The document summarizes Skema's extensive work on the Kashagan oil field development project in Kazakhstan, including:
1) Skema supplied electrical equipment like substations, switchgear, and control systems for both offshore and onshore facilities.
2) Skema also helped with the fabrication of 20 onshore process and utilities buildings and 6 offshore modular equipment rooms in Italy.
3) To increase local content, Skema partnered with a Kazakh company to establish a joint venture called OPPB LLP, which won a contract to build 13 offshore utilities buildings for the project.