SlideShare a Scribd company logo
1 of 31
Download to read offline
Project Finance and
 Contract Pricing



 Project Finance & Contract Pricing
 Contract Cash Flow

 How much is the total cost?

 How to arrange for financing?

 Cash Flow = Cash In –Cash Out

              = Income – Expense

              = Revenue - Cost

 27/11/2006        Emad Elbeltagi   2




                                        1
Project Finance & Contract Pricing
Project Expenses

       The project cost types:

             Fixed cost (equipment,…)

             Time-related cost (distributed over the duration of an activity, e.g.,

             salaries, …)

             Quantity (Production)-related costs (costs per unit of materials or

             unit of resource usage)


       When these costs are paid, it is named expenses


27/11/2006                             Emad Elbeltagi                          3




Project Finance & Contract Pricing
Project Expenses (Smooth curve)

             LE x1000
             700
             600
             500                Cost

             400
             300                 Expense

             200
             100
               0                                                  Time
                   0        2          4         6      8    10



27/11/2006                             Emad Elbeltagi                          4




                                                                                      2
Project Finance & Contract Pricing
Project Expenses
     The project S-Curve:
              Cost (LE)




                                                         Time




 27/11/2006                    Emad Elbeltagi                         5




 Project Finance & Contract Pricing
Project Income

        Project revenue is the summation of the activities prices

        Represents the payment made by the owner to the contractor

        Mostly, the contractor receive his payments after one month

        from submitting his/her invoice

        Retainage of 5 or 10 to ensure that that no problems will arise

        during construction

        When the contractor receive his/her payments, it is called

        Income
 27/11/2006                    Emad Elbeltagi                         6




                                                                          3
Project Finance & Contract Pricing
 Project Income (Stepped curve)

               LE x1000
               800
               700
               600
               500            Revenue
               400                          Income

               300
               200
               100
                  0                                         Time
                      0   2      4         6      8    10

  27/11/2006                     Emad Elbeltagi                        7




  Project Finance & Contract Pricing
Example

       Consider the construction operation of a foundation activity

        Activity duration 8 weeks

        Labor cost of LE 1600 paid weekly

       Equipment cost of LE 4000 paid weekly after 2-month credit facility

       Material cost of LE 800 paid weekly after 3-month credit facility

       Subcontractor cost of LE 2400 paid weekly after 1-month credit
       facility

       When each payment by the contractor is due and how much?

  27/11/2006                     Emad Elbeltagi                        8




                                                                             4
Project Finance & Contract Pricing
      Example
                      Activity total cost = LE 8800


     Week                      1                2           3             4            5       6        7           8

    Payments                  1100          1100        1100             1100         1100    1100    1100     1100


     Total                    1100          2200        3300             4400         5500    6600    7700     8800




      27/11/2006                                                Emad Elbeltagi                                  9




      Project Finance & Contract Pricing
     Project Income (Stepped curve)
wk    1       2       3        4        5   6       7   8        9   10 11 12 13 14 15 16 17 18 19 20


L     - 200 200 200 200 200 200 200 200


E     -        -      -        -        -   -       -   -       500 500 500 500 500 500 500 500


M         -       -       -        -    -   -       -   -        -   -        -   -    100 100 100 100 100 100 100 100


S     -       -       -        -       300 300 300 300 300 300 300 300


T     -       500 200 200 500 500 500 500 1000 800 800 800 600 600 600 600 100 100 100 100




      27/11/2006                                                Emad Elbeltagi                                 10




                                                                                                                         5
Project Finance & Contract Pricing
Contract Cash Flow
 Cost (LE)                                                     Retainage

                       Expense
                         Profile



                                               Income
                                                 Profile


                                                               Month

                     Cash out-of-flow

27/11/2006                    Emad Elbeltagi                           11




Project Finance & Contract Pricing
Contract Cash Flow - Admeasurements contract
Cumulative cost (LE)



                                   Expense


                                   Overdraft



                                           Income


                                                                       Time
             1   2       3    4        5        6      7   8



27/11/2006                    Emad Elbeltagi                           12




                                                                              6
Project Finance & Contract Pricing
Contract Cash Flow - Admeasurements contract
  with advanced payment
    Cumulative Cost (LE)




                                                              Expense
                                     Income




  Advanced
  payment
                                                                               Time
                 0       1       2       3        4       5       6   7    8


27/11/2006                                   Emad Elbeltagi                           13




Project Finance & Contract Pricing
Contract Cash Flow – Lump sum contract with three
  payments
 Cumulative Cost (LE)


                                     Expense

                                                                  Income




                                                                                Time
             0       1       2       3        4       5       6       7    8




27/11/2006                                   Emad Elbeltagi                           14




                                                                                           7
Project Finance & Contract Pricing
Contract Cash Flow
Variables needed to calculate cash flow

        The project bar chart (project schedule)

        Activities’ direct and indirect cost

        Contractor method of paying his/her expenses

        Contractor’s markup

        Retention amount and its payback time

        Time of payment delay by owner

        Advanced or mobilization payment

 27/11/2006                      Emad Elbeltagi                   15




 Project Finance & Contract Pricing
Contract Cash Flow
Procedure to calculate cash flow
        The project bar chart (project schedule)
        Perform project schedule
        Draw bar chart based on early or late timings
        Calculate the cost per time period
        Calculate the cumulative cost
        Adjust the cost to produce the expenses
        Calculate cumulative revenue: revenue = cost x (1 + markup)
        Adjust the revenue to produce the income
        Calculate the cash flow (cash flow = income – expense).
 27/11/2006                      Emad Elbeltagi                   16




                                                                       8
Project Finance & Contract Pricing
    Example
                              4 14                12 22
                                         D(8)
                               2                   3
                  A(4)                                     E(4)
                               6   6              16 18           24 26              32 32
                   B(6)                F(10)                                  I(6)
0    0    1                    4                    5      H(8)   6                       9

                    C(2)                 G(16)
                                                                      K(10)
                                       J(6)        8
                               7

                              2 16               22 22



     27/11/2006                           Emad Elbeltagi                             17




