Agnico Eagle reported its second quarter 2015 results. Key highlights included:
- Payable gold production of 403,678 ounces at total cash costs per ounce of $601.
- Production guidance for 2015 maintained at 1.6 million ounces with costs reduced.
- Approval of mining at the Vault Extension and Goldex Deep 1 projects expected to extend mine life.
- Infill drilling at Amaruq confirmed grades and thicknesses with mineralization extended to depth.
- Continued focus on debt reduction with $25 million repaid on the credit facility in Q2 2015.
Agnico Eagle reported its first quarter 2015 results on May 1, 2015. The document discusses forward-looking statements and provides notes to investors regarding non-GAAP financial measures and production guidance. It reports that the first quarter saw record quarterly gold production of 404,210 ounces at total cash costs per ounce. Key factors discussed include metal prices, exchange rates, mineral reserves and resource estimates, production costs, expansion projects, and estimated mine lives. Risk factors that could affect actual results are also outlined.
Agnico Eagle reported record annual gold production in 2014 of 1.429 million ounces at total cash costs of $637 per ounce. For the fourth quarter of 2014, gold production was 387,538 ounces at total cash costs of $662 per ounce. Agnico Eagle expects gold production to increase to approximately 1.6 million ounces in 2015 at total cash costs of $610 to $630 per ounce, and all-in sustaining costs of $880 to $900 per ounce. Agnico Eagle also provided three-year production guidance for 2015 to 2017, with expected average annual gold production of approximately 1.6 million ounces.
Agnico Eagle provided a corporate update for January 2015 including the following key points:
- 2015 gold production is expected to increase 14% to approximately 1.6 million ounces compared to 2014, driven by higher production at Meadowbank, Kittila, and Mexican operations. Total cash costs per ounce are expected to decline 6% from 2014.
- The company has manageable expansion capital requirements with projects like the Kittila plant expansion and Pinos shaft completion expected to increase production capacity.
- Agnico Eagle has financial flexibility with a net debt of $1.2 billion and $700 million in undrawn credit lines to fund future growth.
The document provides forward-looking statements and notes of caution for Agnico Eagle's presentation at a metals and mining conference. It notes that forward-looking production estimates involve risks and uncertainties beyond Agnico Eagle's control. It also explains that the presentation discloses non-GAAP financial measures like total cash costs per ounce of gold produced, and provides reconciliations to IFRS measures. Finally, it states that the gold production guidance is based on mineral reserves but includes contingencies and price assumptions different than those used for reserves.
This document provides forward-looking statements and notes to investors regarding Agnico Eagle's presentation at the Jefferies 11th Annual Industrials Conference in August 2015. It cautions readers that forward-looking statements are subject to risks and uncertainties. It also notes that the presentation discloses non-GAAP financial measures such as total cash costs per ounce and minesite costs per tonne, and provides reconciliations to IFRS measures. Finally, it states that the gold production guidance is based on mineral reserves but includes contingencies and price assumptions different from reserve estimates.
This document is an introduction and forward-looking statement from Agnico Eagle for their presentation at the Bank of America Merrill Lynch 21st Annual Canada Mining Conference in September 2015. It outlines key assumptions and risk factors for forward-looking production guidance, cost estimates, and timelines. It also provides notes to investors on the use of non-GAAP financial measures and production guidance included in the presentation.
This document provides an overview of a site tour that was conducted at El Barqueño on September 23, 2015. It begins with standard forward-looking statements and disclaimers about projections. It then provides notes to investors about the use of non-GAAP financial measures in evaluations, production guidance assumptions, mineral resource categories, and scientific and technical data standards. Key points covered include projected total cash costs, all-in sustaining costs, mineral reserve estimates used, and qualifications of individuals who approved the scientific and technical content.
The document provides an overview of Agnico Eagle's Amaruq investor tour on August 20, 2015. It begins with forward-looking statements and notes of caution for investors. It then provides an agenda that will discuss Nunavut, the Meadowbank operations including the Vault extension, details on Amaruq, and information on Meliadine. Exploration and development highlights are provided, noting increased resources at Amaruq and optimization studies continuing at Meliadine.
Agnico Eagle reported its first quarter 2015 results on May 1, 2015. The document discusses forward-looking statements and provides notes to investors regarding non-GAAP financial measures and production guidance. It reports that the first quarter saw record quarterly gold production of 404,210 ounces at total cash costs per ounce. Key factors discussed include metal prices, exchange rates, mineral reserves and resource estimates, production costs, expansion projects, and estimated mine lives. Risk factors that could affect actual results are also outlined.
Agnico Eagle reported record annual gold production in 2014 of 1.429 million ounces at total cash costs of $637 per ounce. For the fourth quarter of 2014, gold production was 387,538 ounces at total cash costs of $662 per ounce. Agnico Eagle expects gold production to increase to approximately 1.6 million ounces in 2015 at total cash costs of $610 to $630 per ounce, and all-in sustaining costs of $880 to $900 per ounce. Agnico Eagle also provided three-year production guidance for 2015 to 2017, with expected average annual gold production of approximately 1.6 million ounces.
Agnico Eagle provided a corporate update for January 2015 including the following key points:
- 2015 gold production is expected to increase 14% to approximately 1.6 million ounces compared to 2014, driven by higher production at Meadowbank, Kittila, and Mexican operations. Total cash costs per ounce are expected to decline 6% from 2014.
- The company has manageable expansion capital requirements with projects like the Kittila plant expansion and Pinos shaft completion expected to increase production capacity.
- Agnico Eagle has financial flexibility with a net debt of $1.2 billion and $700 million in undrawn credit lines to fund future growth.
The document provides forward-looking statements and notes of caution for Agnico Eagle's presentation at a metals and mining conference. It notes that forward-looking production estimates involve risks and uncertainties beyond Agnico Eagle's control. It also explains that the presentation discloses non-GAAP financial measures like total cash costs per ounce of gold produced, and provides reconciliations to IFRS measures. Finally, it states that the gold production guidance is based on mineral reserves but includes contingencies and price assumptions different than those used for reserves.
This document provides forward-looking statements and notes to investors regarding Agnico Eagle's presentation at the Jefferies 11th Annual Industrials Conference in August 2015. It cautions readers that forward-looking statements are subject to risks and uncertainties. It also notes that the presentation discloses non-GAAP financial measures such as total cash costs per ounce and minesite costs per tonne, and provides reconciliations to IFRS measures. Finally, it states that the gold production guidance is based on mineral reserves but includes contingencies and price assumptions different from reserve estimates.
This document is an introduction and forward-looking statement from Agnico Eagle for their presentation at the Bank of America Merrill Lynch 21st Annual Canada Mining Conference in September 2015. It outlines key assumptions and risk factors for forward-looking production guidance, cost estimates, and timelines. It also provides notes to investors on the use of non-GAAP financial measures and production guidance included in the presentation.
This document provides an overview of a site tour that was conducted at El Barqueño on September 23, 2015. It begins with standard forward-looking statements and disclaimers about projections. It then provides notes to investors about the use of non-GAAP financial measures in evaluations, production guidance assumptions, mineral resource categories, and scientific and technical data standards. Key points covered include projected total cash costs, all-in sustaining costs, mineral reserve estimates used, and qualifications of individuals who approved the scientific and technical content.
The document provides an overview of Agnico Eagle's Amaruq investor tour on August 20, 2015. It begins with forward-looking statements and notes of caution for investors. It then provides an agenda that will discuss Nunavut, the Meadowbank operations including the Vault extension, details on Amaruq, and information on Meliadine. Exploration and development highlights are provided, noting increased resources at Amaruq and optimization studies continuing at Meliadine.
The document provides an overview of Scotiabank's BBQ on August 18, 2015. It includes forward-looking statements about Agnico Eagle's expected future production, costs, projects, and studies. Highlights from the first half of 2015 include strong operating performance with 807,888 ounces of gold produced at total cash costs of $595 per ounce. Production guidance for 2015 is maintained at 1.6 million ounces with reduced costs. The Goldex Deep 1 project was approved to add 7 years of mine life. Drilling is expanding resources at Amaruq and the Vault extension could reduce the potential production gap with Amaruq.
The document provides an update on Agnico Eagle, a gold mining company. It discusses forward-looking production guidance estimates for 2015, including expected ore grades, metal production, costs per ounce, and estimated timing of technical reports. It notes Agnico Eagle expects around 14% production growth in 2015 and all-in sustaining costs in 2015 are expected to decline by 6% from 2014 levels. The document also contains standard cautionary notes about forward-looking statements and the use of non-GAAP measures in evaluations performance.
