SlideShare a Scribd company logo
July / August 2013 www. .com 
78 tyre management 
In October 1985, Goldsworthy Mining, 
which operated the Goldsworthy and 
Shay Gap iron-ore mines in the 
Pilbara region of Western Australia, 
undertook a pilot ore-haulage pro-gramme 
of 20,000t over a 45km cycle 
from the Nimingarra pit to the Shay Gap 
crusher using Wabco 110t haul trucks. 
Two years later in November 1987, 
routine production began from 
Nimingarra. The ore was again hauled to 
the Shay Gap crusher – however, this 
time over a shorter, realigned haul road 
(32km cycle) that eliminated most of the 
dips and curves of the road used in 
1985. 
These hauls are among the longest 
ever undertaken using rear-dump haul 
trucks of 100t or greater capacity, and 
therefore provide an excellent opportu-nity 
to examine the effect of the improved 
haul road conditions on haul-truck 
productivity and tyre workload. 
The effecTs of change 
Improving the condition of a haul road 
can result in a substantial improvement 
in haul-truck productivity. It can also 
reduce tyre workload considerably, 
thereby reducing the incidence of 
low-life tyre heat failures for mine sites 
that are operating haul-truck tyres close 
to their workload limit. 
The work-shift average speed is 
defined as the distance travelled by a 
haul truck during a mine shift, divided by 
the shift duration. For example, if a haul 
truck covers a total of 120km in an 
eight-hour shift, then its work-shift 
average speed is 15km per hour. 
Work-shift average speed is one of 
the two determinants of tyre workload 
or tonne kilometres per hour (TKPH); the 
other is tyre average load. Generally, 
work-shift average speed increases as 
the haul-cycle distance increases. This is 
because, on a longer haul, a truck 
spends more time travelling relative to 
its periods at rest while being loaded 
and while dumping its load. 
Let us look at two scenarios: scenario 
one is a short haul where the work-shift 
average speed for a haul truck with an 
average payload of 100t operating on a 
4km cycle is 12km/h. Scenario two is a 
long haul. If that same truck were 
operating on an 8km cycle, then its work 
shift average speed would typically be 
higher – in the order of 16km/h. 
For the 4km haul cycle, the productiv-ity 
of each haul truck is 2,400t during an 
eight-hour shift (12k/h x 8hr / 4km x 
100t), while for the 8km haul cycle, 
productivity drops by 33% to 1,600t per 
truck per shift (16k/h x 8hr / 8km x 100t). 
Although the work-shift average 
speed in scenario two is higher by 
one-third, this has been more than offset 
by a doubling of haulage distance, 
causing an overall reduction in truck 
productivity. We can therefore conclude 
that a higher work-shift average speed is 
typically associated with longer haul 
distances, with a resultant increase in 
tyre workload (operational TKPH) and a 
reduction in haul-truck productivity. 
UnexpecTed resUlTs 
The 1985 pilot haulage at Nimingarra 
was on a relatively poorly formed road 
rules of the road 
Tony Cutler of Otraco 
International presents a case 
study from the Nimingarra mine 
site in Australia that examines 
the effect of good haul-road 
conditions on truck productivity 
and tyre workload 
Hauling at the 
Collahuasi 
copper mine 
in Chile 
“Improving 
the 
condition of 
a haul road 
can result in 
a substan-tial 
improve-ment 
in 
haul-truck 
productivity”
79 
www. .com July / August 2013 
tyre management 
that followed the contours of the terrain 
– rising, dipping and curving – between 
the Nimingarra pit and the Shay Gap 
crusher. 
The road was extensively reworked 
prior to the start of full production 
haulage in 1987. Cut and fill was 
undertaken to straighten the road and to 
eliminate many rises and dips. This 
realignment of the road shortened its 
length from 22.5km to 16km – a 
reduction of 29%. 
As we have seen, shorter haul 
distances generally result in a reduced 
work shift average speed which: 
• partially offsets the truck productivity 
increase associated with the shorter 
haul cycle, and 
• reduces tyre workload (operational 
TKPH). 
However, what occurred at Nimingarra 
was quite different and unexpected. The 
highest work-shift average speed 
recorded for the haul trucks operating at 
Nimingarra in 1985 had been 22.5km/h 
for four complete haulage cycles over an 
eight-hour shift. The average shift speed 
noted during the first month of 
operation, November 1987, on the 
realigned and shortened haul road was 
24km/h, which allowed six complete 
haulage cycles over an eight-hour shift. 
Contrary to expectations, the shorter 
haul cycle resulted in a higher work-shift 
average speed, providing much higher 
productivity than had been budgeted. 
While the 29% reduction in haul 
distance had been expected to result in 
