This document summarizes a study evaluating the use of reinforced thermoplastic pipe (RTP) to replace aging offshore pipelines in a mature oil field in a more cost effective manner. Hydraulic modeling showed that RTP generated lower pressure drops than carbon steel pipelines for smaller diameters. An installation cost comparison showed that RTP installation was $2-4 million USD lower cost than other options like flexible pipe and carbon steel. RTP was selected as the best option due to its lower total cost of ownership over the life of the pipeline.
Gas turbine aeroderivative Module LM6000 PCapri kartiwan
Dokumen tersebut merupakan modul pelatihan tentang power plant dengan sistem gas turbin sederhana. Modul ini menjelaskan tentang definisi dan komponen-komponen utama gas turbin aeroderivatif seperti compressor, ruang pembakaran, turbin, serta sistem pendukungnya seperti bahan bakar, pelumas, pendinginan, dan lainnya.
Dokumen tersebut membahas tentang fluida dinamis dan hukum Bernoulli serta beberapa penerapannya dalam alat ukur seperti venturimeter dan tabung Pitot serta gaya angkat pada sayap pesawat. Dibahas pula tentang sifat-sifat fluida ideal dan persamaan kontinuitas.
Este documento presenta un mapa conceptual sobre los principios del derecho colectivo del trabajo en Venezuela según la Constitución y la Ley Orgánica del Trabajo. Explica que la CRBV establece en los artículos 95 y 96 los principios de libertad sindical y de garantía estatal de las relaciones colectivas del trabajo. Luego, detalla cuatro principios fundamentales del derecho colectivo del trabajo en la LOTTT: libertad sindical, autonomía sindical, pureza sindical y transparencia.
Este documento describe aspectos fundamentales del derecho colectivo del trabajo en México, incluyendo la definición de conceptos clave como sindicatos, contratos colectivos de trabajo, huelgas y riesgos laborales. Explica las diferentes categorías de trabajadores y sindicatos, así como los requisitos y procedimientos para la formación y registro de sindicatos. También describe el contenido y terminación de contratos colectivos y leyes laborales, así como las capacidades y obligaciones de los sindicatos.
This document provides a conceptual study for a proposed 330 km iron concentrate slurry pipeline from Mt Reed to Port Cartier, Quebec. Key aspects of the proposed system include:
- A 28" diameter steel pipeline operating at 1.7-1.8 m/s, carrying 24 Mt/y of 65% solids iron concentrate slurry
- Two pump stations, one at the mine site and one intermediate, using positive displacement pumps
- Agitated storage tanks at the mine site, intermediate station, and terminal for continuity of operations
- Cathodic protection, leak detection, and a SCADA system to monitor and control the pipeline
The study concludes the pipeline system is technically feasible. Further optimization and testing are
Internal Coatings on the Rise - World Pipelines September 2016Craig Thomas
1) Internally coating gas transmission pipelines with epoxy provides enhanced gas flow and reduced operational costs. Over 60% of major oil and gas companies now specify these internal coatings.
2) Usage of internal coatings for gas pipelines has increased rapidly in the last decade and is expected to continue rising. Internal coatings allow for 14-21% increased pipeline capacity and provide benefits like reduced corrosion, optimized precommissioning, and lower energy costs.
3) In addition to flow enhancement, internal coatings provide protection from corrosion during storage and precommissioning, allowing for easier cleaning of pipelines and more rapid commissioning. Significant amounts of corrosion can form in uncoated pipes exposed to seawater during construction.
Gas turbine aeroderivative Module LM6000 PCapri kartiwan
Dokumen tersebut merupakan modul pelatihan tentang power plant dengan sistem gas turbin sederhana. Modul ini menjelaskan tentang definisi dan komponen-komponen utama gas turbin aeroderivatif seperti compressor, ruang pembakaran, turbin, serta sistem pendukungnya seperti bahan bakar, pelumas, pendinginan, dan lainnya.
Dokumen tersebut membahas tentang fluida dinamis dan hukum Bernoulli serta beberapa penerapannya dalam alat ukur seperti venturimeter dan tabung Pitot serta gaya angkat pada sayap pesawat. Dibahas pula tentang sifat-sifat fluida ideal dan persamaan kontinuitas.
Este documento presenta un mapa conceptual sobre los principios del derecho colectivo del trabajo en Venezuela según la Constitución y la Ley Orgánica del Trabajo. Explica que la CRBV establece en los artículos 95 y 96 los principios de libertad sindical y de garantía estatal de las relaciones colectivas del trabajo. Luego, detalla cuatro principios fundamentales del derecho colectivo del trabajo en la LOTTT: libertad sindical, autonomía sindical, pureza sindical y transparencia.
Este documento describe aspectos fundamentales del derecho colectivo del trabajo en México, incluyendo la definición de conceptos clave como sindicatos, contratos colectivos de trabajo, huelgas y riesgos laborales. Explica las diferentes categorías de trabajadores y sindicatos, así como los requisitos y procedimientos para la formación y registro de sindicatos. También describe el contenido y terminación de contratos colectivos y leyes laborales, así como las capacidades y obligaciones de los sindicatos.
This document provides a conceptual study for a proposed 330 km iron concentrate slurry pipeline from Mt Reed to Port Cartier, Quebec. Key aspects of the proposed system include:
- A 28" diameter steel pipeline operating at 1.7-1.8 m/s, carrying 24 Mt/y of 65% solids iron concentrate slurry
- Two pump stations, one at the mine site and one intermediate, using positive displacement pumps
- Agitated storage tanks at the mine site, intermediate station, and terminal for continuity of operations
- Cathodic protection, leak detection, and a SCADA system to monitor and control the pipeline
The study concludes the pipeline system is technically feasible. Further optimization and testing are
Internal Coatings on the Rise - World Pipelines September 2016Craig Thomas
1) Internally coating gas transmission pipelines with epoxy provides enhanced gas flow and reduced operational costs. Over 60% of major oil and gas companies now specify these internal coatings.
