1Pivotal Tracker Getting Started Guide
DEFINITIONSPivotal Tracker Story-based project planning tool from Pivotal Labs.Based on agile software methodsAims to maximize team velocity rather than points scored by individualsProjectsEngage, Distro, Business, Operations, Backend (based on teams)IterationTime span of 1 working week is called an iteration.2
3DEFINITIONSStory is a basic  unit in pivotalRepresents small, concrete deliverable for a project.
Easily comprehensible and verifiable.
Placeholder for ongoing conversations.
Maybe estimated in points.Tasks:  To-do list while someone works on a story
Task status does not affect overall story status.LABELS, RELEASES AND CHARTS Labelsare tags, associated with stories.  They are used to organize stories. All labels in the project can be seen in the Labels & Searches panel.A Release  is a special type of story that represents a milestone in the backlog. Releases may be tied to production code pushes or they may simply represent a group of related features.Charts  available in Pivotal Tracker : https://www.pivotaltracker.com/help#whatchartsareavailableintracker4
TYPES OF STORIES
6STATES OF A STORYEstimate the story  Start Working on the StoryFinish the Story34  Commit  SVN & Deploy to LiveVerify5
ESTIMATION OF POINTS7
DEFINITIONSVelocityAverage number of points accepted per iteration, based on recently completed iterations.How is velocity calculated?Accepted stories in the current iteration move to the Done panel.
Team velocity is a running average of the velocity of the past 3 iterations.
Remaining stories are grouped into future iterations based on velocity.8

Pivotal Tracker - Quick Start Guide

  • 1.
  • 2.
    DEFINITIONSPivotal Tracker Story-basedproject planning tool from Pivotal Labs.Based on agile software methodsAims to maximize team velocity rather than points scored by individualsProjectsEngage, Distro, Business, Operations, Backend (based on teams)IterationTime span of 1 working week is called an iteration.2
  • 3.
    3DEFINITIONSStory is abasic unit in pivotalRepresents small, concrete deliverable for a project.
  • 4.
  • 5.
  • 6.
    Maybe estimated inpoints.Tasks: To-do list while someone works on a story
  • 7.
    Task status doesnot affect overall story status.LABELS, RELEASES AND CHARTS Labelsare tags, associated with stories. They are used to organize stories. All labels in the project can be seen in the Labels & Searches panel.A Release is a special type of story that represents a milestone in the backlog. Releases may be tied to production code pushes or they may simply represent a group of related features.Charts available in Pivotal Tracker : https://www.pivotaltracker.com/help#whatchartsareavailableintracker4
  • 8.
  • 9.
    6STATES OF ASTORYEstimate the story Start Working on the StoryFinish the Story34 Commit SVN & Deploy to LiveVerify5
  • 10.
  • 11.
    DEFINITIONSVelocityAverage number ofpoints accepted per iteration, based on recently completed iterations.How is velocity calculated?Accepted stories in the current iteration move to the Done panel.
  • 12.
    Team velocity isa running average of the velocity of the past 3 iterations.
  • 13.
    Remaining stories aregrouped into future iterations based on velocity.8