SlideShare a Scribd company logo
Pocket Form Isolator

“Project Prismoid” Demonstration
     of Potential Savings via
   Concrete Waste Prevention

                                   1
Pocket Form Isolator…
• Seems to “Cost too much” to many people
  if they don’t understand how its cost can
  be offset with Concrete Waste Prevention.
• Stays where it is used to retain level soil,
  which is placed atop a concrete footing.
• May be placed prior to, or after steel
  column erection. Nothing needs to be cut
  in the field – only simple corner bolting.

                                                 2
Pocket Form Isolator…
• Never needs to be removed, which saves
  labor, money, time and reputations.

• Enables a wide variety of finish options.

• Often enables a contractor to cast slabs
  and pocket infill concrete simultaneously.

                                               3
Pocket Form Isolator…

• Works very differently from wooden or any
  other temporary forming method.

• Is designed to meet the specific project
  needs with all factors considered.



                                              4
Temporary Formwork…

• Must always be removed, and therefore; causes
  slab casting and pocket infill to be always placed
  at separate times. This unfortunate circumstance
  always increases time needs and results in
  chipped slab edges due to formwork removal.
  Utility penetrations often become a nightmare!

• PFI offers a very simple, precise solution! We
  have an amazing array of configurations!

                                                   5
Pocket Form Isolator…
• Enables “outside the box” conditions to be
  ideal for uniform thickness slab casting.
  Being able to maintain uniform slab
  thickness makes vapor barrier installation
  more practical and eliminates the waste of
  concrete being cast into unnecessary
  places. Concrete uses valuable natural
  resources and should be conserved.

                                               6
With temporary formwork…
• The contractor must thicken slab edges
  around isolation pockets to prevent loss of
  soil (as cave-ins). It is very rare for anyone
  to bring-in soil and compact this soil to a
  slope atop of the footing to form a “proper
  thickened edge”. The fact is that any
  thickened edge around an isolation pocket
  will always cause problems when the slab
  inevitably shrinks!
                                               7
Concrete Waste Prevention…
• Is the key to building the best possible
  pockets and casting a uniform thickness
  slab-on-grade.

• For the slab to maintain a uniform depth,
  there must not be areas where someone
  wastes money on thickened regions of
  concrete to enable a cheaper form to be
  utilized.
                                              8
Project Prismoid…
• Utilizes hollow wooden
  cubes to indicate one
  cubic yard of concrete.
  Since the scale for this
  model is 1.5” = 1’-0”,
  the cubes have an
  interior measurement of
  4.5” in all three
  directions. This is the
  simplest shape, 1- yard
  in all 3- directions!

                              9
Project Prismoid…
• Is a model where rice indicates waste concrete.
  Using this approach, rice only indicates waste,
  rather than necessary concrete for the slab.




                                                    10
Project Prismoid…
         • This model is built
           with a slope of 1:1,
           which for this model
           and at this scale = 20”
           of rise in 20” of run.

         • Anchor bolts give one
           a feel for where this
           applies to their own
           comparative project.

                                11
Project Prismoid…
         • Just to help this best
           look realistic, we also
           made a scaled-down
           column to mount to
           the anchor bolts.
         • This small column is
           not utilized in showing
           the concrete waste, it
           only provides spatial
           orientation.
                                12
Project Prismoid…

• Is designed to only indicate concrete waste and
  it is for this reason that all wood pockets made
  for this demonstration are 1’-8” deep. This model
  indicates where the change occurs between
  necessary and waste concrete. Obviously, the
  footing and (4” thick) slab are necessary
  concrete, so the rice will only indicate the
  unnecessary concrete. Remember unnecessary
  concrete = waste concrete. This will show you
  where lots of money may be saved.
                                                 13
A 24” square x 20” deep…
• Was made from wood to be
  used for the 24SQ24
  comparison. The top 4” to
  be the floor slab.

• The top photo shows how it
  will be used for rice to be
  placed.

• The lower photo shows how
  it aligns with the red lines
  on the “footing”. The
  pocket’s text is also red.

                                 14
A 28” square x 20” deep…
• Was made from wood to be
  used for the 28SQ24
  comparison. The top 4” to
  be the floor slab.

• The top photo shows how it
  will be used for rice to be
  placed.

• The lower photo shows how
  it aligns with the green lines
  on the “footing”. The
  pocket’s text is also green.

                                   15
A 36” square x 20” deep…
• Was made from wood to be
  used for the 36SQ24
  comparison. The top 4” to
  be the floor slab.