2) Usage of internal coatings for gas pipelines has increased rapidly in the last decade and is expected to continue rising. Internal coatings allow for 14-21% increased pipeline capacity and provide benefits like reduced corrosion, optimized precommissioning, and lower energy costs.
3) In addition to flow enhancement, internal coatings provide protection from corrosion during storage and precommissioning, allowing for easier cleaning of pipelines and more rapid commissioning. Significant amounts of corrosion can form in uncoated pipes exposed to seawater during construction.
l The document discusses how applying an epoxy coating to the internal surface of gas pipelines can increase gas flow capacity and reduce operational costs. International oil and gas companies now commonly use internal pipeline coatings.
l Applying internal coatings can increase gas throughput by 10-20% by reducing surface roughness. Studies have shown coated pipelines require fewer compressor stations and use less fuel. Internal coatings also protect against corrosion during storage and make commissioning and inspection easier.
l Specifications for internal coatings aim to ensure coatings can withstand conditions like saltwater submersion and exposure to hydrocarbons. Developments include higher-solids and solvent-free coatings to reduce emissions while still meeting specifications.
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...IRJET Journal
This document discusses an experimental study and computational fluid dynamics (CFD) analysis of additively manufactured weirs. Four different weir designs - empty and ramped catenary, labyrinth, and piano key - were 3D printed and tested in a 2.5 meter open channel flow experiment. Flow rates, water levels, velocities, and discharge coefficients were measured and compared for each weir design. CFD modeling was also used to simulate the flow and validate the experimental results. The ramped catenary weir design generally performed best across testing parameters for both maximum and minimum flow rates. The study demonstrated the feasibility of using additive manufacturing to create complex weir geometries for experimental fluid mechanics research.
1) Internally coating gas pipelines with epoxy coatings was developed in the 1950s to reduce corrosion and increase pipeline efficiency.
2) Epoxy coatings create a smooth inner surface that allows gas to flow more easily, reducing pressure drops and increasing flow rates. This can allow pipelines to transport more gas without increasing size.
3) Studies have found that epoxy coatings can increase a pipeline's gas transport capacity by 5-20%, reducing operating costs through lower compression needs over the lifetime of the pipeline.
IRJET- Design of Integrated Intake Manifold for Formula Race CarIRJET Journal
The document describes the design of an integrated intake manifold for a Formula race car engine. It discusses selecting carbon fiber for the plenum due to its strength, light weight, and low thermal expansion. Aluminum is used for the runners due to its high heat conductivity. Computational fluid dynamics simulations validated the even static pressure distribution within the intake. The integrated design using composites achieved better heat transfer and vehicle performance compared to other intake manifold designs.
This document discusses lessons learned from recent deepwater riser projects and how risers can become more standardized industrial products. It describes an industrialization process for risers involving a technical hierarchy to systematically organize components. This allows for detailed failure mode and effects analysis (FMECA) and structured engineering. An example FMECA is provided for a hybrid riser tower (HRT) system. The analysis identified 2 high risks related to connections at the top and bottom of the HRT, in line with reliability data. Overall the FMECA found 194 medium risks and 437 low risks. The document advocates standardizing key riser design aspects like materials to improve cost effectiveness while meeting functional requirements.
BHD Creative working in conjunction with the team from GPS to produce a series of Application Brochures using a mix of infographics, photography and text to create a series of engaging technical documents. Also converted to Ebooks with embedded videos to increase usability and engagement.
Oil and gas pipelines are critical infrastructure that require effective corrosion protection to ensure long-term operational effectiveness. Internally coating pipelines with epoxy provides benefits like increased gas flow capacity, faster drying times, and reduced operational costs from decreased pumping needs. Externally, fusion-bonded epoxy coatings form an electrical barrier against corrosion and have proven effective for onshore and offshore pipelines. Pipeline coating technologies continue to evolve to meet industry needs for transporting oil and gas from more challenging environments.
Piping Stress Analysis of a Hypothetical Oil Refinery Plant Having Separate S...IJSRD
In this study, a hypothetical simulation model is analyzed under varying uncertainty conditions; the key features of overlapping and functional interaction affect the performance measures of development time and effort. Findings indicate that, first and foremost, whether or not overlapping occurs, increasing functional interaction eventually leads to a sound system. A selective overview of group & individual process behaviors of a combined suction & discharge cycles of a hypothetical oil refinery plant is suggested. The pipe material is Carbon fiber reinforced plastic which is chosen because of its excellent length to weight ratio & it serves as an integral part the system which involves tank piping. This model uses psychologically legitimate & theoretically grounded models for time & decision rules. The results of preliminary simulation experiments suggest that the model is sensitive to structural & pay- off density & precisely replicates ideal free distributions. Pipe network models allow the modeling of storage tanks in which the working fluid (here, Naphtha) surface is inconsistent with inflow & outflow. Stress analysis of CFRP material shows that the maximum stresses are within allowable material strength. From the trials, it can be accomplished that, with proper design parameters, CFRP can take the design load similar to that of steel & other alloys
This document provides guidelines for hydraulic calculations and line sizing for process plants. It outlines the general approach to hydraulic calculations, including pressure drop criteria, equivalent lengths of valves and fittings, and flow regimes for vapor-liquid mixed phase flow. Tables with typical line sizing criteria are included for liquid, vapor, gas and two-phase flow lines. Special considerations and calculation methods are described for thermosyphon reboiler circuits, kettle reboiler circuits, pump NPSH, and vacuum tower transfer lines. Appendices provide references and additional tables and figures to support the guidelines.
IRJET- CFD Flow Analysis of Station PipelineIRJET Journal
This document summarizes a study analyzing the pressure, temperature, and velocity profiles within a station pipeline carrying fuel from booster pumps to a sample point, using computational fluid dynamics (CFD). Three cases were analyzed representing different operating conditions of the booster pumps. The CFD model was developed in ANSYS and divided into two parts due to software limitations. Results showed the pathlines for pressure, temperature, and velocity within the pipeline for each case. Overall, the study used CFD to better understand fuel flow characteristics within the station pipeline under various pump operating scenarios.