a 3% drop in work-shift average speed 
– from 22.5km/h to 21.8km/h, it in fact 
increased by 6% to 24km/h. Work-shift 
average speed on the new shortened, 
realigned road was 10% higher than 
anticipated – with an equivalent 10% 
increase in actual haul-truck productivity 
compared with what had been 
budgeted. 
Managing Tyre workload 
While the higher than expected 
work-shift average speed on the 
improved Nimingarra haul road 
produced an equally unexpected 
windfall in productivity, it immediately 
set off alarm bells in relation to tyre 
workload. 
The longest haul in the Shay Gap mine 
proper at the time was from Sunset 7 pit 
to the crusher with a work shift average 
speed of 20.6km/h. A heat study 
conducted in March 1987 had shown 
that tyre temperatures on this haul were 
approaching maximum allowable levels. 
So a work-shift average speed of 24km/h 
on the new Nimingarra haul had the 
potential to create a spate of expensive 
(in terms of tyre usage cost and 
tyre-related haul-truck downtime), 
low-life tyre heat separation failures. 
Otraco immediately recommended 
that measures be implemented to 
minimise the risk of tyre heat damage. 
These included: 
• tyre pressure and temperature 
monitoring at the end of each haul 
cycle, with maximum allowable limits 
set for inflation pressure and 
temperature build-up, and 
• swapping trucks between Nimingarra 
and the shorter Shay Gap hauls as 
required. 
While high tyre air-chamber tempera-tures 
and inflation pressure build-ups 
were recorded over the duration of 
Nimingarra haulage from November 
1987 – regular chamber temperatures of 
90ºC and as much as 100ºC, and 
pressure build-ups of 30psi (2.07bar) and 
occasionally considerably higher – the 
incidence of heat-related tyre failures 
was exceptionally low. 
Based on theoretical TKPH calcula-tions, 
the operational TKPH, at a 
work-shift average speed of 24km/h, 
exceeded the tyre manufacturers’ TKPH 
ratings by between 10% and 15%. The 
tyres used on this haul should have been 
suffering an exceedingly high incidence 
of low-life heat-separation damage. 
However, they were not, even when the 
trucks were on occasion left operating 
on the long Nimingarra haul rather than 
being swapped to shorter Shay Gap 
hauls. 
This highlights a major shortcoming of 
the TKPH system of calculating tyre 
workload in that it does not take into 
account haul-road condition. 
Inhospitable 
conditions and 
dusty road 
surfaces can 
cause heavy 
wear on truck 
tyres 
“While the 
higher than 
expected 
work-shift 
average 
speed 
on the 
improved 
Nimingarra 
haul road 
produced a 
windfall in 
productivity, 
it set off 
alarm bells 
in relation 
to tyre 
workload” 
Truck tyres 
sustain a heavy 
workload on long 
mine haul routes
July / August 2013 www. .com 
82 tyre management 
Lessons Learnt 
The lesson from haulage at Nimingarra is 
that improved haul-road conditions can 
lead to a substantial increase in a haul 
truck’s productivity while simultaneously 
reducing the workload of its tyres. 
There are four main elements to 
making haul roads more productive and 
tyre-friendly. They are: 
1. Reducing haul distance and unneces-sary 
gradients, through: 
• horizontal curve minimisation; and 
• vertical curve minimisation. 
2. Recucing rolling resistance and 
tyre/truck stress, through: 
• pothole and undulation elimination; 
• road sub-base material selection and 
compaction; and 
• selection of appropriate road surface 
material and smoothing. 
3. Reducing tyre/truck lateral stress, 
through: 
• road curve radius optimisation; 
• road elevation optimisation; and 
Improving the 
conditions and 
layout of mine 
haul roads can 
make a positive 
contribution to 
tyre efficiency 
Maintaining the condition 
of haul-truck tyres is critical 
to the safe and efficient 
operation of mines 
• road camber minimisation and 
camber profile optimisation. 
4. Reducing haulage bottlenecks, 
through: 
• road width optimisation. 
The improvement in haul-road 
conditions at Nimingarra between the 
1985 pilot haulage programme and 
1987 production haulage – and the 
significant benefits gained in terms of 
truck productivity and tyre workload – 
were achieved mainly through the first 
of these elements (reducing unnecessary 
curves). 
However, all four elements were 
incorporated into the upgraded 
Nimingarra haul road, and they all 
contributed to improved productivity and 
the ability of tyres to sustain an 
operational TKPH that significantly 
exceeded their TKPH rating. Apart from 
productivity and tyre workload capability, 
overall tyre life and truck component life 
will also benefit substantially from 
improved haul-road conditions. 
“Overall 
tyre life 
and truck 
component 
life will also 
benefit 
substan-tially 
from 
improved 
haul-road 
conditions”

