SlideShare a Scribd company logo
Review of Dynamic Model Requirements
John Schmall
ERCOT TransmissionPlanning
ResourceIntegration WorkingGroup Meeting
August 24, 2021
PUBLIC
Overview
2
• This presentationprovides an overviewof dynamic model requirements, including
the approved PGRR075(effective5/1/2020)andPGRR085 (effective3/1/2021)
– PGRR075 introduced dynamic model quality test (MQT) requirements
– PGRR085 introduced dynamic unit model validation (UMV), parameter verificationand
additional PSCAD model quality test requirements
• For IBRs (including wind, solar, and battery):
– PSCAD models must be provided with a model quality test report
• Applicable whenever a PSCAD model is provided or updated
– PSCAD models must be provided with a unit model validation hardware benchmark
• Applicable to make/model of inverter/turbine rather than site specific
• For all resources:
– Tunable parameters in the model must be periodically verified:
• Within 30 days of Part III approval (≈ Commercial Operations Date)or any change in settings
• Within 12 – 24 months of Part III approval (for new resources)
• Within 12 – 24 months of 3/1/21 (for existing resources)
• A minimum of every 10 years
– Different models should yield a consistent response (PSS/E, PSCAD, TSAT)
PUBLIC
Background
• IEs reported challenges in obtaining acceptable UMV reports from
manufacturers ahead of May 1, 2021 QSA deadline
– Projects allowed into the May 1 QSA with the understanding that UMV (and
PSCAD MQT) would be completed by August 1, 2021
– Projects unable to meet August 1 deadline
– Projects also allowed into the August 1 QSA with an incomplete UMV
• ERCOT has been providing feedback on preliminary submissions.
– Some projects are also lacking and acceptable PSCAD MQT
– UMV tests would seem to be more challenging for IEs than PSCAD MQT,
but note that there can be some MQT challenges if there are
inconsistencies between PSCAD and PSS/E MQT results
3
PUBLIC
UMV Acceptance Flexibility
• ERCOT considers hardware-in-the-loop (HiL) and other alternative test
approaches acceptable with sufficient justification
4
PUBLIC
Acceptance of UMV Reports
• Include all test components as specified in Planning Guide
– Section 6.2 (5) (d)
• Demonstrate appropriate model performance relative to test results
• Provide explanations/justificationsfor the test set-up as needed
• Not include disclaimers that render validation results meaningless:
5
PUBLIC
Firm Deadline for UMV & MQT Submissions
• Projects will not be allowed to qualify for November 1, 2021 QSA
unless acceptable UMV and MQT reports are submitted
• Projects that were allowed into the May 1 and August 1 QSA will not be
allowed to synchronize unless acceptable UMV and MQT reports are
submitted
– Exception for projects that submitted their current PSCAD model prior to
3/1/21 (PGRR-085was not intended to apply retroactively), however:
• Parameter verification report is required upon completion of commissioning
• MQT reports are required to accompany any “as-built” model updates
– Potential non-compliance consequences for failure to provide required
modeling data per NERC Reliability Standard MOD-032-1
• Submit UMV/MQT reports with sufficient lead time to allow an
adequate review period
6
PUBLIC
Summary of Dynamic Model Requirements
7
(1) Detailed test information is available in the DWG Procedural Manual 3.1.5.
(2) Benchmark the PSCAD model against actual hardware measurements. This is not a site-specific test; the
same report can be submitted for different projects whenever that the same inverter is used.
Requirement Applicable
Equipment
Required Tests(1) When to Update Responsi
ble Entity
Language
Model Quality Test
for PSS/E Model
All Resources and
Dynamic Transmission
Elements
(system strength test is
only required for inverter-
based devices)
Flat start, small and large
voltage disturbance, small
frequency disturbance, and
system strength tests
A new or updated model Equipment
owner
(RE, IE or
TSP)
PG
6.2(5)(c)
Model Quality Test
for PSCAD Model
Inverter-based
Resources (IBRs) and
Dynamic Transmission
Elements
All above tests plus
phase angle jump test
A new or updated model Equipment
owner
(RE, IE or
TSP)
PG
6.2(5)(c)
Unit Model
Validation for
PSCAD Model(2)
Inverter-based
Resources (IBRs)
Step change in voltage,
large voltage disturbance,
system strength, phase
angle jump, and
subsynchronous tests
A new PSCAD model provided
after 3/1/21. (Validation tests
should not need updating for
model parameter updates on an
existing model.)
Resource
owner (RE
or IE)
PG
6.2(5)(d)
Model Parameter
Verification
(“Verification
Report”)
All Resources and
Dynamic Transmission
Elements
Provide evidence that
tunable model parameters
match what is implemented
in the field. Evidence can
take the form of screenshots,
nameplate photographs,
signed manufacturer
commissioning reports, etc.
1. Required within 30 days of
COD (i.e., Part 3 approval),
2. 12 to 24 months after COD or
12-24 months after March 1,
2021 for existing resources,
3. A minimum of every ten yrs.
4. Within 30 days of a change at
the plant
Equipment
owner
(RE, IE or
TSP)
PG 5.7.1,
PG
6.2(5)(b)
PUBLIC
References
8
• Planning Guide Revision RequestPGRR-085 (approved & effective)
• Planning Guide 5.7.1 (in particular,paragraph (4)(e) & (4)(f))
• Planning Guide 6.2 (in particular,paragraph (5))
• Dynamics WorkingGroup DWGProcedure Manual section 3.1
• Model Quality Guide, published on the RE webpage at ercot.com
• Dynamic Model Templates,publishedon the RE webpage at ercot.com
Miscellaneous Reminders:
• PSS/E Dynamic models must be submitted using a Template
– The Template serves as the vehicle for both the PSS/E and the TSA
T model submission
– If submitting a model that is a User-Defined Model (UDM) then additional UDM files are required for TSAT
– If submitting a model that is a generic or standard library model available in PSS/E and TSA
T
, then no additional
files are required for TSAT
• The TSAT model and PSS/E model should be the same type of model with the same parameter
settings and format. This permits interoperability and allows the same Templateto be used for both
• Performing a NERC MOD 26, 27 study? Running your model quality tests at the same time is an
efficient means to meet both NERC and ERCOT requirements.(Referto the Model Quality Guide.)
• Converting from UDM to Generic? Suggest to have the vendor/manufactureto verify the conversion
and provide their attestation. Details are available in this presentation
PUBLIC
Questions or Comments
Contact:
John Schmall, John.Schmall@ercot.com
Jonathan Rose, Jonathan.Rose@ercot.com
9