• The top photo shows how it
  will be used for rice to be
  placed.

• The lower photo shows how
  it aligns with the blue lines
  on the “footing”. The
  pocket’s text is also blue.

                                  16
In an effort to only indicate…
• Waste concrete, the
  interior pocket is only
  built up to the height
  of the sides – 20” for
  this example of 24”
  square with 20”:20”
  slope of soil base.
• The 24” square wood
  pocket is held-down
  with the anchor bolts.
                                    17
In an effort to only indicate…
• Waste concrete, the
  interior pocket is only
  built up to the height
  of the sides – 20” for
  this example of 28”
  square with 20”:20”
  slope of soil base.
• The 28” square wood
  pocket is held-down
  with the anchor bolts.
                                    18
In an effort to only indicate…
• Waste concrete, the
  interior pocket is only
  built up to the height
  of the sides – 20” for
  this example of 36”
  square with 20”:20”
  slope of soil base.
• The 36” square wood
  pocket is held-down
  with the anchor bolts.
                                    19
To enhance the sales of PFI…
• We have a spreadsheet which shows how
  much concrete waste costs for any variety
  of isolation pocket configurations.

• We are always glad to work w/ customer’s
  “numbers” and show them how much
  money can be saved by eliminating their
  thickened slab edge. They are always
  shocked to learn the savings potential!
                                          20
The Concrete Waste Calculator…

• Uses the aforementioned variables to run
  calculations with a formula for the volume
  of the resultant prismoid with the pocket’s
  infill subtracted from said prismoid. The
  infill is necessary concrete – and cannot,
  therefore; be considered waste. There are
  figures provided “along the way” to verify
  accuracy.

                                            21
Customer’s numbers we need:
• Cost of slab concrete per cubic yard.

• Pocket dimensions X, Y and Z.

• Ideal slab thickness (if uniform).

• Minimum edge width (bearing atop of footing).

• Quantity of similar pockets.

                                                  22
The “numbers” we need are:




                             23
The Concrete Waste Calculator…
• May easily be tailored to any condition for a
  square column isolation pocket.

• Will be easily used to “prove” certain examples
  that we have models made for.

• Uses formulas that are 100% accurate. The
  models simply indicate these volumes in a visual
  manner – which is often more easily understood.
                                                    24
Since the model’s footing exposure…

• Is 6’-0” (72”) square, the below listed
  examples have the following minimum
  edge distances (E.D.):

• 24SQ24 example, E.D. = 24”
• 28SQ24 example, E.D. = 22”
• 36SQ24 example, E.D. = 18”

                                            25
Project Prismoid 24SQ24 results…




• On the left is a photo of the model utilizing the 24”
  square wooden pocket. Around the pocket is rice, which
  is representing unnecessary concrete w/ PFI.
• On the right is a photo showing the removed rice placed
  into measuring cubes. Our spreadsheet proved that this
  example would require 3.44 cubic yards of slab concrete.
                                                        26
Project Prismoid 28SQ24 results…




• On the left is a photo of the model utilizing the 28”
  square wooden pocket. Around the pocket is rice, which
  is representing unnecessary concrete w/ PFI.
• On the right is a photo showing the removed rice placed
  into measuring cubes. Our spreadsheet proved that this
  example would require 3.35 cubic yards of slab concrete.
                                                        27
Project Prismoid 36SQ24 results…




• On the left is a photo of the model utilizing the 36”
  square wooden pocket. Around the pocket is rice, which
  is representing unnecessary concrete w/ PFI.
• On the right is a photo showing the removed rice placed
  into measuring cubes. Our spreadsheet proved that this
  example would require 3.13 cubic yards of slab concrete.
                                                        28
Concrete Waste Prevention…
• People often focus on the cost of the form and
  thereby consider PFI to be more expensive than
  their temporary form, but these same people fail
  to understand that in order to use a removable
  form, they must waste a huge amount of money
  to provide unnecessary concrete.
• PFI permanently retains the soil – placed atop of
  the footing – enabling a uniform thickness slab
  to be cast. This saves lots of money and gives a
  contractor perfect pockets for less cost than has
  been spent in the past.
                                                  29
One could accurately say that his pockets are “free”…

• When the mountain of costs using removable pockets is
  honestly and accurately considered!

• Also, his slab’s edges are clean and undisturbed
  because there has been no form removal.

• Don’t let this problem cause you to lose profits while
  building sloppy, wasteful, time-consuming junk pockets!

• Step-up to the plate and do things the modern way!