Macquarie 2015 Global Metals, Mining % Materials Conference, New YorkAgnico Eagle Mines
This document provides an overview of Agnico Eagle's presentation at the Macquarie 2015 Global Metals, Mining & Materials Conference on June 10-11, 2015. It discusses Agnico Eagle's assets in Nunavut, Finland, Mexico, and the Abitibi Region, which are focused in four low-risk mining jurisdictions. Production is forecast to be approximately 1.6 million ounces in 2015 at a cash cost of $618 per ounce. The presentation also highlights Agnico Eagle's reserve quality, production and cost profile, opportunities to enhance future production, 2014 reserve highlights, and exploration/development pipeline.
The document provides forward-looking statements and production guidance for Agnico Eagle at the BMO Capital Markets 24th Global Metals and Mining Conference in February 2015. It notes key assumptions used in projections, such as metal prices and exchange rates, and risks that could impact projections. It also provides context on non-GAAP terms used, such as total cash costs per ounce and minesite costs per tonne, and reconciles them to GAAP financial reporting. Finally, it states that the gold production guidance is based on mineral reserves but includes contingencies, and does not reconcile exactly to reserve models due to factors like metal price and exchange rate assumptions.
- Agnico Eagle reported strong Q3 2014 operating performance with gold production of 349,273 oz and total cash costs of $716/oz.
- Production for 2014 is expected to exceed guidance and reach approximately 1.4 Moz, while 2015 guidance is increased to approximately 1.6 Moz due to higher forecasts at Meadowbank, Kittila, and Mexican operations.
- Upgrades at LaRonde, lower costs at Goldex, and optimization at Canadian Malartic position the Abitibi operations for increased performance going forward.
This document provides a corporate update for Agnico Eagle. It discusses Agnico Eagle's increased gold production guidance for 2014 and 2015, driven by strong operational performance at Meadowbank, Kittila, and Mexican operations. Production is forecast to increase 14% to 1.6 million ounces in 2015 while total cash costs are expected to decline 6% from 2014 levels. The document also addresses Agnico Eagle's financial position and flexibility.
The document provides an overview of Agnico Eagle's Kittila mine site visit in November 2016. Some key points:
- Kittila is Agnico Eagle's largest gold mine in Europe and has estimated reserves to continue operations through 2035.
- Underground development and mining rates are being optimized to fully access the Rimpi and newly discovered Sisar zones.
- Drilling in Q3 2016 yielded the widest intercept to date in the Sisar Central Zone of 6.6 g/t gold over 12.7 metres.
- The processing plant uses pressure oxidation in an autoclave to treat the refractory gold ore, followed by milling, flotation, leaching and electrowin
Raymond James 38th Annual Institutional Investors ConferenceAgnico Eagle Mines
The document provides forward-looking statements and notes regarding Agnico Eagle's presentation at the Raymond James 38th Annual Institutional Investors Conference in March 2017. It discusses Agnico Eagle's solid production base, high quality long life assets, and proven value creating strategy. It also summarizes Agnico Eagle's 2016 operating and financial highlights, 2016 exploration and reserve highlights, and track record of meeting production guidance. Finally, it notes Agnico Eagle mined below its average reserve grade in 2016 and successfully replaced reserves and resources with grades remaining unchanged.
Agnico Eagle held a Denver Gold Forum in September 2016 to provide information to investors. The document included forward-looking statements about production guidance, costs, and other estimates. It noted the risks that actual results may differ from expectations due to uncertainties in metal prices, costs, and other factors. It also summarized the company's strategy of production growth from its existing assets, high-quality gold reserves with above-average grades, and exploration adding new resources.
The Barsele Gold Project is located in northern Sweden near existing infrastructure. Agnico Eagle has a 55% interest in the project. Previous exploration identified gold mineralization at the Central, Avan, and Skiråsen zones. In 2015-2016, Agnico Eagle conducted drilling programs to expand and define these zones, with the goal of releasing an initial inferred resource estimate by the end of 2016. Drilling to date has shown potential to extend mineralization to depth at the Avan zone.
The document provides an overview of Agnico Eagle's corporate update presentation from January 2018. It includes forward-looking statements and notes regarding non-GAAP measures. The summary highlights Agnico Eagle's growing production base, high quality long life assets, strategy of value creation, track record of meeting guidance, mineral reserves and resources, successful M&A and exploration adding value, and project pipeline expected to drive further production growth to 2 million ounces by 2020.
- Agnico Eagle and Yamana Gold jointly acquired Osisko Mining Corporation on June 16, 2014 to form the Canadian Malartic General Partnership.
- Production guidance for 2014 was increased to 1.35-1.37 million ounces of gold with total cash costs forecasted between $650-675 per ounce.
- Exploration drilling at the IVR discovery near Meadowbank continues to expand the mineralization, with four mineralized zones now outlined and mineralization remaining open in all directions.
Agnico Eagle reported its first quarter 2016 results on April 29, 2016. The document provides forward-looking statements regarding Agnico Eagle's expectations for production, costs, capital expenditures, and other estimates. It notes that actual results may differ materially from expectations due to risks and uncertainties in the business. The document also explains non-GAAP measures used to evaluate performance such as total cash costs per ounce and all-in sustaining costs per ounce.
- Agnico Eagle reported second quarter 2018 results with total payable gold production of 404,961 ounces and total cash costs per ounce of $656.
- Production guidance for 2018 was increased to 1.58 million ounces of gold from 1.53 million ounces previously.
- The Amaruq project received permit approval and preliminary construction work began, while the Meliadine project remains on schedule for first production in Q2 2019.
- LaRonde Zone 5 declared commercial production as of June 1, 2018 and the mine life at Lapa was extended until the fourth quarter of 2018.
Agnico Eagle reported its fourth quarter and full year 2017 results. Some highlights include:
- Production guidance for 2018 of 1.75-1.8 million ounces of gold at total cash costs between $650-700 per ounce and AISC of $950-1000 per ounce.
- Continued progress on construction at the Meliadine and Amaruq projects in Nunavut, with production expected to begin in 2019.
- Exploration success at several mines, with potential to extend mine lives and add new resources.
Bank of America Merrill Lynch 2016 Global Metals, Mining EventAgnico Eagle Mines
This document provides an overview of Agnico Eagle Mines Limited's presentation at the 22nd Annual Canada Mining Event hosted by Bank of America Merrill Lynch in September 2016. It contains forward-looking statements about Agnico Eagle's production guidance, costs, projects and growth plans. It also notes the risks associated with forward-looking statements and provides details on Agnico Eagle's non-GAAP financial measures and production guidance methodology. Finally, it highlights Agnico Eagle's strategy of value creation through consistent performance, production growth, high-quality reserves, exploration success and financial strength.
Raymond james-39th-annual-institutional-investors-conferenceAgnico Eagle Mines
- The document provides forward-looking statements regarding Agnico Eagle's operations, projects, production estimates, costs, and cash flows.
- It notes key assumptions underlying these statements and risks that could cause actual results to differ materially.
- Non-GAAP financial measures including total cash costs, all-in sustaining costs, and minesite costs are discussed and reconciled to IFRS measures.
This document provides an overview of Scotiabank's BBQ on August 15, 2014 and discusses Agnico Eagle's operations. It includes forward-looking statements about production guidance, costs, exploration results and studies. It also notes the acquisition of Osisko Mining Corporation and formation of a joint venture to operate the Canadian Malartic mine. Finally, it summarizes highlights and recent developments at Agnico Eagle's northern mines including LaRonde, Meadowbank, Canadian Malartic JV, and Kittila.
This document provides an overview of Agnico Eagle Mines Limited's annual and special meeting on April 29, 2016. It includes forward-looking statements about production guidance, costs, and projects. It notes the risks associated with forward-looking statements and provides non-GAAP financial measures to assess performance. The company has a strong track record of exceeding production guidance and lowering costs. It is positioned for growth through optimizing existing operations, exploration success adding reserves, and a pipeline of development projects expected to increase production by 30-40% by 2020.
- Agnico Eagle reported its third quarter 2015 results on October 29, 2015.
- The document discusses forward-looking statements regarding production guidance, costs, and expansion projects and contains risks and assumptions.
