SlideShare a Scribd company logo
Project Evaluation Techniques
By
Dr.Venkateswarlu Gogana
To Do
• If Optimistic Time of activities A, B, C, D and E is 9, 4, 7, 6 and
16 days. Pessimistic Time of activities A, B, C, D and E is 14, 12,
10, 16 and 30 days whereas Most likely time of activities A, B,
C, D and E is 12, 8, 9, 9 and 20 days respectively. Predecessor
of activities C, D and E is A, B and B respectively. What is the
expected duration for the project and Critical Path?
Profitability Index (PI) or Benefit-Cost
Ratio
• A benefit-cost ratio (BCR) is an indicator used in cost-
benefit analysis to show the relationship between the
relative costs and benefits of a proposed project,
expressed in monetary or qualitative terms. If a project
has a BCR greater than 1.0, the project is expected to
deliver a positive net present value to a firm and its
investors.
• Profitability Index is a ratio of discounted cash inflow to
the discounted cash outflow. Discounted cash inflow is
our benefit in the project and the initial investment is
our cost, which is why we also call it benefit to cost
ratio.
Operational steps
1. Find the expected cash inflows of the project
2. Find the cash outflows of the project (Initial
Investment + any other cash outflow)
3. Decide an appropriate discount rate
4. Discount the expected cash inflows using the
discount rate
5. Discount the future cash outflows and add to
initial investment
6. Divide step 4 by step 5
Example
Goals Achievement Technique
• A Process of determining appropriate future action by
utilizing scarce resources in such a way as to maximize
the attainment of ends held by the system
• Basic approach is to determine the extent to which
alternative plans will achieve a predetermined set of
goals and objectives. The progress towards the
specified objectives represent respectively the
advantages and disadvantages with alternative plan.
• This is an exante approach i.e, appraisal performed
before the selection and implementation of the final
plans.
Case
• Objectives
• 1) to minimize journey to work cost
• 2) to maximize residential amenity
• 3) to maximize provision of services
• Zones Chosen: 3
• Matrix A: Zone X Objective = Extent of achieving objective
• Matrix B: Zone X Policy = Extent of application of policies in each zone
1 2 3
1 12 12 6
2 15 10 12
3 5 8 8
1 2 3
1 10 7 5
2 4 5 1
3 3 5 11
Matrix Objectives
Zones
Matrix Objectives
Zones
• Matrix C: (A X B)
• Goal X Policy = Extent of satisfying the objective by each of the
alternative policies
• = (Goal X Zone) X (Zone X Policy)
1 2 3
1 195 184 180
2 184 174 158
3 132 142 130
Policy
Objective
• Matrix D: Weighing values are applied to objectives as the desire targets
by different groups of decision takers
1 2 3
1 1 1 1
2 2 1 2
3 3 2 1
Weighatge
Objective
• Matrix E (C X D)
• Policy X Desire target as weighted objectives
• =( Policy X Objective) X (Objective X weights)
1 2 3
1 959 643 695=2297
2 950 642 674=2274
3 936 548 576=2060
Weighted Objectives
Policy
Operational steps of Goals
Achievement Technique
• The relative importance of objectives are established by assigning a
set of numerical values
• The level of achievement of plans are estimated for each objective
interim
• Weighted by the respective values of the objectives, presented in a
matrix
• The relative weighatge set is prepared by the groups of different
classes of decision takers and representatives of different desire
targets who have given to put opinion to arrange the objectives in
preference basis in regard to quantify the qualitative aspects and
different inclinations
• These are then summed up to give an overall index of objective
achievement for each plan
• Finally this index value would be adjusted to take account of equity
of the resulting distribution of gains and losses, giving the
conclusion of the evaluation.
merits and demerits of Goals
Achievement Technique
• Merits
– Quantify the qualitative aspects
– Helps to take decision
– Mutual agreement
• Demerits
– Desires of the communities and groups are not taken
into account
– Lack of stated principles of Plan assessment
– Lack of rationality in selecting the numerical
– Doesn’t help in preparing a new plan
Thank You