     Project Finance & Contract Pricing
    Example
    Example data: Mark up = 5%

                   Duration            Total Cost (LE x       Total Revenue (LE x
     Activity
                    (day)                   1000)                    1000)
         A               4                      04.00                  04.20
         B               6                      12.00                  12.60
         C               2                      04.00                  04.20
         D               8                      16.00                  16.80
         E               4                      20.00                  21.00
         F               10                     20.00                  21.00
         G               16                     16.00                  16.80
         H               8                      24.00                  25.20
         I               6                      12.00                  12.60
         J               6                      12.00                  12.60
         K               10                     10.00                  10.50
     27/11/2006                           Emad Elbeltagi                             18




                                                                                              9
Project Finance & Contract Pricing
Example
Example data:

        Contractor expenses will be paid immediately

        Retention = 10% will be paid with the last payment

        Calculations made every 8 days

        Owner payment will be delayed one period

        First invoice after at the end of the period

        No advanced payment



 27/11/2006                              Emad Elbeltagi                         19




 Project Finance & Contract Pricing
Example                                    Time (days)
     1000/day

       2000/day
        000/day

    2000/day
                         2000/day
                                         5000/day

                              2000/day

                                         1000/day

                                                          3000/day

                                                                     2000/day

                  2000/day

                                                                     1000/day




 27/11/2006                              Emad Elbeltagi                         20




                                                                                     10
Project Finance & Contract Pricing
 Example
1. Cost/2 days x
                                   10   10   12    14    10   10     16       16   8       8   8     8    6    6     6     2   -   -        -     -
     LE1000
2. Cost each period x
                                                   46                         52                    32                    20                      -
     LE1000
3. Cumulative cost x
                                                   46                         98                   130                   150                    150
     LE1000
4. Cumulative
                                                   46                         98                   130                   150                    150
     Expense x 1000
5. Revenue = row 3 x
                                                  48.3                    54.6                     33.6                   21                      -
     1.05
6. Revenue - retention
                                                 43.47                 49.14                    30.24                 18.90                       -
     = row 5 x 0.9

7. Retention x LE1000                                -                         -                      -                    -                 15.75

8. Cumulative revenue
                                                 43.47                 92.61                   122.85                141.75                 157.50
     x LE1000
9. Cumulative income
                                                     -                 43.47                    92.61                122.85                 157.50
     x LE1000
10. Cumulative cash
     flow x LE1000 =                               -46             -98/-54.53          -86.53/-37.39          -57.39/-27.15        -27.15/+7.5
     row 9 – row 4



   27/11/2006                                                  Emad Elbeltagi                                                          21




   Project Finance & Contract Pricing
 Example
                         160
                         150
                         140                                                                                       Area = LE 10,000
                         130                                                                                        x 1 period (8-days)
                         120
                         110
                         100
              LE x1000




                          90
                          80
                          70
                          60
                          50
                          40
                          30
                          20
                          10
                           0
                               0             1            2               3            4             5          6

                                                               Time (period)


   27/11/2006                                                  Emad Elbeltagi                                                          22




                                                                                                                                                      11
Project Finance & Contract Pricing
Example
                       0   1   2          3         4   5   6
                 30

                 10

                 -10
    LE x 1000




                 -30

                 -50

                 -70

                 -90

                -110
                                   Time (period)


27/11/2006                         Emad Elbeltagi               23




Project Finance & Contract Pricing
Minimizing Contract Negative Cash Flow
      Loading of rates

      Adjustment of work schedule to late start timing

      Reduction of delays in receiving revenues

      Asking for advanced or mobilization payment

      Increasing the mark up and reducing the retention

      Adjust the timing of delivery of large material orders

      Delay in paying labor wages, equipment, material
27/11/2006                         Emad Elbeltagi               24




                                                                     12
Project Finance & Contract Pricing
Cost of Borrowing
                        160
                        150
                        140
                                                                   Area = LE 10,000
                        130
                                                                    x 1 period (8-
                        120
                        110
                                                                   days)
                        100
             LE x1000

                         90
                         80
                         70
                         60
                         50
                         40
                         30
                         20
                         10
                          0
                              0   1   2         3          4   5   6

                                           Time (period)

     24 unit areas, interest rate 1% per period
     Cost = 24 x 10000 x 0.01 = LE 2400
27/11/2006                                Emad Elbeltagi                              25




 Project Finance & Contract Pricing
Project Cash Flow
      Time scale is much longer spans the whole life of a project

      Feasibility studies

      Execution

      Operation

Profitability indicators

       Payback period

       Maximum capital – maximum negative cash

       Profit

27/11/2006                                Emad Elbeltagi                              26




                                                                                           13
Project Finance & Contract Pricing
  Project Cash Flow
           Cumulative
           cash flow




                        Payback                                           Profit
                        period

                                                          Project
Maximum                                                   duration
capital




   27/11/2006                      Emad Elbeltagi                             27




   Project Finance & Contract Pricing
  Project Cash Flow: Example
   Project net cash flow
          Year              1     2        3        4      5         6   7         8
Project A (LE x 1000)      -10    -40     -30       20    60     20      15        30
Project B (LE x 1000)      -30    -80     30        50    10     20      40        40



   Project cumulative cash flow
           Year             1      2        3       4      5         6   7         8
 Project A (LE x 1000)     -10     -50     -80      -60    0     20      35        65
 Project B (LE x1000)      -30    -110     -80      -30   -20     0      40        80


   27/11/2006                      Emad Elbeltagi                             28




                                                                                        14
Project Finance & Contract Pricing
 Project Cash Flow: Example
100
                                                             80
                                                             65
 50
                                                 Project A
  0
       0                2                   4            6   8
 -50
                               -80

-100
                      -110   Project B
-150




  27/11/2006                         Emad Elbeltagi           29




  Project Finance & Contract Pricing
 Discounted Cash Flow
Present value (PV)
           Current values of money
           Discounted value due to inflation
           Change in currency power purchasing



           C = P x (1+r) n(1 + r) (1 + r)
                    (1+r)
        P = C / (1+r) n
       Net present value (NPV)= PV income- PV expense

  27/11/2006                         Emad Elbeltagi           30




                                                                   15
Project Finance & Contract Pricing
Net Present Value
  Project net cash flow
      Year          0         1            2     3     4      5
Project A (LE ) -1000       500            400   200   200   100
Project B (LE ) -1000       100            200   200   400   700


        Which project would you prefer?