More Related Content

What's hot

Terminal Blend Rubber Bitumen
Terminal Blend Rubber BitumenTerminal Blend Rubber Bitumen
Terminal Blend Rubber Bitumen
California Asphalt Pavement Association
 
Update on Pavement Smoothness in California
Update on Pavement Smoothness in CaliforniaUpdate on Pavement Smoothness in California
Update on Pavement Smoothness in California
California Asphalt Pavement Association
 
Tyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading ProcessTyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading Process
Jay Ranvir
 
If & vf infographic
If & vf infographicIf & vf infographic
If & vf infographic
Adam Bromilow
 
Experimental Testing of an Off-road Tire in Soft Soil Paper81437
Experimental Testing of an Off-road Tire in Soft Soil Paper81437Experimental Testing of an Off-road Tire in Soft Soil Paper81437
Experimental Testing of an Off-road Tire in Soft Soil Paper81437
International Society for Terrain-Vehicle Systems
 
MICHELIN X® FORCE™ catalogue 2014
MICHELIN X® FORCE™ catalogue 2014MICHELIN X® FORCE™ catalogue 2014
MICHELIN X® FORCE™ catalogue 2014
Michelin Truck Tyres Europe
 
Environmental Regulation & Managing Waste Tyres
Environmental Regulation & Managing Waste TyresEnvironmental Regulation & Managing Waste Tyres
Environmental Regulation & Managing Waste Tyres
John Dyne
 
Soluções em Pelotização (Maintenance)
Soluções em Pelotização (Maintenance)Soluções em Pelotização (Maintenance)
Soluções em Pelotização (Maintenance)
MetsoBrasil
 
A Guide To Proper Tire Care
A Guide To Proper Tire CareA Guide To Proper Tire Care
A Guide To Proper Tire Care
A&M Auto Service
 
Tire Recycling Equipment Manufacturing
Tire Recycling Equipment ManufacturingTire Recycling Equipment Manufacturing
Tire Recycling Equipment Manufacturing
Trade Representation of Russian Federation in Spain
 
TYRE Retreading, a viable option presentation
TYRE Retreading, a viable option presentationTYRE Retreading, a viable option presentation
TYRE Retreading, a viable option presentationSolomon Dogo
 
BS_TBRNewOnOff2016_Brochure_EU
BS_TBRNewOnOff2016_Brochure_EUBS_TBRNewOnOff2016_Brochure_EU
BS_TBRNewOnOff2016_Brochure_EUFerdi Karskens
 
Bauma 2016 Metso Presentation
Bauma 2016 Metso Presentation Bauma 2016 Metso Presentation
Bauma 2016 Metso Presentation
Peter Heath MA, PGCE, MISTC
 
T50flyer
T50flyerT50flyer
T50flyer
Daniel García
 
Axis for tooling machine
Axis for tooling machineAxis for tooling machine
Axis for tooling machine
Stadler Michael
 
Va.ve approach
Va.ve approachVa.ve approach
Va.ve approachAnujKSingh
 
Energent Group: Frac Sand Trends
Energent Group: Frac Sand TrendsEnergent Group: Frac Sand Trends
Energent Group: Frac Sand Trends
Todd Bush
 
Trencher Training Presentation
Trencher Training PresentationTrencher Training Presentation
Trencher Training Presentationabccarolinassafety
 

What's hot (20)

Terminal Blend Rubber Bitumen
Terminal Blend Rubber BitumenTerminal Blend Rubber Bitumen
Terminal Blend Rubber Bitumen
 
Update on Pavement Smoothness in California
Update on Pavement Smoothness in CaliforniaUpdate on Pavement Smoothness in California
Update on Pavement Smoothness in California
 
Tyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading ProcessTyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading Process
 
If & vf infographic
If & vf infographicIf & vf infographic
If & vf infographic
 
Experimental Testing of an Off-road Tire in Soft Soil Paper81437
Experimental Testing of an Off-road Tire in Soft Soil Paper81437Experimental Testing of an Off-road Tire in Soft Soil Paper81437
Experimental Testing of an Off-road Tire in Soft Soil Paper81437
 
MICHELIN X® FORCE™ catalogue 2014
MICHELIN X® FORCE™ catalogue 2014MICHELIN X® FORCE™ catalogue 2014
MICHELIN X® FORCE™ catalogue 2014
 
Environmental Regulation & Managing Waste Tyres
Environmental Regulation & Managing Waste TyresEnvironmental Regulation & Managing Waste Tyres
Environmental Regulation & Managing Waste Tyres
 
Soluções em Pelotização (Maintenance)
Soluções em Pelotização (Maintenance)Soluções em Pelotização (Maintenance)
Soluções em Pelotização (Maintenance)
 
A Guide To Proper Tire Care
A Guide To Proper Tire CareA Guide To Proper Tire Care
A Guide To Proper Tire Care
 
Tire Recycling Equipment Manufacturing
Tire Recycling Equipment ManufacturingTire Recycling Equipment Manufacturing
Tire Recycling Equipment Manufacturing
 
TYRE Retreading, a viable option presentation
TYRE Retreading, a viable option presentationTYRE Retreading, a viable option presentation
TYRE Retreading, a viable option presentation
 
BS_TBRNewOnOff2016_Brochure_EU
BS_TBRNewOnOff2016_Brochure_EUBS_TBRNewOnOff2016_Brochure_EU
BS_TBRNewOnOff2016_Brochure_EU
 