More Related Content

Similar to Project Evaluation Techniques by Dr.Venkateswarlu Gogana.pdf

PMP Module 4 - Cost
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - CostCybrary
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptxInayatSheikh1
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
Session 04 - Project Planning II
Session 04 - Project Planning IISession 04 - Project Planning II
Session 04 - Project Planning IIRakeshSinhaPMP
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxDr. ABEER KHALID MANSOUR
 
Management Planning process
Management Planning processManagement Planning process
Management Planning processAntony Joseph
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectArvinThamsir1
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptArvinThamsir1
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting EngagementSaumya Ganguly
 
Capital Budgeting1.pptx.ppt
Capital Budgeting1.pptx.pptCapital Budgeting1.pptx.ppt
Capital Budgeting1.pptx.ppttanushreesingh23
 
Chapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraintsChapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraintsAKSHAYA0000
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfMadhusha15
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tomNASAPMC
 

Similar to Project Evaluation Techniques by Dr.Venkateswarlu Gogana.pdf (20)

Pm assignment
Pm assignmentPm assignment
Pm assignment
 
PMP Module 4 - Cost
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - Cost
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptx
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
Session 04 - Project Planning II
Session 04 - Project Planning IISession 04 - Project Planning II
Session 04 - Project Planning II
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
Management Planning process
Management Planning processManagement Planning process
Management Planning process
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
Mod 3 construction economics
 
Pmp inititating process group
Pmp inititating process groupPmp inititating process group
Pmp inititating process group
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 
Capital Budgeting1.pptx.ppt
Capital Budgeting1.pptx.pptCapital Budgeting1.pptx.ppt
Capital Budgeting1.pptx.ppt
 
Chapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraintsChapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraints
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
DASHBOARD MANAGER
DASHBOARD MANAGERDASHBOARD MANAGER
DASHBOARD MANAGER
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
 

More from DrVenkateswarluGogan1

Regional Plan for National Capital Region Dr venkateswarlu gogana.pdf
Regional Plan for National Capital Region Dr venkateswarlu gogana.pdfRegional Plan for National Capital Region Dr venkateswarlu gogana.pdf
Regional Plan for National Capital Region Dr venkateswarlu gogana.pdfDrVenkateswarluGogan1
 
National Housing Board Dr Venkateswarlu Gogana.pdf
National Housing Board Dr Venkateswarlu Gogana.pdfNational Housing Board Dr Venkateswarlu Gogana.pdf
National Housing Board Dr Venkateswarlu Gogana.pdfDrVenkateswarluGogan1
 
municipal act by Dr venkateswarlu gogana.pdf
municipal act by Dr venkateswarlu gogana.pdfmunicipal act by Dr venkateswarlu gogana.pdf
municipal act by Dr venkateswarlu gogana.pdfDrVenkateswarluGogan1
 
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdfLand Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdfDrVenkateswarluGogan1
 
Land acquisition Dr gogana venkateswarlu.pdf
Land acquisition Dr gogana venkateswarlu.pdfLand acquisition Dr gogana venkateswarlu.pdf
Land acquisition Dr gogana venkateswarlu.pdfDrVenkateswarluGogan1
 
Land acquisition 1894 and larr 2013.pptx
Land acquisition 1894 and larr 2013.pptxLand acquisition 1894 and larr 2013.pptx
Land acquisition 1894 and larr 2013.pptxDrVenkateswarluGogan1
 
ENDOGENOUS HAZARDS EARTHQUAKES .docx
ENDOGENOUS HAZARDS EARTHQUAKES .docxENDOGENOUS HAZARDS EARTHQUAKES .docx
ENDOGENOUS HAZARDS EARTHQUAKES .docxDrVenkateswarluGogan1
 
Environmental Hazards and Environmental Disaster and Its Types.docx
Environmental Hazards and Environmental Disaster and Its Types.docxEnvironmental Hazards and Environmental Disaster and Its Types.docx
Environmental Hazards and Environmental Disaster and Its Types.docxDrVenkateswarluGogan1
 