This document reviews various repair techniques for gas transmission pipelines. It begins by outlining key parameters that guide the choice of repair techniques, such as pipeline characteristics, operating conditions, location, and defect details. It then categorizes and describes external and internal repair techniques. External techniques include cut-out-and-replace, bypass, grinding, weld deposition, metallic sleeves, and composite sleeves. Internal techniques involve inserting internal liners. The document also introduces an integrated software called PipeRep that can help operators select the most suitable repair technique based on the outlined parameters.
Design and Analysis of an Air Conditioning Duct Using Equal Friction MethodIRJET Journal
This document describes the design and analysis of an air conditioning duct system using the equal friction method. It begins with an introduction to central air conditioning systems and the importance of properly designing ductwork to minimize pressure losses and costs while providing optimal indoor air quality and comfort. The document then outlines the specific steps involved in the equal friction duct design method, which involves setting the duct dimensions so that the pressure drop per unit length is equal across all ducts. The rest of the document provides an example application of this method to size ducts for a central air conditioning system serving an area of 72.2 square meters. Tables and calculations are presented to determine the equivalent diameter, dimensions, air flow rates, velocities and pressure losses for each duct section
IRJET- Fluid Flow Analysis of E-Glass and Hemp Fibre Reinforced Composite ...IRJET Journal
This document analyzes and compares the fluid flow of kerosene through pipe joints made of glass fiber reinforced plastic (GFRP) and hemp fiber reinforced plastic (HFRP) composites. 3D models of straight pipes, elbow joints, T-joints, and Y-joints were created in Solidworks. Computational fluid dynamics analysis was performed to simulate kerosene flow under pressure and velocity. The results show that HFRP joints experienced higher maximum pressures in T-joints and Y-joints compared to GFRP. HFRP also exhibited higher maximum velocities in elbow joints and T-joints than GFRP. Overall, HFRP composites showed better resistance to pressure changes and higher fluid velocities,
fem analysis of cold flaring process of sgp pipeIJAEMSJORNAL
This paper describes about finite element method analysis of cold flaring process of low carbon steel SGP pipe. These large diameter pipes such as φ216.3 mm are used for a plant as a flow channel of gas and liquid. The connection of pipes are generally welded at the plant. However, the other connecting method are required from a viewpoint of making the plant environment worse by welding. Therefore, flaring process of large diameter pipes were proposed. This flaring process is one of a method of pipe flange forming. The formed pipes were connected used with loose flange. Flaring process was generally hot process, thus it has some problem such as becoming complex of forming machine and accuracy of dimension. In this study, cold flaring process of SGP pipe was proposed to satisfy these requisitions. FEM analysis of cold flaring process were performed to clarify the optimum forming conditions for the flat length of connecting surface such as corner R. As a result, the optimum die corner R was from R6 to R9.
City gas distribution- Complete OverviewUjjwal Rao
This document provides an overview of city gas distribution systems. It discusses what city gas distribution is, the basic concepts of distribution systems including developing pipeline networks and maintaining different pressure levels. It outlines the key steps in designing distribution systems such as demand estimation, network design, and route surveys. The document also covers system components including city gate stations, pipelines, regulating stations, meters, and CNG stations. It concludes by discussing applicable codes, standards, and regulations for city gas distribution.
This document summarizes the standardization of requirements for C-Mn steel pipes, clad pipes, and lined pipes performed by PETROBRAS through a workshop with pipe suppliers and installation contractors. Scenarios were defined for various types of subsea pipelines for oil and gas fields in Brazil's pre-salt region. Requirements from the DNV-OS-F101 standard were modified and four technical specifications were developed for C-Mn seamless pipes, C-Mn SAWL pipes, lined pipes, and clad pipes based on discussions within the workgroups. The specifications aim to standardize pipe properties, dimensions, and tolerances to reduce costs and timelines for future subsea pipeline projects.
Evaluation for Mechanical Strength of Aluminium Tubes Filled with PolymersIRJET Journal
This study evaluated the mechanical strength of empty aluminum tubes and aluminum tubes filled with various polymers under quasi-static loading conditions, both experimentally and using finite element analysis. Tubes made of aluminum 6063-T6 were tested when empty as well as when filled with polymers including polyurethane, polyester, vinyl ester, polyurethane foam, and silicone rubber. Experimental testing was conducted using a universal testing machine and the mechanical properties of each tube configuration were measured. Finite element modeling and analysis was also performed using ANSYS Autodyn software. The results found that polyurethane shore A70 filled aluminum tubes absorbed more energy than empty aluminum tubes and could better guide the design of crashworthy vehicle structures.
Refinery mechanical piping systems a fundamental overviewChetan vadodariya
This paper is based on experience gained by the author in fabrication, design and installation in multinational
manufacturing, contracting and client companies in India, Saudi Arabia and Bahrain. Piping systems in
any oil refinery is the most critical mechanical hardware for the transportation of feed product i.e. crude oil to
processing units, process piping intra and inter process units and further movement of intermediate distillates
from one processing unit to another for the purpose of processing, blending, value addition and maximization of
recovery from feed stock to finish products. Pipelines are the ultimate transportation solution for despatch of final
product to storage tank farms and to the shipping terminal for internal consumption and for export. This paper lists
proven and established international design
This document summarizes how welding consumable improvements from ESAB can reduce pipeline construction time. Specifically, it describes a "3 run" welding procedure that uses a modified vertical down basic electrode for the first fill pass after the root and hot passes. This provides benefits over a traditional "2 run" procedure by avoiding issues like gas pores and reducing need for grinding. Field tests showed the new procedure can reduce welding time by over 30% and increase productivity to rates like 120-130 joints/day for a 48" pipeline.
l The document discusses how applying an epoxy coating to the internal surface of gas pipelines can increase gas flow capacity and reduce operational costs. International oil and gas companies now commonly use internal pipeline coatings.
l Applying internal coatings can increase gas throughput by 10-20% by reducing surface roughness. Studies have shown coated pipelines require fewer compressor stations and use less fuel. Internal coatings also protect against corrosion during storage and make commissioning and inspection easier.
l Specifications for internal coatings aim to ensure coatings can withstand conditions like saltwater submersion and exposure to hydrocarbons. Developments include higher-solids and solvent-free coatings to reduce emissions while still meeting specifications.