        Interest rate (discount rate) = 10% /year


 27/11/2006               Emad Elbeltagi                     31




 Project Finance & Contract Pricing
Net Present Value

  Project A




  Project B




 27/11/2006               Emad Elbeltagi                     32




                                                                   16
Project Finance & Contract Pricing
Internal rate of return (IRR)

        The least discount rate (investment rate) that

        acceptable by the contractor or greater than the

        return on capital

        It is the discount rate with zero NPV




27/11/2006                  Emad Elbeltagi                 33




Project Finance & Contract Pricing
Internal rate of return: Example
   Same previous example
 Project A




   Project B




27/11/2006                  Emad Elbeltagi                 34




                                                                17
Project Finance & Contract Pricing
Finalizing Bid Price

                                Price




                 Markup                             Cost




     Risk       Financial                    Indirect
                                 Profit                 Direct cost
  allowance      charge                        cost




 27/11/2006                 Emad Elbeltagi                        35




 Project Finance & Contract Pricing
Indirect Cost

Project Overheads (Site)

       Does not apply to a specific activity

       Cost of site utilities, supervisors, workshop,…

       A detailed analysis can be carried out

       Generally assumed 5 – 15 % of direct cots



 27/11/2006                 Emad Elbeltagi                        36




                                                                       18
Project Finance & Contract Pricing
Indirect Cost

General Overheads (Head-office)

       Does not apply to a specific project

       Cost of head-office, managers, estimators,…

       Generally assumed 2 – 5 % of direct cots

       For a specific project: Project direct cost x general
       overhead of the company in a year/ Expected sum of
       direct costs of all projects during the year
 27/11/2006                 Emad Elbeltagi                     37




 Project Finance & Contract Pricing
Profit Margin

       The contactors’ competition to win a project

        A contractor’s desirability for work

       Volume of work that the contractor has at a certain
       time

       Size of the project and it complexity

       Identity of the client and the engineer


 27/11/2006                 Emad Elbeltagi                     38




                                                                    19
Project Finance & Contract Pricing
Risk Management
       Uncertainty and risks usually leads to project
       completion delays and cost overruns
       Process: Identification of risks
       Responses to avoid, reduce, or transfer risk
       Analysis and assessment of residual risks after the risk
       responses
       Adding time and /or cost contingency for residual risks
       in the project estimates
 27/11/2006                 Emad Elbeltagi                 39




 Project Finance & Contract Pricing
Risk Management
Generally the risk should be carried out by the party

 who is best able to define it. If there is any doubt,

 it should be carried out by the client. This is

 because, it is better for the client to pay for what

 does happen rather than for what the contractor

 thought might happen

 27/11/2006                 Emad Elbeltagi                 40




                                                                  20
Project Finance & Contract Pricing
Risk Management
Risk Identification

       Risk is the possibility of undesirable extra cost or
       delay due to factors having uncertain future outcome

       Material may not be available prior to construction
       thus delay the project

       Risks defined through: check lists, experts opinions,
       comparisons with other

 27/11/2006                 Emad Elbeltagi                    41




 Project Finance & Contract Pricing
Risk Management: identification
Administrative
       Delay in possesses of site
        Limited working hours
       Limited access to the site
       Troubles with public services

Logistical
        Shortage or late supply of different resources
        Site remoteness problems


 27/11/2006                 Emad Elbeltagi                    42




                                                                   21
Project Finance & Contract Pricing
 Risk Management: identification
Physical
       Periods of high temperature
       Placing fill in dry season
       Diverting water canals in time of low flow
 Construction
        limited work space
        Changes in soil condition
        Availability of skilled labor
        Equipment breakdown
 27/11/2006                   Emad Elbeltagi        43




  Project Finance & Contract Pricing
 Risk Management: identification
Design
       Design incomplete
       Design changes
       Design errors
Financial
      Inflation
      New restrictions applied on importing
      Exchange rate fluctuation
      Availability of funds
 27/11/2006                   Emad Elbeltagi        44




                                                         22
Project Finance & Contract Pricing
Risk Management: identification
Political
       Change of local laws and regulations
       Necessity to use local resources
       Effect of wars and revolutions
Disasters
       Floods and storms
       Earthquakes
       Accidents
       Diseases
 27/11/2006                Emad Elbeltagi                   45




 Project Finance & Contract Pricing
Risk Management: Response
       Using construction methods with high success
       Using extra resources
       Securing alternative suppliers
       Providing temporary roads
       Allowing free housing near construction
       Locating site facilities away of the working space
       Assuming realistic reduced resources output
       Using equipments with available spare parts
       Providing facilities for mechanical maintenance
 27/11/2006                Emad Elbeltagi                   46




                                                                 23
Project Finance & Contract Pricing
Risk Management: Response
Time contingency

       extra time that added to the contract time to offset
       the effect of risks
       A general allowance is added to the overall contract
       duration, e.g., weather conditions

       Allowance is added to a particular activity affected by

       the risk

 27/11/2006                  Emad Elbeltagi                47




 Project Finance & Contract Pricing
Risk Management: Response
Cost contingency

      extra cost is added to the estimate and the contract
      price

      Based on the experience, a fixed percentage is added
      This might not be accurate

      A detailed risk analysis may be done to determine the
      suitable contingency
 27/11/2006                  Emad Elbeltagi                48




                                                                 24
Project Finance & Contract Pricing
Pricing Policy
       direct cost are associated directly to contract activities

       Indirect costs and markup are related to the whole

       contract

       Pricing policy is the method by which the indirect

       costs and markup will be distributed among the items

       of the bill of quantities

 27/11/2006                  Emad Elbeltagi                  49




 Project Finance & Contract Pricing
Pricing Policy
Balanced bid (Straight forward)

The share of specific item =

Direct cost of this item x (total indirect cost + markup)
Total contract direct cost




 27/11/2006                  Emad Elbeltagi                  50




                                                                    25
Project Finance & Contract Pricing
Pricing Policy: Balanced Bid

Example

      Contract price 3,500,000

      Direct cost 2,800,000

      If the direct cost of an activity is 400,000

      Determine the price of that activity


 27/11/2006                 Emad Elbeltagi               51




 Project Finance & Contract Pricing
Pricing Policy: Balanced Bid

Example
      Bid price = direct cost + indirect cost + markup
      Indirect cost + markup = 3,500,000 - 2,800,000 = LE