- Spatial Analysis and Modeling.pptx
- Spatial Analysis and Modeling.pptx- Spatial Analysis and Modeling.pptx
- Spatial Analysis and Modeling.pptxDrVenkateswarluGogan1
 

More from DrVenkateswarluGogan1 (20)

EG NOTES.docx
EG NOTES.docxEG NOTES.docx
EG NOTES.docx
 
EG QUESTION BANK.docx
EG QUESTION BANK.docxEG QUESTION BANK.docx
EG QUESTION BANK.docx
 
PHOTOGRAMMETRY.pptx
PHOTOGRAMMETRY.pptxPHOTOGRAMMETRY.pptx
PHOTOGRAMMETRY.pptx
 
MODERN SURVEYING TECHNIQUES.pptx
 MODERN SURVEYING TECHNIQUES.pptx MODERN SURVEYING TECHNIQUES.pptx
MODERN SURVEYING TECHNIQUES.pptx
 
GPS.ppt
GPS.pptGPS.ppt
GPS.ppt
 
Modern surveying instruments.pdf
Modern surveying instruments.pdfModern surveying instruments.pdf
Modern surveying instruments.pdf
 
HOUSING AND COMMUNITY PLANNING.pdf
HOUSING AND COMMUNITY PLANNING.pdfHOUSING AND COMMUNITY PLANNING.pdf
HOUSING AND COMMUNITY PLANNING.pdf
 
Slum improvement act.pdf
Slum improvement act.pdfSlum improvement act.pdf
Slum improvement act.pdf
 
Regional Plan for National Capital Region Dr venkateswarlu gogana.pdf
Regional Plan for National Capital Region Dr venkateswarlu gogana.pdfRegional Plan for National Capital Region Dr venkateswarlu gogana.pdf
Regional Plan for National Capital Region Dr venkateswarlu gogana.pdf
 
National Housing Board Dr Venkateswarlu Gogana.pdf
National Housing Board Dr Venkateswarlu Gogana.pdfNational Housing Board Dr Venkateswarlu Gogana.pdf
National Housing Board Dr Venkateswarlu Gogana.pdf
 
municipal act by Dr venkateswarlu gogana.pdf
municipal act by Dr venkateswarlu gogana.pdfmunicipal act by Dr venkateswarlu gogana.pdf
municipal act by Dr venkateswarlu gogana.pdf
 
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdfLand Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
 
Land acquisition Dr gogana venkateswarlu.pdf
Land acquisition Dr gogana venkateswarlu.pdfLand acquisition Dr gogana venkateswarlu.pdf
Land acquisition Dr gogana venkateswarlu.pdf
 
Land acquisition 1894 and larr 2013.pptx
Land acquisition 1894 and larr 2013.pptxLand acquisition 1894 and larr 2013.pptx
Land acquisition 1894 and larr 2013.pptx
 
Environmental Legislations.pptx
Environmental Legislations.pptxEnvironmental Legislations.pptx
Environmental Legislations.pptx
 
EXOGENOUS HAZARDS docx
EXOGENOUS HAZARDS docxEXOGENOUS HAZARDS docx
EXOGENOUS HAZARDS docx
 
ENDOGENOUS HAZARDS EARTHQUAKES .docx
ENDOGENOUS HAZARDS EARTHQUAKES .docxENDOGENOUS HAZARDS EARTHQUAKES .docx
ENDOGENOUS HAZARDS EARTHQUAKES .docx
 
Environmental Hazards and Environmental Disaster and Its Types.docx
Environmental Hazards and Environmental Disaster and Its Types.docxEnvironmental Hazards and Environmental Disaster and Its Types.docx
Environmental Hazards and Environmental Disaster and Its Types.docx
 
HOW GIS USED IN TENDERING
HOW GIS USED IN TENDERINGHOW GIS USED IN TENDERING
HOW GIS USED IN TENDERING
 
- Spatial Analysis and Modeling.pptx
- Spatial Analysis and Modeling.pptx- Spatial Analysis and Modeling.pptx
- Spatial Analysis and Modeling.pptx
 