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...IRJET Journal
This document discusses an experimental study and computational fluid dynamics (CFD) analysis of additively manufactured weirs. Four different weir designs - empty and ramped catenary, labyrinth, and piano key - were 3D printed and tested in a 2.5 meter open channel flow experiment. Flow rates, water levels, velocities, and discharge coefficients were measured and compared for each weir design. CFD modeling was also used to simulate the flow and validate the experimental results. The ramped catenary weir design generally performed best across testing parameters for both maximum and minimum flow rates. The study demonstrated the feasibility of using additive manufacturing to create complex weir geometries for experimental fluid mechanics research.
1) Internally coating gas pipelines with epoxy coatings was developed in the 1950s to reduce corrosion and increase pipeline efficiency.
2) Epoxy coatings create a smooth inner surface that allows gas to flow more easily, reducing pressure drops and increasing flow rates. This can allow pipelines to transport more gas without increasing size.
3) Studies have found that epoxy coatings can increase a pipeline's gas transport capacity by 5-20%, reducing operating costs through lower compression needs over the lifetime of the pipeline.
IRJET- Design of Integrated Intake Manifold for Formula Race CarIRJET Journal
The document describes the design of an integrated intake manifold for a Formula race car engine. It discusses selecting carbon fiber for the plenum due to its strength, light weight, and low thermal expansion. Aluminum is used for the runners due to its high heat conductivity. Computational fluid dynamics simulations validated the even static pressure distribution within the intake. The integrated design using composites achieved better heat transfer and vehicle performance compared to other intake manifold designs.
This document discusses lessons learned from recent deepwater riser projects and how risers can become more standardized industrial products. It describes an industrialization process for risers involving a technical hierarchy to systematically organize components. This allows for detailed failure mode and effects analysis (FMECA) and structured engineering. An example FMECA is provided for a hybrid riser tower (HRT) system. The analysis identified 2 high risks related to connections at the top and bottom of the HRT, in line with reliability data. Overall the FMECA found 194 medium risks and 437 low risks. The document advocates standardizing key riser design aspects like materials to improve cost effectiveness while meeting functional requirements.
BHD Creative working in conjunction with the team from GPS to produce a series of Application Brochures using a mix of infographics, photography and text to create a series of engaging technical documents. Also converted to Ebooks with embedded videos to increase usability and engagement.
Oil and gas pipelines are critical infrastructure that require effective corrosion protection to ensure long-term operational effectiveness. Internally coating pipelines with epoxy provides benefits like increased gas flow capacity, faster drying times, and reduced operational costs from decreased pumping needs. Externally, fusion-bonded epoxy coatings form an electrical barrier against corrosion and have proven effective for onshore and offshore pipelines. Pipeline coating technologies continue to evolve to meet industry needs for transporting oil and gas from more challenging environments.
Piping Stress Analysis of a Hypothetical Oil Refinery Plant Having Separate S...IJSRD
In this study, a hypothetical simulation model is analyzed under varying uncertainty conditions; the key features of overlapping and functional interaction affect the performance measures of development time and effort. Findings indicate that, first and foremost, whether or not overlapping occurs, increasing functional interaction eventually leads to a sound system. A selective overview of group & individual process behaviors of a combined suction & discharge cycles of a hypothetical oil refinery plant is suggested. The pipe material is Carbon fiber reinforced plastic which is chosen because of its excellent length to weight ratio & it serves as an integral part the system which involves tank piping. This model uses psychologically legitimate & theoretically grounded models for time & decision rules. The results of preliminary simulation experiments suggest that the model is sensitive to structural & pay- off density & precisely replicates ideal free distributions. Pipe network models allow the modeling of storage tanks in which the working fluid (here, Naphtha) surface is inconsistent with inflow & outflow. Stress analysis of CFRP material shows that the maximum stresses are within allowable material strength. From the trials, it can be accomplished that, with proper design parameters, CFRP can take the design load similar to that of steel & other alloys
This document provides guidelines for hydraulic calculations and line sizing for process plants. It outlines the general approach to hydraulic calculations, including pressure drop criteria, equivalent lengths of valves and fittings, and flow regimes for vapor-liquid mixed phase flow. Tables with typical line sizing criteria are included for liquid, vapor, gas and two-phase flow lines. Special considerations and calculation methods are described for thermosyphon reboiler circuits, kettle reboiler circuits, pump NPSH, and vacuum tower transfer lines. Appendices provide references and additional tables and figures to support the guidelines.
IRJET- CFD Flow Analysis of Station PipelineIRJET Journal
This document summarizes a study analyzing the pressure, temperature, and velocity profiles within a station pipeline carrying fuel from booster pumps to a sample point, using computational fluid dynamics (CFD). Three cases were analyzed representing different operating conditions of the booster pumps. The CFD model was developed in ANSYS and divided into two parts due to software limitations. Results showed the pathlines for pressure, temperature, and velocity within the pipeline for each case. Overall, the study used CFD to better understand fuel flow characteristics within the station pipeline under various pump operating scenarios.
This document reviews various repair techniques for gas transmission pipelines. It begins by outlining key parameters that guide the choice of repair techniques, such as pipeline characteristics, operating conditions, location, and defect details. It then categorizes and describes external and internal repair techniques. External techniques include cut-out-and-replace, bypass, grinding, weld deposition, metallic sleeves, and composite sleeves. Internal techniques involve inserting internal liners. The document also introduces an integrated software called PipeRep that can help operators select the most suitable repair technique based on the outlined parameters.