      700,000
      Indirect cost + markup For the activity =
      400,000/2,800,000 x 700,000 = 100,000
      Activity price = 400,000 + 100,000 =500,000

 27/11/2006                 Emad Elbeltagi               52




                                                              26
Project Finance & Contract Pricing
 Pricing Policy: Unbalanced Bid

       Called also loading of rates

       Increasing prices for early items in the BOQ

       Increase the cash revenue at the beginning

       Decrease negative cash flow

       May be risky to the owner or the contractor


  27/11/2006                            Emad Elbeltagi                         53




  Project Finance & Contract Pricing
 Pricing Policy: Unbalanced Bid

Example : Consider the following project

                          Direct cost       Balanced bid         Unbalanced bid
Activity       Quantity
                               rate       Rate           Price   Rate      Price
   A             100          4            5             500      6        600
   B             100          8            10            1000     14       1400
   C             100          16           20            2000     18       1800
   D             100          16           20            2000     18       1800
   E             100          8            10            1000     9        900

           Tender price                                  6500              6500




  27/11/2006                            Emad Elbeltagi                         54




                                                                                    27
Project Finance & Contract Pricing
Pricing Policy: Unbalanced Bid

Example
         Draw the cash flow curves for both balanced and
         unbalanced bids
         Determine the effect of increasing quantity of activity
         B by 50%
         Determine the effect of increasing quantity of activity
         C by 50%


 27/11/2006                         Emad Elbeltagi                55




 Project Finance & Contract Pricing
Pricing Policy: Unbalanced Bid
         7000

         6000

         5000

         4000
 Price




                          Unbalanced bid
         3000

         2000                          Balanced bid

         1000

              0
                  0   1         2            3        4   5   6
                                           Time

 27/11/2006                         Emad Elbeltagi                56




                                                                       28
Project Finance & Contract Pricing
  Pricing Policy: Unbalanced Bid

Example : Effect of Increasing activity B by 50%


                      Direct         Balanced bid          Unbalanced bid
Activity Quantity
                     cost rate    Rate             Price   Rate      Price
   A           100      4            5             500       6        600
   B           150       8          10             1500     14       2100
   C           100      16          20             2000     18       1800
   D           100      16          20             2000     18       1800
   E           100       8          10             1000      9        900

  Tender Price                                    7000              7200

  27/11/2006                     Emad Elbeltagi                        57




   Project Finance & Contract Pricing
  Pricing Policy: Unbalanced Bid

Example : Effect of Increasing activity C by 50%

                      Direct         Balanced bid          Unbalanced bid
Activity Quantity
                     cost rate    Rate             Price   Rate     Price
   A           100      4            5             500      6        600
   B           100      8           10             1000    14        1400
   C           150      16          20             3000    18        2700
   D           100      16          20             2000    18        1800
   E           100      8           10             1000     9        900

  Tender Price                                    7500             7400

  27/11/2006                     Emad Elbeltagi                        58




                                                                             29
Project Finance & Contract Pricing
Pricing Policy: Method related charge

     In conventional BOQ, all costs are related to quantity
     of work
     Result in financial problems
     Example, site overheads
     Specifying independent items from quantities as
     separate items in the BOQ
     These items may be fixed cost or time related


27/11/2006                Emad Elbeltagi                  59




Project Finance & Contract Pricing
Pricing Policy: Method related charge

     Sample BOQ in Method Related Charge

                     Fixed        Time-related
  Activity / Resource                           Unit   Price
                     charge         charge
    Establish site   Fixed             -       Sum
   Site overheads      -          Time-related Month
     Bulldozers        -          Time-related Day
     Excavators        -          Time-related Day
  General overheads    -          Time-related Month
   -----------------   -               -         -
   -----------------   -               -         -

27/11/2006                Emad Elbeltagi                  60




                                                               30
UNIT    TOTAL
ITEM        DESCRIPTION            QUANTITY   UNIT
                                                       PRICE   PRICE
       Heath Safety
                                              Lump
       Equipment and
                                              Sum
       Monitoring.
 1
       Project Site                           Lump
       Mobilization.                          Sum

       Steel Structure
 2
       Decontamination.
       a) Decontaminate steel                 Square
                                     1100
       structure                              Meters
       b) Load and haul debris
                                      5        Ton
       to Landfill in Alexandria
       Walls Decontamination
 3
       and Coating.
                                              Square
       a) Support walls              1200
                                              Meters
                                              Square
       b) Rolling Scaffold           1200
                                              Meters




                                                                       31

More Related Content

Similar to P project finance

Implementing Partnerships in California
Implementing Partnerships in CaliforniaImplementing Partnerships in California
Implementing Partnerships in CaliforniaAdam Nicolopoulos
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 9
Course on Regulation and Sustainable Energy in Developing Countries - Session 9Course on Regulation and Sustainable Energy in Developing Countries - Session 9
Course on Regulation and Sustainable Energy in Developing Countries - Session 9Leonardo ENERGY
 
Natalia Meylunas - Head of Regional Programme, Small Business Support Team at...
Natalia Meylunas - Head of Regional Programme, Small Business Support Team at...Natalia Meylunas - Head of Regional Programme, Small Business Support Team at...
Natalia Meylunas - Head of Regional Programme, Small Business Support Team at...Serbian Business Angels Network
 
Iii 2 Bsdl At Iess
Iii 2 Bsdl At IessIii 2 Bsdl At Iess
Iii 2 Bsdl At IessIESS
 
8013 lecture depreciation
8013 lecture depreciation8013 lecture depreciation
8013 lecture depreciationBoran Eshtawi
 
Financial Analysis - China Communications Construction Company Ltd. is a tran...
Financial Analysis - China Communications Construction Company Ltd. is a tran...Financial Analysis - China Communications Construction Company Ltd. is a tran...
Financial Analysis - China Communications Construction Company Ltd. is a tran...BCV
 
Interim results Q4 2009
Interim results Q4 2009Interim results Q4 2009
Interim results Q4 2009EDB
 
Prakash Narayan Killer S O Aapps Using J2 E E
Prakash  Narayan   Killer S O Aapps Using J2 E EPrakash  Narayan   Killer S O Aapps Using J2 E E
Prakash Narayan Killer S O Aapps Using J2 E ESOA Symposium
 