More Related Content

Similar to PGRR085_RIWG_Aug24.pdf

ABC of developer test
ABC of developer testABC of developer test
ABC of developer test
Dr. Anish Cheriyan (PhD)
 
2013 OHSUG - Integration of Argus and Other Products Using the E2B Interchange
2013 OHSUG - Integration of Argus and Other Products Using the E2B Interchange2013 OHSUG - Integration of Argus and Other Products Using the E2B Interchange
2013 OHSUG - Integration of Argus and Other Products Using the E2B Interchange
Perficient
 
Dependable Systems -Reliability Prediction (9/16)
Dependable Systems -Reliability Prediction (9/16)Dependable Systems -Reliability Prediction (9/16)
Dependable Systems -Reliability Prediction (9/16)
Peter Tröger
 
Yizhe_Liu_Resume_11092016
Yizhe_Liu_Resume_11092016Yizhe_Liu_Resume_11092016
Yizhe_Liu_Resume_11092016Yizhe Liu
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)Vijayakumar Kumar
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentationRanvijay Akela
 
Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01
BhimKunwar2
 
Bringing Engineering Analysis Codes Into Real-Time Full-Scope Simulators
Bringing Engineering Analysis Codes Into Real-Time Full-Scope SimulatorsBringing Engineering Analysis Codes Into Real-Time Full-Scope Simulators
Bringing Engineering Analysis Codes Into Real-Time Full-Scope Simulators
GSE Systems, Inc.
 
Dcs capabilities
Dcs capabilitiesDcs capabilities
Dcs capabilities
Generic Logical
 
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
Sandia National Laboratories: Energy & Climate: Renewables
 
TWCCB Charter Docunent
TWCCB Charter DocunentTWCCB Charter Docunent
TWCCB Charter DocunentYarin Tuval
 
OPAL-RT real-time simulation at RTE
OPAL-RT real-time simulation at RTEOPAL-RT real-time simulation at RTE
OPAL-RT real-time simulation at RTE
OPAL-RT TECHNOLOGIES
 
150616 Progress Update WP2 (Bram Westerweel)
150616 Progress Update WP2 (Bram Westerweel)150616 Progress Update WP2 (Bram Westerweel)
150616 Progress Update WP2 (Bram Westerweel)
SINTAS
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
John Kingsley
 
Aerospace Project Integration at OPAL-RT
Aerospace Project Integration at OPAL-RT Aerospace Project Integration at OPAL-RT
Aerospace Project Integration at OPAL-RT
OPAL-RT TECHNOLOGIES
 
Portfolio control version sn_v5
Portfolio control version sn_v5Portfolio control version sn_v5
Portfolio control version sn_v5
Samuel Narcisse
 