READING A TYRE
READING A TYREREADING A TYRE
READING A TYRE
 
Bauma 2016 Metso Presentation
Bauma 2016 Metso Presentation Bauma 2016 Metso Presentation
Bauma 2016 Metso Presentation
 
T50flyer
T50flyerT50flyer
T50flyer
 
Axis for tooling machine
Axis for tooling machineAxis for tooling machine
Axis for tooling machine
 
Va.ve approach
Va.ve approachVa.ve approach
Va.ve approach
 
Energent Group: Frac Sand Trends
Energent Group: Frac Sand TrendsEnergent Group: Frac Sand Trends
Energent Group: Frac Sand Trends
 
Trencher Training Presentation
Trencher Training PresentationTrencher Training Presentation
Trencher Training Presentation
 
Tyres
TyresTyres
Tyres
 

Viewers also liked

eresource 3GL ERP | ERP For Transportation Business | Tyre Module
 eresource 3GL ERP | ERP For Transportation Business | Tyre Module eresource 3GL ERP | ERP For Transportation Business | Tyre Module
eresource 3GL ERP | ERP For Transportation Business | Tyre Module
eresource infotech pvt ltd
 
Tyre Tread depth and Tyre Management - NTDA Conference 2016
Tyre Tread depth and Tyre Management - NTDA Conference 2016Tyre Tread depth and Tyre Management - NTDA Conference 2016
Tyre Tread depth and Tyre Management - NTDA Conference 2016
Sue Pryce
 
Tyre claim management
Tyre claim managementTyre claim management
WebXpress Tyre Management
WebXpress Tyre ManagementWebXpress Tyre Management
WebXpress Tyre Management
WebXpress.IN
 
Tyre Management Services / Fleet Management Services
Tyre Management Services / Fleet Management ServicesTyre Management Services / Fleet Management Services
Tyre Management Services / Fleet Management Services
Shabbir Ahmed Khan
 
Tyre maintenance in open cast mines
Tyre maintenance in open cast minesTyre maintenance in open cast mines
Tyre maintenance in open cast minesChandan Chaman
 
Fleet Management System
Fleet Management SystemFleet Management System
Fleet Management System
lontongcorp
 
Tyre Industry Analysis
Tyre Industry AnalysisTyre Industry Analysis
Tyre Industry Analysis
Soupa Soundararajan
 

Viewers also liked (8)

eresource 3GL ERP | ERP For Transportation Business | Tyre Module
 eresource 3GL ERP | ERP For Transportation Business | Tyre Module eresource 3GL ERP | ERP For Transportation Business | Tyre Module
eresource 3GL ERP | ERP For Transportation Business | Tyre Module
 
Tyre Tread depth and Tyre Management - NTDA Conference 2016
Tyre Tread depth and Tyre Management - NTDA Conference 2016Tyre Tread depth and Tyre Management - NTDA Conference 2016
Tyre Tread depth and Tyre Management - NTDA Conference 2016
 
Tyre claim management
Tyre claim managementTyre claim management
Tyre claim management
 
WebXpress Tyre Management
WebXpress Tyre ManagementWebXpress Tyre Management
WebXpress Tyre Management
 
Tyre Management Services / Fleet Management Services
Tyre Management Services / Fleet Management ServicesTyre Management Services / Fleet Management Services
Tyre Management Services / Fleet Management Services
 
Tyre maintenance in open cast mines
Tyre maintenance in open cast minesTyre maintenance in open cast mines
Tyre maintenance in open cast mines
 
Fleet Management System
Fleet Management SystemFleet Management System
Fleet Management System
 
Tyre Industry Analysis
Tyre Industry AnalysisTyre Industry Analysis
Tyre Industry Analysis
 

Similar to Rules of the Road - Tyre Management Otraco Intl at Mining Magazine

Umang sanadhya presentation
Umang sanadhya presentationUmang sanadhya presentation
Umang sanadhya presentation
Umang Sanadhya
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
IRJET Journal
 
12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LRAndrew de Villiers
 
Technology Innovation in the Mining Sector
Technology Innovation in the Mining SectorTechnology Innovation in the Mining Sector
Technology Innovation in the Mining Sector
SammyOmbiro1
 
Mine Engineering project
Mine Engineering projectMine Engineering project
Mine Engineering projectLawrence Tjale
 
Transport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MITransport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MI
Dr Romil Mishra
 
Conveyor vs haul_truck
Conveyor vs haul_truckConveyor vs haul_truck
Conveyor vs haul_truck
PRABIR DATTA
 
CEMEX_SeniorDesignPosterUpdate4.21.3.pptx
CEMEX_SeniorDesignPosterUpdate4.21.3.pptxCEMEX_SeniorDesignPosterUpdate4.21.3.pptx
CEMEX_SeniorDesignPosterUpdate4.21.3.pptxArda Onkol
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
David H Moloney
 
