2. Outline
● Introduction
● Business Need
● Approach
● Product Description
● Assumptions and Constraints
● Scope: Project Charter, Mind
map
● Organizational Structure
● Work BreakDown Structure
● Project Schedule: PDM
● Project Schedule: Gantt Chart
● Project Budget
● Performance Monitoring:EVM
● Cost-Benefit Analysis
● HR : RACI Chart
● Risk Analysis
● Quality : Checklist
● Procurement Plan
● Communication Plan
3. Introduction
● Bangkok Mass Transit System Public Limited
● electric mass transit railway system
● 47 Trains
● Objective:
● Installation of Vibration Energy Harvester based Wireless Sensor
Networks in 5 Trains
● Estimated Outcome
● Reduction in Maintenance time and cost
● Increase Safety
4. Business Need
● Increasing demand of safety in railways
● Reduction in maintenance cost and time of railways parts
● Shift from “Maintenance on Mileage” to “Maintenance on Need”
● Reduction of cost on spare parts (axles and wheels) by 10,000 USD per
train per year.
http://www.albion-ventures.co.uk/portfolionew/perpetuum-wins-contract-supply-southeastern-railways-energy%C2%A0
5. Approach
● Sensors
● Vibration and Temperature
● Requires an approx. average power of
3mW that can be produced from 40-50
mg of Vibration
● Communication
● Wireless communications to link the
Sensor Nodes with a Data Concentrator
and 3G connection to the central server
● Power
● Powered by vibration energy harvester.
● Data Display
● Patterns of vibration and temperature
● Alarm and Notification
7. Assumptions and Constraints
● Maintenance and operation time frame of trains should be adjusted for the
required sensor network installation and testing.
● Approximately, 1 Month monitoring period is required to monitor sensor
readings to calibrate and fine tune the threshold values.
● External factors such as excess noise level can impact the sensor
performance and calibration procedure should handle them.
16. Cost Benefit Analysis
Year Cash Inflows Cummulative Cash Flow Present Value
0 (123,600.00) (123,600.00) (123,600.00)
1 50,000.00 (73,600.00) 45,454.55
2 50,000.00 (23,600.00) 41,322.31
3 50,000.00 26,400.00 37,565.74
4 50,000.00 76,400.00 34,150.67
Net Present Value 34,893.27
Average Annual Profit 19,100.00
ROI 15.45
Interest Rate: 10%
Revenue is from
saving from
reduction in
maintenance
(10,000 USD per
train per year)
http://www.albion-ventures.co.uk/portfolionew/perpetuum-wins-contract-supply-southeastern-railways-energy%C2%A0
19. Risk Impact
Analysis Risk ID Project Risk
Probabilit
y Scope Cost
Schedul
e Quality
R1.1 Possible defects in sensor 0.4 H H
R1.2
Impact of noise condition for sensor
performance 0.5 H
R1.3 Impact of defects on server system 0.2 M H
R1.4 Data monitoring period may overrun 0.6 M H
R1.5 Security threats for sensor network 0.3 L
R1.6 Interference to Wifi connection 0.4
M
R1.7
Service impact when connecting new
network with existing O&M data com
network 0.3 M
R1.8 Connection reliability of 3G network 0.3 H
R2.1 Impact of bad weather 0.4 M M
R2.2
Delay with suppliers 0.4 L H
R2.3 Natural Disaster 0.3 H H H H
R3.1 Policy changes 0.4 L
R4.1 Change of staff members or resign 0.4 L L
20. Risk Register
Risk ID Cause Event Effect Likelihood Response
R1.1
Component
failure
Loss of data from
sensors
Acceptance test
failure
Likely
Backup storage of
sensors and
replace
R1.2
Environmental
Factors
Increase in Noise
level
Poor data quality Likely
Apply data
cleansing
R1.4
No enough data
for calibration
Long Calibration
period
Project extension Likely
Inform to
stakeholder
R2.2
Delay in
shipments
Delay with supplies
Delay in project
deliverables
Likely
Early order and
follow up
21. SWOT Analysis
Strength
Built-in analytics and alarming capabilities
Scalable
Self powered sensor network
Remote monitoring and visualization system
Weakness Periodic calibration
Opportunity
Automated monitoring system
Operational cost reduction
First deployment in South East Asia
High safety
Threat Loss of maintenance data
22. Quality Checklist
Project Name:
QUALITY CHECKLIST
Main Item Sub Item Verification Method Y N NA Date Remark
1
Quality of Central server
network
Rack and server installation
Should follow the installation guideline
provided by the vendors
Cabling
Should follow the installation guideline
provided by the vendors
2
Quality of Wireless Sensor
Network
Sensor, harvester and
communication module
installation
Should follow the installation guideline
provided by the vendor
Error free sensor data receive
rate. Using system KPI reports.