Integrating Oracle Argus Safety with other Clinical Systems Using Argus Inter...
Integrating Oracle Argus Safety with other Clinical Systems Using Argus Inter...Integrating Oracle Argus Safety with other Clinical Systems Using Argus Inter...
Integrating Oracle Argus Safety with other Clinical Systems Using Argus Inter...Perficient
 

Similar to PGRR085_RIWG_Aug24.pdf (20)

ABC of developer test
ABC of developer testABC of developer test
ABC of developer test
 
2013 OHSUG - Integration of Argus and Other Products Using the E2B Interchange
2013 OHSUG - Integration of Argus and Other Products Using the E2B Interchange2013 OHSUG - Integration of Argus and Other Products Using the E2B Interchange
2013 OHSUG - Integration of Argus and Other Products Using the E2B Interchange
 
Dependable Systems -Reliability Prediction (9/16)
Dependable Systems -Reliability Prediction (9/16)Dependable Systems -Reliability Prediction (9/16)
Dependable Systems -Reliability Prediction (9/16)
 
Yizhe_Liu_Resume_11092016
Yizhe_Liu_Resume_11092016Yizhe_Liu_Resume_11092016
Yizhe_Liu_Resume_11092016
 
Resume
ResumeResume
Resume
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentation
 
Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01
 
Bringing Engineering Analysis Codes Into Real-Time Full-Scope Simulators
Bringing Engineering Analysis Codes Into Real-Time Full-Scope SimulatorsBringing Engineering Analysis Codes Into Real-Time Full-Scope Simulators
Bringing Engineering Analysis Codes Into Real-Time Full-Scope Simulators
 
Dcs capabilities
Dcs capabilitiesDcs capabilities
Dcs capabilities
 
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
 
TWCCB Charter Docunent
TWCCB Charter DocunentTWCCB Charter Docunent
TWCCB Charter Docunent
 
OPAL-RT real-time simulation at RTE
OPAL-RT real-time simulation at RTEOPAL-RT real-time simulation at RTE
OPAL-RT real-time simulation at RTE
 
Resume
ResumeResume
Resume
 
150616 Progress Update WP2 (Bram Westerweel)
150616 Progress Update WP2 (Bram Westerweel)150616 Progress Update WP2 (Bram Westerweel)
150616 Progress Update WP2 (Bram Westerweel)
 
CV_Vikram
CV_VikramCV_Vikram
CV_Vikram
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
 
Aerospace Project Integration at OPAL-RT
Aerospace Project Integration at OPAL-RT Aerospace Project Integration at OPAL-RT
Aerospace Project Integration at OPAL-RT
 
Portfolio control version sn_v5
Portfolio control version sn_v5Portfolio control version sn_v5
Portfolio control version sn_v5
 
Integrating Oracle Argus Safety with other Clinical Systems Using Argus Inter...
Integrating Oracle Argus Safety with other Clinical Systems Using Argus Inter...Integrating Oracle Argus Safety with other Clinical Systems Using Argus Inter...
Integrating Oracle Argus Safety with other Clinical Systems Using Argus Inter...
 

Recently uploaded

basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
itech2017
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 