BEB801 - Elliott Martin
BEB801 - Elliott MartinBEB801 - Elliott Martin
BEB801 - Elliott Martin
Elliott Martin
 
readymixconcrete-.pdf
readymixconcrete-.pdfreadymixconcrete-.pdf
readymixconcrete-.pdf
FaizanSolanki
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
Aglaia Connect
 
cement industry program development
cement industry program developmentcement industry program development
cement industry program development
Hyder Ali Larik
 
Gujarat ambuja redefining operational efficiency
Gujarat ambuja   redefining operational efficiencyGujarat ambuja   redefining operational efficiency
Gujarat ambuja redefining operational efficiency
Sourabh Chitre
 
BT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_FBT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_Fphilip dobson
 
Australian perspective on rubberized hot mix asphalt
Australian perspective on rubberized hot mix asphaltAustralian perspective on rubberized hot mix asphalt
Australian perspective on rubberized hot mix asphalt
California Asphalt Pavement Association
 
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperSHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperDennis McElroy
 

Similar to Rules of the Road - Tyre Management Otraco Intl at Mining Magazine (20)

Umang sanadhya presentation
Umang sanadhya presentationUmang sanadhya presentation
Umang sanadhya presentation
 
Megaroller Track Record
Megaroller Track RecordMegaroller Track Record
Megaroller Track Record
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR
 
Technology Innovation in the Mining Sector
Technology Innovation in the Mining SectorTechnology Innovation in the Mining Sector
Technology Innovation in the Mining Sector
 
Mine Engineering project
Mine Engineering projectMine Engineering project
Mine Engineering project
 
Transport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MITransport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MI
 
Conveyor vs haul_truck
Conveyor vs haul_truckConveyor vs haul_truck
Conveyor vs haul_truck
 
JNPGT-5-149
JNPGT-5-149JNPGT-5-149
JNPGT-5-149
 
My report vfd
My  report vfdMy  report vfd
My report vfd
 
CEMEX_SeniorDesignPosterUpdate4.21.3.pptx
CEMEX_SeniorDesignPosterUpdate4.21.3.pptxCEMEX_SeniorDesignPosterUpdate4.21.3.pptx
CEMEX_SeniorDesignPosterUpdate4.21.3.pptx
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
BEB801 - Elliott Martin
BEB801 - Elliott MartinBEB801 - Elliott Martin
BEB801 - Elliott Martin
 
readymixconcrete-.pdf
readymixconcrete-.pdfreadymixconcrete-.pdf
readymixconcrete-.pdf
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
cement industry program development
cement industry program developmentcement industry program development
cement industry program development
 
Gujarat ambuja redefining operational efficiency
Gujarat ambuja   redefining operational efficiencyGujarat ambuja   redefining operational efficiency
Gujarat ambuja redefining operational efficiency
 
BT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_FBT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_F
 
Australian perspective on rubberized hot mix asphalt
Australian perspective on rubberized hot mix asphaltAustralian perspective on rubberized hot mix asphalt
Australian perspective on rubberized hot mix asphalt
 
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperSHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
 

Recently uploaded

The Significance of Flowers in Our Lives
The Significance of Flowers in Our LivesThe Significance of Flowers in Our Lives
The Significance of Flowers in Our Lives
BISOU Flowers
 
USCG Quick Guide For Uniform Medals and Ribbons wear and placement.pdf
USCG Quick Guide For Uniform Medals and Ribbons wear and placement.pdfUSCG Quick Guide For Uniform Medals and Ribbons wear and placement.pdf
USCG Quick Guide For Uniform Medals and Ribbons wear and placement.pdf
Pin-iT Military Uniform Tools
 
x ray baggage scanner manufacturers in India
x ray baggage scanner manufacturers in Indiax ray baggage scanner manufacturers in India
x ray baggage scanner manufacturers in India
Gujar Industries India Pvt. Ltd
 
3 Examples of new capital gains taxes in Canada
3 Examples of new capital gains taxes in Canada3 Examples of new capital gains taxes in Canada
3 Examples of new capital gains taxes in Canada
Lakshay Gandhi
 
Office Business Furnishings | Office Equipment
Office Business Furnishings |  Office EquipmentOffice Business Furnishings |  Office Equipment
Office Business Furnishings | Office Equipment
OFWD
 
Citizen Air Conditioning Services|Air Conditioning Nyc
Citizen Air Conditioning Services|Air Conditioning NycCitizen Air Conditioning Services|Air Conditioning Nyc
Citizen Air Conditioning Services|Air Conditioning Nyc
citizenairconditioni
 
Best Immigration Consultants in Amritsar- SAGA Studies
Best Immigration Consultants in Amritsar- SAGA StudiesBest Immigration Consultants in Amritsar- SAGA Studies
Best Immigration Consultants in Amritsar- SAGA Studies
SAGA Studies
 
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptxTop Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Merchantech - Payment Processing Services
 
METS Lab SASO Certificate Services in Dubai.pdf
METS Lab SASO Certificate Services in Dubai.pdfMETS Lab SASO Certificate Services in Dubai.pdf
METS Lab SASO Certificate Services in Dubai.pdf
sandeepmetsuae
 