- It also notes that certain measures used are non-GAAP measures and provides reconciliations to IFRS, and that production guidance is based on reserves but includes contingencies and different price assumptions than reserves.
Agnico-Eagle Mines Limited has emerged as a top gold stock due to its emphasis on quality, exceptional record of shareholder value creation, and robust growth profile. The document discusses Agnico-Eagle's corporate strategy of increasing gold production and reserves while maintaining a solid financial profile and low costs. It provides an overview of the company's operating results, strong financial position, industry-leading growth estimates, and high gold reserves per share.
Agnico Eagle Mines reported first quarter 2013 results with gold production of 236,975 ounces at a total cash cost of $740 per ounce. Cash flow from operations was $146 million. Production and costs were in line with expectations. The company's Goldex and La India projects remain ahead of schedule with initial production expected in Q4 2013 and commissioning beginning late Q4 2013 respectively. Kittila's scheduled mill maintenance was extended resulting in reduced 2013 production estimates.
The document provides an overview of Scotiabank's BBQ on August 18, 2015. It includes forward-looking statements about Agnico Eagle's expected future production, costs, projects, and studies. Highlights from the first half of 2015 include strong operating performance with 807,888 ounces of gold produced at total cash costs of $595 per ounce. Production guidance for 2015 is maintained at 1.6 million ounces with reduced costs. The Goldex Deep 1 project was approved to add 7 years of mine life. Drilling is expanding resources at Amaruq and the Vault extension could reduce the potential production gap with Amaruq.
The document provides an update on Agnico Eagle, a gold mining company. It discusses forward-looking production guidance estimates for 2015, including expected ore grades, metal production, costs per ounce, and estimated timing of technical reports. It notes Agnico Eagle expects around 14% production growth in 2015 and all-in sustaining costs in 2015 are expected to decline by 6% from 2014 levels. The document also contains standard cautionary notes about forward-looking statements and the use of non-GAAP measures in evaluations performance.
Macquarie 2015 Global Metals, Mining % Materials Conference, New YorkAgnico Eagle Mines
This document provides an overview of Agnico Eagle's presentation at the Macquarie 2015 Global Metals, Mining & Materials Conference on June 10-11, 2015. It discusses Agnico Eagle's assets in Nunavut, Finland, Mexico, and the Abitibi Region, which are focused in four low-risk mining jurisdictions. Production is forecast to be approximately 1.6 million ounces in 2015 at a cash cost of $618 per ounce. The presentation also highlights Agnico Eagle's reserve quality, production and cost profile, opportunities to enhance future production, 2014 reserve highlights, and exploration/development pipeline.
The document provides forward-looking statements and production guidance for Agnico Eagle at the BMO Capital Markets 24th Global Metals and Mining Conference in February 2015. It notes key assumptions used in projections, such as metal prices and exchange rates, and risks that could impact projections. It also provides context on non-GAAP terms used, such as total cash costs per ounce and minesite costs per tonne, and reconciles them to GAAP financial reporting. Finally, it states that the gold production guidance is based on mineral reserves but includes contingencies, and does not reconcile exactly to reserve models due to factors like metal price and exchange rate assumptions.
- Agnico Eagle reported strong Q3 2014 operating performance with gold production of 349,273 oz and total cash costs of $716/oz.
- Production for 2014 is expected to exceed guidance and reach approximately 1.4 Moz, while 2015 guidance is increased to approximately 1.6 Moz due to higher forecasts at Meadowbank, Kittila, and Mexican operations.
- Upgrades at LaRonde, lower costs at Goldex, and optimization at Canadian Malartic position the Abitibi operations for increased performance going forward.
This document provides a corporate update for Agnico Eagle. It discusses Agnico Eagle's increased gold production guidance for 2014 and 2015, driven by strong operational performance at Meadowbank, Kittila, and Mexican operations. Production is forecast to increase 14% to 1.6 million ounces in 2015 while total cash costs are expected to decline 6% from 2014 levels. The document also addresses Agnico Eagle's financial position and flexibility.
The document provides an overview of Agnico Eagle's Kittila mine site visit in November 2016. Some key points:
- Kittila is Agnico Eagle's largest gold mine in Europe and has estimated reserves to continue operations through 2035.
- Underground development and mining rates are being optimized to fully access the Rimpi and newly discovered Sisar zones.
- Drilling in Q3 2016 yielded the widest intercept to date in the Sisar Central Zone of 6.6 g/t gold over 12.7 metres.
- The processing plant uses pressure oxidation in an autoclave to treat the refractory gold ore, followed by milling, flotation, leaching and electrowin
Raymond James 38th Annual Institutional Investors ConferenceAgnico Eagle Mines
The document provides forward-looking statements and notes regarding Agnico Eagle's presentation at the Raymond James 38th Annual Institutional Investors Conference in March 2017. It discusses Agnico Eagle's solid production base, high quality long life assets, and proven value creating strategy. It also summarizes Agnico Eagle's 2016 operating and financial highlights, 2016 exploration and reserve highlights, and track record of meeting production guidance. Finally, it notes Agnico Eagle mined below its average reserve grade in 2016 and successfully replaced reserves and resources with grades remaining unchanged.
Agnico Eagle held a Denver Gold Forum in September 2016 to provide information to investors. The document included forward-looking statements about production guidance, costs, and other estimates. It noted the risks that actual results may differ from expectations due to uncertainties in metal prices, costs, and other factors. It also summarized the company's strategy of production growth from its existing assets, high-quality gold reserves with above-average grades, and exploration adding new resources.
The Barsele Gold Project is located in northern Sweden near existing infrastructure. Agnico Eagle has a 55% interest in the project. Previous exploration identified gold mineralization at the Central, Avan, and Skiråsen zones. In 2015-2016, Agnico Eagle conducted drilling programs to expand and define these zones, with the goal of releasing an initial inferred resource estimate by the end of 2016. Drilling to date has shown potential to extend mineralization to depth at the Avan zone.
The document provides an overview of Agnico Eagle's corporate update presentation from January 2018. It includes forward-looking statements and notes regarding non-GAAP measures. The summary highlights Agnico Eagle's growing production base, high quality long life assets, strategy of value creation, track record of meeting guidance, mineral reserves and resources, successful M&A and exploration adding value, and project pipeline expected to drive further production growth to 2 million ounces by 2020.
- Agnico Eagle and Yamana Gold jointly acquired Osisko Mining Corporation on June 16, 2014 to form the Canadian Malartic General Partnership.
- Production guidance for 2014 was increased to 1.35-1.37 million ounces of gold with total cash costs forecasted between $650-675 per ounce.
- Exploration drilling at the IVR discovery near Meadowbank continues to expand the mineralization, with four mineralized zones now outlined and mineralization remaining open in all directions.
Agnico Eagle reported its first quarter 2016 results on April 29, 2016. The document provides forward-looking statements regarding Agnico Eagle's expectations for production, costs, capital expenditures, and other estimates. It notes that actual results may differ materially from expectations due to risks and uncertainties in the business. The document also explains non-GAAP measures used to evaluate performance such as total cash costs per ounce and all-in sustaining costs per ounce.
- Agnico Eagle reported second quarter 2018 results with total payable gold production of 404,961 ounces and total cash costs per ounce of $656.
- Production guidance for 2018 was increased to 1.58 million ounces of gold from 1.53 million ounces previously.
- The Amaruq project received permit approval and preliminary construction work began, while the Meliadine project remains on schedule for first production in Q2 2019.
- LaRonde Zone 5 declared commercial production as of June 1, 2018 and the mine life at Lapa was extended until the fourth quarter of 2018.
Agnico Eagle reported its fourth quarter and full year 2017 results. Some highlights include:
- Production guidance for 2018 of 1.75-1.8 million ounces of gold at total cash costs between $650-700 per ounce and AISC of $950-1000 per ounce.
- Continued progress on construction at the Meliadine and Amaruq projects in Nunavut, with production expected to begin in 2019.
- Exploration success at several mines, with potential to extend mine lives and add new resources.
Bank of America Merrill Lynch 2016 Global Metals, Mining EventAgnico Eagle Mines
This document provides an overview of Agnico Eagle Mines Limited's presentation at the 22nd Annual Canada Mining Event hosted by Bank of America Merrill Lynch in September 2016. It contains forward-looking statements about Agnico Eagle's production guidance, costs, projects and growth plans. It also notes the risks associated with forward-looking statements and provides details on Agnico Eagle's non-GAAP financial measures and production guidance methodology. Finally, it highlights Agnico Eagle's strategy of value creation through consistent performance, production growth, high-quality reserves, exploration success and financial strength.