Xbrl Conference Brussels - Bas Groenveld And Paul Hulst - Comparability Of Se...
Xbrl Conference Brussels - Bas Groenveld And Paul Hulst - Comparability Of Se...Xbrl Conference Brussels - Bas Groenveld And Paul Hulst - Comparability Of Se...
Xbrl Conference Brussels - Bas Groenveld And Paul Hulst - Comparability Of Se...Paul Hulst
 
Annual Report 2008
Annual Report 2008Annual Report 2008
Annual Report 2008Tele2
 
Alexco jan13presentation
Alexco jan13presentationAlexco jan13presentation
Alexco jan13presentationnabarnes
 
Presentation at SEB's press conference for Q4 2011
Presentation at SEB's press conference for Q4 2011Presentation at SEB's press conference for Q4 2011
Presentation at SEB's press conference for Q4 2011SEBgroup
 
Investors Presentation 2012 | Presentación Inversores 2012
Investors Presentation 2012 | Presentación Inversores 2012Investors Presentation 2012 | Presentación Inversores 2012
Investors Presentation 2012 | Presentación Inversores 2012Ferrovial
 
Presentación Inversores 2012
Presentación Inversores 2012Presentación Inversores 2012
Presentación Inversores 2012Ferrovial
 
2012 Ferrovial Investors Presentation
2012 Ferrovial Investors Presentation2012 Ferrovial Investors Presentation
2012 Ferrovial Investors PresentationFerrovial
 
Willbros Group at D.A. Davidson's 11th Annual Engineering & Construction Con...
Willbros Group at  D.A. Davidson's 11th Annual Engineering & Construction Con...Willbros Group at  D.A. Davidson's 11th Annual Engineering & Construction Con...
Willbros Group at D.A. Davidson's 11th Annual Engineering & Construction Con...Willbros Group, Inc.
 

Similar to P project finance (20)

Panel 1: MAPC Presentation
Panel 1: MAPC PresentationPanel 1: MAPC Presentation
Panel 1: MAPC Presentation
 
Implementing Partnerships in California
Implementing Partnerships in CaliforniaImplementing Partnerships in California
Implementing Partnerships in California
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 9
Course on Regulation and Sustainable Energy in Developing Countries - Session 9Course on Regulation and Sustainable Energy in Developing Countries - Session 9
Course on Regulation and Sustainable Energy in Developing Countries - Session 9
 
Natalia Meylunas - Head of Regional Programme, Small Business Support Team at...
Natalia Meylunas - Head of Regional Programme, Small Business Support Team at...Natalia Meylunas - Head of Regional Programme, Small Business Support Team at...
Natalia Meylunas - Head of Regional Programme, Small Business Support Team at...
 
G Cloud - ApplyCamp 2011-11-22
G Cloud - ApplyCamp 2011-11-22G Cloud - ApplyCamp 2011-11-22
G Cloud - ApplyCamp 2011-11-22
 
Iii 2 Bsdl At Iess
Iii 2 Bsdl At IessIii 2 Bsdl At Iess
Iii 2 Bsdl At Iess
 
8013 lecture depreciation
8013 lecture depreciation8013 lecture depreciation
8013 lecture depreciation
 
Financial Analysis - China Communications Construction Company Ltd. is a tran...
Financial Analysis - China Communications Construction Company Ltd. is a tran...Financial Analysis - China Communications Construction Company Ltd. is a tran...
Financial Analysis - China Communications Construction Company Ltd. is a tran...
 
Interim results Q4 2009
Interim results Q4 2009Interim results Q4 2009
Interim results Q4 2009
 
Prakash Narayan Killer S O Aapps Using J2 E E
Prakash  Narayan   Killer S O Aapps Using J2 E EPrakash  Narayan   Killer S O Aapps Using J2 E E
Prakash Narayan Killer S O Aapps Using J2 E E
 
Xbrl Conference Brussels - Bas Groenveld And Paul Hulst - Comparability Of Se...
Xbrl Conference Brussels - Bas Groenveld And Paul Hulst - Comparability Of Se...Xbrl Conference Brussels - Bas Groenveld And Paul Hulst - Comparability Of Se...
Xbrl Conference Brussels - Bas Groenveld And Paul Hulst - Comparability Of Se...
 
Annual Report 2008
Annual Report 2008Annual Report 2008
Annual Report 2008
 
Alexco jan13presentation
Alexco jan13presentationAlexco jan13presentation
Alexco jan13presentation
 
Alexco jan13presentation
Alexco jan13presentationAlexco jan13presentation
Alexco jan13presentation
 
Alexco feb13presentation
Alexco feb13presentationAlexco feb13presentation
Alexco feb13presentation
 
Presentation at SEB's press conference for Q4 2011
Presentation at SEB's press conference for Q4 2011Presentation at SEB's press conference for Q4 2011
Presentation at SEB's press conference for Q4 2011
 
Investors Presentation 2012 | Presentación Inversores 2012
Investors Presentation 2012 | Presentación Inversores 2012Investors Presentation 2012 | Presentación Inversores 2012
Investors Presentation 2012 | Presentación Inversores 2012
 
Presentación Inversores 2012
Presentación Inversores 2012Presentación Inversores 2012
Presentación Inversores 2012
 
2012 Ferrovial Investors Presentation
2012 Ferrovial Investors Presentation2012 Ferrovial Investors Presentation
2012 Ferrovial Investors Presentation
 
Willbros Group at D.A. Davidson's 11th Annual Engineering & Construction Con...
Willbros Group at  D.A. Davidson's 11th Annual Engineering & Construction Con...Willbros Group at  D.A. Davidson's 11th Annual Engineering & Construction Con...
Willbros Group at D.A. Davidson's 11th Annual Engineering & Construction Con...
 