Design and Analysis of an Air Conditioning Duct Using Equal Friction MethodIRJET Journal
This document describes the design and analysis of an air conditioning duct system using the equal friction method. It begins with an introduction to central air conditioning systems and the importance of properly designing ductwork to minimize pressure losses and costs while providing optimal indoor air quality and comfort. The document then outlines the specific steps involved in the equal friction duct design method, which involves setting the duct dimensions so that the pressure drop per unit length is equal across all ducts. The rest of the document provides an example application of this method to size ducts for a central air conditioning system serving an area of 72.2 square meters. Tables and calculations are presented to determine the equivalent diameter, dimensions, air flow rates, velocities and pressure losses for each duct section
IRJET- Fluid Flow Analysis of E-Glass and Hemp Fibre Reinforced Composite ...IRJET Journal
This document analyzes and compares the fluid flow of kerosene through pipe joints made of glass fiber reinforced plastic (GFRP) and hemp fiber reinforced plastic (HFRP) composites. 3D models of straight pipes, elbow joints, T-joints, and Y-joints were created in Solidworks. Computational fluid dynamics analysis was performed to simulate kerosene flow under pressure and velocity. The results show that HFRP joints experienced higher maximum pressures in T-joints and Y-joints compared to GFRP. HFRP also exhibited higher maximum velocities in elbow joints and T-joints than GFRP. Overall, HFRP composites showed better resistance to pressure changes and higher fluid velocities,
fem analysis of cold flaring process of sgp pipeIJAEMSJORNAL
This paper describes about finite element method analysis of cold flaring process of low carbon steel SGP pipe. These large diameter pipes such as φ216.3 mm are used for a plant as a flow channel of gas and liquid. The connection of pipes are generally welded at the plant. However, the other connecting method are required from a viewpoint of making the plant environment worse by welding. Therefore, flaring process of large diameter pipes were proposed. This flaring process is one of a method of pipe flange forming. The formed pipes were connected used with loose flange. Flaring process was generally hot process, thus it has some problem such as becoming complex of forming machine and accuracy of dimension. In this study, cold flaring process of SGP pipe was proposed to satisfy these requisitions. FEM analysis of cold flaring process were performed to clarify the optimum forming conditions for the flat length of connecting surface such as corner R. As a result, the optimum die corner R was from R6 to R9.
City gas distribution- Complete OverviewUjjwal Rao
This document provides an overview of city gas distribution systems. It discusses what city gas distribution is, the basic concepts of distribution systems including developing pipeline networks and maintaining different pressure levels. It outlines the key steps in designing distribution systems such as demand estimation, network design, and route surveys. The document also covers system components including city gate stations, pipelines, regulating stations, meters, and CNG stations. It concludes by discussing applicable codes, standards, and regulations for city gas distribution.
This document summarizes the standardization of requirements for C-Mn steel pipes, clad pipes, and lined pipes performed by PETROBRAS through a workshop with pipe suppliers and installation contractors. Scenarios were defined for various types of subsea pipelines for oil and gas fields in Brazil's pre-salt region. Requirements from the DNV-OS-F101 standard were modified and four technical specifications were developed for C-Mn seamless pipes, C-Mn SAWL pipes, lined pipes, and clad pipes based on discussions within the workgroups. The specifications aim to standardize pipe properties, dimensions, and tolerances to reduce costs and timelines for future subsea pipeline projects.
Evaluation for Mechanical Strength of Aluminium Tubes Filled with PolymersIRJET Journal
This study evaluated the mechanical strength of empty aluminum tubes and aluminum tubes filled with various polymers under quasi-static loading conditions, both experimentally and using finite element analysis. Tubes made of aluminum 6063-T6 were tested when empty as well as when filled with polymers including polyurethane, polyester, vinyl ester, polyurethane foam, and silicone rubber. Experimental testing was conducted using a universal testing machine and the mechanical properties of each tube configuration were measured. Finite element modeling and analysis was also performed using ANSYS Autodyn software. The results found that polyurethane shore A70 filled aluminum tubes absorbed more energy than empty aluminum tubes and could better guide the design of crashworthy vehicle structures.
Refinery mechanical piping systems a fundamental overviewChetan vadodariya
This paper is based on experience gained by the author in fabrication, design and installation in multinational
manufacturing, contracting and client companies in India, Saudi Arabia and Bahrain. Piping systems in
any oil refinery is the most critical mechanical hardware for the transportation of feed product i.e. crude oil to
processing units, process piping intra and inter process units and further movement of intermediate distillates
from one processing unit to another for the purpose of processing, blending, value addition and maximization of
recovery from feed stock to finish products. Pipelines are the ultimate transportation solution for despatch of final
product to storage tank farms and to the shipping terminal for internal consumption and for export. This paper lists
proven and established international design
This document summarizes how welding consumable improvements from ESAB can reduce pipeline construction time. Specifically, it describes a "3 run" welding procedure that uses a modified vertical down basic electrode for the first fill pass after the root and hot passes. This provides benefits over a traditional "2 run" procedure by avoiding issues like gas pores and reducing need for grinding. Field tests showed the new procedure can reduce welding time by over 30% and increase productivity to rates like 120-130 joints/day for a 48" pipeline.
1. OTC-25767-MS
Conceptual Design for Offshore Pipeline Replacement in Mature Field,
Using Reinforced Thermoplastic Pipe for CAPEX optimization in F-Field
Pipeline Repair and Replacement Program
Hanto Yananto, Pertamina Hulu Energi ONWJ, Yuyung Girindra, Pertamina Hulu Energi ONWJ, and Steven
Kennedy, Polyflow Global
Copyright 2015, Offshore Technology Conference
This paper was prepared for presentation at the Offshore Technology Conference held in Houston, Texas, USA, 4–7 May 2015.
This paper was selected for presentation by an OTC program committee following review of information contained in an abstract submitted by the author(s). Contents
of the paper have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material does not necessarily reflect
any position of the Offshore Technology Conference, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written
consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may
not be copied. The abstract must contain conspicuous acknowledgment of OTC copyright.
Abstract
A study was initiated to evaluate the benefit of low capital
cost and low maintenance cost technologies to rehabilitate
pipelines in marginal fields and apply artificial lift
solutions to marginal wells to keep them running profitably
and with an attractive return on investment (and with no
sacrifice to safety and environmental risks).
The challenge is to have a new technology with lower
“Total” cost from design, procurement, installation,
operation and maintenance during its life time. In addition,
the technology must meet the required planned production
flow, which, in some cases, can be higher than current
flow.