Raymond james-39th-annual-institutional-investors-conferenceAgnico Eagle Mines
- The document provides forward-looking statements regarding Agnico Eagle's operations, projects, production estimates, costs, and cash flows.
- It notes key assumptions underlying these statements and risks that could cause actual results to differ materially.
- Non-GAAP financial measures including total cash costs, all-in sustaining costs, and minesite costs are discussed and reconciled to IFRS measures.
This document provides an overview of Scotiabank's BBQ on August 15, 2014 and discusses Agnico Eagle's operations. It includes forward-looking statements about production guidance, costs, exploration results and studies. It also notes the acquisition of Osisko Mining Corporation and formation of a joint venture to operate the Canadian Malartic mine. Finally, it summarizes highlights and recent developments at Agnico Eagle's northern mines including LaRonde, Meadowbank, Canadian Malartic JV, and Kittila.
This document provides an overview of Agnico Eagle Mines Limited's annual and special meeting on April 29, 2016. It includes forward-looking statements about production guidance, costs, and projects. It notes the risks associated with forward-looking statements and provides non-GAAP financial measures to assess performance. The company has a strong track record of exceeding production guidance and lowering costs. It is positioned for growth through optimizing existing operations, exploration success adding reserves, and a pipeline of development projects expected to increase production by 30-40% by 2020.
- Agnico Eagle reported its third quarter 2015 results on October 29, 2015.
- The document discusses forward-looking statements regarding production guidance, costs, and expansion projects and contains risks and assumptions.
- It also notes that certain measures used are non-GAAP measures and provides reconciliations to IFRS, and that production guidance is based on reserves but includes contingencies and different price assumptions than reserves.
Agnico-Eagle Mines Limited has emerged as a top gold stock due to its emphasis on quality, exceptional record of shareholder value creation, and robust growth profile. The document discusses Agnico-Eagle's corporate strategy of increasing gold production and reserves while maintaining a solid financial profile and low costs. It provides an overview of the company's operating results, strong financial position, industry-leading growth estimates, and high gold reserves per share.
Agnico Eagle Mines reported first quarter 2013 results with gold production of 236,975 ounces at a total cash cost of $740 per ounce. Cash flow from operations was $146 million. Production and costs were in line with expectations. The company's Goldex and La India projects remain ahead of schedule with initial production expected in Q4 2013 and commissioning beginning late Q4 2013 respectively. Kittila's scheduled mill maintenance was extended resulting in reduced 2013 production estimates.
Agnico-Eagle Mines Limited reported its second quarter 2011 results. Production is expected to increase by approximately 20% in the second half of 2011 compared to the first half. The company has a strong financial position with its next phase of growth fully funded. Agnico-Eagle has maintained its strategy of increasing leverage to gold through reserves and production per share growth, leading to increasing cash flow and dividends per share over time.
The document provides an update on Agnico Eagle's Meliadine and Meadowbank projects in Nunavut, Canada. It summarizes recent drilling results at Meliadine that have expanded mineral resources and reserves. A 2014 drilling program completed 38,000 meters of infill and conversion drilling at Meliadine deposits. Meadowbank continues to optimize operations and extend mine life through 2022. Exploration drilling has also expanded mineralization identified at the nearby IVR discovery, with further drilling planned.
The document provides an overview of Agnico Eagle Mines' (AEM) LaRonde mine tour scheduled for November 22, 2013. It begins with forward-looking statements and notes about non-GAAP financial measures and production guidance. It then outlines an agenda for the tour that includes an introduction to AEM, the Abitibi mining belt, the history and infrastructure of the LaRonde mine, its mining methods and challenges, and visits to the LaRonde, Lapa, and Goldex mines.
- The document is a presentation from Agnico Eagle Mines Limited given at a Scotia BBQ on August 18, 2016.
- It discusses Agnico Eagle's forward-looking statements and production guidance, provides an overview of the company's strong financial position and long history of dividend payments, and outlines its growth strategy through projects in its development pipeline.
- Agnico Eagle has successfully grown production and reserves through acquisitions and exploration over the past decade and expects its project pipeline to drive a new phase of 30-40% production growth by 2020.
Scotia building a high quality manageable gold business in challenging timesAgnico Eagle Mines
Agnico Eagle Mines is preparing to begin commercial production at its La India gold mine in Mexico in Q1 2014, ahead of schedule and on budget. La India is expected to produce approximately 90,000 ounces of gold per year at total cash costs of $500 per ounce. The project was commissioned just 22 months after Agnico Eagle acquired it in 2011 for $157.6 million. La India adds a new source of low-cost gold production in Mexico for Agnico Eagle.
Bank of America Merrill Lynch 2016 Global Metals, Mining & Steel ConferenceAgnico Eagle Mines
This document is from Agnico Eagle's presentation at the 2016 Bank of America Merrill Lynch Global Metals, Mining & Steel Conference in May 2016. It includes forward-looking statements regarding Agnico Eagle's estimated production metrics, costs, and project timelines that are based on certain assumptions that may prove to be incorrect. It also notes that certain non-GAAP financial measures are used such as total cash costs per ounce and all-in sustaining costs per ounce, and provides definitions for these terms. The presentation contains cautionary language regarding the risks and uncertainties inherent in forward-looking information.
Agnico Eagle reported its fourth quarter and full year 2016 results. Key highlights included:
1) Continued strong operating performance in 2016 with gold production exceeding guidance and lower than expected costs.
2) The Amaruq satellite deposit at Meadowbank and the Meliadine project were approved for development with both expected to start up in Q3 2019.
3) A four-year production guidance was issued with gold production expected to increase from current levels to 2 million ounces by 2020 and unit costs expected to decline over that period.
The document discusses Agnico Eagle's third quarter 2016 results. It provides forward-looking statements regarding production guidance, projects, and costs. It notes the risks and assumptions underlying the forward-looking statements. It also discusses non-GAAP measures used to evaluate performance such as total cash costs per ounce and all-in sustaining costs per ounce.
The LaRonde mine achieved record quarterly gold production of 105,345 ounces due to higher tonnage and grades from mining areas. Production guidance for 2017 was increased to over 1.68 million ounces of gold and unit costs were reduced based on strong year-to-date operational performance across Agnico Eagle's mines. Exploration continues at LaRonde to evaluate mining below current levels and infill drilling is ongoing to define higher grade mineralization in the western portions of the deposit.
The document provides an update on Agnico Eagle Mines for August 2016. It includes forward-looking statements and notes of caution regarding the use of non-GAAP measures in financial presentations. The update discusses Agnico Eagle's consistent strategy of production growth, high quality gold reserves with above peer average grades, strong balance sheet, and exploration as a value driver. It also provides highlights on recent operational and financial results and production guidance into 2019 and beyond.
- Agnico Eagle provides a corporate update for September 2016, outlining key points such as production growth targets, high quality gold reserves, ongoing exploration success, and a strong balance sheet.
- The company has a goal of producing over 2 million ounces of gold annually by 2020 through exploiting its existing asset base, which contains high average grade reserves over double the industry average.
- Exploration continues to deliver value by expanding reserves and resources at mines such as Kittila, Meadowbank, Meliadine, Pinos Altos, and La India.
BMO Capital Markets 26th Global Metals & Mining ConferenceAgnico Eagle Mines
- The document discusses Agnico Eagle's forward-looking statements and provides context for non-GAAP financial measures used. It notes key assumptions and risks that could impact projections.
- Agnico Eagle exceeded 2016 production guidance of 1.6 million ounces at total cash costs of $600 per ounce. Production was 1.66 million ounces at total cash costs of $573 per ounce.
- New four-year guidance forecasts production growth to over 2 million ounces in 2020 as the Amaruq and Meliadine projects come online. Costs are expected to decline as production increases.
Agnico Eagle reported strong results for the second quarter of 2016, including:
- Gold production of 408,932 ounces at total cash costs of $592 per ounce
- Increased 2016 production guidance to 1.58-1.6 million ounces at lower costs
- Repaid $210 million credit facility balance and $20 million loan, reducing net debt to $742 million
- Declared a 25% increased quarterly dividend to $0.10 per share
Operations continue to deliver strong performance in the second quarter of 2017, with total gold production of 427,743 ounces and total cash costs per ounce of $556. Infill and exploration drilling at multiple properties, including LaRonde and Amaruq, yielded positive results that are expected to result in mineral resource additions and conversions. The Meliadine project is progressing on schedule and budget, with underground development ahead of plan and engineering 80% complete at the end of June 2017.