3 Security of the system
Datacom network security Check VPN Connection
Security of sensor network Enable Encryption protocols
Automatic Backup Check configuration and result
4 Documentation
Provide user manuals Check document versions
Provide network diagrams,
connectivity diagrams Continuous review and update
23. Procurement Plan - TOR
Item Description Qty
Energy
Harvesters
The energy Harvester with feed power to the wireless sensors up to 20 mW (4mA, 5 V)
It should operate on industrial operating range : -40 to +85 degree celsius.
Should compliance with FCC regulations.
60
Wireless
Sensors
Should support measurement of Temperature, Vibration and Acceleration
Should transmit continuous data at fixed collection intervals
Flexible power with replaceable battery module and external power module
60
Monitoring
Software
Equipped with toolset to view data of machine condition for 30 days
Plotting tools to view data on bar graph and pie chart.
Should be able to access from web GUI
1
Server The monitoring server should have the following minimum requirement;
2.83 GHz Intel Xeon Processor
2 GB RAM, 250 GB hard disk drive
Available USB port, VD-ROM drive
Window Server 2008 R2 x64
1
24. Procurement Plan
● Type of Contract: Firm Fixed price contract
● With BTS we have the Fixed price contract
● With the vendor where we purchase required platform also, we have
Fixed price contract.
● Currency : Everything will be dealt in USD (US Dollars)
25. Procurement Plan Vendors
Vendor selection criteria
● Price
● Technical specification of product
● Seller’s portfolio
Vendors considered
● Texas Instrument
● Perpenduum
● General Electric → Selected Vendor
○ Previous Business use and clear road path
26. Communication Plan
Audience Information Method Frequency Responsible Person
Project Team Daily project progress Email Daily Project Manager
Project Team, Project
Administrator Detail Project Progress
Face-to-face
Meeting Weekly Project Manager
Project Administrators and
Stakeholder
Milestone completions
Face-to-face
Meeting Milestone
Date
Project Manager
Video conferencing
Vendors
Follow up Purchase
Orders
Email When
required
Project
Administrators
Video conferencing
As a result of the increasing demand in safety and maintenance of the trains that serves 50,000 passengers per hour every day, Bangkok Mass Transit System Public Co., Ltd. (BTSC) is in the need of an improvement in its maintenance procedure. To comply with the international safety standard of such large railway system, the BTS railway system need to have a real time monitoring of its trains system such as wheel and axles so that faults in the moving parts are identified prior it become incidents. In addition, the cost of maintenance need to reduced such that company will meet its financial benefit by shifting to “maintain on need” from “maintain on mileage”.
Vibration Energy Harvester based Wireless Sensor Networks in 5 Trains
Energy harvesters powers the vibration and temperature sensors, which provide data in real time to the central server
Monitoring software process measurements and ;
predict the failure of rotating components such as bearings, motors and gearboxes.
Provide health condition of the components
A Web based monitoring system with built-in analytics and alarming capabilities solution for monitoring the health of the system components.
The rotating components decrease its performance or create noise than sensor will send the data.