RTP per API15S was shown as the most cost effective
solution in rehabilitation of pipelines in marginal fields.
Introduction
Offshore North West Java (ONWJ) field has been operated
for more than 40 year and comprises 9 flow-stations and
hundreds of NUI platforms. About 600 pipelines are used
for transporting either fluid or gas. At least 5 pipelines have
to be repaired or replaced due to integrity of aging
facilities. As a mature field, any additional Capex to
maintain base production shall be carefully assessed.
Figures 1 and 2 show examples of “F” field network.
Figure-1 Pipeline Network at F3-F2
Figure-2 Pipeline Network at FS1-FS231-F261
The objective of this paper is to evaluate and select the right
existing pipeline candidates that are suitable for pipe in
2. 2 OTC-25767-MS
pipe pull through method. Success criteria include
acceptable hydraulics which meets line requirements, flow
velocity minimum performance to minimize maintenance
expenses, material selection to eliminate chemical
treatment and capital cost estimates to demonstrate a
beneficial return on investment to ONWJ.
Pipeline Replacement Strategy
The replacement strategies followed by ONWJ are
according to the following steps, i.e.
- To utilize the existing pipeline casing as the conduit for
RTP flow line pull through method.
- RTP flow line will be pulled through from tie-in flange
below Emergency Shutdown (ESD) Valve at one
platform to the same elevation at another designated
platform.
- RTP diameters which meet the hydraulic method and do
not require a modification to existing riser bends are
preferable to those that require riser bends.
- Modifications to bend does not constitute a rejection of
the process. ROI analysis will determine if project is
viable.
- Total installation cost comparison will be generated to
compare technology options.
Design Scope
The assessment effort was limited to a process that will
engage the lower hanger flange (just below the
Emergency Safety Valve) on one platform to the lower
hanger flange of the terminating platform, as in Figure 1
Figure 3. Design Scope
Appraise Stage
In the appraise stage, several technology options were
considered to select the best option to maintain the
pipeline; API 17J Flexible Pipe and API 5S RTP with Pull-
Thru Installation method are the alternative options
compared to traditional rigid carbon steel pipeline..
Commercially Available Pipe Sizing
The new pipeline will be designed to anticipate maximum
fluid or gas production from the existing platform. It is
essential to establish the right size of the pipe for current
and future operating requirements as proper pipe sizing can
minimize the ongoing maintenance by creating critical
velocities to move solids with the liquid flow stream.
One of the benefits of RTP and Flexible pipe systems are
their polymer liners which are smooth extruded surfaces
compared with carbon steel pipe. These smooth liner
surfaces reduce flowing pressure drop for comparable
diameters, thus allowing smaller diameter RTP to replace
larger diameter carbon steel pipe.
References have shown carbon steel to have a relative
roughness of ~ 0.006 in/in versus thermoplastic extruded
relative roughness of ~ 0.00005 in/in. This allows for
smaller diameter polymer lined pipes to create critical
minimum velocities to move solids while not creating
excessive pressure drop.
Modeling was performed to establish the desired diameter
using a polymer lined pipe. Table 1 summarizes the
comparison between new line size and commercially
available existing pipeline size for API 5S, API 17J and
steel pipe. Technical selection was later performed based
on market availability, material capabilities, practicality in
installation, pipeline size and length.
Table-1 Technical Selection Pipeline candidates in F-
Field
Installation Total Cost Comparison
Table 2 shows an installation total cost comparison for the
various technologies assessed. The least cost total
installation cost technology) is RTP per API 15S. Flexible
pipe per API17J is more expensive and carbon steel per
API 5L the most expensive.
RTP (API15S) ~$2MM USD less than API 17J flexible
RTP (API15S) ~ $3-4MM USD less than carbon steel
Table-2 Price Comparison of Selected Pipelines in
F-Field
1 F2-FP 6" N/A 2.2 Y Y N/A
2 F3-F2 4" 12" 2.6 Y Y Y
3 F4-F3 6" N/A 0.9 Y Y N/A
4 FP-F62 8" 12" 8.8 Y N/A N/A
5 F62-FP 16" 12" 8.8 Y N/A N/A
6 F62-F3 12" 12" 8.8 Y N/A N/A
7 FS1-F62 16" 16" 8.9 Y N/A N/A
8 F62-FS1 6" 16" 8.9 Y Y Y
9 F11-F3 12" 6" 7.6 Y N/A N/A
10 FS231-FS1 10" 12" 2.6 Y Y N/A
11 FS1-FS231 4" 12" 2.6 Y Y Y
12 F261-FS231 8" 10" 4.4 Y Y N/A
13 FS231-F261 4" 10" 4.4 Y Y Y
14 H2651-F14P 10" 12" 13.1 Y N/A N/A
15 F231-sstH2651 8" 8" 0.2 Y Y N/A
16 F14P-FP 12" 16" 11 Y N/A N/A
Carbon Steel
API 5L
Flexible Pipe
API 17J
RTP
API 15S
No. Pipeline
Existing
Size
New
Size
Length
(KM)
3. OTC-25767-MS 3
Installation Schedule
One additional advantage that flexible pipes have over
carbon steel pipes is in the duration of the installation.
Figure 4 shows a generic “pipe-in-pipe” installation
schedule for RTP per API 15S for pipeline lengths less than
5km.
Figure-4 Generic Installation Schedule
RTP per API15S was seen to offer the least cost total
rehabilitation solution and was then selected best return on
investment for use in marginal fields.
Following is a more detailed discussion of RTP
technology.
Selection of New Pipeline
The new pipeline is proposed to be installed by using
Reinforce Thermoplastic Pipe (RTP). The general
construction of RTP piping system consists of an
internal liner and substructure (either Nylon or PPS) that
is wrapped externally by aramid fibre in order to
increase allowable pressure of polymer pipe.
The PPS liner is recommended due to its low permeation
rates for both CO2 and H2S gasses. The Fortron liner
has a relative roughness friction coefficient of 0.00005
in/in was used which approximately a hundred times less
than the value is used for steel pipe (0.006 in/in).