- Agnico Eagle provides a corporate update for November 2016, outlining its consistent strategy and solid execution that drives superior per share returns.
- Production is expected to grow to approximately 2.0 million ounces of gold in 2020 from its existing asset base.
- Agnico Eagle has high quality gold reserves with an average grade more than double that of North American peers that will support production growth.
- Exploration continues to be a key value driver, with several prospects delivering results.
- Agnico Eagle reported strong fourth quarter and full year 2015 results, exceeding annual gold production guidance for the fourth consecutive year.
- For 2016, the company expects gold production of 1.525-1.565 million ounces at total cash costs of $590-630 per ounce, with continued stable production and costs through 2018.
- Significant increases in gold resources were reported at the Amaruq, El Barqueño, and Sisar Zone projects, which could support future production growth beyond 2019.
This document provides an overview of Agnico Eagle's European Gold Forum presentation in Zurich in April 2016. It includes forward-looking statements about production guidance and costs. It also notes that total cash costs, all-in sustaining costs, and minesite costs per tonne are non-GAAP measures and provides definitions for these terms. Finally, it directs readers to Agnico Eagle's regulatory filings for further information.
The Nunavut Experience Mining and Exploring North of 60Agnico Eagle Mines
The document discusses permitting for mining and exploration projects in Nunavut, Canada. It notes that [1] Inuit organizations own subsurface and surface rights to portions of the land in Nunavut. [2] Key Inuit organizations that must be engaged with for agreements include Nunavut Tungavik Incorporated and regional Inuit organizations. [3] Permitting for exploration projects in Nunavut involves engaging with both Inuit organizations and various federal and territorial government bodies.
2. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 2
Forward Looking Statements
The information in this presentation has been prepared as at July 30, 2015. Certain statements contained in this document constitute “forward-looking statements”
within the meaning of the United States Private Securities Litigation Reform Act of 1995 and “forward-looking information” under the provisions of Canadian
provincial securities laws and are referred to herein as “forward-looking statements”. When used in this document, the words “anticipate”, “expect”, “estimate”,
“forecast”, “will”, “planned” and similar expressions are intended to identify forward-looking statements. Such statements include without limitation: the Company's
forward-looking production guidance, including estimated ore grades, project timelines, drilling results, metal production, mine estimates horizons, production, total
cash costs per ounce, minesite costs per tonne; all-in sustaining costs and cash flows; the estimated timing and conclusions of technical reports and other studies;
the methods by which ore will be extracted or processed; statements concerning expansion projects, recovery rates, mill throughput, and projected exploration
expenditures, including costs and other estimates upon which such projections are based; estimates of depreciation expense, general and administrative expense
and tax rates; the impact of maintenance shutdowns; statements regarding timing and amounts of capital expenditures and other assumptions; estimates of future
reserves, resources, mineral production, optimization efforts and sales; estimates of mine life; estimates of future mining costs, total cash costs, minesite costs, all-in
sustaining costs and other expenses; estimates of future capital expenditures and other cash needs, and expectations as to the funding thereof; statements and
information as to the projected development of certain ore deposits, including estimates of exploration, development and production and other capital costs, and
estimates of the timing of such exploration, development and production or decisions with respect to such exploration, development and production; estimates of
reserves and resources, and statements and information regarding anticipated future exploration; the anticipated timing of events with respect to the Company’s
mine sites and statements and information regarding the sufficiency of the Company’s cash resources and other statements and information regarding anticipated
trends with respect to the Company's operations, exploration and the funding thereof. Such statements and information reflect the Company’s views as at the date
of this document and are subject to certain risks, uncertainties and assumptions, and undue reliance should not be placed on such statements and information.
Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by Agnico Eagle as of the date of
such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The material factors and assumptions
used in the preparation of the forward looking statements contained herein, which may prove to be incorrect, include, but are not limited to, the assumptions set forth
herein and in management's discussion and analysis (“MD&A”) and the Company's Annual Information Form (“AIF”) for the year ended December 31, 2104 filed
with Canadian securities regulators and that are included in its Annual Report on Form 40-F for the year ended December 31, 2014 (“Form 40-F”) filed with the U.S.
Securities and Exchange Commission (the “SEC”) as well as: that there are no significant disruptions affecting operations; that production, permitting and expansion
at each of Agnico Eagle's properties proceeds on a basis consistent with current expectations and plans; that the relevant metals prices, exchange rates and prices
for key mining and construction supplies will be consistent with Agnico Eagle's expectations; that Agnico Eagle's current estimates of mineral reserves, mineral
resources, mineral grades and metal recovery are accurate; that there are no material delays in the timing for completion of ongoing growth projects; that the
Company's current plans to optimize production are successful; and that there are no material variations in the current tax and regulatory environment. Many
factors, known and unknown could cause the actual results to be materially different from those expressed or implied by such forward looking statements and
information. Such risks include, but are not limited to: the volatility of prices of gold and other metals; uncertainty of mineral reserves, mineral resources, mineral
grades and mineral recovery estimates; uncertainty of future production, capital expenditures, and other costs; currency fluctuations; financing of additional capital
requirements; cost of exploration and development programs; mining risks; community protests; risks associated with foreign operations; governmental and
environmental regulation; the volatility of the Company’s stock price; and risks associated with the Company’s by-product metal derivative strategies. For a more
detailed discussion of such risks and other factors that may affect the Company’s ability to achieve the expectations set forth in the forward-looking statements
contained in this document, see the AIF and MD&A filed on SEDAR at www.sedar.com and included in the Form 40-F filed on EDGAR at www.sec.gov, as well as
the Company’s other filings with the Canadian securities regulators and the SEC. The Company does not intend, and does not assume any obligation, to update
these forward-looking statements and information. For a detailed breakdown of the Company’s reserve and resource position see the Company’s press release
dated February 11, 2015.
3. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 3
Notes to Investors
Note Regarding the Use of Non-GAAP Financial Measures
This presentation discloses certain measures, including ‘‘total cash costs per ounce’’ and ‘‘minesite costs per tonne’’ that are not recognized measures under IFRS.
This data may not be comparable to data presented by other gold producers. For a reconciliation of these measures to the most directly comparable financial
information presented in the consolidated financial statements prepared in accordance with IFRS and for an explanation of how management uses these measures,
see “Reconciliation of Non-GAAP Financial Performance Measures” below. Total cash costs per ounce of gold produced is presented on both a by-product basis
(deducting by-product metal revenues from production costs) and co-product basis (before by-product metal revenues). Total cash costs per ounce of gold produced
on a by-product basis is calculated by adjusting production costs as recorded in the consolidated statements of income (loss) for by-product revenues, unsold
concentrate inventory production costs, smelting, refining and marketing charges and other adjustments, and then dividing by the number of ounces of gold
produced. Total cash costs per ounce of gold produced on a co-product basis is calculated in the same manner as total cash costs per ounce of gold produced on a
by-product basis except that no adjustment for by-product metal revenues is made. Accordingly, the calculation of total cash costs per ounce of gold produced on a
co-product basis does not reflect a reduction in production costs or smelting, refining and marketing charges associated with the production and sale of by-product
metals. Total cash costs per ounce of gold produced is intended to provide information about the cash generating capabilities of the Company’s mining operations.
Management also uses these measures to monitor the performance of the Company’s mining operations. As market prices for gold are quoted on a per ounce
basis, using the total cash cost per ounce of gold produced on a by-product basis measure allows management to assess a mine’s cash generating capabilities at
various gold prices. Management is aware that these per ounce measures of performance can be affected by fluctuations in and exchange rates. and, in the case of
total cash costs per ounce of gold produced on a by-product basis, by-product metal prices. Management compensates for these inherent limitations by using these
measures in conjunction with minesite costs per tonne (discussed below) as well as other data prepared in accordance with IFRS. Management also performs
sensitivity analyses in order to quantify the effects of fluctuating exchange rates and metal prices. This presentation also contains information as to estimated future
total cash costs per ounce, all-in sustaining costs and minesite costs per tonne. The estimates are based upon the total cash costs per ounce, all-in sustaining costs
and minesite costs per tonne that the Company expects to incur to mine gold at its mines and projects and, consistent with the reconciliation of these actual costs
referred to above, do not include production costs attributable to accretion expense and other asset retirement costs, which will vary over time as each project is
developed and mined. It is therefore not practicable to reconcile these forward-looking Non-GAAP financial measures to the most comparable IFRS measure.