                                                            30

More Related Content

Similar to Project Prismoid Demonstration

Deck structural design
Deck structural designDeck structural design
Deck structural design
Praveen Sudarsan
 
Pouring concrete into formwork
Pouring concrete into formwork Pouring concrete into formwork
Pouring concrete into formwork
Dosy21
 
Heals - structural presentation
Heals -  structural presentationHeals -  structural presentation
Heals - structural presentation
Tanvir Khan
 
Woodworking: The Essentila "all Purpose" workbench
Woodworking: The Essentila "all Purpose" workbenchWoodworking: The Essentila "all Purpose" workbench
Woodworking: The Essentila "all Purpose" workbench
YadeaHerman
 
Deck structural design
Deck structural designDeck structural design
Deck structural design
Zulaiha Amaria
 
Production of concrete
Production of concreteProduction of concrete
Production of concrete
Darshil Vekaria
 
casting in manufacturing process in me.pptx
casting in manufacturing process in me.pptxcasting in manufacturing process in me.pptx
casting in manufacturing process in me.pptx
RavikumarK51
 
Bricks
BricksBricks
Low cost housing
Low cost housingLow cost housing
Low cost housing
SAI KIRAN
 
Fresh Concrete.pdf
Fresh Concrete.pdfFresh Concrete.pdf
TEC Products: Setting Material Technology Solutions for Wood Substrates
TEC Products: Setting Material Technology Solutions for Wood SubstratesTEC Products: Setting Material Technology Solutions for Wood Substrates
TEC Products: Setting Material Technology Solutions for Wood Substrates
TEC Installation Systems
 
ANALYZING OF THE HOUSE MATERIALS & CONSTRUCTION PROCESS.pdf
ANALYZING OF THE HOUSE MATERIALS & CONSTRUCTION PROCESS.pdfANALYZING OF THE HOUSE MATERIALS & CONSTRUCTION PROCESS.pdf
ANALYZING OF THE HOUSE MATERIALS & CONSTRUCTION PROCESS.pdf
Sayeem Abdul Hakim
 
Deebans container project
Deebans container project Deebans container project
Deebans container project
Deeban Fernandez Kandiban
 
Introduction to Casting
Introduction to CastingIntroduction to Casting
Introduction to Casting
Thulasikanth Vaddi
 
flat Slab
flat Slabflat Slab
flat Slab
Vikas Mehta
 
Form Work
Form Work Form Work
Form Work
Kezar Ali. Shah
 
Cov 09 How To Avoid Failure C
Cov 09 How To Avoid Failure CCov 09 How To Avoid Failure C
Cov 09 How To Avoid Failure C
DaveGobis
 
Process of manufacture of concrete
Process of manufacture of  concreteProcess of manufacture of  concrete
Process of manufacture of concrete
Manpreet Singh
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
Tarun kumar
 
Spring Box_compressed
Spring Box_compressedSpring Box_compressed
Spring Box_compressed
Lynn Roberts
 

Similar to Project Prismoid Demonstration (20)

Deck structural design
Deck structural designDeck structural design
Deck structural design
 
Pouring concrete into formwork
Pouring concrete into formwork Pouring concrete into formwork
Pouring concrete into formwork
 
Heals - structural presentation
Heals -  structural presentationHeals -  structural presentation
Heals - structural presentation
 
Woodworking: The Essentila "all Purpose" workbench
Woodworking: The Essentila "all Purpose" workbenchWoodworking: The Essentila "all Purpose" workbench
Woodworking: The Essentila "all Purpose" workbench
 
Deck structural design
Deck structural designDeck structural design
Deck structural design
 
Production of concrete
Production of concreteProduction of concrete
Production of concrete
 
casting in manufacturing process in me.pptx
casting in manufacturing process in me.pptxcasting in manufacturing process in me.pptx
casting in manufacturing process in me.pptx
 
Bricks
BricksBricks
Bricks
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
 
Fresh Concrete.pdf
Fresh Concrete.pdfFresh Concrete.pdf
Fresh Concrete.pdf
 
TEC Products: Setting Material Technology Solutions for Wood Substrates
TEC Products: Setting Material Technology Solutions for Wood SubstratesTEC Products: Setting Material Technology Solutions for Wood Substrates
TEC Products: Setting Material Technology Solutions for Wood Substrates
 
ANALYZING OF THE HOUSE MATERIALS & CONSTRUCTION PROCESS.pdf
ANALYZING OF THE HOUSE MATERIALS & CONSTRUCTION PROCESS.pdfANALYZING OF THE HOUSE MATERIALS & CONSTRUCTION PROCESS.pdf
ANALYZING OF THE HOUSE MATERIALS & CONSTRUCTION PROCESS.pdf
 