PGRR085_RIWG_Aug24.pdf

  • 1. Review of Dynamic Model Requirements John Schmall ERCOT TransmissionPlanning ResourceIntegration WorkingGroup Meeting August 24, 2021
  • 2. PUBLIC Overview 2 • This presentationprovides an overviewof dynamic model requirements, including the approved PGRR075(effective5/1/2020)andPGRR085 (effective3/1/2021) – PGRR075 introduced dynamic model quality test (MQT) requirements – PGRR085 introduced dynamic unit model validation (UMV), parameter verificationand additional PSCAD model quality test requirements • For IBRs (including wind, solar, and battery): – PSCAD models must be provided with a model quality test report • Applicable whenever a PSCAD model is provided or updated – PSCAD models must be provided with a unit model validation hardware benchmark • Applicable to make/model of inverter/turbine rather than site specific • For all resources: – Tunable parameters in the model must be periodically verified: • Within 30 days of Part III approval (≈ Commercial Operations Date)or any change in settings • Within 12 – 24 months of Part III approval (for new resources) • Within 12 – 24 months of 3/1/21 (for existing resources) • A minimum of every 10 years – Different models should yield a consistent response (PSS/E, PSCAD, TSAT)
  • 3. PUBLIC Background • IEs reported challenges in obtaining acceptable UMV reports from manufacturers ahead of May 1, 2021 QSA deadline – Projects allowed into the May 1 QSA with the understanding that UMV (and PSCAD MQT) would be completed by August 1, 2021 – Projects unable to meet August 1 deadline – Projects also allowed into the August 1 QSA with an incomplete UMV • ERCOT has been providing feedback on preliminary submissions. – Some projects are also lacking and acceptable PSCAD MQT – UMV tests would seem to be more challenging for IEs than PSCAD MQT, but note that there can be some MQT challenges if there are inconsistencies between PSCAD and PSS/E MQT results 3
  • 4. PUBLIC UMV Acceptance Flexibility • ERCOT considers hardware-in-the-loop (HiL) and other alternative test approaches acceptable with sufficient justification 4
  • 5. PUBLIC Acceptance of UMV Reports • Include all test components as specified in Planning Guide – Section 6.2 (5) (d) • Demonstrate appropriate model performance relative to test results • Provide explanations/justificationsfor the test set-up as needed • Not include disclaimers that render validation results meaningless: 5
  • 6. PUBLIC Firm Deadline for UMV & MQT Submissions • Projects will not be allowed to qualify for November 1, 2021 QSA unless acceptable UMV and MQT reports are submitted • Projects that were allowed into the May 1 and August 1 QSA will not be allowed to synchronize unless acceptable UMV and MQT reports are submitted – Exception for projects that submitted their current PSCAD model prior to 3/1/21 (PGRR-085was not intended to apply retroactively), however: • Parameter verification report is required upon completion of commissioning • MQT reports are required to accompany any “as-built” model updates – Potential non-compliance consequences for failure to provide required modeling data per NERC Reliability Standard MOD-032-1 • Submit UMV/MQT reports with sufficient lead time to allow an adequate review period 6
  • 7. PUBLIC Summary of Dynamic Model Requirements 7 (1) Detailed test information is available in the DWG Procedural Manual 3.1.5. (2) Benchmark the PSCAD model against actual hardware measurements. This is not a site-specific test; the same report can be submitted for different projects whenever that the same inverter is used. Requirement Applicable Equipment Required Tests(1) When to Update Responsi ble Entity Language Model Quality Test for PSS/E Model All Resources and Dynamic Transmission Elements (system strength test is only required for inverter- based devices) Flat start, small and large voltage disturbance, small frequency disturbance, and system strength tests A new or updated model Equipment owner (RE, IE or TSP) PG 6.2(5)(c) Model Quality Test for PSCAD Model Inverter-based Resources (IBRs) and Dynamic Transmission Elements All above tests plus phase angle jump test A new or updated model Equipment owner (RE, IE or TSP) PG 6.2(5)(c) Unit Model Validation for PSCAD Model(2) Inverter-based Resources (IBRs) Step change in voltage, large voltage disturbance, system strength, phase angle jump, and subsynchronous tests A new PSCAD model provided after 3/1/21. (Validation tests should not need updating for model parameter updates on an existing model.) Resource owner (RE or IE) PG 6.2(5)(d) Model Parameter Verification (“Verification Report”) All Resources and Dynamic Transmission Elements Provide evidence that tunable model parameters match what is implemented in the field. Evidence can take the form of screenshots, nameplate photographs, signed manufacturer commissioning reports, etc. 1. Required within 30 days of COD (i.e., Part 3 approval), 2. 12 to 24 months after COD or 12-24 months after March 1, 2021 for existing resources, 3. A minimum of every ten yrs. 4. Within 30 days of a change at the plant Equipment owner (RE, IE or TSP) PG 5.7.1, PG 6.2(5)(b)
  • 8. PUBLIC References 8 • Planning Guide Revision RequestPGRR-085 (approved & effective) • Planning Guide 5.7.1 (in particular,paragraph (4)(e) & (4)(f)) • Planning Guide 6.2 (in particular,paragraph (5)) • Dynamics WorkingGroup DWGProcedure Manual section 3.1 • Model Quality Guide, published on the RE webpage at ercot.com • Dynamic Model Templates,publishedon the RE webpage at ercot.com Miscellaneous Reminders: • PSS/E Dynamic models must be submitted using a Template – The Template serves as the vehicle for both the PSS/E and the TSA T model submission – If submitting a model that is a User-Defined Model (UDM) then additional UDM files are required for TSAT – If submitting a model that is a generic or standard library model available in PSS/E and TSA T , then no additional files are required for TSAT • The TSAT model and PSS/E model should be the same type of model with the same parameter settings and format. This permits interoperability and allows the same Templateto be used for both • Performing a NERC MOD 26, 27 study? Running your model quality tests at the same time is an efficient means to meet both NERC and ERCOT requirements.(Referto the Model Quality Guide.) • Converting from UDM to Generic? Suggest to have the vendor/manufactureto verify the conversion and provide their attestation. Details are available in this presentation
  • 9. PUBLIC Questions or Comments Contact: John Schmall, John.Schmall@ercot.com Jonathan Rose, Jonathan.Rose@ercot.com 9