Note Regarding Production Guidance
The gold production guidance is based on the Company’s mineral reserves but includes contingencies and assumes metal prices and foreign exchange rates that
are different from those used in the reserve estimates. These factors and others mean that the gold production guidance presented in this disclosure does not
reconcile exactly with the production models used to support these mineral reserves.
4. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 4
Continued strong operating performance – Payable gold production was 403,678 ounces of gold at total cash
costs per ounce on a by-product basis of $601, and All-in sustaining costs of $864 per ounce
Second consecutive record quarter of precious metal production in Mexico - Payable gold and silver production
was 92,056 ounces and 685,869 ounces respectively. Total cash costs per ounce of gold on a by-product basis were
$394
2015 production guidance maintained and costs reduced – Expected gold production for 2015 is maintained at
approximately 1.6 million ounces with total cash costs on a by-product basis of $600 to $620 per ounce and AISC of
approximately $870 to $890 per ounce
Vault Extension and Goldex Deep 1 approved for mining – Vault extension expected to reduce the potential
production gap with Amaruq by approximately one year. Goldex Deep 1 expected to add approximately 7 years of
production at 100,000 ounces of gold per year
Infill drilling at Amaruq’s Whale Tail deposit confirms grades and thicknesses; mineralization extended to
depth – highlights include:13.2 g/t gold over 14.3 metres at 133 metres depth and 8.8 g/t gold over 6.0 metres at 568
metres depth
Continued focus on debt reduction – In Q2 2015, $25 million was repaid on the Company’s credit facility, and
C$57.5 million of Canadian Malartic debt was retired
A quarterly dividend of $0.08 per share declared
Second Quarter Highlights
5. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 5
Operating Results
Strong quarterly production and steady cost performance
Q2 2015 H1 2015
All amounts are in US$
(Unless Otherwise Indicated)
Production
(Gold oz)
Total Cash Cost*
($/oz)
Operating Margin
($000’s)
Production
(Gold oz)
Total Cash Cost*
($/oz)
Northern Business
LaRonde 64,007 $613 $32,799 122,900 $656
Lapa 19,450 $678 $11,351 45,370 $615
Goldex 26,462 $633 $15,525 55,712 $585
Canadian Malartic (50%) 68,441 $609 $44,737 136,334 $621
Kittila 41,986 $776 $16,145 86,640 $727
Meadowbank 91,276 $688 $49,600 179,799 $672
311,622 $662 $170,157 626,755 $653
Southern Business
Pinos Altos 50,647 $384 $44,538 100,753 $371
Creston Mascota 15,606 $402 $12,968 28,054 $421
La India 25,803 $410 $18,834 52,326 $414
92,056 $394 $76,340 181,133 $391
Total 403,678 $601 $246,497 807,888 $595
Q2 2015 Total Operating Margin – $246.5 MQ2 2015 Revenue by Metal
Meadowbank,
20%
Pinos Altos, 18%
Canadian
Malartic, 18%LaRonde, 13%
La India, 8%
Kittila, 7%
Goldex, 6%
Lapa, 5%
Creston
Mascota, 5%
*Total cash costs are presented on a by-product basis, that is net of by-product revenue
Gold
95%
Silver
4%
Base Metals
1%
6. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 6
Financial Position
Cash position increased and debt levels reduced
Long-term Debt Maturities
2016 2017 2020 2022 2024
Notes Outstanding
(millions)
$115 $360 $225 $100
Coupon 6.13% 6.67% 5.93% 5.02%
Canadian Malartic Debt
(50% share) (millions)
C$20 C$20
Coupon 6.875% 6.875%
All Amounts Are In US$ (Unless Otherwise Indicated) June 30, 2015
Cash And Cash Equivalents (millions) $184
Outstanding Debt (millions) $1,196
Available Credit Facilities (millions) $825
Common Shares Outstanding, Basic (Q2 2015 Weighted Average, millions) 215
Common Shares Outstanding, Fully Diluted (Q2 2015 Weighted Average, millions) 217
9. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 9
Gold grades improve as tonnage from the higher-
grade lower mine area continues to increase
New conveyor and connection to internal ramp at the
281 level expected to be completed by the end of Q3
2015, which should improve mining flexibility
Studies are continuing to assess the potential to
extend the reserve base and carry out mining
activities between the 311 level and 371 level (a
depth of 3.7 km below the surface)
LaRonde
Gold Production Steadily Increasing, Commissioning of Coarse Ore Conveyor expected late Q3 2015
Proven & probable gold
reserves (million oz)
3.4
Indicated gold resource
(million oz)
0.7
Inferred gold resource
(million oz)
1.2
Total Cash Costs/oz
$613
Production
(koz)
64
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
$80
$90
$100
$110
$120
$130
-
10
20
30
40
50
60
Q3-13Q4-13Q1-14Q2-14Q3-14Q4-14Q1-15Q2-15
Production (koz) Cost/tonne
10. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 10
Further initiatives to optimize operations include:
Improvements to SAG mill liners to reduce the number of
planned shutdowns
Maintaining mining throughput levels at two million tonnes
per month in the higher grade North zone
Waste rock backfilling of the Gouldie pit to reduce haulage
distances and noise
Permitting activities for the Barnat Extension and
deviation of Highway 117 remain on schedule with
receipt of permits expected in late 2016
Drilling continues on the Odyssey North and South
underground targets
Canadian Malartic GP (50% Interest)
Mining Productivity Improves, North Zone Mining Rate Increases in Q2 2015
*Includes 11,878 ounces attributable to AEM post the Osisko acquisition
** Excludes royalties
Proven & probable gold
reserves (million oz)
4.3
Measured & indicated
gold resource (million oz)
1.0
Inferred gold resource
(million oz)
0.6
Total Cash Costs/oz
$609
Production
(koz)
68
Reserves and resources represent Agnico Eagle’s 50% interest as of December 31, 2014
$17
$18
$19
$20
$21
$22
100
110
120
130
140
150
Q1-14 Q2-14* Q3-14 Q4-14 Q1-15 Q2-15
Production (koz) Cost/tonne**
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
11. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 11
Goldex Deep 1 Project approved for production
Gold production expected to average >100,000 oz per
year through 2024 at an average annual total cash cost
per ounce of approximately $620
Advancement of the Deep 1 Project also unlocks
additional upside opportunities:
Potential for mining at Deep 2 (below Level 120)
Potential to develop the South Zone (a narrow high-grade zone
accessible via Deep 1 infrastructure)
Development of the Akasaba West deposit, which could
increase production
Goldex
Low Cost Production Continues
Proven & probable gold
reserves (million oz)
0.31
Measured & indicated
gold resource (million oz)
2.1
Inferred gold resource
(million oz)
1.5
Total Cash Costs/oz
$633
Production
(koz)
26
$20
$25
$30
$35
$40
15
20
25
30
Q4-13 Q1-14 Q2-14 Q3-14 Q4-14 Q1-15 Q2-15
Production (koz) Cost/tonne
12. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 12
Production Expected to Extend Through 2024
New mining area includes lower part of the
Dx zone and top of the D zone
Zone developed from current infrastructure,
no change in mining method
Mining rate expected to be approximately
6,000 tpd, at an average grade of 1.69 g/t
gold
Minesite costs per tonne are estimated at
C$35 to C$40
Development capital forecast to be
approximately $135 to $140 million. Total
sustaining capital over the expected seven
year mine life is estimated to be
approximately $60 to $70 million
Goldex Deep 1 Project
13. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 13
Feed head of Lapa ball mill sent for repairs in Q2
2015, and ore currently being processed through the
old LaRonde copper regrind circuit
Throughput levels expected to be lower than normal
until repairs completed in mid-Q3 2015.
