) Program Resources by Cat Plein
Charging Fueling & Infrastructure (CFI) Program Resources by Cat Plein
 
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
 
Catalytic Converter theft prevention - NYC.pptx
Catalytic Converter theft prevention - NYC.pptxCatalytic Converter theft prevention - NYC.pptx
Catalytic Converter theft prevention - NYC.pptx
 
Charging Fueling & Infrastructure (CFI) Program by Kevin Miller
Charging Fueling & Infrastructure (CFI) Program  by Kevin MillerCharging Fueling & Infrastructure (CFI) Program  by Kevin Miller
Charging Fueling & Infrastructure (CFI) Program by Kevin Miller
 
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
 
AadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects ( Asp Cranes ) RaipurAadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects ( Asp Cranes ) Raipur
 
EV Charging at Multifamily Properties by Kevin Donnelly
EV Charging at Multifamily Properties by Kevin DonnellyEV Charging at Multifamily Properties by Kevin Donnelly
EV Charging at Multifamily Properties by Kevin Donnelly
 
Kaizen SMT_MI_PCBA for Quality Engineerspptx
Kaizen SMT_MI_PCBA for Quality EngineerspptxKaizen SMT_MI_PCBA for Quality Engineerspptx
Kaizen SMT_MI_PCBA for Quality Engineerspptx
 
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
Here's Why Every Semi-Truck Should Have ELDs
Here's Why Every Semi-Truck Should Have ELDsHere's Why Every Semi-Truck Should Have ELDs
Here's Why Every Semi-Truck Should Have ELDs
 
EN Artificial Intelligence by Slidesgo.pptx
EN Artificial Intelligence by Slidesgo.pptxEN Artificial Intelligence by Slidesgo.pptx
EN Artificial Intelligence by Slidesgo.pptx
 
EV Charging at MFH Properties by Whitaker Jamieson
EV Charging at MFH Properties by Whitaker JamiesonEV Charging at MFH Properties by Whitaker Jamieson
EV Charging at MFH Properties by Whitaker Jamieson
 
Hand Gesture Control Robotic Arm using image processing.pptx
Hand Gesture Control Robotic Arm using image processing.pptxHand Gesture Control Robotic Arm using image processing.pptx
Hand Gesture Control Robotic Arm using image processing.pptx
 
Expanding Access to Affordable At-Home EV Charging by Vanessa Warheit
Expanding Access to Affordable At-Home EV Charging by Vanessa WarheitExpanding Access to Affordable At-Home EV Charging by Vanessa Warheit
Expanding Access to Affordable At-Home EV Charging by Vanessa Warheit
 
RACI Matrix Managed Services on Cloud 08-11-19_AS.pdf
RACI Matrix Managed Services on Cloud 08-11-19_AS.pdfRACI Matrix Managed Services on Cloud 08-11-19_AS.pdf
RACI Matrix Managed Services on Cloud 08-11-19_AS.pdf
 