Deebans container project
Deebans container project Deebans container project
Deebans container project
 
Introduction to Casting
Introduction to CastingIntroduction to Casting
Introduction to Casting
 
flat Slab
flat Slabflat Slab
flat Slab
 
Form Work
Form Work Form Work
Form Work
 
Cov 09 How To Avoid Failure C
Cov 09 How To Avoid Failure CCov 09 How To Avoid Failure C
Cov 09 How To Avoid Failure C
 
Process of manufacture of concrete
Process of manufacture of  concreteProcess of manufacture of  concrete
Process of manufacture of concrete
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
 
Spring Box_compressed
Spring Box_compressedSpring Box_compressed
Spring Box_compressed
 

Project Prismoid Demonstration

  • 1. Pocket Form Isolator “Project Prismoid” Demonstration of Potential Savings via Concrete Waste Prevention 1
  • 2. Pocket Form Isolator… • Seems to “Cost too much” to many people if they don’t understand how its cost can be offset with Concrete Waste Prevention. • Stays where it is used to retain level soil, which is placed atop a concrete footing. • May be placed prior to, or after steel column erection. Nothing needs to be cut in the field – only simple corner bolting. 2
  • 3. Pocket Form Isolator… • Never needs to be removed, which saves labor, money, time and reputations. • Enables a wide variety of finish options. • Often enables a contractor to cast slabs and pocket infill concrete simultaneously. 3
  • 4. Pocket Form Isolator… • Works very differently from wooden or any other temporary forming method. • Is designed to meet the specific project needs with all factors considered. 4
  • 5. Temporary Formwork… • Must always be removed, and therefore; causes slab casting and pocket infill to be always placed at separate times. This unfortunate circumstance always increases time needs and results in chipped slab edges due to formwork removal. Utility penetrations often become a nightmare! • PFI offers a very simple, precise solution! We have an amazing array of configurations! 5
  • 6. Pocket Form Isolator… • Enables “outside the box” conditions to be ideal for uniform thickness slab casting. Being able to maintain uniform slab thickness makes vapor barrier installation more practical and eliminates the waste of concrete being cast into unnecessary places. Concrete uses valuable natural resources and should be conserved. 6
  • 7. With temporary formwork… • The contractor must thicken slab edges around isolation pockets to prevent loss of soil (as cave-ins). It is very rare for anyone to bring-in soil and compact this soil to a slope atop of the footing to form a “proper thickened edge”. The fact is that any thickened edge around an isolation pocket will always cause problems when the slab inevitably shrinks! 7
  • 8. Concrete Waste Prevention… • Is the key to building the best possible pockets and casting a uniform thickness slab-on-grade. • For the slab to maintain a uniform depth, there must not be areas where someone wastes money on thickened regions of concrete to enable a cheaper form to be utilized. 8
  • 9. Project Prismoid… • Utilizes hollow wooden cubes to indicate one cubic yard of concrete. Since the scale for this model is 1.5” = 1’-0”, the cubes have an interior measurement of 4.5” in all three directions. This is the simplest shape, 1- yard in all 3- directions! 9
  • 10. Project Prismoid… • Is a model where rice indicates waste concrete. Using this approach, rice only indicates waste, rather than necessary concrete for the slab. 10
  • 11. Project Prismoid… • This model is built with a slope of 1:1, which for this model and at this scale = 20” of rise in 20” of run. • Anchor bolts give one a feel for where this applies to their own comparative project. 11
  • 12. Project Prismoid… • Just to help this best look realistic, we also made a scaled-down column to mount to the anchor bolts. • This small column is not utilized in showing the concrete waste, it only provides spatial orientation. 12
  • 13. Project Prismoid… • Is designed to only indicate concrete waste and it is for this reason that all wood pockets made for this demonstration are 1’-8” deep. This model indicates where the change occurs between necessary and waste concrete. Obviously, the footing and (4” thick) slab are necessary concrete, so the rice will only indicate the unnecessary concrete. Remember unnecessary concrete = waste concrete. This will show you where lots of money may be saved. 13
  • 14. A 24” square x 20” deep… • Was made from wood to be used for the 24SQ24 comparison. The top 4” to be the floor slab. • The top photo shows how it will be used for rice to be placed. • The lower photo shows how it aligns with the red lines on the “footing”. The pocket’s text is also red. 14