More from Tu Nguyen, PMP®,PMI-RMP®

More from Tu Nguyen, PMP®,PMI-RMP® (20)

4.contracting
4.contracting4.contracting
4.contracting
 
3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 

P project finance

  • 1. Project Finance and Contract Pricing Project Finance & Contract Pricing Contract Cash Flow How much is the total cost? How to arrange for financing? Cash Flow = Cash In –Cash Out = Income – Expense = Revenue - Cost 27/11/2006 Emad Elbeltagi 2 1
  • 2. Project Finance & Contract Pricing Project Expenses The project cost types: Fixed cost (equipment,…) Time-related cost (distributed over the duration of an activity, e.g., salaries, …) Quantity (Production)-related costs (costs per unit of materials or unit of resource usage) When these costs are paid, it is named expenses 27/11/2006 Emad Elbeltagi 3 Project Finance & Contract Pricing Project Expenses (Smooth curve) LE x1000 700 600 500 Cost 400 300 Expense 200 100 0 Time 0 2 4 6 8 10 27/11/2006 Emad Elbeltagi 4 2
  • 3. Project Finance & Contract Pricing Project Expenses The project S-Curve: Cost (LE) Time 27/11/2006 Emad Elbeltagi 5 Project Finance & Contract Pricing Project Income Project revenue is the summation of the activities prices Represents the payment made by the owner to the contractor Mostly, the contractor receive his payments after one month from submitting his/her invoice Retainage of 5 or 10 to ensure that that no problems will arise during construction When the contractor receive his/her payments, it is called Income 27/11/2006 Emad Elbeltagi 6 3
  • 4. Project Finance & Contract Pricing Project Income (Stepped curve) LE x1000 800 700 600 500 Revenue 400 Income 300 200 100 0 Time 0 2 4 6 8 10 27/11/2006 Emad Elbeltagi 7 Project Finance & Contract Pricing Example Consider the construction operation of a foundation activity Activity duration 8 weeks Labor cost of LE 1600 paid weekly Equipment cost of LE 4000 paid weekly after 2-month credit facility Material cost of LE 800 paid weekly after 3-month credit facility Subcontractor cost of LE 2400 paid weekly after 1-month credit facility When each payment by the contractor is due and how much? 27/11/2006 Emad Elbeltagi 8 4
  • 5. Project Finance & Contract Pricing Example Activity total cost = LE 8800 Week 1 2 3 4 5 6 7 8 Payments 1100 1100 1100 1100 1100 1100 1100 1100 Total 1100 2200 3300 4400 5500 6600 7700 8800 27/11/2006 Emad Elbeltagi 9 Project Finance & Contract Pricing Project Income (Stepped curve) wk 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 L - 200 200 200 200 200 200 200 200 E - - - - - - - - 500 500 500 500 500 500 500 500 M - - - - - - - - - - - - 100 100 100 100 100 100 100 100 S - - - - 300 300 300 300 300 300 300 300 T - 500 200 200 500 500 500 500 1000 800 800 800 600 600 600 600 100 100 100 100 27/11/2006 Emad Elbeltagi 10 5
  • 6. Project Finance & Contract Pricing Contract Cash Flow Cost (LE) Retainage Expense Profile Income Profile Month Cash out-of-flow 27/11/2006 Emad Elbeltagi 11 Project Finance & Contract Pricing Contract Cash Flow - Admeasurements contract Cumulative cost (LE) Expense Overdraft Income Time 1 2 3 4 5 6 7 8 27/11/2006 Emad Elbeltagi 12 6
  • 7. Project Finance & Contract Pricing Contract Cash Flow - Admeasurements contract with advanced payment Cumulative Cost (LE) Expense Income Advanced payment Time 0 1 2 3 4 5 6 7 8 27/11/2006 Emad Elbeltagi 13 Project Finance & Contract Pricing Contract Cash Flow – Lump sum contract with three payments Cumulative Cost (LE) Expense Income Time 0 1 2 3 4 5 6 7 8 27/11/2006 Emad Elbeltagi 14 7
  • 8. Project Finance & Contract Pricing Contract Cash Flow Variables needed to calculate cash flow The project bar chart (project schedule) Activities’ direct and indirect cost Contractor method of paying his/her expenses Contractor’s markup Retention amount and its payback time Time of payment delay by owner Advanced or mobilization payment 27/11/2006 Emad Elbeltagi 15 Project Finance & Contract Pricing Contract Cash Flow Procedure to calculate cash flow The project bar chart (project schedule) Perform project schedule Draw bar chart based on early or late timings Calculate the cost per time period Calculate the cumulative cost Adjust the cost to produce the expenses Calculate cumulative revenue: revenue = cost x (1 + markup) Adjust the revenue to produce the income Calculate the cash flow (cash flow = income – expense). 27/11/2006 Emad Elbeltagi 16 8
  • 9. Project Finance & Contract Pricing Example 4 14 12 22 D(8) 2 3 A(4) E(4) 6 6 16 18 24 26 32 32 B(6) F(10) I(6) 0 0 1 4 5 H(8) 6 9 C(2) G(16) K(10) J(6) 8 7 2 16 22 22 27/11/2006 Emad Elbeltagi 17 Project Finance & Contract Pricing Example Example data: Mark up = 5% Duration Total Cost (LE x Total Revenue (LE x Activity (day) 1000) 1000) A 4 04.00 04.20 B 6 12.00 12.60 C 2 04.00 04.20 D 8 16.00 16.80 E 4 20.00 21.00 F 10 20.00 21.00 G 16 16.00 16.80 H 8 24.00 25.20 I 6 12.00 12.60 J 6 12.00 12.60 K 10 10.00 10.50 27/11/2006 Emad Elbeltagi 18 9
  • 10. Project Finance & Contract Pricing Example Example data: Contractor expenses will be paid immediately Retention = 10% will be paid with the last payment Calculations made every 8 days Owner payment will be delayed one period First invoice after at the end of the period No advanced payment 27/11/2006 Emad Elbeltagi 19 Project Finance & Contract Pricing Example Time (days) 1000/day 2000/day 000/day 2000/day 2000/day 5000/day 2000/day 1000/day 3000/day 2000/day 2000/day 1000/day 27/11/2006 Emad Elbeltagi 20 10
  • 11. Project Finance & Contract Pricing Example 1. Cost/2 days x 10 10 12 14 10 10 16 16 8 8 8 8 6 6 6 2 - - - - LE1000 2. Cost each period x 46 52 32 20 - LE1000 3. Cumulative cost x 46 98 130 150 150 LE1000 4. Cumulative 46 98 130 150 150 Expense x 1000 5. Revenue = row 3 x 48.3 54.6 33.6 21 - 1.05 6. Revenue - retention 43.47 49.14 30.24 18.90 - = row 5 x 0.9 7. Retention x LE1000 - - - - 15.75 8. Cumulative revenue 43.47 92.61 122.85 141.75 157.50 x LE1000 9. Cumulative income - 43.47 92.61 122.85 157.50 x LE1000 10. Cumulative cash flow x LE1000 = -46 -98/-54.53 -86.53/-37.39 -57.39/-27.15 -27.15/+7.5 row 9 – row 4 27/11/2006 Emad Elbeltagi 21 Project Finance & Contract Pricing Example 160 150 140 Area = LE 10,000 130 x 1 period (8-days) 120 110 100 LE x1000 90 80 70 60 50 40 30 20 10 0 0 1 2 3 4 5 6 Time (period) 27/11/2006 Emad Elbeltagi 22 11