RTP line will be installed inside of existing carbon steel
pipeline using method called Pull Thru. The existing line
is currently no flow since the platform is inactive now.
The main concern of using this method is the capability
of existing bends in the steel in handling RTP inside
which depend on the size of the RTP used. Bend
modification, if required, will give impact to the ROI
calculation.
Material comparison of RTP and steel pipeline is shown
in Table 3.
Table 3 Material Comparison
Hydraulic simulation of the new pipeline comparing
RTP and carbon steel line is summarized in Table 4.
Table 4 Comparison of hydraulic simulation result using
RTP and Carbon Steel
As shown in Table 4, for 6 inch pipeline, generally RTP
and steel pipeline generate similar pressure drop (only
0.2 psi difference). For 4 inch, pressure drop along the
steel line is higher than pressure drop along RTP, as well
as for 3.5 inch. It shows that for small diameter, the RTP
will generate less pressure drop.
Still shown in Table 4, fluid velocity for RTP is quite
higher than steel line. It minimizes solid deposition as
long as it is still lower than erosional velocity. An
operational cost avoidance benefit of the higher velocity
is the possible elimination of pigging operations.
Another significant cost benefit for RTP is in the
installation process and associated cost. Steel line lay
process requires lay barge, possibly DP2 vessels, which
resulted in high cost installation. RTP system can use
small work barges and utility vessels to transport small
machinery and materials hence the installation cost will
be less expensive.
Table 5 shows options selection by comparing
advantage and disadvantage of various sizes and
material of pipeline.
Table 5 Option Selection
2 F3-F2 4 2.6 7.2 6.6 4
11 FS1-FS231 4 2.6 7.2 6.6 4
13 FS231-F261 4 4.4 10.08 7.7 5.76
Total 24.48 20.9 13.76
CARBON STEEL
API 5L
RTP
API15S
Estimate Cost
(USD x 106
)
FLEXIBLE PIPE
API 17J
Estimate Cost
(USD x 106
)
Estimate Cost
(USD x 106
)
Length
(KM)
No. Pipeline
Size
(Inch)
Day 1 Day2 Day3 Day 4 Day 5 Day 6 Day 7
Vessel Equipment Loading
Vessel Transit to location
Deoil
Scaffolding and Equipment Setup
Actual Lay
Hydro-test
On Production
Line Down x x x
Nominal Size
Pipeline
Resulting
Pressure Drop
(psi)
Landed
Pressure (psi)
Velocity
(ft/s)
Requirement for
bend modification
6” RTP 3.6 671.4 8 Yes
6” Steel 3.4 671.6 5.5 -
4” RTP 24 651 18 No
4” Steel 26 649 12.8 -
3.5” RTP 48 627 24 No
3.5” Steel 50.1 624.9 16.3 -
4. 4 OTC-25767-MS
Generally steel has proven reliability but the installation
cost is very high. On the other side, RTP installation and
operational costs are lower but reliability is unknown
since it has never been implemented on this field.
For similar size, RTP generate less pressure drop than
steel line. Due to that reason, RTP will be more efficient
to be implemented first time in the recommended
options since it is only for gas lift. Six (6) inch size will
be oversized considered the maximum rate is only 3.4
MMSCFD.
The allowable pressure drop along the line should be
about 10-20 psi/mile (6.2-12.4 psi/km). The 3.5” RTP
and steel is resulted in very high pressure drop (48 and
50.1 psi). The only option left is 4” which is technically
and commercially feasible since it is resulted lower
pressure drop (24 psi) and the cost is cheaper than
installing new steel line.
Bend Modification Implications
An additional consideration in pipeline rehabilitation or
conversion of lines to gas lift etc. is whether the existing
bends in the steel casing need to be modified.
This is a critical cost impact item in the Return on
Investment (ROI) calculation – not as important when
production flow is sizeable but very critical for pipe-in-
pipe applications in marginal fields.
The recommended initial applications do not require
modification to existing bends.
RTP Pipeline Data
The line pipe is described as Piping and associated Joining
System pulled inside the existing steel line pipe casing. In
combination, both systems provide a stable flow line
system for the transport of gas/crude or other products.
The existing carbon steel casing does not require the use of
anodes, cathodes or other corrosion inhibitors as a
requirement for further operation as the RTP pipe will
assume all the integrity requirements for flow. This can
result in a significant operation cost avoidance.
By nature, the piping system is inert to hydrocarbons;
except for flange and splice sections which can be coated
(inner tubular) with surface protectant; such as Fortron
Polylphenylene Sulphide (PPS) or other coating, prior to
installation.
Material Selection
The RTP pipe evaluated was constructed with internal liner
of Fortron Polyphenylene Sulfide (PPS), reinforced with
aramid fibers and jacketed with Nylon (refer to Figure 5)
Figure 5: RTP Pipe Construction
The PPS liner was selected because of its resistance to
hydrocarbons and Brine, as well as CO2 and H2S. In
addition, PPS exhibits very low permeation rates for both
H2S and CO2 gas.
Permeation
Permeation through the liner does not necessarily damage
the liner but rather can create operational issues such as
build up gas pressure in the reinforcement layer creating
issues with the outer jacket. In the case of the rehabilitation
of a carbon steel pipeline, a build up of gas in the annulus
between the RTP and the steel pipe can create non desirable
issues.
The Figure 6 is comparing various polymers permeation
rates in CO2 at various temperature to show a side by side
comparisons.
Figure 6 Comparison of Polymer Permeation Rates
Figure 6 shows that polyethylene, a common polymer used
in the oilfield has significant permeation rate compared to
No Option Advantage Disadvantage Cost (USD)
1A 6” Steel
- Reliability is proven - High installation
cost
7,200,000
1B 6” RTP - Low installation cost
- Unknown
reliability
- Bend modification
is needed
N/A
1C
6” Flexible
Pipe
- Reliability is proven
- Low installation cost
- Material is slightly
expensive
6,600,000
2A 4” Steel - Reliability is proven
- High installation
cost
N/A
2B 4” RTP
- Generate less pressure drop
than steel line (for same
size)
- Low installation cost
- No need bend modification
- Pipeline repair if
leak during
operation
- Unknown
reliability
4,000,000
3A 3.5” Steel - Reliability is proven
- High pressure
drop
- High installation
cost
N/A
3B 3.5” RTP
- Generate less pressure drop
than steel line (for same
size)
- Low installation cost
- No need bend modification
- Unknown
reliability
N/A
5. OTC-25767-MS 5
the other engineering plastics and Fortron (PPS) showed
significantly lower levels of permeation.