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Summerland Environmental
 
Discover How Long Do Aluminum Gutters Last?
Discover How Long Do Aluminum Gutters Last?Discover How Long Do Aluminum Gutters Last?
Discover How Long Do Aluminum Gutters Last?
SteveRiddle8
 
Keyword Density Evolution: Elevating SEO Excellence, Leading as Top SEO Agenc...
Keyword Density Evolution: Elevating SEO Excellence, Leading as Top SEO Agenc...Keyword Density Evolution: Elevating SEO Excellence, Leading as Top SEO Agenc...
Keyword Density Evolution: Elevating SEO Excellence, Leading as Top SEO Agenc...
Barrownz.in
 
Bridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Bridging the Language Gap The Power of Simultaneous Interpretation in RwandaBridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Bridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Kasuku Translation Ltd
 
The Best Premium IPTV Service Frane.docx
The Best Premium IPTV Service Frane.docxThe Best Premium IPTV Service Frane.docx
The Best Premium IPTV Service Frane.docx
Industry Foods UK
 
Satrya Jaya Mulia - Company Profile - 2024 - CS PROJECT.pptx
Satrya Jaya Mulia - Company Profile - 2024 - CS PROJECT.pptxSatrya Jaya Mulia - Company Profile - 2024 - CS PROJECT.pptx
Satrya Jaya Mulia - Company Profile - 2024 - CS PROJECT.pptx
RichoRamadhan2
 
Solar Panel For Home Price List In india
Solar Panel For Home Price List In indiaSolar Panel For Home Price List In india
Solar Panel For Home Price List In india
janhaviconaxweb
 
WORK PERMIT IN NORWAY | WORK VISA SERVICE
WORK  PERMIT  IN  NORWAY | WORK VISA SERVICEWORK  PERMIT  IN  NORWAY | WORK VISA SERVICE
WORK PERMIT IN NORWAY | WORK VISA SERVICE
RKIMT
 
SEO For Interior Designers In Delhi.pdf
SEO For Interior  Designers In Delhi.pdfSEO For Interior  Designers In Delhi.pdf
SEO For Interior Designers In Delhi.pdf
SEOServicesinDelhi
 
Greeting powerpoint slide for kids( 4-6 years old)
Greeting powerpoint slide for kids( 4-6 years old)Greeting powerpoint slide for kids( 4-6 years old)
Greeting powerpoint slide for kids( 4-6 years old)
lenguyenthaotrang663
 
Siddhivinayak temple timings Houston, TX
Siddhivinayak temple timings Houston, TXSiddhivinayak temple timings Houston, TX
Siddhivinayak temple timings Houston, TX
gaurisiddhivinayakte
 

Recently uploaded (20)

The Significance of Flowers in Our Lives
The Significance of Flowers in Our LivesThe Significance of Flowers in Our Lives
The Significance of Flowers in Our Lives
 
USCG Quick Guide For Uniform Medals and Ribbons wear and placement.pdf
USCG Quick Guide For Uniform Medals and Ribbons wear and placement.pdfUSCG Quick Guide For Uniform Medals and Ribbons wear and placement.pdf
USCG Quick Guide For Uniform Medals and Ribbons wear and placement.pdf
 
x ray baggage scanner manufacturers in India
x ray baggage scanner manufacturers in Indiax ray baggage scanner manufacturers in India
x ray baggage scanner manufacturers in India
 
3 Examples of new capital gains taxes in Canada
3 Examples of new capital gains taxes in Canada3 Examples of new capital gains taxes in Canada
3 Examples of new capital gains taxes in Canada
 
Office Business Furnishings | Office Equipment
Office Business Furnishings |  Office EquipmentOffice Business Furnishings |  Office Equipment
Office Business Furnishings | Office Equipment
 
Citizen Air Conditioning Services|Air Conditioning Nyc
Citizen Air Conditioning Services|Air Conditioning NycCitizen Air Conditioning Services|Air Conditioning Nyc
Citizen Air Conditioning Services|Air Conditioning Nyc
 
Best Immigration Consultants in Amritsar- SAGA Studies
Best Immigration Consultants in Amritsar- SAGA StudiesBest Immigration Consultants in Amritsar- SAGA Studies
Best Immigration Consultants in Amritsar- SAGA Studies
 
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptxTop Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
 
METS Lab SASO Certificate Services in Dubai.pdf
METS Lab SASO Certificate Services in Dubai.pdfMETS Lab SASO Certificate Services in Dubai.pdf
METS Lab SASO Certificate Services in Dubai.pdf
 
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
 
Discover How Long Do Aluminum Gutters Last?
Discover How Long Do Aluminum Gutters Last?Discover How Long Do Aluminum Gutters Last?
Discover How Long Do Aluminum Gutters Last?
 
Keyword Density Evolution: Elevating SEO Excellence, Leading as Top SEO Agenc...
Keyword Density Evolution: Elevating SEO Excellence, Leading as Top SEO Agenc...Keyword Density Evolution: Elevating SEO Excellence, Leading as Top SEO Agenc...
Keyword Density Evolution: Elevating SEO Excellence, Leading as Top SEO Agenc...
 
Bridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Bridging the Language Gap The Power of Simultaneous Interpretation in RwandaBridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Bridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
 
The Best Premium IPTV Service Frane.docx
The Best Premium IPTV Service Frane.docxThe Best Premium IPTV Service Frane.docx
The Best Premium IPTV Service Frane.docx
 
Satrya Jaya Mulia - Company Profile - 2024 - CS PROJECT.pptx
Satrya Jaya Mulia - Company Profile - 2024 - CS PROJECT.pptxSatrya Jaya Mulia - Company Profile - 2024 - CS PROJECT.pptx
Satrya Jaya Mulia - Company Profile - 2024 - CS PROJECT.pptx
 
Solar Panel For Home Price List In india
Solar Panel For Home Price List In indiaSolar Panel For Home Price List In india
Solar Panel For Home Price List In india
 
WORK PERMIT IN NORWAY | WORK VISA SERVICE
WORK  PERMIT  IN  NORWAY | WORK VISA SERVICEWORK  PERMIT  IN  NORWAY | WORK VISA SERVICE
WORK PERMIT IN NORWAY | WORK VISA SERVICE
 
SEO For Interior Designers In Delhi.pdf
SEO For Interior  Designers In Delhi.pdfSEO For Interior  Designers In Delhi.pdf
SEO For Interior Designers In Delhi.pdf
 
Greeting powerpoint slide for kids( 4-6 years old)
Greeting powerpoint slide for kids( 4-6 years old)Greeting powerpoint slide for kids( 4-6 years old)
Greeting powerpoint slide for kids( 4-6 years old)
 
Siddhivinayak temple timings Houston, TX
Siddhivinayak temple timings Houston, TXSiddhivinayak temple timings Houston, TX
Siddhivinayak temple timings Houston, TX
 