Recently uploaded

Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfNurvisNavarroSanchez
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdfPratik Pawar
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptssuser9bd3ba
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industriesMuhammadTufail242431
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdfKamal Acharya
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxwendy cai
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdfKamal Acharya
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectRased Khan
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 

Recently uploaded (20)

Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 

Project Evaluation Techniques by Dr.Venkateswarlu Gogana.pdf

  • 2. To Do • If Optimistic Time of activities A, B, C, D and E is 9, 4, 7, 6 and 16 days. Pessimistic Time of activities A, B, C, D and E is 14, 12, 10, 16 and 30 days whereas Most likely time of activities A, B, C, D and E is 12, 8, 9, 9 and 20 days respectively. Predecessor of activities C, D and E is A, B and B respectively. What is the expected duration for the project and Critical Path?
  • 3. Profitability Index (PI) or Benefit-Cost Ratio • A benefit-cost ratio (BCR) is an indicator used in cost- benefit analysis to show the relationship between the relative costs and benefits of a proposed project, expressed in monetary or qualitative terms. If a project has a BCR greater than 1.0, the project is expected to deliver a positive net present value to a firm and its investors. • Profitability Index is a ratio of discounted cash inflow to the discounted cash outflow. Discounted cash inflow is our benefit in the project and the initial investment is our cost, which is why we also call it benefit to cost ratio.
  • 4. Operational steps 1. Find the expected cash inflows of the project 2. Find the cash outflows of the project (Initial Investment + any other cash outflow) 3. Decide an appropriate discount rate 4. Discount the expected cash inflows using the discount rate 5. Discount the future cash outflows and add to initial investment 6. Divide step 4 by step 5
  • 6.
  • 7. Goals Achievement Technique • A Process of determining appropriate future action by utilizing scarce resources in such a way as to maximize the attainment of ends held by the system • Basic approach is to determine the extent to which alternative plans will achieve a predetermined set of goals and objectives. The progress towards the specified objectives represent respectively the advantages and disadvantages with alternative plan. • This is an exante approach i.e, appraisal performed before the selection and implementation of the final plans.
  • 8. Case • Objectives • 1) to minimize journey to work cost • 2) to maximize residential amenity • 3) to maximize provision of services • Zones Chosen: 3 • Matrix A: Zone X Objective = Extent of achieving objective • Matrix B: Zone X Policy = Extent of application of policies in each zone 1 2 3 1 12 12 6 2 15 10 12 3 5 8 8 1 2 3 1 10 7 5 2 4 5 1 3 3 5 11 Matrix Objectives Zones Matrix Objectives Zones
  • 9. • Matrix C: (A X B) • Goal X Policy = Extent of satisfying the objective by each of the alternative policies • = (Goal X Zone) X (Zone X Policy) 1 2 3 1 195 184 180 2 184 174 158 3 132 142 130 Policy Objective • Matrix D: Weighing values are applied to objectives as the desire targets by different groups of decision takers 1 2 3 1 1 1 1 2 2 1 2 3 3 2 1 Weighatge Objective
  • 10. • Matrix E (C X D) • Policy X Desire target as weighted objectives • =( Policy X Objective) X (Objective X weights) 1 2 3 1 959 643 695=2297 2 950 642 674=2274 3 936 548 576=2060 Weighted Objectives Policy
  • 11. Operational steps of Goals Achievement Technique • The relative importance of objectives are established by assigning a set of numerical values • The level of achievement of plans are estimated for each objective interim • Weighted by the respective values of the objectives, presented in a matrix • The relative weighatge set is prepared by the groups of different classes of decision takers and representatives of different desire targets who have given to put opinion to arrange the objectives in preference basis in regard to quantify the qualitative aspects and different inclinations • These are then summed up to give an overall index of objective achievement for each plan • Finally this index value would be adjusted to take account of equity of the resulting distribution of gains and losses, giving the conclusion of the evaluation.
  • 12. merits and demerits of Goals Achievement Technique • Merits – Quantify the qualitative aspects – Helps to take decision – Mutual agreement • Demerits – Desires of the communities and groups are not taken into account – Lack of stated principles of Plan assessment – Lack of rationality in selecting the numerical – Doesn’t help in preparing a new plan