  • 12. Project Finance & Contract Pricing Example 0 1 2 3 4 5 6 30 10 -10 LE x 1000 -30 -50 -70 -90 -110 Time (period) 27/11/2006 Emad Elbeltagi 23 Project Finance & Contract Pricing Minimizing Contract Negative Cash Flow Loading of rates Adjustment of work schedule to late start timing Reduction of delays in receiving revenues Asking for advanced or mobilization payment Increasing the mark up and reducing the retention Adjust the timing of delivery of large material orders Delay in paying labor wages, equipment, material 27/11/2006 Emad Elbeltagi 24 12
  • 13. Project Finance & Contract Pricing Cost of Borrowing 160 150 140 Area = LE 10,000 130 x 1 period (8- 120 110 days) 100 LE x1000 90 80 70 60 50 40 30 20 10 0 0 1 2 3 4 5 6 Time (period) 24 unit areas, interest rate 1% per period Cost = 24 x 10000 x 0.01 = LE 2400 27/11/2006 Emad Elbeltagi 25 Project Finance & Contract Pricing Project Cash Flow Time scale is much longer spans the whole life of a project Feasibility studies Execution Operation Profitability indicators Payback period Maximum capital – maximum negative cash Profit 27/11/2006 Emad Elbeltagi 26 13
  • 14. Project Finance & Contract Pricing Project Cash Flow Cumulative cash flow Payback Profit period Project Maximum duration capital 27/11/2006 Emad Elbeltagi 27 Project Finance & Contract Pricing Project Cash Flow: Example Project net cash flow Year 1 2 3 4 5 6 7 8 Project A (LE x 1000) -10 -40 -30 20 60 20 15 30 Project B (LE x 1000) -30 -80 30 50 10 20 40 40 Project cumulative cash flow Year 1 2 3 4 5 6 7 8 Project A (LE x 1000) -10 -50 -80 -60 0 20 35 65 Project B (LE x1000) -30 -110 -80 -30 -20 0 40 80 27/11/2006 Emad Elbeltagi 28 14
  • 15. Project Finance & Contract Pricing Project Cash Flow: Example 100 80 65 50 Project A 0 0 2 4 6 8 -50 -80 -100 -110 Project B -150 27/11/2006 Emad Elbeltagi 29 Project Finance & Contract Pricing Discounted Cash Flow Present value (PV) Current values of money Discounted value due to inflation Change in currency power purchasing C = P x (1+r) n(1 + r) (1 + r) (1+r) P = C / (1+r) n Net present value (NPV)= PV income- PV expense 27/11/2006 Emad Elbeltagi 30 15
  • 16. Project Finance & Contract Pricing Net Present Value Project net cash flow Year 0 1 2 3 4 5 Project A (LE ) -1000 500 400 200 200 100 Project B (LE ) -1000 100 200 200 400 700 Which project would you prefer? Interest rate (discount rate) = 10% /year 27/11/2006 Emad Elbeltagi 31 Project Finance & Contract Pricing Net Present Value Project A Project B 27/11/2006 Emad Elbeltagi 32 16
  • 17. Project Finance & Contract Pricing Internal rate of return (IRR) The least discount rate (investment rate) that acceptable by the contractor or greater than the return on capital It is the discount rate with zero NPV 27/11/2006 Emad Elbeltagi 33 Project Finance & Contract Pricing Internal rate of return: Example Same previous example Project A Project B 27/11/2006 Emad Elbeltagi 34 17
  • 18. Project Finance & Contract Pricing Finalizing Bid Price Price Markup Cost Risk Financial Indirect Profit Direct cost allowance charge cost 27/11/2006 Emad Elbeltagi 35 Project Finance & Contract Pricing Indirect Cost Project Overheads (Site) Does not apply to a specific activity Cost of site utilities, supervisors, workshop,… A detailed analysis can be carried out Generally assumed 5 – 15 % of direct cots 27/11/2006 Emad Elbeltagi 36 18
  • 19. Project Finance & Contract Pricing Indirect Cost General Overheads (Head-office) Does not apply to a specific project Cost of head-office, managers, estimators,… Generally assumed 2 – 5 % of direct cots For a specific project: Project direct cost x general overhead of the company in a year/ Expected sum of direct costs of all projects during the year 27/11/2006 Emad Elbeltagi 37 Project Finance & Contract Pricing Profit Margin The contactors’ competition to win a project A contractor’s desirability for work Volume of work that the contractor has at a certain time Size of the project and it complexity Identity of the client and the engineer 27/11/2006 Emad Elbeltagi 38 19
  • 20. Project Finance & Contract Pricing Risk Management Uncertainty and risks usually leads to project completion delays and cost overruns Process: Identification of risks Responses to avoid, reduce, or transfer risk Analysis and assessment of residual risks after the risk responses Adding time and /or cost contingency for residual risks in the project estimates 27/11/2006 Emad Elbeltagi 39 Project Finance & Contract Pricing Risk Management Generally the risk should be carried out by the party who is best able to define it. If there is any doubt, it should be carried out by the client. This is because, it is better for the client to pay for what does happen rather than for what the contractor thought might happen 27/11/2006 Emad Elbeltagi 40 20
  • 21. Project Finance & Contract Pricing Risk Management Risk Identification Risk is the possibility of undesirable extra cost or delay due to factors having uncertain future outcome Material may not be available prior to construction thus delay the project Risks defined through: check lists, experts opinions, comparisons with other 27/11/2006 Emad Elbeltagi 41 Project Finance & Contract Pricing Risk Management: identification Administrative Delay in possesses of site Limited working hours Limited access to the site Troubles with public services Logistical Shortage or late supply of different resources Site remoteness problems 27/11/2006 Emad Elbeltagi 42 21