Rules of the Road - Tyre Management Otraco Intl at Mining Magazine

  • 1. July / August 2013 www. .com 78 tyre management In October 1985, Goldsworthy Mining, which operated the Goldsworthy and Shay Gap iron-ore mines in the Pilbara region of Western Australia, undertook a pilot ore-haulage pro-gramme of 20,000t over a 45km cycle from the Nimingarra pit to the Shay Gap crusher using Wabco 110t haul trucks. Two years later in November 1987, routine production began from Nimingarra. The ore was again hauled to the Shay Gap crusher – however, this time over a shorter, realigned haul road (32km cycle) that eliminated most of the dips and curves of the road used in 1985. These hauls are among the longest ever undertaken using rear-dump haul trucks of 100t or greater capacity, and therefore provide an excellent opportu-nity to examine the effect of the improved haul road conditions on haul-truck productivity and tyre workload. The effecTs of change Improving the condition of a haul road can result in a substantial improvement in haul-truck productivity. It can also reduce tyre workload considerably, thereby reducing the incidence of low-life tyre heat failures for mine sites that are operating haul-truck tyres close to their workload limit. The work-shift average speed is defined as the distance travelled by a haul truck during a mine shift, divided by the shift duration. For example, if a haul truck covers a total of 120km in an eight-hour shift, then its work-shift average speed is 15km per hour. Work-shift average speed is one of the two determinants of tyre workload or tonne kilometres per hour (TKPH); the other is tyre average load. Generally, work-shift average speed increases as the haul-cycle distance increases. This is because, on a longer haul, a truck spends more time travelling relative to its periods at rest while being loaded and while dumping its load. Let us look at two scenarios: scenario one is a short haul where the work-shift average speed for a haul truck with an average payload of 100t operating on a 4km cycle is 12km/h. Scenario two is a long haul. If that same truck were operating on an 8km cycle, then its work shift average speed would typically be higher – in the order of 16km/h. For the 4km haul cycle, the productiv-ity of each haul truck is 2,400t during an eight-hour shift (12k/h x 8hr / 4km x 100t), while for the 8km haul cycle, productivity drops by 33% to 1,600t per truck per shift (16k/h x 8hr / 8km x 100t). Although the work-shift average speed in scenario two is higher by one-third, this has been more than offset by a doubling of haulage distance, causing an overall reduction in truck productivity. We can therefore conclude that a higher work-shift average speed is typically associated with longer haul distances, with a resultant increase in tyre workload (operational TKPH) and a reduction in haul-truck productivity. UnexpecTed resUlTs The 1985 pilot haulage at Nimingarra was on a relatively poorly formed road rules of the road Tony Cutler of Otraco International presents a case study from the Nimingarra mine site in Australia that examines the effect of good haul-road conditions on truck productivity and tyre workload Hauling at the Collahuasi copper mine in Chile “Improving the condition of a haul road can result in a substan-tial improve-ment in haul-truck productivity”
  • 2. 79 www. .com July / August 2013 tyre management that followed the contours of the terrain – rising, dipping and curving – between the Nimingarra pit and the Shay Gap crusher. The road was extensively reworked prior to the start of full production haulage in 1987. Cut and fill was undertaken to straighten the road and to eliminate many rises and dips. This realignment of the road shortened its length from 22.5km to 16km – a reduction of 29%. As we have seen, shorter haul distances generally result in a reduced work shift average speed which: • partially offsets the truck productivity increase associated with the shorter haul cycle, and • reduces tyre workload (operational TKPH). However, what occurred at Nimingarra was quite different and unexpected. The highest work-shift average speed recorded for the haul trucks operating at Nimingarra in 1985 had been 22.5km/h for four complete haulage cycles over an eight-hour shift. The average shift speed noted during the first month of operation, November 1987, on the realigned and shortened haul road was 24km/h, which allowed six complete haulage cycles over an eight-hour shift. Contrary to expectations, the shorter haul cycle resulted in a higher work-shift average speed, providing much higher productivity than had been budgeted. While the 29% reduction in haul distance had been expected to result in a 3% drop in work-shift average speed – from 22.5km/h to 21.8km/h, it in fact increased by 6% to 24km/h. Work-shift average speed on the new shortened, realigned road was 10% higher than anticipated – with an equivalent 10% increase in actual haul-truck productivity compared with what had been budgeted. Managing Tyre workload While the higher than expected work-shift average speed on the improved Nimingarra haul road produced an equally unexpected windfall in productivity, it immediately set off alarm bells in relation to tyre workload. The longest haul in the Shay Gap mine proper at the time was from Sunset 7 pit to the crusher with a work shift average speed of 20.6km/h. A heat study conducted in March 1987 had shown that tyre temperatures on this haul were approaching maximum allowable levels. So a work-shift average speed of 24km/h on the new Nimingarra haul had the potential to create a spate of expensive (in terms of tyre usage cost and tyre-related haul-truck downtime), low-life tyre heat separation failures. Otraco immediately recommended that measures be implemented to minimise the risk of tyre heat damage. These included: • tyre pressure and temperature monitoring at the end of each haul cycle, with maximum allowable limits set for inflation pressure and temperature build-up, and • swapping trucks between Nimingarra and the shorter Shay Gap hauls as required. While high tyre air-chamber tempera-tures and inflation pressure build-ups were recorded over the duration of Nimingarra haulage from November 1987 – regular chamber temperatures of 90ºC and as much as 100ºC, and pressure build-ups of 30psi (2.07bar) and occasionally considerably higher – the incidence of heat-related tyre failures was exceptionally low. Based on theoretical TKPH calcula-tions, the operational TKPH, at a work-shift average speed of 24km/h, exceeded the tyre manufacturers’ TKPH ratings by between 10% and 15%. The tyres used on this haul should have been suffering an exceedingly high incidence of low-life heat-separation damage. However, they were not, even when the trucks were on occasion left operating on the long Nimingarra haul rather than being swapped to shorter Shay Gap hauls. This highlights a major shortcoming of the TKPH system of calculating tyre workload in that it does not take into account haul-road condition. Inhospitable conditions and dusty road surfaces can cause heavy wear on truck tyres “While the higher than expected work-shift average speed on the improved Nimingarra haul road produced a windfall in productivity, it set off alarm bells in relation to tyre workload” Truck tyres sustain a heavy workload on long mine haul routes
  • 3. July / August 2013 www. .com 82 tyre management Lessons Learnt The lesson from haulage at Nimingarra is that improved haul-road conditions can lead to a substantial increase in a haul truck’s productivity while simultaneously reducing the workload of its tyres. There are four main elements to making haul roads more productive and tyre-friendly. They are: 1. Reducing haul distance and unneces-sary gradients, through: • horizontal curve minimisation; and • vertical curve minimisation. 2. Recucing rolling resistance and tyre/truck stress, through: • pothole and undulation elimination; • road sub-base material selection and compaction; and • selection of appropriate road surface material and smoothing. 3. Reducing tyre/truck lateral stress, through: • road curve radius optimisation; • road elevation optimisation; and Improving the conditions and layout of mine haul roads can make a positive contribution to tyre efficiency Maintaining the condition of haul-truck tyres is critical to the safe and efficient operation of mines • road camber minimisation and camber profile optimisation. 4. Reducing haulage bottlenecks, through: • road width optimisation. The improvement in haul-road conditions at Nimingarra between the 1985 pilot haulage programme and 1987 production haulage – and the significant benefits gained in terms of truck productivity and tyre workload – were achieved mainly through the first of these elements (reducing unnecessary curves). However, all four elements were incorporated into the upgraded Nimingarra haul road, and they all contributed to improved productivity and the ability of tyres to sustain an operational TKPH that significantly exceeded their TKPH rating. Apart from productivity and tyre workload capability, overall tyre life and truck component life will also benefit substantially from improved haul-road conditions. “Overall tyre life and truck component life will also benefit substan-tially from improved haul-road conditions”