No Venting Required
Safety is of critical concern for ONWJ. Therfore, it is
preferable to have a pipe-in-pipe system that does not
require venting of the annulus as a consequence of gas
permeation through the RTP wall into the annulus. This
criteria negated the use of polyethylene (PE) based liners
and materials.
PPS liners do not require venting of the annulus.
Typical RTP Installation Method
The first step in installation is to disconnect the
terminations at the lower hanger flange as in Figure 7
(before the safety shut off valve). In some cases due to
limited space the safety valve and associated piping might
be removed to gain acceptable access for pull through.
Figure-7 Typical Lower Hanger Flange Access /
Disconnected Flange
Operational Pigging Philosophy
Once the lower hanger flanges are disconnected, a
gauging pig will be sent through the line with cable
attached to assure that the existing casing has an
acceptable size opening to accept the RTP.
For sending of the gauging/messenger pig, a compressor
is required.
The compressor will be integrated with a temporary
pigging joint “in-line”. Figure 8 gives a visual of this
connector type which is standard in industry. When
messenger process is complete this joint is removed.
The temporary pig launcher will have flange connection
to connect with existing terminations at the platform.
Figure-8 Messenger Pig
Pulling Method
A pulling cone is attached to the RTP pipe. The pulling
cone has holes that allow for water to fill the pipe as it is
pulled within the steel casing. The operator must use a light
weight, high strength rope for the messenger pig and pull
through operation.
A winch and rope should be capable of pulling with greater
than 2x the expected pulling force (which will provide the
operator with a suitable safety factor).
The pull through speed is expected to be 7-14 m/minute.
Speed is monitored via winch controller. A faster pulling
rate is possible when the size of the casing is much larger
than the RTP pipe.
As one RTP spool is completely unwound, the pull is
stopped, the existing empty spool removed and replaced
with a new spool in the unwinding station. Then a splice
coupling is used to join the two pipe sections and continue
spooling.
A custom designed 10,000 psi rated pump is required to
swage the couplings at joining locations. The final issue is
determining the end connections. When possible it is
recommended to flange to the existing steel flange
termination because as the RTP pipe is flexible,
terminating to a non-rigid structure can cause some issues
with excessive bending.
The pipe is then pulled past the lower flange hanger (~ 5-
10 m) and the pipe is cut near the lower flange.
The proprietary termination coupling is then added using
the hydraulic press. Terminations are provided that mate
to the existing flange structure. The termination flange is
then bolted to the lower hanger flange assembly to close
off the pipe in pipe system.
Pre-commissioning
6. 6 OTC-25767-MS
The final installation process step is to hydro-test the line
to ensure splice and termination joint integrity. In general,
the installation contractor will follow the following
recommended hydro testing guidelines for RTP. Typically
the hydro-test is done at 1.5 x the “operating” pressure for
gas lines and 1.25x the operating pressure for liquid lines
of the line for an 8 hour period. However, there are a few
requirements from the RTP Supplier:
1. Pressures testing should be done with liquid (salt water
is acceptable).
2. The line should be increased in 250-500 psi increments
and held for ~15-20 minutes before increasing pressure,
thus allowing the pressure to stabilize. (There is some
stretching of the line and pressure drops can occur
during the pressurization of the line.)
3. Once the final pressure is achieved, there may be a few
recharges required during the pipe relaxation before the
pressure test hold procedures begin.
4. The pressure profile curve is asymptotic, so there may
be slight pressure decay for several hours before the
pressure stabilizes.
Conclusions
During Appraise-Select Stage, 3 pipelines were proposed
to be replaced with RTP by pull through method as shown
in Table 6.
Table 6 Summary of RTP pipeline candidates
Pipeline
Section
Cost Subsea
Work
Pulling
Through*
F3-F2 $ 4 mio No < 1 day
FS1-FS231 $ 4 mio No < 1 day
FS231-F261 $ 5.76 No < 1 days
*) RTP pull-thru equal to sending the messenger wire up to
pulling thru the RTP.
The budget required for capital expenditure on those RTP
pipelines can be optimized to 56% of regular carbon steel
pipeline laying by pipe lay barge as shown on table 7.
Table 7 Summary of CAPEX optimization
Additional operation cost reductions can be acheived from
RTP systems by elimination of pigging operations and
chemical injections associated with carbon steel pipelines.
The following is the summary of selection RTP as the most
valuable for those 3 pipelines.
- Pulling Through method is the most valuable solution
for pipeline rehabilitation in marginal field where there
were suficient existing abandoned pipeline as casing for
RTP pipe.
- No subsea intervention, but might need subsea team
support to be standby during pigging.
- For the selected lines, the maximum size RTP
applicable for existing pipeline as casing without
modification is about 4”, All for gas lift.
Pipeline rehabilitation using RTP technology has the
potential to greatly impact the performance of marginal
fields. Rehabilitation of existing lines can realized ~56+%
less capital cost compared to an installation using
conventional carbon steel pipeline. Proper planning and
analysis of the pipeline to be rehabilitated shall be executed
at earlier stage to ensure smoother installation process and
better achievement to the project in term of schedule and
expenditure spending.
References
- N/A
CAPEX
Optimization
2 F3-F2 4 2.6 7.2 4 56%
11 FS1-FS231 4 2.6 7.2 4 56%
13 FS231-F261 4 4.4 10.08 5.76 57%
Total 24.48 13.76 56%
Length
(KM)
No. Pipeline
Size
(Inch)
Estimate Cost
(USD x 106
)
RTP API15S
to CS API5L
CARBON STEEL
API 5L
RTP
API15S
Estimate Cost
(USD x 106
)