STAGE 1 PRESENTATION.pptx

  • 1. STAGE 1 PRESENTATION AT….M/S Larsen & Toubro Vishal Kotiya (60012148002) Mentor :- E Narayanan
  • 2. INTRODUCTION TO L&T • Larsen & Toubro Limited” is India’s premier technology – driven company with leading edge capabilities in the fields related to Engineering, Infrastructure & Basic Industries • The main functioning L&T workshop is located at Hazira, which is spread over an area of 73,600sq.mtrs. • The powai campus of L&T is the oldest facility as well as the most diverse in terms of employee strength and operations • The campus is well equipped with facilites for fabrication, machining, handling & quality control
  • 4. PRESENT STATUS OF L&T • L&T From the last 7 Decades Serving Vital Human needs have diversified into its each and every range of products and projects. • Ranging from nuclear, hydrocarbon, aerospace, shipbuilding, electrical & electronics • the company produces precision engineering components and have mastered in the manufacturing of heat exchangers and pressure vessels. • L&T now have 23 manufacturing units spread all over the country. • IT aims to build on its traditional strengths and fulfils its vision of becoming a world-class company dedicated to professionalism & excellence.
  • 5. INTRODUCTION TO FLIGHT SYSTEM BUISNESS UNIT (FSBU)
  • 6. FLIGHT SYSTEM BUISNESS UNIT • As the name implies, the department is concerned with the production of testing equipment's for defence & space vehicles. • This department manufactures the motor casing of the Polar Satellite Launch Vehicle (PSLV) as well as the booster of the Geo-stationary Satellite Launch Vehicle (GSLV). • Current projects undergoing in the department are Reflector deployment mechanism, Hpersonic wind tunnel system. • manufacture of Rocket Motor Casings: S200 for GSLV Mk III and S139 for PSLV & GSLV. • The group is been divided into 4 sub groups such as Design group, project management group, marketing & quality control.
  • 7. INTRODUCTION TO PROJECT MANGEMENT GROUP • The group is involved in management and planning of all critical activity which is required for the production of the job. • The department is been subdivided into no of teams which deals with planning of different components to be manufactured from the whole as a project. • For eg of a wind tunnel system different group deals with production of different components individually. •
  • 8. OBJECTIVES • To study the drawings and to decide the proper sequence for manufacturing of job. • To decide the estimated starting and completion date of the project and to keep a track on project with the help of software’s like MS Project. • To co-ordinate with the shop floor supervisor and workers and to solve the problem if any. • To decide the necessary templates, gauges, tools required for production. • To find out the vendor details if a particular material or component is to be procured from vendor.
  • 9. FUNCTIONS • To prepare the detailed plate cutting layout (PCL) & plate cutting requisition (PCR) • To prepare the Detailed Process Plan (DPP) for fabrication and machining. • To manage the necessary inventory with the help of software’s like ERP-LN • Preparing design change requisition(DCR) • Checking material requisition (MR).
  • 10. INTRODUCTION TO WIND TUNNEL SYSTEM
  • 11. SUBSYSTEMS OF WIND TUNNEL • PRESSURE REGULATING SYSTEM • HEATING SYSTEM • SETTLING CHAMBER • NOZZLE • TEST SECTION • DIFFUSER • CONNECTING DUCT • VACCUM SPHERES
  • 12. SETTLING CHAMBER • Settling chamber is a large area low velocity section connected to a pipeline it is connevted to a nozzle • It is needed to improve the uniformity of flow entering the nozzle • The settling chamber is used to reduce this turbulence in the flow before it enters the nozzle
  • 13. NOZZLE • Nozzle are required to accelerate the flow from low speed to high speed • The nozzle are assembled with the settling chamber with the upstream end and with the test section in the downsteam end
  • 14. Diffuser • The air leaving the test section of the High speed test facility is at high temperatures (high enough to disallow direct exhaust into the atmosphere) and is at velocities at this temperature • Hence, slowing down and cooling the air leaving the test section is an absolute necessity for the safe day-to-day operation of the tunnel.
  • 15. CONNECTING DUCT • Connecting duct is the interface between the Diffuser & after cooler. It is sloping downwards form inlet to outlet to bridge the height difference between the outlet of Diffuser & inlet of After cooler. • . A manhole is provided on the connecting duct near the after cooler end to enable any inspection / maintenance.
  • 16. Project 1:- Comparing The Cost of The Weld Through Value Engineering Process • OBJECTIVE: Determining the total welding cost for each welding process for Circumseam seam and Longseam weld for a 6500 x 2000 x 16 THICK plate For flange to shell and total long seam weld. Progress Achieved : cost calculation completed for 1. Shielded metal arc welding (Smaw) 2. Tungsten arc welding (TIG)
  • 17. Project 2 :- Design And Load Calculation For Trolley of Diffuser System Progress achieved :- 1. Design calculations for screw jack completed 2. Selection of bearing for trolley completed 3. Drawing 3d models in Solidworks