  • 15. A 28” square x 20” deep… • Was made from wood to be used for the 28SQ24 comparison. The top 4” to be the floor slab. • The top photo shows how it will be used for rice to be placed. • The lower photo shows how it aligns with the green lines on the “footing”. The pocket’s text is also green. 15
  • 16. A 36” square x 20” deep… • Was made from wood to be used for the 36SQ24 comparison. The top 4” to be the floor slab. • The top photo shows how it will be used for rice to be placed. • The lower photo shows how it aligns with the blue lines on the “footing”. The pocket’s text is also blue. 16
  • 17. In an effort to only indicate… • Waste concrete, the interior pocket is only built up to the height of the sides – 20” for this example of 24” square with 20”:20” slope of soil base. • The 24” square wood pocket is held-down with the anchor bolts. 17
  • 18. In an effort to only indicate… • Waste concrete, the interior pocket is only built up to the height of the sides – 20” for this example of 28” square with 20”:20” slope of soil base. • The 28” square wood pocket is held-down with the anchor bolts. 18
  • 19. In an effort to only indicate… • Waste concrete, the interior pocket is only built up to the height of the sides – 20” for this example of 36” square with 20”:20” slope of soil base. • The 36” square wood pocket is held-down with the anchor bolts. 19
  • 20. To enhance the sales of PFI… • We have a spreadsheet which shows how much concrete waste costs for any variety of isolation pocket configurations. • We are always glad to work w/ customer’s “numbers” and show them how much money can be saved by eliminating their thickened slab edge. They are always shocked to learn the savings potential! 20
  • 21. The Concrete Waste Calculator… • Uses the aforementioned variables to run calculations with a formula for the volume of the resultant prismoid with the pocket’s infill subtracted from said prismoid. The infill is necessary concrete – and cannot, therefore; be considered waste. There are figures provided “along the way” to verify accuracy. 21
  • 22. Customer’s numbers we need: • Cost of slab concrete per cubic yard. • Pocket dimensions X, Y and Z. • Ideal slab thickness (if uniform). • Minimum edge width (bearing atop of footing). • Quantity of similar pockets. 22
  • 23. The “numbers” we need are: 23
  • 24. The Concrete Waste Calculator… • May easily be tailored to any condition for a square column isolation pocket. • Will be easily used to “prove” certain examples that we have models made for. • Uses formulas that are 100% accurate. The models simply indicate these volumes in a visual manner – which is often more easily understood. 24
  • 25. Since the model’s footing exposure… • Is 6’-0” (72”) square, the below listed examples have the following minimum edge distances (E.D.): • 24SQ24 example, E.D. = 24” • 28SQ24 example, E.D. = 22” • 36SQ24 example, E.D. = 18” 25
  • 26. Project Prismoid 24SQ24 results… • On the left is a photo of the model utilizing the 24” square wooden pocket. Around the pocket is rice, which is representing unnecessary concrete w/ PFI. • On the right is a photo showing the removed rice placed into measuring cubes. Our spreadsheet proved that this example would require 3.44 cubic yards of slab concrete. 26
  • 27. Project Prismoid 28SQ24 results… • On the left is a photo of the model utilizing the 28” square wooden pocket. Around the pocket is rice, which is representing unnecessary concrete w/ PFI. • On the right is a photo showing the removed rice placed into measuring cubes. Our spreadsheet proved that this example would require 3.35 cubic yards of slab concrete. 27
  • 28. Project Prismoid 36SQ24 results… • On the left is a photo of the model utilizing the 36” square wooden pocket. Around the pocket is rice, which is representing unnecessary concrete w/ PFI. • On the right is a photo showing the removed rice placed into measuring cubes. Our spreadsheet proved that this example would require 3.13 cubic yards of slab concrete. 28
  • 29. Concrete Waste Prevention… • People often focus on the cost of the form and thereby consider PFI to be more expensive than their temporary form, but these same people fail to understand that in order to use a removable form, they must waste a huge amount of money to provide unnecessary concrete. • PFI permanently retains the soil – placed atop of the footing – enabling a uniform thickness slab to be cast. This saves lots of money and gives a contractor perfect pockets for less cost than has been spent in the past. 29
  • 30. One could accurately say that his pockets are “free”… • When the mountain of costs using removable pockets is honestly and accurately considered! • Also, his slab’s edges are clean and undisturbed because there has been no form removal. • Don’t let this problem cause you to lose profits while building sloppy, wasteful, time-consuming junk pockets! • Step-up to the plate and do things the modern way! 30