Excess ore currently being stockpiled and mill
capacity is expected to be sufficient to meet annual
throughput rate (tonnes and ounces) over the
balance of 2015
2015 is the last full year of production based on
current mine plan. Additional exploration drilling is
ongoing in the Zulapa Z7 zone at depth which, if
successful, could extend the 2016 mine life
Lapa
Zulapa Z7 Zone Continues to Yield Higher Grades and Recoveries
Proven & probable gold
reserves (million oz)
0.21
Indicated gold resource
(million oz)
0.1
Inferred gold resource
(million oz)
0.2
Total Cash Costs/oz
$678
Production
(koz)
19
$90
$100
$110
$120
$130
$140
$150
-
5
10
15
20
25
30
Q3-13Q4-13Q1-14Q2-14Q3-14Q4-14Q1-15Q2-15
Production (koz) Cost/tonne
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
14. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 14
Vault pit expansion extends Meadowbank production
to Q3 2018
Mine life extension expected to shorten potential
production gap associated with the start-up of a
possible satellite operation at Amaruq
Meadowbank 2015 capital budget increased by $27
million to develop the Vault pit extension (higher
deferred stripping and the purchase of additional
haul trucks)
Meadowbank
Mine Life Extended as Vault Pit Extension Approved
Proven & probable gold
reserves (million oz)
1.2
Measured & indicated
gold resource (million oz)
0.8
Inferred gold resource
(million oz)
0.4
Total Cash Costs/oz
$688
Production
(koz)
91
$65
$70
$75
$80
$85
$90
-
25
50
75
100
125
150
175
Q3-13Q4-13Q1-14Q2-14Q3-14Q4-14Q1-15Q2-15
Production (koz) Cost/tonne
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
15. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 15
Amaruq – Highlights From Phase One 2015 Drill Program
Drilling Continues to Infill Whale Tail Zone; Positive Results at Mammoth Lake; Phase
Two Exploration Program Underway
AMQ15-239
6.0 g/t Au / 3.2 m
And 3.8 g/t Au / 3.7 m
AMQ15-243
11.6 g/t Au / 8.1 m
And 4.8 g/t Au / 3.2 m
AMQ15-226
13.3 g/t Au / 3.0 m
AMQ15-234
8.8 g/t Au / 6.0 m
AMQ15-249
10.2 g/t Au / 6.8 m
And 13.2 g/t Au / 14.3 m
AMQ15-205
6.7 g/t Au / 2.6 m
AMQ15-225
4.9 g/t Au / 3.9 m
AMQ15-191
3.9 g/t Au / 4.0 m
AMQ15-230
3.4 g/t Au / 4.4 m
And 3.9 g/t Au / 7.1 m
AMQ15-246
2.0 g/t Au / 8.8 m
And 6.8 g/t Au / 12.9 m
Incl. 14.4 g/t Au / 2.5 m
Incl. 8.8 g/t Au / 3.5 m
AMQ15-236
3.7 g/t Au / 10.3 m
And 11.7 g/t Au / 3.1 m
And 13.0 g/t Au / 7.1 m
IMQ15-209A
11.5 g/t Au / 5.6 m
And 5.2 g/t Au / 3.5 m
And 11.8 g/t Au / 3.2 m
And 11.9 g/t Au / 4.6 m
And 7.5 g/t Au / 3.4 m
AMQ15-221
11.3 g/t Au / 3.9 m
And 7.3 g/t Au / 5.4 m
AMQ15-250
13.9 g/t Au / 11.0 m
And 4.8 g/t Au / 6.5 m
And 10.2 g/t Au / 9.8 m
AMQ15-261
6.2 g/t Au / 11.3 m
AMQ15-267
5.5 g/t Au / 4.8 m
AMQ15-264
8.0 g/t Au / 8.4 m
16. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 16
Amaruq – Whale Tail Resource Model
Whale Tail deposit now defined over 1.2 km of strike length and to a depth of more than 450 metres.
Deposit remains open in all directions
AMQ15-249
10.2 g/t Au / 6.8 m
And 13.2 g/t Au / 14.3 m
AMQ15-236
3.7 g/t Au / 10.3 m
And 11.7 g/t Au / 3.1 m
And 13.0 g/t Au / 7.1 m
IVR14-209A
11.5 g/t Au / 5.6 m
And 5.2 g/t Au / 3.5 m
And 11.8 g/t Au / 3.2 m
And 11.9 g/t Au / 4.6 m
AMQ15-209A
7.5 g/t Au / 3.4 m
AMQ15-234
8.8 g/t Au / 6.0 m
AMQ15-243
11.6 g/t Au / 8.1 m
And 4.8 g/t Au / 3.2 m
AMQ15-225
4.9 g/t Au / 3.9 m
AMQ15-221
11.3 g/t Au / 3.9 m
And 7.3 g/t Au / 5.4 m
AMQ15-250
13.9 g/t Au / 11.0 m
And 4.8 g/t Au / 6.5 m
And 10.2 g/t Au / 9.8 m
17. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 17
In July 2015, the Kivalliq Inuit Association (KIA) and Agnico
Eagle signed the Inuit Impact Benefit Agreement (IIBA) for the
Meliadine gold project
Optimization studies continue on the large reserve and
resource base at Meliadine
Underground ramp development is on schedule and currently
at a depth of approximately 275 metres below surface
Project on track for a potential late 2019 startup, 2015 capital
budget has been increased by $22 million to expand the
existing surface and underground infrastructure, and prepare
for the 2016 work program
The company will be in a position to make a construction
decision in early 2016. Investment decision is dependent
on project economics and prevailing market conditions
Meliadine
Inuit Impact Benefit Agreement Signed
Proven & probable gold
reserves (million oz)
3.31
Indicated gold resource
(million oz)
3.3
Inferred gold resource
(million oz)
3.5
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
18. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 18
Higher throughput levels and the discovery of a new parallel
gold zone opens up potential for increased production
levels and further optimization of the Kittila mine plan
Main underground ramp at Kittila is being extended to reach
the Rimpi Zone and a surface ramp is also being developed
to access shallower portions of the Rimpi deposit
In April 2015, drilling encountered a new parallel lens of
mineralization approximately 1.3 km below surface and 150
meters east of the main Kittila ore zone
A recent hole in this area yielded 5.2 g/t gold over 13.3
meters at approximately 975 meters below surface. This
intersection is located approximately 150 metres below the
main exploration ramp being driven towards Rimpi
Kittila
Gold Production Increases, Unit Costs Decline, Drilling Continues on New Parallel Zone
No production in Q2-13 due to scheduled shutdown
Proven & probable gold
reserves (million oz)
4.5
Measured & indicated
gold resource (million oz)
1.4
Inferred gold resource
(million oz)
1.2
Total Cash Costs/ozProduction
(koz)
42
60 €
70 €
80 €
90 €
100 €
-
10
20
30
40
50
60
Q3-13 Q4-13 Q1-14 Q2-14 Q3-14 Q4-14 Q1-15 Q2-15
Production (koz) Cost/tonne
$776
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
20. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 20
Construction and engineering work continues on the
Phase IV heap leach pad
The Pinos Altos shaft remains on schedule for
completion in 2016.
Evaluation of regional satellite deposits continues. An in-
fill and conversion drill program is 50% complete on the
Sinter deposit with the expectation to add this to the
Pinos Altos mine plan beginning in 2020
Pinos Altos
Strong Performance Driven by Lower Costs and Higher Throughput
Proven & probable gold
reserves (million oz)
1.8
Indicated gold resource
(million oz)
0.7
Inferred gold resource
(million oz)
0.5
Total Cash Costs/oz
$384
Production
(koz)
51
$30
$35
$40
$45
$50
$55
$60
$65
$70
-
10
20
30
40
50
60
Q4-13 Q1-14 Q2-14 Q3-14 Q4-14 Q1-15 Q2-15
Production (koz) Cost/tonne
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
21. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 21
In April 2015, higher grade mineralization was discovered
at the bottom of the pit and outside the block model.
Additional drilling is underway to test for continuity, and
results are currently being compiled
In 2H 2015, infill and conversion drilling is planned on the
Bravo satellite zone. If successful, this could potentially
extend the Creston Mascota mine life
Creston Mascota
Improved Ore Stacking in Q2 2015
Proven & probable gold
reserves (million oz)
0.2
Indicated gold resource
(million oz)
0.05
Inferred gold resource
(million oz)
0.2
Total Cash Costs/oz
$402
Production
(koz)
16
No production in Q4-12 and Q1-13 due to temporary suspension of Phase one leach pad
$-
$5
$10
$15
$20
$25
$30
$35
$40
-
2
4
6
8
10
12
14
16
18
Q3-13Q4-13Q1-14Q2-14Q3-14Q4-14Q1-15Q2-15
Production (koz) Cost/tonne
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
22. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 22
Development of second phase leach pad continues. This
pad provides capacity for the current planned life-of-mine
production and ~5.0 million tonnes of additional stacking
Block model reconciliation remains favorable. Infill drilling
and technical studies are underway to refine the model. This
information is expected to be incorporated into year-end
2015 reserve and resource estimates
Re-evaluation of historical drill core at La India has better
quantified areas with gold bearing sulphide mineralization.