  • 22. Project Finance & Contract Pricing Risk Management: identification Physical Periods of high temperature Placing fill in dry season Diverting water canals in time of low flow Construction limited work space Changes in soil condition Availability of skilled labor Equipment breakdown 27/11/2006 Emad Elbeltagi 43 Project Finance & Contract Pricing Risk Management: identification Design Design incomplete Design changes Design errors Financial Inflation New restrictions applied on importing Exchange rate fluctuation Availability of funds 27/11/2006 Emad Elbeltagi 44 22
  • 23. Project Finance & Contract Pricing Risk Management: identification Political Change of local laws and regulations Necessity to use local resources Effect of wars and revolutions Disasters Floods and storms Earthquakes Accidents Diseases 27/11/2006 Emad Elbeltagi 45 Project Finance & Contract Pricing Risk Management: Response Using construction methods with high success Using extra resources Securing alternative suppliers Providing temporary roads Allowing free housing near construction Locating site facilities away of the working space Assuming realistic reduced resources output Using equipments with available spare parts Providing facilities for mechanical maintenance 27/11/2006 Emad Elbeltagi 46 23
  • 24. Project Finance & Contract Pricing Risk Management: Response Time contingency extra time that added to the contract time to offset the effect of risks A general allowance is added to the overall contract duration, e.g., weather conditions Allowance is added to a particular activity affected by the risk 27/11/2006 Emad Elbeltagi 47 Project Finance & Contract Pricing Risk Management: Response Cost contingency extra cost is added to the estimate and the contract price Based on the experience, a fixed percentage is added This might not be accurate A detailed risk analysis may be done to determine the suitable contingency 27/11/2006 Emad Elbeltagi 48 24
  • 25. Project Finance & Contract Pricing Pricing Policy direct cost are associated directly to contract activities Indirect costs and markup are related to the whole contract Pricing policy is the method by which the indirect costs and markup will be distributed among the items of the bill of quantities 27/11/2006 Emad Elbeltagi 49 Project Finance & Contract Pricing Pricing Policy Balanced bid (Straight forward) The share of specific item = Direct cost of this item x (total indirect cost + markup) Total contract direct cost 27/11/2006 Emad Elbeltagi 50 25
  • 26. Project Finance & Contract Pricing Pricing Policy: Balanced Bid Example Contract price 3,500,000 Direct cost 2,800,000 If the direct cost of an activity is 400,000 Determine the price of that activity 27/11/2006 Emad Elbeltagi 51 Project Finance & Contract Pricing Pricing Policy: Balanced Bid Example Bid price = direct cost + indirect cost + markup Indirect cost + markup = 3,500,000 - 2,800,000 = LE 700,000 Indirect cost + markup For the activity = 400,000/2,800,000 x 700,000 = 100,000 Activity price = 400,000 + 100,000 =500,000 27/11/2006 Emad Elbeltagi 52 26
  • 27. Project Finance & Contract Pricing Pricing Policy: Unbalanced Bid Called also loading of rates Increasing prices for early items in the BOQ Increase the cash revenue at the beginning Decrease negative cash flow May be risky to the owner or the contractor 27/11/2006 Emad Elbeltagi 53 Project Finance & Contract Pricing Pricing Policy: Unbalanced Bid Example : Consider the following project Direct cost Balanced bid Unbalanced bid Activity Quantity rate Rate Price Rate Price A 100 4 5 500 6 600 B 100 8 10 1000 14 1400 C 100 16 20 2000 18 1800 D 100 16 20 2000 18 1800 E 100 8 10 1000 9 900 Tender price 6500 6500 27/11/2006 Emad Elbeltagi 54 27
  • 28. Project Finance & Contract Pricing Pricing Policy: Unbalanced Bid Example Draw the cash flow curves for both balanced and unbalanced bids Determine the effect of increasing quantity of activity B by 50% Determine the effect of increasing quantity of activity C by 50% 27/11/2006 Emad Elbeltagi 55 Project Finance & Contract Pricing Pricing Policy: Unbalanced Bid 7000 6000 5000 4000 Price Unbalanced bid 3000 2000 Balanced bid 1000 0 0 1 2 3 4 5 6 Time 27/11/2006 Emad Elbeltagi 56 28
  • 29. Project Finance & Contract Pricing Pricing Policy: Unbalanced Bid Example : Effect of Increasing activity B by 50% Direct Balanced bid Unbalanced bid Activity Quantity cost rate Rate Price Rate Price A 100 4 5 500 6 600 B 150 8 10 1500 14 2100 C 100 16 20 2000 18 1800 D 100 16 20 2000 18 1800 E 100 8 10 1000 9 900 Tender Price 7000 7200 27/11/2006 Emad Elbeltagi 57 Project Finance & Contract Pricing Pricing Policy: Unbalanced Bid Example : Effect of Increasing activity C by 50% Direct Balanced bid Unbalanced bid Activity Quantity cost rate Rate Price Rate Price A 100 4 5 500 6 600 B 100 8 10 1000 14 1400 C 150 16 20 3000 18 2700 D 100 16 20 2000 18 1800 E 100 8 10 1000 9 900 Tender Price 7500 7400 27/11/2006 Emad Elbeltagi 58 29
  • 30. Project Finance & Contract Pricing Pricing Policy: Method related charge In conventional BOQ, all costs are related to quantity of work Result in financial problems Example, site overheads Specifying independent items from quantities as separate items in the BOQ These items may be fixed cost or time related 27/11/2006 Emad Elbeltagi 59 Project Finance & Contract Pricing Pricing Policy: Method related charge Sample BOQ in Method Related Charge Fixed Time-related Activity / Resource Unit Price charge charge Establish site Fixed - Sum Site overheads - Time-related Month Bulldozers - Time-related Day Excavators - Time-related Day General overheads - Time-related Month ----------------- - - - ----------------- - - - 27/11/2006 Emad Elbeltagi 60 30
  • 31. UNIT TOTAL ITEM DESCRIPTION QUANTITY UNIT PRICE PRICE Heath Safety Lump Equipment and Sum Monitoring. 1 Project Site Lump Mobilization. Sum Steel Structure 2 Decontamination. a) Decontaminate steel Square 1100 structure Meters b) Load and haul debris 5 Ton to Landfill in Alexandria Walls Decontamination 3 and Coating. Square a) Support walls 1200 Meters Square b) Rolling Scaffold 1200 Meters 31