Preliminary metallurgical testing indicates that some of this
material may be heap leachable, and there could be
potential to reassign some of the sulphide mineral inventory
back into the resource category.
La India
Gold Production Exceeds Design Expectation as Growth Studies Continue
Proven & probable gold
reserves (million oz)
0.7
Measured & indicated
gold resource (million oz)
0.73
Inferred gold resource
(million oz)
1.0
Total Cash Costs/oz
$410
Production
(koz)
26
$-
$5
$10
$15
$20
-
5
10
15
20
25
30
Q2-14 Q3-14 Q4-14 Q1-15 Q2-15
Production (koz) Cost/tonne
See AEM Feb 11, 2015 press release and appendix for detailed breakdown of reserves and resources
24. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 24
Additional drill results from Amaruq with an updated mineral resource (including
indicated resources) expected later this summer
Further drill results from El Barqueno with a focus on mineral resource delineation by
year-end 2015
At Kittila, higher throughput levels, the discovery of a new parallel zone of gold
mineralization, and potential development of the higher-grade Rimpi zone opens up
the potential for increased production levels and further optimization of the mine plan
The advancement of the Deep 1 project at Goldex also unlocks significant upside
through the potential for additional mineral resource conversion in Deep 1, potential for
mining at Deep 2 (below Level 120), and potential to develop the Akasaba West
deposit
Future Catalysts
29. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 29
Notes to Investors Regarding
The Use of Resources
Cautionary Note to Investors Concerning Estimates of Measured and Indicated Resources
This document uses the terms “measured resources” and “indicated resources”. Investors are advised that while those terms are recognized and required by Canadian regulations, the
SEC does not recognize them. Investors are cautioned not to assume that any part or all of mineral deposits in these categories will ever be converted into reserves.
Cautionary Note to Investors Concerning Estimates of Inferred Resources
This document also uses the term “inferred resources”. Investors are advised that while this term is recognized and required by Canadian regulations, the SEC does not recognize it.
“Inferred resources” have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of
an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or pre-
feasibility studies, except in rare cases. Investors are cautioned not to assume that part or all of an inferred resource exists, or is economically or legally mineable.
Scientific and Technical Data
Cautionary Note To U.S. Investors - The SEC permits U.S. mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically
and legally extract or produce. Agnico Eagle Mines Limited reports mineral resource and reserve estimates in accordance with the CIM guidelines for the estimation, classification and
reporting of resources and reserves in accordance with the Canadian securities regulatory authorities' (the "CSA") National Instrument 43-101 Standards of Disclosure for Mineral
Projects ("NI 43-101"). These standards are similar to those used by the SEC’s Industry Guide No. 7, as interpreted by Staff at the SEC ("Guide 7"). However, the definitions in NI 43-
101 differ in certain respects from those under Guide 7. Accordingly, mineral reserve information contained herein may not be comparable to similar information disclosed by U.S.
companies. Under the requirements of the SEC, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be
economically and legally produced or extracted at the time the reserve determination is made. A "final" or "bankable" feasibility study is required to meet the requirements to designate
reserves under Industry Guide 7. Agnico Eagle uses certain terms in this presentation, such as "measured", "indicated", and "inferred", and "resources" that the SEC guidelines strictly
prohibit U.S. registered companies from including in their filings with the SEC.
In prior periods, reserves for all properties were typically estimated using historic three-year average metals prices and foreign exchange rates in accordance with the SEC guidelines.
These guidelines require the use of prices that reflect current economic conditions at the time of reserve determination, which the Staff of the SEC has interpreted to mean historic
three-year average prices. Given the current lower commodity price environment, Agnico Eagle has decided to use price assumptions that are below the three-year averages. The
assumptions used for the mineral reserves estimates at all mines and advanced projects as of December 31, 2014, reported by the Company on February 11, 2015, are $1,150 per
ounce gold, $18.00 per ounce silver, $1.00 per pound zinc, $3.00 per pound copper, $0.91 per pound lead and C$/US$, US$/Euro and MXP/US$ exchange rates of 1.08, 1.30 and
13.00, respectively.
For the reserves estimate at the Canadian Malartic mine, the Company has decided to continue to report the reserves estimated as of June 15, 2014, reported by the Company in a
news release dated August 13, 2014, minus the production to the end of 2014. The assumptions used were $1,300 per ounce gold, a cut-off grade between 0.28 g/t and 0.35 g/t gold
(depending on the deposit), and a C$/US$ exchange rate of 1.10.
NI 43-101 requires mining companies to disclose reserves and resources using the subcategories of "proven" reserves, "probable" reserves, "measured" resources, "indicated"
resources and "inferred" resources. Mineral resources that are not mineral reserves do not have demonstrated economic viability.
30. AGNICO EAGLE | SECOND QUARTER 2015 RESULTS | 30
Notes to Investors Regarding
The Use of Resources
A mineral reserve is the economically mineable part of a measured and/or indicated mineral resource. It includes diluting materials and allowances for losses, which may occur when
the material is mined or extracted and is defined by studies at pre-feasibility or feasibility level as appropriate that include application of modifying factors. Such studies demonstrate
that, at the time of reporting, extraction could reasonably be justified.
Modifying factors are considerations used to convert mineral resources to mineral reserves. These include, but are not restricted to, mining, processing, metallurgical, infrastructure,
economic, marketing, legal, environmental, social and governmental factors.
A proven mineral reserve is the economically mineable part of a measured mineral resource. A proven mineral reserve implies a high degree of confidence in the modifying factors. A
probable mineral reserve is the economically mineable part of an indicated and, in some circumstances, a measured mineral resource. The confidence in the modifying factors applying
to a probable mineral reserve is lower than that applying to a proven mineral reserve.
A mineral resource is a concentration or occurrence of solid material of economic interest in or on the Earth's crust in such form, grade or quality and quantity that there are reasonable
prospects for eventual economic extraction. The location, quantity, grade or quality, continuity and other geological characteristics of a mineral resource are known, estimated or
interpreted from specific geological evidence and knowledge, including sampling.
A measured mineral resource is that part of a mineral resource for which quantity, grade or quality, densities, shape and physical characteristics are estimated with confidence
sufficient to allow the application of modifying factors to support detailed mine planning and final evaluation of the economic viability of the deposit. Geological evidence is derived from
detailed and reliable exploration, sampling and testing and is sufficient to confirm geological and grade or quality continuity between points of observation. An indicated mineral
resource is that part of a mineral resource for which quantity, grade or quality, densities, shape and physical characteristics are estimated with sufficient confidence to allow the
application of modifying factors in sufficient detail to support mine planning and evaluation of the economic viability of the deposit. Geological evidence is derived from adequately
detailed and reliable exploration, sampling and testing and is sufficient to assume geological and grade or quality continuity between points of observation. An inferred mineral resource
is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to
imply but not verify geological and grade or quality continuity.
Investors are cautioned not to assume that part or all of an inferred resource exists, or is economically or legally mineable.
A feasibility study is a comprehensive technical and economic study of the selected development option for a mineral project that includes appropriately detailed assessments of
applicable modifying factors together with any other relevant operational factors and detailed financial analysis that are necessary to demonstrate, at the time of reporting, that
extraction is reasonably justified (economically mineable). The results of the study may reasonably serve as the basis for a final decision by a proponent or financial institution to
proceed with, or finance, the development of the project. The confidence level of the study will be higher than that of a Pre-Feasibility Study.
The effective date for all of the Company's mineral resource and reserve estimates in this presentation is December 31, 2014. Additional information about each of the mineral projects
that is required by NI 43-101, sections 3.2 and 3.3 and paragraphs 3.4 (a), (c) and (d) can be found in the Technical Reports filed by Agnico Eagle, which may be found at
www.sedar.com. Other important operating information can be found in the Company's AIF and Form 40-F.
The scientific and technical information contained herein has been approved by Daniel Doucet, Senior Corporate Director, Reserve Development, and/or Alain Blackburn, Senior Vice-
President, Exploration. Both Mr. Doucet and Mr. Blackburn are designated Ing. with the Ordredes ingenieurs du Québec and qualified persons as defined by NI 43-101.